The gas plant, equipment, and facilities of a utility shall be constructed, installed, inspected, maintained, and operated in accordance with accepted engineering and gas industry practices to assure continuity of service, uniformity in the quality of service, and the safety of persons and property.

## Document text

The gas plant, equipment, and facilities of a utility shall be constructed, installed,
inspected, maintained, and operated in accordance with accepted engineering and gas

industry practices to assure continuity of service, uniformity in the quality of service, and
the safety of persons and property.

## Provenance

- Official: Yes
- Source: <https://www.sos.state.co.us/CCR/DisplayRule.do?action=ruleinfo&ruleId=2260&deptID=18&agencyID=96&deptName=Department%20of%20Regulatory%20Agencies&agencyName=Public%20Utilities%20Commission&seriesNum=4%20CCR%20723-4>
- Source ID: `co-sos-ccr`
- SHA-256: `58328831af46c142fdd4684e205620f90eb97bc60c404e65ae6a3d1c3c34c0f3`
- Retrieved: 2026-08-12T04:36:48.096Z
- Exported: 2026-08-24T09:49:36.504Z
- Document slug: `co-ccr-4-723-4-4200`

### Source metadata

```json
{
  "jurisdiction": "US-CO",
  "code": "4 CCR 723-4",
  "ruleKey": "4200",
  "pipelineScope": "colorado-jurisdictional-gas-utilities",
  "legalScope": "Current 4 CCR 723-4 rules regulating Colorado jurisdictional gas utilities and gas master-meter operators, including construction, operation, system safety, gas infrastructure planning, metering, service, and enforcement provisions. This is an adjacent gas-utility corpus, not a replacement for the repealed dedicated 4900-series pipeline-safety rules.",
  "applicabilityCaveat": "Part 4 applies according to Colorado Public Utilities Commission jurisdiction and each rule's scope. The former dedicated pipeline-safety rules 4900 through 4975 are reserved after repeal; this connector does not represent them as current. Part 4 does not replace federal pipeline-safety requirements, determine whether a facility is interstate or intrastate, or resolve operator-specific orders, waivers, tariffs, or later rulemaking.",
  "references": [],
  "ruleInfoUrl": "https://www.sos.state.co.us/CCR/DisplayRule.do?action=ruleinfo&ruleId=2260&deptID=18&agencyID=96&deptName=Department%20of%20Regulatory%20Agencies&agencyName=Public%20Utilities%20Commission&seriesNum=4%20CCR%20723-4",
  "pucRulesUrl": "https://puc.colorado.gov/gasrulesandregulations",
  "ruleVersionId": "12549",
  "editionEffectiveOn": "2026-06-14",
  "publicationStatus": "The Colorado Secretary of State identifies the source as the official publication of state administrative rules. The edition date applies to the compiled rule version and is not represented as the effective date of every provision.",
  "rights": "Official state rule text is preserved with attribution and source links. Public accessibility does not imply rights in agency marks, third-party material, or incorporated standards; commercial redistribution requires review.",
  "region": "CO"
}
```