# Inspection: General.

**Citation:** 49 CFR 192.305  
**Type / status:** regulation / current  
**Agency:** Pipeline and Hazardous Materials Safety Administration  
**Effective:** 2026-08-18  
**Published:** Not stated

Link to an amendment published at 80 FR 12779, Mar. 11, 2015.

This amendment was delayed indefinitely at 80 FR 58633, Sept. 30, 2015.

Each transmission line or main must be inspected to ensure that it is constructed in accordance with this part.

## Document text

Link to an amendment published at 80 FR 12779, Mar. 11, 2015.

This amendment was delayed indefinitely at 80 FR 58633, Sept. 30, 2015.

Each transmission line or main must be inspected to ensure that it is constructed in accordance with this part.

## Provenance

- Official: Yes
- Source: <https://www.ecfr.gov/on/2026-08-18/title-49/section-192.305>
- Source ID: `ecfr`
- SHA-256: `ba84de9ba42e7c021cea06df5099239f5db3b5185e5a4c9e96b4476bcbced2eb`
- Retrieved: 2026-08-20T05:54:34.435Z
- Exported: 2026-08-22T23:12:02.103Z
- Document slug: `49-cfr-192-305`

### Source metadata

```json
{
  "cfrTitle": 49,
  "part": "192",
  "section": "192.305",
  "subpart": "Subpart G—General Construction Requirements for Transmission Lines and Mains",
  "corpusVersion": "2026-08-18",
  "jurisdiction": "US"
}
```