# PERMIT AMENDMENTS.

**Citation:** Minn. R. 7852.3400  
**Type / status:** regulation / current  
**Agency:** Minnesota Public Utilities Commission  
**Effective:** Not stated  
**Published:** 2007-08-21

Following issuance of a pipeline routing permit, the permittee may apply to the commission for amendments on route location and conditions specified in the permit. The permittee shall submit an application for amendment that contains sufficient information for the commission to determine the followi

## Document text

Following issuance of a pipeline routing permit, the permittee may apply to the commission for amendments on route location and conditions specified in the permit. The permittee shall submit an application for amendment that contains sufficient information for the commission to determine the following:

A. whether, in light of the criteria in parts 7852.0700 and 7852.1900, the requested changes are significant enough to warrant commission study and approval;

B. whether to order public information meetings near the affected area; and

C. whether additional fees shall be assessed. The commission shall make the determinations in items A to C within 45 days of receipt of the application. If the commission cannot make the determinations in items A to C in 45 days and decides to study the application further, the commission shall make the determinations in items A to C within 70 days. The commission shall grant or deny the permittee's application for permit amendment, as appropriate.

## Provenance

- Official: Yes
- Source: <https://www.revisor.mn.gov/rules/7852.3400>
- Source ID: `mn-revisor`
- SHA-256: `c7affcb0c3609ef558b010d0bde26cbf6807e43e9c1a8baaa579630e1a8dea48`
- Retrieved: 2026-08-12T03:50:50.897Z
- Exported: 2026-08-24T04:14:05.655Z
- Document slug: `minn-r-7852-3400`

### Source metadata

```json
{
  "jurisdiction": "US-MN",
  "collection": "rules-7852",
  "pipelineScope": "pipeline-route-permitting",
  "legalScope": "Pipeline route selection, permit applications, environmental review, construction conditions, restoration, complaints, amendments, and completion certification under Minnesota Rules chapter 7852. This chapter regulates routing and location review, not pipeline design or construction safety standards.",
  "versionListUrl": "https://www.revisor.mn.gov/rules/7852/versions",
  "authenticatedPdfUrl": "https://www.revisor.mn.gov/rules/pdf/7852/2024-11-06%2014:55:30+00:00",
  "publicationStatus": "Revisor-hosted HTML with an online authenticated PDF designated as the official electronic record where linked.",
  "officialRecordFormat": "authenticated-pdf",
  "rightsReviewRequired": true,
  "rightsNoticeUrl": "https://www.revisor.mn.gov/rules/info/",
  "rightsNote": "Minnesota Revisor states that website rules information is intended for personal, noncommercial use and does not authorize commercial republication. Obtain a rights review before redistribution.",
  "chapter": "7852",
  "part": "7852.3400",
  "statutoryAuthority": "MS s 116I.015; 216G.02",
  "statutoryAuthorityReferences": [
    {
      "text": "116I.015",
      "url": "https://www.revisor.mn.gov/statutes/cite/116I.015",
      "referenceType": "minnesota-statute"
    },
    {
      "text": "216G.02",
      "url": "https://www.revisor.mn.gov/statutes/cite/216G.02",
      "referenceType": "minnesota-statute"
    }
  ],
  "stateRegisterHistory": "13 SR 2046; L 2005 c 97 art 3 s 19",
  "stateRegisterCitations": [
    "13 SR 2046"
  ],
  "historyReferences": [],
  "publishedElectronically": "August 21, 2007",
  "publishedElectronicallyOn": "2007-08-21",
  "publicationDateCaveat": "Published Electronically identifies Revisor publication and is not necessarily the date of the latest substantive amendment.",
  "region": "MN"
}
```