# What general requirements apply to pipelines regulated under this part?

**Citation:** 192.13  
**Type / status:** regulation / current  
**Agency:** Arkansas Public Service Commission  
**Effective:** Not stated  
**Published:** Not stated

§ 192.13 What general requirements apply to pipelines regulated under this part? (a) No person may operate a segment of pipeline listed in the first column of paragraph (a)(3) of this section that is readied for service after the date in the second column, unless: (1) The pipeline has been designed,

## Document text

§ 192.13 What general requirements apply to pipelines regulated under this part? (a) No person may operate a segment of pipeline listed in the first column of paragraph (a)(3) of this section that is readied for service after the date in the second column, unless: (1) The pipeline has been designed, installed, constructed, initially inspected, and initially tested in accordance with this part; or (2) The pipeline qualifies for use under this part according to the requirements in § 192.14. (3) The compliance deadlines are as follows: Pipeline Date (i) Offshore gathering pipeline July 31, 1977 (ii) Regulated onshore gathering pipeline to which this part did March 15, 2007 not apply until April 14, 2006 (iii) Regulated onshore gathering pipeline to which this part did May 16, 2023 not apply until May 16, 2022 (iv) All other pipelines March 12, 1971 (b) No person may operate a segment of pipeline listed in the first column of this paragraph (b) that is replaced, relocated, or otherwise changed after the date in the second column of this paragraph (b), unless the replacement, relocation or change has been made according to the requirements in this part. Pipeline Date (1) Offshore gathering pipeline July 31, 1977 (2) Regulated onshore gathering pipeline to which this part did March 15, 2007 not apply until April 14, 2006 (3) Regulated onshore gathering pipeline to which this part did May 16, 2023 not apply until May 16, 2022 (4) All other pipelines November 12, 1970 (c) Each operator shall maintain, modify as appropriate, and follow the plans, procedures, and programs that it is required to establish under this part. (d) Each operator of an onshore gas transmission pipeline must evaluate and mitigate, as necessary, significant changes that pose a risk to safety or the environment through a management of change process. Each operator of an onshore gas transmission pipeline must develop and follow a management of change process, as outlined in ASME B31.8S, section 11 (incorporated by reference, see § 192.7), that addresses technical, design, physical, environmental, procedural, operational, maintenance, and organizational changes to the pipeline or processes, whether permanent or temporary. A management of change process must include the following: reason for change, authority for approving changes, analysis of implications, acquisition of required work permits, documentation, communication of change to affected parties, time limitations, and qualification of staff. For pipeline segments other than those covered in subpart O of this part, this management of change process must be implemented by February 26, 2024. The requirements of this paragraph (d) do not apply to gas gathering pipelines. Operators may request an extension of up to 1 year by submitting a notification to PHMSA at least 90 days before February 26, 2024, in accordance with § 192.18. The notification must include a reasonable and technically justified basis, an up-to-date plan for completing all actions required by this section, the reason for the requested extension, current safety or mitigation status of the pipeline segment, the proposed completion date, and any needed temporary safety measures to mitigate the impact on safety.

## Provenance

- Official: Yes
- Source: <https://codeofarrules.arkansas.gov/Rules/Rule?chapterID=40&levelType=part&partID=1394&subChapterID=392&titleID=23>
- Source ID: `ar-car-pipeline-safety`
- SHA-256: `8602a63d531d5f698a4ee86cb5e8136eeff93c19ee254ae1e79780a36ef217d7`
- Retrieved: 2026-08-12T08:10:37.612Z
- Exported: 2026-08-24T05:44:10.001Z
- Document slug: `ar-car-23-500-192-13`

### Source metadata

```json
{
  "jurisdiction": "US-AR",
  "subject": "intrastate-gas",
  "caveats": {
    "exactScope": "The searchable corpus contains every current numbered section, the code-wide definitions, and every operative appendix in official 23 CAR Part 500, plus direct pipeline rules 15 CAR sections 275-406 and 275-504. Reserved and removed provisions are inventory-only.",
    "excludedScope": "This is not all Arkansas pipeline law. Standalone statutes, dockets and orders, one-call law, utility rates and service, siting, environmental permits, highway crossings, local law, forms, and incorporated third-party standards are excluded. Other current AOGC gas and transportation rules are inventoried as adjacent production, conservation, storage, or fluid-transport material.",
    "applicabilityCaveat": "APSC administers certified intrastate gas safety downstream of producer custody transfer. AOGC section 275-406 separately reaches specified producer or producer-affiliated natural-gas systems. AOGC section 275-504 imposes state permitting and operational duties on specified hazardous-liquid pipelines, but PHMSA states that it directly inspects and enforces intrastate hazardous-liquid pipeline safety in Arkansas. Inclusion does not establish applicability to a particular facility.",
    "incorporationCaveat": "AOGC sections 275-406 and 275-504 use dynamic 'as amended' wording for federal Parts 190, 191, 192, 195, and 199. Part 500 is a state code that reproduces and modifies federal-derived gas provisions. References and relationship records do not substitute a retrieval-date federal text or decide the legal effect of incorporation.",
    "publicationCaveat": "The Code of Arkansas Rules identifies its online database as the official version, effective as a publication system January 1, 2025, updated weekly, and potentially behind recent agency rulemaking. The official Part 500 page reports Ark. R. 2026-6 effective January 8, 2026; its PDF is headed August 22, 2025 and Docket 25-025-R. Retrieval and site-update dates are publication observations, not inferred legal effective dates for every section.",
    "rights": "Official Arkansas and federal government artifacts are archived with attribution and SHA-256 provenance. Public access does not settle rights in seals, site presentation, forms, incorporated standards, or third-party material; downstream redistribution requires separate review."
  },
  "rightsReviewRequired": true,
  "references": [],
  "codePart": "23 CAR pt. 500",
  "partEffectiveOn": "2026-01-08",
  "partEffectiveDateNotImputedToIndividualProvision": true,
  "federalDerivedStateCode": true,
  "sourceCollection": "ar-car-23-part-500",
  "region": "AR"
}
```