# 255.503 General requirements.

**Citation:** 16 NYCRR 255.503  
**Type / status:** regulation / current  
**Agency:** New York State Public Service Commission  
**Effective:** Not stated  
**Published:** Not stated

Transmission and Distribution of Gas. (a) No person may operate a new segment of pipeline, or return to service a segment of pipeline that has been reconstructed, relocated, replaced, or reactivated until it has been tested in accordance with this Part to substantiate the proposed maximum allowable operating pressure and each leak has been located and eliminated.

(b) The test medium must be liq

## Document text

(a) No person may operate a new segment of pipeline, or return to service a segment of pipeline that has been reconstructed, relocated, replaced, or reactivated until it has been tested in accordance with this Part to substantiate the proposed maximum allowable operating pressure and each leak has been located and eliminated.

(b) The test medium must be liquid, air, natural gas or inert gas that is:

(1) compatible with the material of which the pipeline is constructed;

(2) relatively free of sedimentary materials; and

(3) except for natural gas, nonflammable.

(c) If air, natural gas, or inert gas is used as the test medium, the following maximum hoop stress limitations apply:

Maximum hoop stress allowed as
percentage of SMYS
Class | Natural | Air or inert
Location | gas | gas
1 | 80 | 80
2 | 30 | 75
3 | 30 | 50
4 | 30 | 40

(d) Each weld used to tie-in a test segment of pipeline is excepted from the test requirements of this Part.

(e) If a component other than pipe is the only item being replaced or added to a pipeline, a strength test after installation is not required, if the manufacturer of the component certifies that:

(1) the component was tested to at least the pressure required for the pipeline to which it is being added;

(2) the component was manufactured under a quality control system that ensures that each item manufactured is at least equal in strength to a prototype and that the prototype was tested to at least the pressure required for the pipeline to which it is being added; or

(3) the component carries a pressure rating established through applicable ASME/ANSI, Manufacturers Standardization Society of the Valve and Fittings Industry, Inc. (MSS) specifications, or by unit strength calculations as described in section 255.143 of this Part.

## Provenance

- Official: Yes
- Source: <https://govt.westlaw.com/nycrr/Document/I505d3321cd1711dda432a117e6e0f345?viewType=FullText&originationContext=documenttoc&transitionType=CategoryPageItem&contextData=(sc.Default)>
- Source ID: `ny-dps-nycrr`
- SHA-256: `c2b11f6a6ca06fd5ed4d9ba68d0fd43a3437b87f1818f08726efcea4883d598c`
- Retrieved: 2026-08-12T06:20:40.894Z
- Exported: 2026-08-27T03:19:48.105Z
- Document slug: `ny-nycrr-255-503`

### Source metadata

```json
{
  "jurisdiction": "US-NY",
  "title": 16,
  "part": "255",
  "partTitle": "Transmission and Distribution of Gas",
  "scopeKind": "gas-pipeline-safety",
  "tocPath": [
    "Part 255 Transmission and Distribution of Gas",
    "Test Requirements"
  ],
  "legalScope": "Complete current terminal legal unit exposed by the DPS-designated Title 16 NYCRR pipeline-safety part inventory.",
  "applicabilityCaveat": "Applicability depends on the part and section, Commission jurisdiction, commodity and facility type, intrastate or interstate status, operator and activity, exemptions, waivers, federal preemption, Commission orders, and incorporated law. DPS inspects portions of interstate systems for PHMSA, but PHMSA retains federal enforcement authority. DPS states that all jurisdictional Part 256 gas-holder and Part 257 LPG-plant facilities have been decommissioned even though those regulations remain unrepealed.",
  "incorporationCaveat": "These parts incorporate or rely on federal pipeline regulations, federal and New York statutes, Commission rules and orders, and privately authored technical standards. Part 10 supplies incorporation details. References metadata preserves explicit citations but does not reproduce external material, determine licensing rights, or decide whether a particular incorporation is static or dynamic.",
  "publicationCaveat": "The New York Department of Public Service identifies these eleven Title 16 NYCRR parts as its state pipeline-safety regulations and links to the public DOS/Westlaw NYCRR reading copy. That site labels the online text unofficial and directs users needing evidentiary accuracy to the Official NYCRR maintained by the Department of State Division of Administrative Rules. Each section's 'Current through' date is the most recent official NYCRR supplement covering that section, not a uniform corpus-wide amendment date.",
  "rights": "New York government-edict text is preserved with DPS, Department of State, and publisher attribution. The public reading site's presentation and enhancements, agency marks, forms, annotations, and incorporated federal or privately authored standards require separate rights review; this connector does not claim rights in those materials.",
  "rightsReviewRequired": true,
  "currentThrough": "2024-05-31",
  "historyEvents": "No event is emitted because the section reading copy does not supply an explicit adoption, filing, or effective-date history.",
  "publisherCitation": "16 CRR-NY 255.503",
  "identityAnomaly": null,
  "references": [
    {
      "citation": "16 NYCRR 255.143",
      "referenceType": "new-york-administrative-code",
      "url": "https://govt.westlaw.com/nycrr/Document/I505c6ff5cd1711dda432a117e6e0f345?viewType=FullText&originationContext=documenttoc&transitionType=CategoryPageItem&contextData=(sc.Default)"
    }
  ],
  "region": "NY"
}
```