Pipe associated with tie-ins must be pressure tested, either with the section to be tied in or separately.

[Amdt. 195-22, 46 FR 38360, July 27, 1981, as amended by Amdt. 195-51, 59 FR 29385, June 7, 1994]

## Document text

Pipe associated with tie-ins must be pressure tested, either with the section to be tied in or separately.

[Amdt. 195-22, 46 FR 38360, July 27, 1981, as amended by Amdt. 195-51, 59 FR 29385, June 7, 1994]

## Provenance

- Official: Yes
- Source: <https://www.ecfr.gov/on/2026-08-18/title-49/section-195.308>
- Source ID: `ecfr`
- SHA-256: `41b5bd956cd9562822cb1ae0cbf28f34099564a31c5fbce5a6c1b20057e638d5`
- Retrieved: 2026-08-20T05:54:41.219Z
- Exported: 2026-08-22T15:31:38.467Z
- Document slug: `49-cfr-195-308`

### Source metadata

```json
{
  "cfrTitle": 49,
  "part": "195",
  "section": "195.308",
  "subpart": "Subpart E—Pressure Testing",
  "corpusVersion": "2026-08-18",
  "jurisdiction": "US"
}
```