# BUCKEYE PARTNERS, LP — Notice of Probable Violation

**Citation:** CPF 120095002  
**Type / status:** enforcement / historical  
**Agency:** Pipeline and Hazardous Materials Safety Administration  
**Effective:** Not stated  
**Published:** 2009-06-26

CLOSED notice of probable violation citing 195.401(b), 195.402(a), 195.403(b), 195.406(b), 195.412(a), 195.438, 195.452(b)(2), 195.452(f)(3), 195.452(f)(6), 195.452(i)(2), 195.452(i)(4), 195.452(j)(2), 195.557(a), 195.561, 195.571, 195.573(c), 195.573(e), 195.583(a).

## Document text

Notice of Probable Violation involving BUCKEYE PARTNERS, LP. PHMSA's enforcement data identifies the cited regulations as 195.401(b),  195.402(a),  195.403(b),  195.406(b),  195.412(a),  195.438,  195.452(b)(2),  195.452(f)(3),  195.452(f)(6),  195.452(i)(2),  195.452(i)(4),  195.452(j)(2),  195.557(a),  195.561,  195.571,  195.573(c),  195.573(e),  195.583(a). The case was opened on 2009-06-26 and is reported as closed as of 2013-06-17. Proposed civil penalty: $645,200. Assessed civil penalty: $524,900. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

120095002_ Operator Response to Notice letter_09252009.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120095002/120095002_%20Operator%20Response%20to%20Notice%20letter_09252009.pdf

120095002_Closure Letter_06172013.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120095002/120095002_Closure%20Letter_06172013.pdf

120095002_Closure Letter_06172013_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120095002/120095002_Closure%20Letter_06172013_text.pdf

120095002_Final Order _05302012.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120095002/120095002_Final%20Order%20_05302012.pdf

120095002_Final_Order_05302012_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120095002/120095002_Final_Order_05302012_text.pdf

120095002_NOPV-PCP-PCO_06262009.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120095002/120095002_NOPV-PCP-PCO_06262009.pdf

120095002_NOPV-PCP-PCO_06262009_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120095002/120095002_NOPV-PCP-PCO_06262009_text.pdf

120095002_NOPV-PCP-PCO_06262009_text.pdf

U.S. Department 820 Bear Tavern Road. Suite 306
of Transportation West Trenton, N.J. 08628
Pipeline and
Hazardous Materials
Safety Administration
NOTICE OF PROBABLE VIOLATION
NOTICE OF PROBABLE CIVIL PENALTY
AND
NOTICE OF PROPOSED COMPLIANCE ORDER
CERTIFIED MAIL - RETURN RECEIPT REQUESTED
June 26, 2009
Mr. Lawrence Shelton
Vice President, Field Operations
Buckeye Partners, L.P.
5 TEK Park
9999 Hamilton Blvd
Breinigsville, PA 18031
CPF 1-2009-5002
Dear Mr. Shelton:
From May to December 2008, representatives of the Pipeline and Hazardous Materials Safety
Administration (PHMSA) and the New York Public Service Commission pursuant to Chapter
601 of 49 United States Code inspected Buckeye Partners, L.P. (BPL)’s procedures and
records for Operations and Maintenance, Operator Qualification, and Integrity Management at
BPL’s Headquarters office, and field inspection of pipeline facilities in the states of
Pennsylvania, Ohio, Illinois, Michigan and Colorado.
As a result of the inspection, it appears that BPL has committed probable violations of the
Pipeline Safety Regulations, Title 49, Code of Federal Regulations. The probable violations
are:



1. § 195.401 General requirements.
(b) Whenever an operator discovers any condition that could adversely
affect the safe operation of its pipeline system, it shall correct it within a
reasonable time. However, if the condition is of such a nature that it
presents an immediate hazard to persons or property, the operator may not
operate the affected part of the system until it has corrected the unsafe
condition….
The inspection team discovered that 1) a block of wood was being used as support for a
control valve in the Greensburg Station; 2) a support device at the tank farm in Toledo,
Ohio was installed on the 16-inch manifold where pipe modifications had been made, but
no associated concrete foundation was present under the pipe support; 3) at the Malvern
Station, the pipeline was found to be in contact with a cutoff section of pipe near a line
tank; and 4) at the Greensburg Station, the pipeline was found to be in non-intentional
contact with a concrete block at the pig receiver. Buckeye failed to correct these adverse
conditions within a reasonable time, as required by the regulation.
2. §195.402 Procedural manual for operations, maintenance, and emergencies.
(a) General. Each operator shall prepare and follow for each pipeline
system a manual of written procedures for conducting normal operations
and maintenance activities and handling abnormal operations and
emergencies. This manual shall be reviewed at intervals not exceeding 15
months, but at least once each calendar year, and appropriate changes
made as necessary to insure that the manual is effective. This manual shall
be prepared before initial operations of a pipeline system commence, and
appropriate parts shall be kept at locations where operations and
maintenance activities are conducted....
At the time of the inspection, BPL could not demonstrate that required reviews of the
operations, maintenance, and emergency manuals had been performed once per calendar year
at intervals not exceeding 15 months.
3. §195.402 Procedural manual for operations, maintenance, and emergencies.
(a) General. Each operator shall prepare and follow for each pipeline
system a manual of written procedures for conducting normal operations
and maintenance activities and handling abnormal operations and
emergencies. This manual shall be reviewed at intervals not exceeding 15
months, but at least once each calendar year, and appropriate changes
made as necessary to insure that the manual is effective…
BPL failed to follow its O&M procedures which require a root cause analysis for accident
reports. The PHMSA inspection team identified 25 accident reports that did not include a root
cause analysis as required by company procedures.
2



4. §195.403 Emergency Response Training.
(a) Each operator shall establish and conduct a continuing training
program to instruct emergency response personnel…
(b) At the intervals not exceeding 15 months, but at least once each
calendar year, each operator shall:
(1) Review with personnel their performance in meeting the objectives of
the emergency response training program set forth in paragraph (a) of this
section; and
(2) Make appropriate changes to the emergency response training program
as necessary to ensure that it is effective….
At the time of the inspection, BPL could not demonstrate that the company had reviewed the
performance of personnel during emergencies at the required intervals.
5. §195.412 Inspection of rights-of-way and crossing under navigable
waters.
(a) Each operator shall, at intervals not exceeding 3 weeks, but at least 26
times each calendar year, inspect the surface conditions on or adjacent to
each pipeline right-of-way. Methods of inspection include walking, driving,
flying or other appropriate mean of traversing the right-of-way….
BPL uses aerial patrols to inspect surface conditions. However, at the time of the inspection,
excessive vegetation and overgrowth was found at 1) the Perryville Station, PA;
2) near stations 814+59, 1290+71 and 128+60 on the Laurel pipeline, in PA; and 3) and near
Strawberry Mansion (station 1049+72) in PA. Therefore, detrimental conditions or leaks could
not be adequately observed by aerial patrols due to the overgrowth.
6. § 195.557 Which pipelines must have coating for external corrosion control?
Except bottoms of aboveground breakout tanks, each buried or submerged
pipeline must have an external coating for external corrosion control if the
pipeline is—
(a) Constructed, relocated, replaced, or otherwise changed after the applicable
date in §195.401(c), not including the movement of pipe covered by §195.424….
At the time of the inspection, soil-to-air interface on the 301 Line pump discharge pipe and two
sample lines at the BPL Toledo Station in Ohio were not coated as required by the regulation.
7. § 195.583 What must I do to monitor atmospheric corrosion control?
(a) You must inspect each pipeline or portion of pipeline that is exposed to the
atmosphere for evidence of atmospheric corrosion, as follows:
3



If the pipeline
is
located: Then the frequency of inspection is:
Onshore At least once every 3 calendar years, but with intervals not exceeding 39
months.
Offshore At least once each calendar year, but with intervals not exceeding 15
months.
BPL records indicated that atmospheric corrosion control inspection for the above ground
piping of Mantua Station exceeded the required intervals. Inspections were conducted on
5/4/2004 and 1/29/2008 which exceeded the 39 months interval.
8. § 195.573 What must I do to monitor external corrosion control?
(c) Rectifiers and other devices. You must electrically check for proper
performance each device in the first column at the frequency stated in the second
column.
Device Check frequency
Rectifier
Reverse current switch.
Diode.
Interference bond whose failure
Would jeopardize structural
protection.
At least six times each
calendar year, but with
intervals not exceeding 2
1/2 months.
Other interference bond At least once each
calendar year, but with
intervals not exceeding 15
months.
BPL failed to check multiple rectifiers at the required frequencies to ensure proper
performance. Specifically, a review of the BPL Rectifier Output History Report for 1/1/2006
to 5/1/2008 indicated that inspection intervals for the Harristown Shell system exceeded the 2-
1/2 month maximum interval between May and September 2006) by approximately 1-1/2
months for three rectifiers.
A review of the Rectifier Output History Report for 1/1/2006 to 5/1/2008 demonstrates that
rectifiers (No.1, No.2, No.3, PM-0.01) in the BPL Trans PA, Malvern Station Tank farm,
Paulsboro Deep Well, and Chester Park were not checked at least six times in the 2006 - 2007
calendar period.
4



A review of the Rectifier Output History Report for 1/1/2006 to 5/1/2008 indicated that
inspections for the Booth Rectifier LP-07 for Tank #15 exceeded the maximum 2-1/2 month
interval between 03/05/2006 to 05/26/2006.
A review of the Rectifier Output History Report for 1/1/2006 to 5/1/2008 indicated that BPL
did not inspect the rectifier at Booth LP-08 STA40009 BH724SK between 9/5/2006 and
1/12/2007, exceeding the maximum 2 ½ month interval.
9. § 195.571 What criteria must I use to determine the adequacy of cathodic
protection?
Cathodic protection required by this subpart must comply with one or more of the
applicable criteria and other considerations for cathodic protection contained in
paragraphs 6.2 and 6.3 of NACE Standard RP 0169 (incorporated by reference,
see §195.3).
BPL could not demonstrate that the cathodic protection for the facilities at the Philadelphia, PA
airport complied with the applicable criteria. According to BPL’s representative, the company
does not know if there are adequate levels of cathodic protection for BPL facilities at the
Philadelphia, PA Airport apparently due to access limitations. BPL has not taken any pipe-to-
soil readings since October 2006.
10. § 195.573 What must I do to monitor external corrosion control?
(e) Corrective action. You must correct any identified deficiency in corrosion
control as required by §195.401(b). However, if the deficiency involves a pipeline
in an integrity management program under §195.452, you must correct the
deficiency as required by §195.452(h).
BPL did not correct identified corrosion control deficiencies within a reasonable time period,
as required by the regulation. A review of Test Point Survey Reports, for 920 NGL, identified
inadequate levels of cathodic protection. Specifically, the CP survey at the test point location
I-70 XING South, for 920 NGL, indicated inadequate levels of CP in the 2006 and 2007 annual
surveys but were not corrected until February 2008.
11. § 195.573 What must I do to monitor external corrosion control?
(e) Corrective action. You must correct any identified deficiency in corrosion
control as required by §195.401(b). However, if the deficiency involves a pipeline
in an integrity management program under §195.452, you must correct the
deficiency as required by §195.452(h).
The inspection team’s review of the BPL work orders demonstrated that several locations with
low CP readings were not corrected by the next inspection cycle. Under §195.401(b), BPL
was required to correct the deficiency within a reasonable time. Although BPL had an
5



obligation to correct the deficiency within the time period set in the regulation, the company
records reflected that the work at the twelve locations was scheduled to start between years
2005-2007 and yet had not been completed by the time the PHMSA inspection occurred.
12. § 195.438 Smoking or open flames.
Each operator shall prohibit smoking and open flames in each pump station area
and each breakout tank area where there is a possibility of the leakage of a
flammable hazardous liquid or of the presence of flammable vapors.
BPL did not prohibit smoking and open flames in the designated areas. Buckeye could have
posted signs identifying potential hazards and prohibiting smoking and open flames. During
the field inspection, it was noted that the National Fire Protection Association (NFPA)
hazardous diamond placards, indicating that the tanks contain flammable liquid and vapors,
were not posted on tanks at the Chelsea or the Booth facilities in PA. It was also noted that
“No Smoking” signs were not posted at the entrance to tank dikes at Booth Station. Although
some of the Booth area tanks were marked as a “No Smoking” area, others were not
appropriately marked.
13. §195.402 Procedural manual for operations, maintenance, and emergencies.
(a) General. Each operator shall prepare and follow for each pipeline system a
manual of written procedures for conducting normal operations and maintenance
activities and handling abnormal operations and emergencies. This manual shall
be reviewed at intervals not exceeding 15 months, but at least once each calendar
year, and appropriate changes made as necessary to insure that the manual is
effective. This manual shall be prepared before initial operations of a pipeline
system commence, and appropriate parts shall be kept at locations where
operations and maintenance activities are conducted….
On March 22, 2005, on BPL’s 209 Line in Wayne, Michigan, personnel failed to follow
Buckeye’s repair procedures for dents. Per Buckeye’s procedure MA E-08 and associated
Exhibit H, all “sharp” dents shall be repaired using a sleeve. However, the dent at Sta. 913+96
was not repaired using a sleeve.
On June 1, 2005, BPL’s personnel failed to repair a wrinkle bend in conformance with
Buckeye’s repair procedures. At the listed MOP of 1233 psig, the wrinkle bend would require
repair per Procedure MA E-08, MA E-08 Exhibit I. Instead, Buckeye’s management decided
that since the line does not normally operate above 900 psig, no repair was necessary.
However, Buckeye did not re-establish the MOP of the line to the lower 900 psig. BPL did not
initiate an engineering evaluation of the wrinkle bend until 2008, after the issue was brought to
BPL’s attention during the PHMSA inspection.
14. §195.452 (j) What is a continual process of evaluation and assessment to maintain
a pipeline's integrity?
6



(2) Evaluation. An operator must conduct a periodic evaluation as frequently as
needed to assure pipeline integrity. An operator must base the frequency of
evaluation on risk factors specific to its pipeline, including the factors specified in
paragraph (e) of this section. The evaluation must consider the results of the
baseline and periodic integrity assessments, information analysis (paragraph (g) of
this section), and decisions about remediation, and preventive and mitigative
actions (paragraphs (h) and (i) of this section).
At the time of inspection, BPL could not demonstrate that periodic evaluations of the pipeline
integrity program were performed as required by the integrity management regulations. The
BPL Integrity Management Plan manages approximately 3,558 miles of HCA piping.
15. §195.452(b) What program and practices must operators use to manage pipeline
integrity? Each operator of a pipeline covered by this section must:
(2) Include in the program an identification of each pipeline or pipeline segment
in the first column of the following table not later than the date in the second
column:
------------------------------------------------------------------------
Pipeline Date
------------------------------------------------------------------------
Category 1................................ December 31, 2001.
Category 2................................ November 18, 2002.
Category 3................................ Date the pipeline begins
operation.
------------------------------------------------------------------------
At the time of inspection, BPL failed to identify in its Baseline Assessment Plan idle pipelines
intersecting with HCAs. BPL’s identification of facilities that could affect HCAs was to be
completed by Dec. 31, 2001, per the regulation. Identification of idle pipelines is necessary to
consider risks which could affect an HCA.
16. §195.452(b) What program and practices must operators use to manage pipeline
integrity? Each operator of a pipeline covered by this section must:
(2) Include in the program an identification of each pipeline or pipeline segment
in the first column of the following table not later than the date in the second
column:
------------------------------------------------------------------------
Pipeline Date
7



------------------------------------------------------------------------
Category 1................................ December 31, 2001.
Category 2................................ November 18, 2002.
Category 3................................ Date the pipeline begins
operation.
------------------------------------------------------------------------
Buckeye did not identify all facilities affecting HCAs. Buckeye did not consider the
contribution of tank volumes from tank farms to overland spread, nor was an overland spread
analysis performed at facilities greater than ¼ mile from HCAs. After identification of this
issue by the PHMSA inspection team in 2008, Buckeye subsequently identified 6 additional
facilities with the potential to affect HCAs using overland spread analysis.
17. §195.452(f) What are the elements of an integrity management program? An
integrity management program begins with the initial framework. An operator
must continually change the program to reflect operating experience, conclusions
drawn from results of the integrity assessments, and other maintenance and
surveillance data, and evaluation of consequences of a failure on the high
consequence area. An operator must include, at minimum, each of the following
elements in its written integrity management program:
(6) Identification of preventive and mitigative measures to protect the high
consequence area (see paragraph (i) of this section);
Buckeye failed to include a process to identify potential preventive and mitigative actions in its
written integrity management program. Buckeye operates 5,576 miles of pipe of which 3,558
miles could affect an HCA. Therefore, it is particularly important for Buckeye to consider and
identify preventive and mitigative measures to provide further protection to these areas.
18. §195.452(i) What preventive and mitigative measures must an operator take to
protect the high consequence area?
(2) Risk analysis criteria. In identifying the need for additional preventive and
mitigative measures, an operator must evaluate the likelihood of a pipeline release
occurring and how a release could affect the high consequence area. This
determination must consider all relevant risk factors, including, but not limited to:
(i) Terrain surrounding the pipeline segment, including drainage systems such as
small streams and other smaller waterways that could act as a conduit to the high
consequence area;
(ii) Elevation profile;
(iii) Characteristics of the product transported;
(iv) Amount of product that could be released;
(v) Possibility of a spillage in a farm field following the drain tile into a waterway;
(vi) Ditches along side a roadway the pipeline crosses;
(vii) Physical support of the pipeline segment such as by a cable suspension
bridge;
8



(viii) Exposure of the pipeline to operating pressure exceeding established
maximum operating pressure….
Buckeye failed to evaluate the likelihood of a pipeline release occurring and how such an event
could affect the HCAs in order to determine the need for additional preventive and mitigative
measures. This determination must consider all relevant risk factors including but not limited
to the criteria listed in §195.452(i)(2)(i)-(viii). Buckeye failed to assess these risk factors.
19. §195.452(i) What preventive and mitigative measures must an operator take to
protect the high consequence area?
(4) Emergency Flow Restricting Devices (EFRD). If an operator determines that
an EFRD is needed on a pipeline segment to protect a high consequence area in
the event of a hazardous liquid pipeline release, an operator must install the
EFRD. In making this determination, an operator must, at least, consider the
following factors–the swiftness of leak detection and pipeline shutdown
capabilities, the type of commodity carried, the rate of potential leakage, the
volume that can be released, topography or pipeline profile, the potential for
ignition, proximity to power sources, location of nearest response personnel,
specific terrain between the pipeline segment and the high consequence area, and
benefits expected by reducing the spill size.
At the time of inspection, Buckeye had not performed EFRD evaluations since 2005. BPL’s
Integrity Management Plan, Section 15, issued 12/2005, requires annual review of pipelines
scheduled for integrity assessment during that year to determine whether impact to an HCA
can be mitigated by adding an EFRD. Buckeye also did not have a technical justification
explaining why the EFRDs recommended in 2002 had not been installed.
20. §195.452 (f) What are the elements of an integrity management program? An
integrity management program begins with the initial framework. An operator
must continually change the program to reflect operating experience, conclusions
drawn from results of the integrity assessments, and other maintenance and
surveillance data, and evaluation of consequences of a failure on the high
consequence area. An operator must include, at minimum, each of the following
elements in its written integrity management program:
(3) An analysis that integrates all available information about the integrity of the
entire pipeline and the consequences of a failure (see paragraph (g) of this section)
Buckeye did not change its integrity management program to reflect relevant operating
experience. In May 2005, Buckeye’s Risk Management Team determined that the risk analysis
program did not provide the necessary insight for the risks associated with the analyzed
pipeline segments. However, actions to improve the risk analysis model were not initiated
until 2008.
21. § 195.561 When must I inspect pipe coating used for external corrosion control?
9



(a) You must inspect all external pipe coating required by § 195.557 just prior to
lowering the pipe into the ditch or submerging the pipe.
(b) You must repair any coating damage discovered.
Buckeye did not properly repair coating damage when inspecting pipe coating. During the
NORCO pipe replacement project in 2008, PHMSA staff observed that Buckeye's contractor
personnel were improperly applying patchstick repairs to fusion bonded epoxy coating. In lieu
of having BPL procedures in place, personnel were not properly following the manufacturer's
instructions.
22.
§ 195.406 Maximum operating pressure.
(b) No operator may permit the pressure in a pipeline during surges or other
variations from normal operations to exceed 110 percent of the operating pressure
limit established under paragraph (a) of this section. Each operator must provide
adequate controls and protective equipment to control the pressure within this
limit.
According to BPL's Abnormal Operating Condition (AOC) forms, BPL exceeded 110 percent
of the operating pressure limit established in §195.406(a) on three separate occasions. The
AOC forms dated May 11, 2006, November 5, 2007, and June 3, 2007 document the three
events.
Proposed Civil Penalty
Under 49 United States Code, § 60122, you are subject to a civil penalty not to exceed
$100,000 for each violation for each day the violation persists up to a maximum of $1,000,000
for any related series of violations. The Compliance Officer has reviewed the circumstances
and supporting documentation involved in the above probable violation(s) and has
recommended that you be preliminarily assessed a civil penalty of $645,200 as follows:
Item number
PENALTY
#3
$
41,500
#4
$
29,000
#7
$
#8
14,000
$
14,000
#9
$
35,300
#11
$
29,000
#13
$
41,500
#14
$
120,300
#17
$
200,300
#19
$
120,300
10



Warning Items
With respect to item #1, #2, #5, #6, #10, #12, #15, #16, #18, #20, #21, and #22 we have
reviewed the circumstances and supporting documents involved in this case and have decided
not to conduct additional enforcement action or penalty assessment proceedings at this time.
We advise you to promptly correct these items. Be advised that failure to do so may result in
Buckeye Partners, L.P. being subject to additional enforcement action.
Proposed Compliance Order
With respect to items #3, #9, #17, #19, pursuant to 49 United States Code § 60118, the Pipeline
and Hazardous Materials Safety Administration proposes to issue a Compliance Order to
Buckeye Partners, L.P. Please refer to the Proposed Compliance Order, which is enclosed and
made a part of this Notice.
Response to this Notice
Enclosed as part of this Notice is a document entitled Response Options for Pipeline Operators
in Compliance Proceedings. Please refer to this document and note the response options. Be
advised that all material you submit in response to this enforcement action is subject to being
made publicly available. If you believe that any portion of your responsive material qualifies
for confidential treatment under 5 U.S.C. 552(b), along with the complete original document
you must provide a second copy of the document with the portions you believe qualify for
confidential treatment redacted and an explanation of why you believe the redacted
information qualifies for confidential treatment under 5 U.S.C. 552(b). If you do not respond
within 30 days of receipt of this Notice, this constitutes a waiver of your right to contest the
allegations in this Notice and authorizes the Associate Administrator for Pipeline Safety to find
facts as alleged in this Notice without further notice to you and to issue a Final Order.
In your correspondence on this matter, please refer to CPF 1-2009-5002 and for each
document you submit, please provide a copy in electronic format whenever possible.
Sincerely,
Byron E. Coy, P.E.
Director, Eastern Region
Pipeline and Hazardous Materials Safety Administration
Enclosures: Proposed Compliance Order
Response Options for Pipeline Operators in Compliance Proceedings
11



PROPOSED COMPLIANCE ORDER
Pursuant to 49 United States Code § 60118, the Pipeline and Hazardous Materials Safety
Administration (PHMSA) proposes to issue to Buckeye Partners, L.P. a Compliance Order
incorporating the following remedial requirements to ensure the compliance of Buckeye
Partners, L.P.(BPL) with the pipeline safety regulations:
1. In regard to Item Number 3 of the Notice pertaining to the numerous accident
reports that did not include documentation of the required root cause analysis (from
BPL’s Operations and Maintenance (O&M) Manual). BPL shall develop a plan to
ensure that a root cause analysis is conducted and documented for all accidents that
occur as required by BPL’s O&M Manual, and that recommended corrective
action(s) from the root cause analysis is implemented.
2. In regard to Item Number 9 of the Notice, BPL must establish and implement a plan
to correct access problems to BPL cathodic protection test point facilities at the
Philadelphia, PA airport area. Any outstanding remedial problems with those test
points must also be included in the plan.
3. In regard to Item Number 17 of the Notice, BPL must establish and implement
processes to evaluate their pipeline segments for additional preventive and
mitigative actions. Upon completion of the evaluation of pipeline segments, a
schedule for implementing additional preventive and mitigative measures must be
submitted.
4. In regard to Item Number 19 of the Notice, BPL must establish an improved
process to evaluate the need for additional EFRDs. Upon establishment of the
improved process, BPL must perform EFRD evaluations on its pipeline segments
and develop a schedule for installing EFRDs where necessary and document the
logic where EFRDs are not necessary for all locations BPL considered.
5. BPL shall submit a plan and schedule for completing the Proposed Compliance
Order Items above to PHMSA for review and approval within 60 days after receipt
of the Final Order. Upon receiving approval of the plan and schedule, BPL shall
submit evidence of completion for the Proposed Compliance Order Items above to
PHMSA within 180 days after receipt of the Final Order. Submit all correspondence
for review and approval to Mr. Byron Coy Director, Eastern Region, Office of
Pipeline Safety, Pipeline and Hazardous Materials Safety Administration, 409 3rd
Street, S.W., Washington, DC 20024.
6. BPL shall maintain documentation of the safety improvement costs associated with
fulfilling this Compliance Order and submit the total to Mr. Byron Coy, Director,
Eastern, Pipeline and Hazardous Materials Safety Administration. Costs shall be
reported in two categories: 1) total cost associated with preparation/revision of
plans, procedures, studies and analyses, and 2) total cost associated with
replacements, additions and other changes to pipeline infrastructure.
12

120095002_Closure Letter_06172013_text.pdf

U.S. Department Of Transportation Pipeline and 609.989.2171
Hazardous Materials
Safety Administration
820 Bear Tavern Road, Suite 103
West Trenton, NJ 08628
OVERNIGHT EXPRESS MAIL
June 17, 2013
Mr. Thomas S. Collier,
VP Performance Assurance & Asset Integrity
Buckeye Partners, L.P.
Five TEK Park
9999 Hamilton Boulevard
Breinigsville, PA 18031
CPF 1-2009-5002
Dear Mr. Collier:
On May 30, 2012, the Pipeline and Hazardous Materials Safety Administration (PHMSA) issued
to Buckeye Partners, L.P. a Final Order in the above-referenced case. This Order included a
Compliance Order and Civil Penalty assessment. Based on our review of the documentation you
provided, and confirmation of payment of the civil penalty, it has been determined that you have
complied with the terms of this Order.
Accordingly, this case is now closed and no further action is contemplated with respect to the
matters involved in this case. Thank you for your cooperation in this matter.
Sincerely,
Byron Coy, PE
Director, Eastern Region
Pipeline and Hazardous Materials Safety Administration

120095002_Final Order _05302012.pdf

U.S. Department
1200 New Jersey Avenue SE
of Transportation
Washington. DC 20590
Materials Safety
Pipeline and Hazardous
Administration
MAY 3 0 2012
Mr. Clark Smith
President and CEO
Buckeye Partners, LP
One Greenway Plaza, Suite 600
Houston, TX 77046
Re: CPF No. 1-2009-5002
Dear Mr. Smith:
Enclosed please find the Final Order issued in the above-referenced case. It withdraws one of
the allegations of violation, makes other findings of violation, assesses a civil penalty of
$524,900, and specifies actions that need to be taken by Buckeye Partners, LP, to comply with
the pipeline safety regulations. The penalty payment terms are set forth in the Final Order.
When the civil penalty has been paid and the terms of the compliance order completed, as
determined by the Director, Eastern Region, this enforcement action will be closed. Service of
the Final Order by certified mail is deemed effective upon the date of mailing, or as otherwise
provided under 49 C.F.R. § 190.5.
Thank you for your cooperation in this matter.
Sincerely,
/
Jeffrey D. Wiese
Associate Administrator
for Pipeline Safety
Enclosure
Cc:
Mr. Byron Coy, PE, Director, Eastern Region, OPS
Mr. Alan Mayberry, Deputy Associate Administrator for Field Operations, OPS
Ir. Scott Collier, Vice President, Buckeye Partners, LI
TEK Park, 9999 Hamilton Boulevard. Breiniasville PA 1803
CERTIFIED MAIL - RETURN RECEIPT REQUESTED



U.S. DEPARTMENT OF TRANSPORTATION
PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION
OFFICE OF PIPELINE SAFETY
WASHINGTON, D.C. 20590
In the Matter of
Buckeye Partners, LP,
CPF No. 1-2009-5002
Respondent.
FINAL ORDER
During the period from May to December, 2008, pursuant to 49 U.S.C. § 60117, representatives
of the Pipeline and Hazardous Materials Safety Administration (PHMSA), Office of Pipeline
Safety (OPS), and the New York Public Service Commission conducted on-site pipeline safety
inspections of the facilities and records of Buckeye Partners, LP (BPL or Respondent), in several
states, including Pennsylvania, Ohio and Michigan. BPL owns and operates approximately
6,000 miles of pipelines transporting refined petroleum products and highly volatile liquids,
principally in the Northeastern and upper Midwestern states.' Approximately 3,558 of those
pipeline miles are in or could affect High Consequence Areas (HCAs) and are covered by
BPL's integrity management program.
As a result of the inspection, the Director, Eastern Region, PHMSA (Director), issued to
Respondent, by letter dated June 26, 2009, a Notice of Probable Violation, Proposed Civil
Penalty, and Proposed Compliance Order (Notice). In accordance with 49 C.F.R. § 190.207, the
Notice proposed finding that BPL had committed various violations of 49 C.F.R. Part 195,
assessing a civil penalty of $645,200 for the alleged violations, and ordering Respondent to take
certain measures to correct the alleged violations. The Notice also proposed finding that
Respondent had committed other probable violations of 49 C.F.R. Part 195 and warning the
company to take appropriate corrective action or be subject to future enforcement action.
BPL responded to the Notice by letters dated September 25, 2009 (Response), and
January 6, 2010 (Supplemental Response). The company contested some of the allegations of
violation and requested reduction or elimination of the associated penalties. BPL did not contest
other allegations and provided information concerning the corrective actions it had taken.
Respondent did not request a hearing and therefore has waived its right to one.
'http://www.buckeye.com/BusinessOperations/tabid/56/Default.aspx and
http://www.buckeye.com/AboutUs/tabid/54/Default.aspx (last accessed on March 22, 2012).
= 49 C.F.R. $ 195.450.
* 19 C.F.R. $ 195.452.



2
FINDINGS OF VIOLATION
The Notice alleged that Respondent violated 49 C.F.R. Part 195, as follows:
Operations and Maintenance Items:
Item 3: The Notice alleged that Respondent violated 49 C.F.R. § 195.402(a), which states in
relevant part:
$ 195.402 Procedural manual for operations, maintenance, and
(a) General. Each operator shall prepare and follow for each pipeline
emergencies.
system a manual of written procedures for conducting normal operations
and maintenance activities and handling abnormal operations anc
emergencies. This manual shall be reviewed at intervals not exceeding 15
months, but at least once each calendar year, and appropriate changes
made as necessary to insure that the manual is effective....
The Notice alleged that BPL violated 49 C.F.R. § 195.402(a) by failing to follow its manual of
written procedures for conducting normal operations and maintenance (O&M) activities and
handling abnormal operations and emergencies. Specifically, it alleged that BPL had failed to
conduct root-cause analyses in 25 accident reports, as required by its own O&M procedures.
The BPL Safety Manual, Section A-04, required that a root cause analysis be conducted for each
product release that required regulatory reporting.
In its Response, BPL did not contest the allegation of violation but contended that in August
positions was to conduct root cause analyses for accidents. BPL also stated that the 25 accident
2006, it had created six new positions within the company and that one of the duties of these new
positions.® BPL stated that it had "recognized that there was a need to ensure that root cause
reports which lacked a root cause analysis had all been performed before the creation of the new
that the penalty associated with this Item be "rescinded."" Since this argument relates to a
analyses were conducted... almost two years prior to the integrated inspection" and requested
potential reduction in the amount of the penalty, it is discussed in the "Assessment of Penalty"
section below.
Accordingly, based upon a review of all of the evidence, I find that Respondent violated
49 C.F.R. $ 195.402(a) by failing to follow its manual of written procedures for conducting
normal O&M activities and handling abnormal operations and emergencies.
Item 4: The Notice alleged that Respondent violated 49 C.F.R. § 195.403(b), which states:
* Pipeline Safety Violation Report (Violation Report), Exhibit A (on file with PHMSA).
" Response at 2.
" Id.
1 Id.



3
$ 195.403 Emergency response training.
(a) Each operator shall establish and conduct a continuing training
program to instruct emergency response personnel...
(b) At the intervals not exceeding 15 months, but at least once each
calendar year, each operator shall:
(1) Review with personnel their performance in meeting the
objectives of the emergency response training program set forth in
paragraph (a) of this section; and
(2) Make appropriate changes to the emergency response training
program as necessary to ensure that it is effective.
The Notice alleged that BPL violated 49 C.F.R. § 195.403(b) by failing to review with company
personnel their performance in meeting the objectives of the company's emergency response
training program, at intervals not exceeding 15 months but at least once each calendar year.
In its Response, BPL did not explicitly contest the allegation but argued that it had reviewed the
performance of its employees in responding to emergencies through the use of a form which had
been "approved by the government" and which had documented personnel "responses and follow
up actions to emergencies."* The company further explained that its Training Manual called for
a critique of employee responses after all emergencies and response drills but acknowledged that
it did not "specifically document the review of the performance of its employees on the form."
Notwithstanding these existing procedures, BPL indicated that it had revised the form to include
a check box to document specifically that the performance of company personnel had been
reviewed. The company provided OPS with a blank copy of the revised form.?
While BPL indicated that the form had been approved by the government, there is no indication
that the form had ever been approved by PHMSA for purposes of satisfying this regulatory
requirement. In addition, BPL did not provide any completed forms to demonstrate that the
required reviews had actually been conducted. Therefore, it is impossible to tell whether the
reviews were properly completed in a timely manner.
Accordingly, after considering all of the evidence, I find that Respondent violated
49 C.F.R. $ 195.403(b) by failing to review with company personnel, at the required intervals.
their performance in meeting the objectives of BPL's emergency response training program.
Item 13: The Notice alleged that Respondent violated 49 C.F.R. § 195.402(a), as quoted above,
by failing to follow its manual of written procedures for conducting normal O&M activities and
handling abnormal operations and emergencies. Specifically, it alleged that BPL failed to follow
its Maintenance Manual, Procedure E-08, Damaged or Defective Non-Leaking Pipe, on two
occasions. On March 22, 2005, the company allegedly failed to repair a sharp dent at Sta.
913+96 on its 209 Line in Wayne, Michigan, using a sleeve required by its own written
procedures. Similarly, the Notice alleged that on June 1, 2005, the company allegedly failed to
repair a wrinkle bend in accordance with BPL's own written procedures.
8 Response at 3.
• Id.
10 Violation Report, Exhibit B.



4
According to the Notice, BPL's procedures stated that at the pipeline's listed Maximum
Operating Pressure (MOP) of 1233 psig, the wrinkle bend had to be repaired in accordance with
the company's Procedure MA E-08, Exhibit I. The company allegedly decided, however, that
no repair was needed for the wrinkle bend because the line did not normally operate at over 900
psig. However, BPL did not subsequently lower the MOP on the line to 900 psig.
BPL did not contest the alleged violations. The company acknowledged that in August 2009, it
had excavated and re-evaluated the sharp dent in the 209 line and had installed a repair sleeve."
As for the wrinkle bend, the company stated that it was in the process of conducting an
engineering evaluation to determine the appropriate MOP for this line segment.' Accordingly,
based upon a review of all of the evidence, I find that Respondent violated
49 C.F.R. § 195.402(a) by failing to follow its manual of written procedures for conducting
normal O&M activities and handling abnormal operations and emergencies.
Corrosion Control Items
Item 7: The Notice alleged that Respondent violated 49 C.F.R. § 195.583(a), which states:
§ 195.583 What must I do to monitor atmospheric corrosion control?
(a) You must inspect each pipeline or portion of pipeline that is
exposed to the atmosphere for evidence of atmospheric corrosion, as
follows:
If the pipeline is
located:
Then the frequency of inspection is:
Onshore..
At least once every 3 calendar years, but with
intervals not exceeding 39 months.
Offshore...
At least once each calendar year, but with
intervals not exceeding 15 months.
The Notice alleged that BPL violated 49 C.F.R. § 195.583(a) by failing to inspect the above-
ground pipeline facilities at the company's Mantua Station for atmospheric corrosion at least
once every three calendar years, but at intervals not exceeding 39 months. Specifically, it
alleged that BPL's own records showed inspections had been conducted on May 4, 2004, and
January 29, 2008, an interval that exceeded 39 months.
BPL did not contest this allegation. Accordingly, after considering all of the evidence, I find that
ipeline exposed to the atmosphere for atmospheric corrosion. It is noted that BPL represent
respondent violated 49 C.F.K. § 195.583(a) by failing to inspect, at the required intervals, eac
that it has improved its process for conducting such inspections.
" Response at 6.
12 Id.



5
Item 8: The Notice alleged that Respondent violated 49 C.F.R. § 195.573(c), which states:
§ 195.573 What must I do to monitor external corrosion control?
(c) Rectifiers and other devices. You must electrically check for
proper performance each device in the first column at the frequency stated
in the second column.
Device
Check frequency
Rectifier..........
At least six times each calendar year,
but with intervals not exceeding 2½
Reverse current switch.
months.
Diode.
Interference bond whose
failure would jeopardize
structural protection.
Other interference bond......
At least once each calendar year, but
with intervals not exceeding 15
months.
The Notice alleged that BPL violated 49 C.F.R. § 195.573(c) by failing to electrically check
several rectifiers for proper performance at the required frequency. Specifically, it alleged the
following failures:
1. Three rectifiers in the Harristown Shell system were not inspected at the required
intervals twice during 2006, each time exceeding the 2½-month maximum by 1½
months;
2. The rectifiers in the BPL Trans PA, Malvern Station Tank Farm, Paulsboro Deep Well,
and Chester Park systems were not checked at least six times each year during 2006-
2007;
3. The Booth rectifier LP-07 for Tank #15 was not inspected between March 5, 2006, and
May 26, 2006, an interval that exceeded 2½ months; and
4. The Booth rectifier LP-08 STA40009 BH724SK was not inspected between
September 5, 2006, and January 12, 2007, an interval that exceeded 2½ months.
In its Response, BPL only contested the portion of the allegation relating to the rectifiers on the
Harristown Shell system. The company asserted that during the March and July inspections, the
Harristown rectifiers were out of service due to tank projects and were noted as "locked



6
out/tagged out" on the company's inspection records." BPL's rectifier output-history documents
included comments for the Harristown rectifiers for the March and July inspections. In March,
the rectifiers were noted as "Locked out - Due to cleaning tank" and in July they were listed as
"Down - Due to construction." Based on these records and BPL's explanation for them, it is
plausible that the rectifiers were out of service during these inspections.
To remain in compliance with the regulation, however, BPL was obliged to check the rectifiers
before they were put back into service. The company failed to inspect them until the next
scheduled inspection two months later, resulting in a four-month interval between inspections.
BPL stated that it had subsequently revised its procedures to require that rectifiers be checked
both prior to and after being locked out and that the company had added a field in its work order
system to show when an inspection would be out of compliance with § 195.573(c). '4
Accordingly, after considering all of the evidence, I find that Respondent violated
49 C.F.R. § 195.573(c) by failing to check several rectifiers for proper performance within the
required intervals.
Item 9: The Notice alleged that Respondent violated 49 C.F.R. § 195.571, which states:
§ 195.571 What criteria must I use to determine the adequacy of
cathodic protection?
Cathodic protection required by [Subpart H] must comply with one or
more of the applicable criteria and other considerations for cathodic
protection contained in paragraphs 6.2 and 6.3 of NACE SP 0169
(incorporated by reference, see § 195.3).
The Notice alleged that BPL violated 49 C.F.R. § 195.571 by failing to ensure that cathodic
protection for the company's facilities at the Philadelphia Airport (Airport) complied with one or
more of the applicable criteria and other considerations for cathodic protection contained in
paragraphs 6.2 and 6.3 of NACE Standard SP 0169 (NACE Standard). Specifically, it alleged
that BPL had failed to take any pipe-to-soil readings at the Airport since October 2006 and that
therefore the adequacy of cathodic protection at these locations was unknown.
In its Response, BPL acknowledged that it did not take pipe-to-soil readings at the Airport test
test points at the Airport represented only a small fraction of the points on its entire system.'
points, but contended that it had been unable to gain access to the Airport in 2007 and that the
BPL stated that all the other test points had been tested in 2007 and that the Airport points were
accessed and tested in October 2008. The company also stated that it had now arranged a new
method for arranging security escorts at the Airport and that it had made arrangements for the
2009 inspection within the required interval.'°
1? Response at 4.
It ld.
15 Response at 4.
I Response at 4-5.



7
BPL is obligated to ensure that cathodic protection is adequate and complies with the NACE
Standard at all times. BPL's failure to gain access to the Airport does not serve to refute the
allegation of violation. Accordingly, after considering all of the evidence, I find that Respondent
violated 49 C.F.R. § 195.571 by failing to ensure that cathodic protection on its pipeline
complied with the applicable criteria and other considerations for cathodic protection contained
in the NACE Standard.
Item 11: The Notice alleged that Respondent violated 49 C.F.R. § 195.573(e), which states:
$ 195.573 What must I do to monitor external corrosion control?
(2) Corrective action. You must correct any identified deficiency in
corrosion control as required by § 195.401(b). However, if the deficiency
involves a pipeline in an integrity management program under § 195.452,
you must correct the deficiency as required by § 195.452(h).
The Notice alleged that BPL violated 49 C.F.R. § 195.573(e) by failing to correct identified
deficiencies in corrosion control, as required by § 195.401(b), which states that an operator must
correct, within a reasonable time. any deficiency that could adversely affect the safe operation of
the pipeline. Specifically, the Notice alleged that the company's own work orders showed that
several locations along the pipeline with low cathodic protection readings had been scheduled for
work between 2005 and 2007, but that the work had not been completed by the time of the
PHMSA inspections in 2008.
BPL did not contest this allegation and explained that it had improved its process for remediating
low cathodic protection readings by adding a field in its work order system to show when
proposed remediation efforts would fail to be in compliance." Accordingly, after considering all
of the evidence. I find that Respondent violated 49 C.F.R. § 195.573(e) by failing to correct
identified deficiencies in corrosion control within a reasonable time.
Integrity Management Program (IMP) Items
Item 14: The Notice alleged that Respondent violated 49 C.F.R. § 195.452(j)(2), which states:
§ 195.452 Pipeline integrity management in high consequence areas.
(a)
What is a continual process of evaluation and assessment to
maintain a pipeline's integrity?—
(1) General. After completing the baseline integrity assessment, an
operator must continue to assess the line pipe at specified intervals and
periodically evaluate the integrity of each pipeline segment that could
affect a high consequence area.
(2) Evaluation. An operator must conduct a periodic evaluation as
frequently as needed to assure pipeline integrity. An operator must base
1 Response at 5.



8
the frequency of evaluation on risk factors specific to its pipeline,
including the factors specified in paragraph (e) of this section. The
evaluation must consider the results of the baseline and periodic integrity
assessments, information analysis (paragraph (g) of this section), and
decisions about remediation, and preventive and mitigative actions
(paragraphs (h) and (i) of this section).
The Notice alleged that BPL violated 49 C.F.R. § 195.452(j)(2) by failing to conduct periodic
evaluations as frequently as needed to assure pipeline integrity. Specifically, the Notice alleged
hat "BPL could not demonstrate that periodic evaluations of the pipeline integrity program wer
ertormed as required by the integrity management regulations.
BPL contested the allegation,
and compliance with integrity regulations involves its Risk Management Team. "19 The
stating that the company's "process for periodic evaluation of the integrity of BPL's pipelines
Response broadly described the responsibilities and activities of the team, including ensuring
"[clompliance with all regulatory requirements regarding operational risk management" and a
"I clontinuous improvement process for BPL's integrity management program."20 BPL also
stated that minutes and "action items" from the team's meetings documented the company's
periodic evaluation process.
BPL did not offer any documentation or evidence of any of its integrity program evaluations. The
meeting minutes and actions items which BPL referenced in its Response were not provided, nor
did BPL demonstrate that results of any evaluations were used to make decisions about
remediation and preventive and mitigative (P&M) actions. BPL offered examples of "programs
that were recommended through the periodic evaluations" but did not offer any documentation of
the evaluations or the recommendations that they had claimed to have made."
Neither party has presented sufficient proof to prove its position, but OPS bears the burden of
proving that BPL has committed the violation. Section 195.452(j) requires continuous
evaluation and assessment of an operator's individual pipeline segments, not simply its overall
IMP. The evidence presented by OPS in the Violation Report and Notice are insufficient to
prove that Respondent's IMP failed to include periodic pipe segment evaluations under §
195.452(j). The record contains no documents, procedures, interview notes or any other
evidence to support the allegation that the company's IMP was devoid of the sort of continuous
evaluations required by the regulation. Accordingly, based upon the foregoing, I find that OPS
has failed to meet its burden of proof and hereby order that Item 14 be withdrawn.
Item 17: The Notice alleged that Respondent violated 49 C.F.R. $ 195.452(f)(6), which states:
18 Notice at 7.
1° Response at 6.
20 Id.
" Response at 7.
" Id.



§ 195.452 Pipeline integrity management in high consequence areas.
(a)
(f) What are the elements of an integrity management program? An
integrity management program begins with the initial framework. An
operator must continually change the program to reflect operating
experience, conclusions drawn from results of the integrity assessments,
and other maintenance and surveillance data, and evaluation of
consequences of a failure on the high consequence area. An operator must
include, at minimum, each of the following elements in its written
integrity management program:
(1) ...
(6) Identification of preventive and mitigative measures to protect the
high consequence area (see paragraph (i) of this section).
The Notice alleged that BPL violated 49 C.F.R. § 195.452(f)(6) by failing to include in its IMP a
process for identifying (P&M) measures to protect HCAs. Under
§ 195.452(f), an operator's IMP must contain eight separate elements, including a process for
identifying HCAs, a baseline assessment plan, an information-integration analysis, criteria for
taking remedial action, a continual process of periodic assessments of line pipe segments (see
Item 14 above), the identification of P&M measures tailored to the operator's unique system, and
methods to measure the IMP's overall effectiveness.
The Violation Report stated that the OPS inspection team had found no indication that BPL had
ever developed a process within its IMP for identifying P&M measures that would reduce the
likelihood and consequences of pipeline releases, had ever identified specific P&M measures to
protect HCAs, or had compiled any documentation to show such processes were in place. The
Violation Report also noted that BPL's integrity manager had stated that BPL would be
developing such procedures in the future.
In its Response, BPL contested the alleged violation, stating that its Integrity Management
Manual (IMM) did indeed contain a process for identifying potential P&M measures and
summarizing the process. It claimed that Section 6 of its IMM fully described the company's
process for identifying P&M measures, including the use of a Risk Model to identify high-risk
areas, the use of subject matter expert teams to develop and test "various preventive and
mitigative scenarios that potentially will provide positive impacts to reducing the identified risk,"
the selection and evaluation of "physically feasible" measures, and the implementation of those
measures having the greatest benefit in terms of risk reduction and financial feasibility?3 In
addition, the company contended that the "Exhibit A-01A flowchart in Buckeye's IMM and
referenced in Section 6 clearly shows that preventive and mitigative measures are an integral part
of the Continual Assessment Program." 24 The company, however, did not submit any of these
procedures or any other documentation in either its Response or Supplemental Response.
23
Response at 8.
24 Response at 8.



10
Such general statements do not constitute credible evidence that BPL actually had a process for
identifying P&M measures or that it had actually developed specific measures to reduce the
likelihood or consequences of failures on HCAs. Not only did BPL fail to produce
documentation of a P&M process that was in effect as of the date of the OPS inspection in May
2008, but it also failed to provide any evidence showing that any specific P&M measures had ever
been actually identified, evaluated by its subject matter expert team, or implemented by the
company•
While BPL may indeed have had some general framework of a process for identifying P&M
measures, the company failed to produce any evidence that it had implemented any such process
or that it had met the requirements of the regulation. Accordingly, based upon a review of all of
the evidence. I find that BPL violated 49 C.F.R. § 195.452(f)(6) by failing to include a process
for identifying P&M measures to protect HCAs in its written IMP.
Item 19: The Notice alleged that Respondent violated 49 C.F.R. § 195.452(i)(4), which states:
§ 195.452 Pipeline integrity management in high consequence areas.
(a)
(i) What preventive and mitigative measures must an operator take to
protect the high consequence area!-
(1) ...
(4) Emergency Flow Restricting Devices (EFRD). If an operator
determines that an EFRD is needed on a pipeline segment to protect a high
consequence area in the event of a hazardous liquid pipeline release, an
operator must install the EFRD. In making this determination, an operator
must, at least, consider the following factors-the swiftness of leak
detection and pipeline shutdown capabilities, the type of commodity
carried, the rate of potential leakage, the volume that can be released,
topography or pipeline profile, the potential for ignition, proximity to
power sources, location of nearest response personnel, specific terrain
between the pipeline segment and the high consequence area, and benefits
expected by reducing the spill size.
The Notice alleged that BPL violated 49 C.F.R. § 195.452(i)(4) by failing to determine whether
EFRDs were needed to protect against failures that could affect HAs along its pipeline and, if
so, to install them. Specifically, the Notice alleged that, since 2005, BPL had failed to conduct
annual EFRD analyses of pipeline segments scheduled for integrity re-assessments, as required
by $ 195.452(i) and Section 15 of the company's own IMM. The Notice also alleged that BPL
had failed to install certain EFRDs that had been recommended as a result of a 2002 evaluation.
In its Response, BPL noted that pipelines scheduled for integrity assessments between 2002 and
2005 had been analyzed for EFRDs and that the recommended devices had been included in
BPL's capital plan. The company claimed, however, that it had ultimately decided to allocate
funds to other risk-management projects instead.? BPL also noted that its spending on pipeline
maintenance had drastically increased since 2000 and that EFRDs were "still being considered
'5 Response at 8-9.



11
and installed when the benefits match the expenditure."' For example, it cited the example of a
block valve that had been installed as a "risk mitigation project," which showed that BPL was
"not opposed to adding EFRDs."' The company, however, did not contest the facts set out in
the allegation.
BPL's spending on other maintenance projects does not lessen the potential consequences of the
violation at hand, nor do budgetary considerations absolve BPL of its obligation to comply with
the regulation and its own IMP. Accordingly, after considering all of the evidence, I find that
Respondent violated 49 C.F.R. § 195.452(i)(4) by failing to determine whether EFRDs were
needed on its pipeline to protect against failures, and, if so, to install them.
These findings of violation will be considered prior offenses in any subsequent enforcement
action taken against Respondent.
ASSESSMENT OF PENALTY
Under 49 U.S.C. $ 60122, Respondent is subject to an administrative civil penalty not to exceed
$100,000 per violation for each day of the violation, up to a maximum of $1,000,000 for any
related series of violations. In determining the amount of a civil penalty under
49 U.S.C. § 60122 and 49 C.F.R. § 190.225, I must consider the following criteria: the nature,
circumstances, and gravity of the violation, including adverse impact on the environment; the
degree of Respondent's culpability; the history of Respondent's prior offenses; the Respondent's
ability to pay the penalty and any effect that the penalty may have on its ability to continue doing
business; and the good faith of Respondent in attempting to comply with the pipeline safety
regulations. In addition, I may consider the economic benefit gained from the violation without
any reduction because of subsequent damages, and such other matters as justice may require.
The Notice proposed a total civil penalty of $645,200 for the violations cited above.
Item 3: The Notice proposed a civil penalty of $41,500 for Respondent's violation of
49 C.F.R. § 195.402(a), for failing to follow its own manual of written procedures for conducting
normal O&M activities and handling abnormal operations and emergencies. As noted above, I
found that BPL failed to conduct root cause analyses in 25 accident reports, as required by its
O&M procedures. Respondent argued, however. that the penalty should be "rescinded" because
BPL had recognized the need to ensure root cause analyses were done, and had created a job
position for this purpose two years before the OPS inspection. I fail to see any basis for
rescission or reduction of the penalty. Recognizing a need to comply and actually complying are
two different things. Respondent's arguments do not mitigate the fact that BPL prepared 25
accident reports during 2002-2007 that did not include a root cause analysis, as required by its
own procedures.
A root cause analysis is an important tool for identifying safety problems before they cause
accidents. Presumably, this is the very reason BPL included the requirement in its O&M
manual. The gravity of the violation is not mitigated by the fact that BPL recognized the
" Response at 9.
" Id.



12
problem and made plans to correct it. On the contrary, it is troubling to see that the violation
continued for years because the company apparently did not place a high enough priority on
investigating the root causes of 25 separate accidents or complying with its own internal
procedures. BPL has not presented any evidence or argument that would justify a reduction or
elimination of the proposed penalty. Accordingly, having reviewed the record and considered
the assessment criteria, I assess Respondent a civil penalty of $41,500 for violation of
49 C.F.R. $ 195.402(a).
Item 4: The Notice proposed a civil penalty of $29,000 for Respondent's violation of
49 C.F.R. § 195.403(b), for failing to review with company personnel their performance in
meeting the objectives of BPL's emergency response training program, at intervals not
exceeding 15 months but at least once each calendar year. I found that, while Respondent used a
form to document employee responses to emergencies, it did not document such reviews on the
forms and did not provide PHMSA with copies of any completed forms to demonstrate that the
required reviews had actually been conducted.
Adequate emergency response training is essential to the safety of the public and protection of
the environment in the event of emergencies. Respondent's failure to review or document the
performance of its personnel reduced the safety of its operations insofar as the company had no
established method of regularly reviewing employee performance that was related specifically to
emergency response. Accordingly, having reviewed the record and considered the assessment
criteria. I assess Respondent a civil penalty of $29,000 for violations of 49 C.F.R. § 195.403(b).
Item 7: The Notice proposed a civil penalty of $14,000 for Respondent's violation of
49 C.F.R. § 195.583(a), for failing to inspect the above-ground pipeline facilities at the Mantua
Station for atmospheric corrosion at least once every three calendar years, but at intervals not
exceeding 39 months. BPL neither contested the allegation nor presented any evidence or
argument justifying a reduction in the proposed penalty; therefore, I found that Respondent failed
to inspect each pipeline exposed to the atmosphere for atmospheric corrosion at the required
intervals. Atmospheric corrosion at the Mantua Station could result in a release of hazardous
liquids, thus posing a risk to life, property and the environment. Accordingly, having reviewed
the record and considered the assessment criteria, I assess Respondent a civil penalty of $14,000
for violation of 49 C.F.R. § 195.583(a).
Item 8: The Notice proposed a civil penalty of $14,000 for Respondent's violation of
49 C.F.R. § 195.573(c), for failing to check several rectifiers for proper performance at the
required frequency. Respondent contested the allegations relating to the Harristown Shell
system but not the others. As discussed above, I found that Respondent was required to check
the locked-out rectifiers before putting them back into service. The proposed penalty amount
reflects the fact that neither pipeline integrity nor safe operations were seriously affected by the
violations. Based upon the foregoing, I assess Respondent a civil penalty of $14,000 for
violation of 49 C.F.R. § 195.573(c).
Item 9: The Notice proposed a civil penalty of $35,300 for Respondent's violation of
49 C.F.R. § 195.571, for failing to ensure that cathodic protection for the company's pipeline
facilities at the Airport complied with the NACE Standard. BPL failed to take any pipe-to-soil
readings at the Airport from October 2006 until October 2008, and therefore the adequacy of the



13
cathodic protection at this location was unknown. As noted above, I found that BPL's failure to
gain access to the Airport did not serve to refute the allegation of violation.
BPL has a responsibility to ensure that its facilities can be operated safely, which includes
maintaining adequate cathodic protection. The potential failure of this pipeline in an HCA near
the Airport could jeopardize the safety and operation of an important facility where the public
often congregates in large numbers. The importance of ensuring adequate cathodic protection at
such a facility increases the gravity of the violation, as does its duration. BPL has not presented
any evidence or argument justifying a reduction or elimination of the proposed penalty.
Accordingly, having reviewed the record and considered the assessment criteria, 1 assess
Respondent a civil penalty of $35,300 for violation of 49 C.F.R. § 195.571.
Item 11: The Notice proposed a civil penalty of $29,000 for Respondent's violation of
49 C.F.R. $ 195.573(e), for failing to correct, within a reasonable time, identified deficiencies in
corrosion control. Respondent's work orders showed that several locations having low cathodic
protection readings along the pipeline had been scheduled for work between 2005 and 2007 but
the work had not been completed by the time of the PHMSA inspections in 2008. BPL neither
contested the allegation nor presented any evidence or argument justifying a reduction in the
proposed penalty. Inadequate cathodic protection can result in pipeline leaks and the release of
hazardous liquid. Two of the identified deficiencies were located within an HCA, thus
aggravating the gravity of the violation. Accordingly, having reviewed the record and
considered the assessment criteria, I assess Respondent a civil penalty of $29,000 for violation of
49 C.F.R. § 195.573(e).
Item 13: The Notice proposed a civil penalty of $41,500 for Respondent's violation of
79 C.F.R. $ 195.402(a), for failing to follow its own manual of written procedures for conducting
normal O&M activities and for handling abnormal operations and emergencies. BPL neither
contested the allegation nor presented any evidence or argument justifying a reduction in the
proposed penalty. As noted above, I found that Respondent failed on two occasions to repair
abnormal conditions, as required by its written procedures. These conditions potentially affected
HCAs, meaning the safety of the public and the environment were at increased risk. Therefore,
the gravity of the violation supports the proposed penalty. Accordingly, having reviewed the
record and considered the assessment criteria, I assess Respondent a civil penalty of $41,500 for
violation of 49 C.F.R. § 195.402(a).
Item 14: The Notice proposed a civil penalty of $120,300 for Respondent's violation of
49 C.F.R. $ 195.452(j)(2), for failing to conduct periodic evaluations as frequently as needed to
assure pipeline integrity. As discussed above, the allegation is withdrawn. Therefore, I also
withdraw the proposed penalty for violation of 49 C.F.R. § 195.452(j)(2).
Item 17: The Notice proposed a civil penalty of $200,300 for Respondent's violation of
49 C.F.R. $ 195.452(f)(6), for failing to include a process in its IMP for identifying P&M
measures to protect HCAs. As noted above, I found that BPL failed to produce evidence of a
P&M process that was in effect as of the date the PHMSA inspection began in May 2008.
Early identification and implementation of P&M measures can help prevent some or all of the
damage that can result from a pipeline failure. The unique features of each pipeline, the terrain



14
and environment around the pipeline, and the particular features of the surrounding community
mean that each operator must implement a process uniquely tailored to its own individual
system. This process is a critical element of the IMP and helps to ensure its efficacy. Such a
process was required to be in BPL's written IMP no later than March 2002, but there is no
evidence that it was in place by the time of the inspection in May 2008.
More than half of BPL's pipelines are either located within or could affect HCAs. The company
is therefore required to implement and maintain a complete IMP to protect the public and the
environment in HCAs from potentially dangerous pipeline failures. The failure to do so is a
serious violation of the integrity management regulations, as a pipeline failure in or near an HCA
could have catastrophic consequences for the public and the environment. Therefore the nature
and gravity of the violation and BPL's culpability justify the proposed penalty.
This violation continued for years, yet the amount of the proposed penalty is far below the limit
of $100,000 per violation per day. BPL has not presented any other evidence or argument
justifying a reduction or elimination of the proposed penalty. Accordingly, having reviewed the
record and considered the assessment criteria, I assess Respondent a civil penalty of $200,300 for
violation of 49 C.F.R. § 195.452(f)(6).
Item 19: The Notice proposed a civil penalty of $120,300 for Respondent's violation of
49 C.F.R. § 195.452(i)(4), for failing to determine whether EFRDs were needed on its pipeline to
protect against failures that could affect HCAs. Specifically, it alleged that BPL had failed to
conduct annual EFRD analyses of pipeline segments scheduled for integrity re-assessments and
to install EFRDs that the company had previously determined were needed.
BPL's defense was that instead of installing the EFRDs, the company had allocated funds to
other repairs with greater risk-mitigation benefits. In addition, Respondent noted that it had
dramatically increased spending on pipeline maintenance between 2000 and 2008.
EFRDs have been shown to be effective in mitigating the consequences of many hazardous
liquid pipeline releases. If the need for EFRDs is not assessed and appropriate action taken, a
pipeline failure can cause additional damage that could have been prevented, thereby putting the
environment and public safety at unnecessary risk. Spending on other maintenance activities.
while commendable, does not mitigate an operator's duty to conduct EFRD evaluations and
install them as needed, as required under both § 195.452(i)(4) and the company's own
procedures. That BPL did not complete the EFRD installations that were recommended in its
own 2002 evaluation is particularly troubling because the company recognized a safety hazard
but consciously decided to forego action that could mitigate the effects of a spill. Therefore, the
nature and gravity of the violation and the culpability of the operator justify the proposed penalty
amount.
BPL has not presented any other evidence or argument justifying a reduction or elimination of
the proposed penalty. Accordingly, having reviewed the record and considered the assessment
criteria, I assess Respondent a civil penalty of $120,300 for violation of
49 C.F.R. § 195.452(i)(4).



15
In summary, having reviewed the record and considered the assessment criteria for each of the
Items cited above, I assess Respondent a total civil penalty of $524,900.
Payment of the civil penalty must be made within 20 days of service. Federal regulations
(49 C.F.R. § 89.21(b)(3)) require such payment to be made by wire transfer through the Federal
Reserve Communications System (Fedwire), to the account of the U.S. Treasury. Detailed
instructions are contained in the enclosure. Questions concerning wire transfers should be
directed to: Financial Operations Division (AMZ-341), Federal Aviation Administration, Mike
Monroney Aeronautical Center, P.O. Box 269039, Oklahoma City, Oklahoma 73125. The
Financial Operations Division telephone number is (405) 954-8893.
Failure to pay the $524,900 civil penalty will result in accrual of interest at the current annual
rate in accordance with 31 U.S.C. § 3717, 31 C.F.R. § 901.9 and 49 C.F.R. § 89.23. Pursuant to
those same authorities, a late penalty charge of six percent (6%) per annum will be charged if
payment is not made within 110 days of service. Furthermore, failure to pay the civil penalty
may result in referral of the matter to the Attorney General for appropriate action in a district
court of the United States.
COMPLIANCE ORDER
The Notice proposed a compliance order with respect to Items 3, 9, 17, and 19 in the Notice for
violations of 49 C.F.R. $$ 195.402(a), 195.571, 195.452(f)(6), and 195.452(i)(4), respectively.
Under 49 U.S.C. § 60118(a), each person who engages in the transportation of hazardous liquids
or who owns or operates a pipeline facility is required to comply with the applicable safety
standards established under chapter 601. Pursuant to the authority of 49 U.S.C. § 60118(b) and
49 C.F.R. § 190.217, Respondent is ordered to take the following actions to ensure compliance
with the pipeline safety regulations applicable to its operations:
1. With respect to the violation of § 195.402(a) (Item 3), Respondent must develop a
plan to ensure that a root cause analysis is conducted and documented for all
accidents, as required by BPL's O&M Manual, and that any corrective actions
recommended by each analysis are implemented.
2. With respect to the violation of § 195.571 (Item 9), Respondent must establish and
implement a plan to gain access to BPL facilities at the Philadelphia Airport in order
to ensure its cathodic protection complies with paragraphs 6.2 and 6.3 of NACE
Standard SP 0169.
3. With respect to the violation of § 195.452(f)(6) (Item 17), Respondent must establish
and implement processes to evaluate its pipeline segments for additional P&M
measures. Upon completion of the evaluation of pipeline segments, a schedule for
implementing any needed P&M actions must be submitted.
4. With respect to the violation of § 195.452(i)(4) (Item 19), Respondent must establish
an improved process to evaluate the need for additional EFRDs. Upon establishment
of the improved process, Respondent must perform EFRD evaluations on its pipeline



16
segments, develop a schedule for installing EFRDs where necessary, and document
the reasoning for why EFRDs are not necessary for all locations Respondent
considered.
5. Respondent must submit a plan and schedule for completing the Compliance Order
items listed above to PHMSA for review and approval within 60 days after receipt of
the Final Order. Upon receiving approval of the plan and schedule, Respondent must
submit evidence of completion for the Compliance Order items listed above to
PHMSA within 180 days after receipt of the Final Order. Submit all correspondence
for review and approval to the Director, Eastern Region, Office of Pipeline Safety.
PHMSA, 820 Bear Tavern Road, Suite 306, West Trenton, NJ 08628.
6. It is requested that Respondent maintain documentation of the safety improvement
costs associated with fulfilling this Compliance Order and submit that total to the
Director, Eastern Region, PHMSA. It is requested that costs be reported in two
categories: (1) total cost associated with preparation and revision of plans,
procedures, studies and analyses: and (2) total cost associated with replacements,
additions and other changes to pipeline infrastructure.
The Director may grant an extension of time to comply with any of the required items upon a
written request timely submitted by the Respondent and demonstrating good cause for an
extension.
Failure to comply with this Order may result in the administrative assessment of civil penalties
not to exceed $100,000 per violation for each day the violation continues or in referral to the
Attorney General for appropriate relief in a district court of the United States.
WARNING ITEMS
With respect to Items 1, 2, 5, 6, 10, 12, 15, 16, 18, 20, 21, and 22, the Notice alleged probable
violations of Part 195 but did not propose a civil penalty or compliance order for these items.
Therefore, these are considered to be warning items. The warnings were for:
49 C.F.R. § 195.401(b) (Item 1) - Respondent's alleged failure to correct four
conditions that could have adversely affected the safe operation of its pipeline within a
reasonable time.
19 C.F.R. § 195.402(a) (Item 2) - Respondent's alleged failure to review and update its
operations, maintenance, and emergency manuals at intervals not exceeding 15 months,
but at least once each calendar year. Respondent claimed that its manual review process
satisfied the requirements of $ 195.402(a) and that it had revised its procedures to
include a documented annual review of its manuals.? However, Respondent did not
provide any evidence that the reviews had been conducted at the required intervals.
18 Response at 2.



17
49 C.F.R. § 195.412(a) (Item 5) - Respondent's alleged failure to inspect the surface
conditions on or adjacent to each pipeline right-of-way at intervals not exceeding 3
weeks, but at least 26 times a year.
19 C.F.R. § 195.557 (Item 6) - Respondent's alleged failure to provide coating for
external corrosion control as required for certain pipelines.
49 C.F.R. § 195.573(e) (Item 10) - Respondent's alleged failure to correct identified
deficiencies in external corrosion control within a reasonable time period. Cathodic
protection survey test results in 2006 and 2007 identified inadequate levels of cathodic
protection, but this condition was not addressed until 2008. In its Response, BPL
claimed these test results were not indicative of a deficiency in corrosion control, but
were simply the result of defective test leads." Regardless of the cause of the test
results, the condition needed to be corrected before the next annual test.
49 C.F.R. § 195.438 (Item 12) - Respondent's alleged failure to prohibit smoking and
open flames at each pump station and breakout tank area where there was a possibility
of leakage of a flammable hazardous liquid or the presence of flammable vapors. BPL
had "No Smoking" signs at some, but not all, tank areas, and not at the entrance to tank
dikes at the Booth Station, an inconsistency that could confuse workers and visitors
regarding where it was safe to smoke within the facility. In its Response, BPL claimed
that signs were not required at each tank dike since the company had signs on its
perimeter fences and its written policy prohibited smoking inside the fenced areas.*°
While it is necessary and appropriate for operators to have written policies prohibiting
does not constitute compliance with the regulation.?" In addition, the presence of "No
smoking and open flames in pump station areas, the existence of such procedures alone
Smoking" signs at some, but not all, tank areas could lead to confusion and an
ineffective implementation of the "no smoking" policy.
49 C.F.R. § 195.452(b)(2) (Items 15 and 16) - Respondent's alleged failure to identify
all pipelines that could affect a HCA.
49 C.F.R. $ 195.452(i)(2) (Item 18) - Respondent's alleged failure to properly consider
all relevant risk factors in its evaluation of what P&M measures were needed to protect
HCAs in the event of a pipeline release.
49 C.F.R. § 195.452(f)(3) (Item 20) - Respondent's alleged failure to continually update
its IMP to reflect relevant operating experience.
" Response at 5.
30 Response at 6.
3 See In the Matter of Nustar Logistics. L.P.. F/K/A Valero Logistics Operations. L. P.., CPF No. 4-2005-5048
(March 11. 2009). Final orders are generally available on PHMSA website at
http://primis.phmsa.dot.gov/comm/reports/enforce/Actions_opid_0.html?nocache=8998#_TP_|_tab_2.



18
49 C.F.R. $ 195.561(b) (Item 21) - Respondent's alleged failure to properly repair any
coating damage discovered during an inspection of external pipe.
49 C.F.R. $ 195.406(b) (Item 22) - Respondent's alleged failure to provide adequate
controls and protective equipment to keep the surge pressure on the pipeline below
110% of the operating pressure limit established under § 195.406(a). The Notice listed
three documented events where the surge pressure exceeded 110% of the MOP. In its
Response, BPL stated that in two of these instances, the pressure did not actually exceed
110% of the MOP, and that the company's Abnormal Operating Event forms had
mismarked the pressure due to an employee's miscalculation. However, BPL did not
provide any evidence to substantiate this explanation. The third event was not
disputed.2
BPL presented information in its Response showing that it had taken certain actions to address
the cited items. Accordingly, having considered such information, I find. pursuant to
49 C.F.R. § 190.205, that probable violations of 49 C.F.R. § 195.401(b) (Item 1), § 195.402(a)
(Item 2), $ 195.412(a) (Item 5), § 195.557 (Item 6), § 195.573(e) (Item 10), § 195.438 (Item 12),
$ 195.452(b)(2) (Items 15 and 16), § 195.452(i)(2) (Item 18), § 195.452(f) (Item 20),
$ 195.561(b) (Item 21), and § 195.406(b) (Item 22) have occurred and Respondent is hereby
advised to correct such conditions. In the event that OPS finds a violation of any of these items
in a subsequent inspection, Respondent may be subject to future enforcement action.
Under 49 C.F.R. § 190.215, Respondent has a right to submit a Petition for Reconsideration of
this Final Order. The petition must be sent to: Associate Administrator, Office of Pipeline
Safety, PHMSA, 1200 New Jersey Avenue. SE, East Building, 2'd Floor, Washington, DC
20590, with a copy sent to the Office of Chief Counsel, PHSA, at the same address. PHMSA
will accept petitions received no later than 20 days after receipt of service of this Final Order by
the Respondent, provided they contain a brief statement of the issue(s) and meet all other
requirements of 49 C.F.R. § 190.215. The filing of a petition automatically stays the payment of
any civil penalty assessed. Unless the Associate Administrator, upon request, grants a stay, all
other terms and conditions of this Final Order are effective upon service in accordance with
49 C.F.R. $ 190.5.
Busese
MAY 302012
Jeffrey D. Wiese
Date Issued
Associate Administrator
for Pipeline Safety
32 Response at 10.

120095002_Final_Order_05302012_text.pdf

MAY 30 2012
Mr. Clark Smith
President and CEO
Buckeye Partners, LP
One Greenway Plaza, Suite 600
Houston, TX 77046
Re: CPF No. 1-2009-5002
Dear Mr. Smith:
Enclosed please find the Final Order issued in the above-referenced case. It withdraws one of
the allegations of violation, makes other findings of violation, assesses a civil penalty of
$524,900, and specifies actions that need to be taken by Buckeye Partners, LP, to comply with
the pipeline safety regulations. The penalty payment terms are set forth in the Final Order.
When the civil penalty has been paid and the terms of the compliance order completed, as
determined by the Director, Eastern Region, this enforcement action will be closed. Service of
the Final Order by certified mail is deemed effective upon the date of mailing, or as otherwise
provided under 49 C.F.R. § 190.5.
Thank you for your cooperation in this matter.
Sincerely,
Jeffrey D. Wiese
Associate Administrator
for Pipeline Safety
Enclosure
cc: Mr. Byron Coy, PE, Director, Eastern Region, OPS
Mr. Alan Mayberry, Deputy Associate Administrator for Field Operations, OPS
Mr. Scott Collier, Vice President, Buckeye Partners, LP,
5 TEK Park, 9999 Hamilton Boulevard, Breinigsville, PA 18031
CERTIFIED MAIL – RETURN RECEIPT REQUESTED



U.S. DEPARTMENT OF TRANSPORTATION
PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION
OFFICE OF PIPELINE SAFETY
WASHINGTON, D.C. 20590
____________________________________
)
In the Matter of )
)
Buckeye Partners, LP, ) CPF No. 1-2009-5002
)
Respondent. )
____________________________________)
FINAL ORDER
During the period from May to December, 2008, pursuant to 49 U.S.C. § 60117, representatives
of the Pipeline and Hazardous Materials Safety Administration (PHMSA), Office of Pipeline
Safety (OPS), and the New York Public Service Commission conducted on-site pipeline safety
inspections of the facilities and records of Buckeye Partners, LP (BPL or Respondent), in several
states, including Pennsylvania, Ohio and Michigan. BPL owns and operates approximately
6,000 miles of pipelines transporting refined petroleum products and highly volatile liquids,
principally in the Northeastern and upper Midwestern states.
1 Approximately 3,558 of those
pipeline miles are in or could affect High Consequence Areas (HCAs)2 and are covered by
BPL’s integrity management program.
3
As a result of the inspection, the Director, Eastern Region, PHMSA (Director), issued to
Respondent, by letter dated June 26, 2009, a Notice of Probable Violation, Proposed Civil
Penalty, and Proposed Compliance Order (Notice). In accordance with 49 C.F.R. § 190.207, the
Notice proposed finding that BPL had committed various violations of 49 C.F.R. Part 195,
assessing a civil penalty of $645,200 for the alleged violations, and ordering Respondent to take
certain measures to correct the alleged violations. The Notice also proposed finding that
Respondent had committed other probable violations of 49 C.F.R. Part 195 and warning the
company to take appropriate corrective action or be subject to future enforcement action.
BPL responded to the Notice by letters dated September 25, 2009 (Response), and
January 6, 2010 (Supplemental Response). The company contested some of the allegations of
violation and requested reduction or elimination of the associated penalties. BPL did not contest
other allegations and provided information concerning the corrective actions it had taken.
Respondent did not request a hearing and therefore has waived its right to one.
1 http://www.buckeye.com/BusinessOperations/tabid/56/Default.aspx and
http://www.buckeye.com/AboutUs/tabid/54/Default.aspx (last accessed on March 22, 2012).
2 49 C.F.R. § 195.450.
3 49 C.F.R. § 195.452.



2
FINDINGS OF VIOLATION
The Notice alleged that Respondent violated 49 C.F.R. Part 195, as follows:
Operations and Maintenance Items:
Item 3: The Notice alleged that Respondent violated 49 C.F.R. § 195.402(a), which states in
relevant part:
§ 195.402 Procedural manual for operations, maintenance, and
emergencies.
(a) General. Each operator shall prepare and follow for each pipeline
system a manual of written procedures for conducting normal operations
and maintenance activities and handling abnormal operations and
emergencies. This manual shall be reviewed at intervals not exceeding 15
months, but at least once each calendar year, and appropriate changes
made as necessary to insure that the manual is effective….
The Notice alleged that BPL violated 49 C.F.R. § 195.402(a) by failing to follow its manual of
written procedures for conducting normal operations and maintenance (O&M) activities and
handling abnormal operations and emergencies. Specifically, it alleged that BPL had failed to
conduct root-cause analyses in 25 accident reports, as required by its own O&M procedures.
The BPL Safety Manual, Section A-04, required that a root cause analysis be conducted for each
product release that required regulatory reporting.4
In its Response, BPL did not contest the allegation of violation but contended that in August
2006, it had created six new positions within the company and that one of the duties of these new
positions was to conduct root cause analyses for accidents.5 BPL also stated that the 25 accident
reports which lacked a root cause analysis had all been performed before the creation of the new
positions.6 BPL stated that it had “recognized that there was a need to ensure that root cause
analyses were conducted… almost two years prior to the integrated inspection” and requested
potential reduction in the amount of the penalty, it is discussed in the “Assessment of Penalty”
that the penalty associated with this Item be “rescinded.”7 Since this argument relates to a
section below.
Accordingly, based upon a review of all of the evidence, I find that Respondent violated
49 C.F.R. § 195.402(a) by failing to follow its manual of written procedures for conducting
normal O&M activities and handling abnormal operations and emergencies.
Item 4: The Notice alleged that Respondent violated 49 C.F.R. § 195.403(b), which states:
4 Pipeline Safety Violation Report (Violation Report), Exhibit A (on file with PHMSA).
5 Response at 2.
6 Id.
7 Id.



3
§ 195.403 Emergency response training.
(a) Each operator shall establish and conduct a continuing training
program to instruct emergency response personnel…
(b) At the intervals not exceeding 15 months, but at least once each
calendar year, each operator shall:
(1) Review with personnel their performance in meeting the
objectives of the emergency response training program set forth in
paragraph (a) of this section; and
(2) Make appropriate changes to the emergency response training
program as necessary to ensure that it is effective.
The Notice alleged that BPL violated 49 C.F.R. § 195.403(b) by failing to review with company
personnel their performance in meeting the objectives of the company’s emergency response
training program, at intervals not exceeding 15 months but at least once each calendar year.
In its Response, BPL did not explicitly contest the allegation but argued that it had reviewed the
performance of its employees in responding to emergencies through the use of a form which had
been “approved by the government” and which had documented personnel “responses and follow
up actions to emergencies.”8 The company further explained that its Training Manual called for
a critique of employee responses after all emergencies and response drills but acknowledged that
it did not “specifically document the review of the performance of its employees on the form.”
Notwithstanding these existing procedures, BPL indicated that it had revised the form to include
a check box to document specifically that the performance of company personnel had been
reviewed. The company provided OPS with a blank copy of the revised form.9
While BPL indicated that the form had been approved by the government, there is no indication
that the form had ever been approved by PHMSA for purposes of satisfying this regulatory
requirement. In addition, BPL did not provide any completed forms to demonstrate that the
required reviews had actually been conducted. Therefore, it is impossible to tell whether the
reviews were properly completed in a timely manner.
Accordingly, after considering all of the evidence, I find that Respondent violated
49 C.F.R. § 195.403(b) by failing to review with company personnel, at the required intervals,
their performance in meeting the objectives of BPL’s emergency response training program.
Item 13: The Notice alleged that Respondent violated 49 C.F.R. § 195.402(a), as quoted above,
by failing to follow its manual of written procedures for conducting normal O&M activities and
handling abnormal operations and emergencies. Specifically, it alleged that BPL failed to follow
its Maintenance Manual, Procedure E-08, Damaged or Defective Non-Leaking Pipe, on two
occasions. On March 22, 2005, the company allegedly failed to repair a sharp dent at Sta.
913+96 on its 209 Line in Wayne, Michigan, using a sleeve required by its own written
procedures. Similarly, the Notice alleged that on June 1, 2005, the company allegedly failed to
repair a wrinkle bend in accordance with BPL’s own written procedures.10
8 Response at 3.
9 Id.
10 Violation Report, Exhibit B.



4
According to the Notice, BPL’s procedures stated that at the pipeline’s listed Maximum
Operating Pressure (MOP) of 1233 psig, the wrinkle bend had to be repaired in accordance with
the company’s Procedure MA E-08, Exhibit 1. The company allegedly decided, however, that
no repair was needed for the wrinkle bend because the line did not normally operate at over 900
psig. However, BPL did not subsequently lower the MOP on the line to 900 psig.
BPL did not contest the alleged violations. The company acknowledged that in August 2009, it
had excavated and re-evaluated the sharp dent in the 209 line and had installed a repair sleeve.11
As for the wrinkle bend, the company stated that it was in the process of conducting an
engineering evaluation to determine the appropriate MOP for this line segment.12
Accordingly,
based upon a review of all of the evidence, I find that Respondent violated
49 C.F.R. § 195.402(a) by failing to follow its manual of written procedures for conducting
normal O&M activities and handling abnormal operations and emergencies.
Corrosion Control Items
Item 7: The Notice alleged that Respondent violated 49 C.F.R. § 195.583(a), which states:
§ 195.583 What must I do to monitor atmospheric corrosion control?
(a) You must inspect each pipeline or portion of pipeline that is
exposed to the atmosphere for evidence of atmospheric corrosion, as
follows:
If the pipeline is
located:
Then the frequency of inspection is:
Onshore..................... At least once every 3 calendar years, but with
intervals not exceeding 39 months.
Offshore……………. At least once each calendar year, but with
intervals not exceeding 15 months.
The Notice alleged that BPL violated 49 C.F.R. § 195.583(a) by failing to inspect the above-
ground pipeline facilities at the company’s Mantua Station for atmospheric corrosion at least
once every three calendar years, but at intervals not exceeding 39 months. Specifically, it
alleged that BPL’s own records showed inspections had been conducted on May 4, 2004, and
January 29, 2008, an interval that exceeded 39 months.
BPL did not contest this allegation. Accordingly, after considering all of the evidence, I find that
Respondent violated 49 C.F.R. § 195.583(a) by failing to inspect, at the required intervals, each
pipeline exposed to the atmosphere for atmospheric corrosion. It is noted that BPL represents
that it has improved its process for conducting such inspections.
11 Response at 6.
12 Id.



5
Item 8: The Notice alleged that Respondent violated 49 C.F.R. § 195.573(c), which states:
§ 195.573 What must I do to monitor external corrosion control?
(a) ….
(c) Rectifiers and other devices. You must electrically check for
proper performance each device in the first column at the frequency stated
in the second column.
Device Check frequency
Rectifier…………………….
Reverse current switch.
Diode.
Interference bond whose
failure would jeopardize
structural protection.
At least six times each calendar year,
but with intervals not exceeding 2½
months.
Other interference bond……. At least once each calendar year, but
with intervals not exceeding 15
months.
The Notice alleged that BPL violated 49 C.F.R. § 195.573(c) by failing to electrically check
several rectifiers for proper performance at the required frequency. Specifically, it alleged the
following failures:
1. Three rectifiers in the Harristown Shell system were not inspected at the required
intervals twice during 2006, each time exceeding the 2½-month maximum by 1½
months;
2. The rectifiers in the BPL Trans PA, Malvern Station Tank Farm, Paulsboro Deep Well,
and Chester Park systems were not checked at least six times each year during 2006-
2007;
3. The Booth rectifier LP-07 for Tank #15 was not inspected between March 5, 2006, and
May 26, 2006, an interval that exceeded 2½ months; and
4. The Booth rectifier LP-08 STA40009 BH724SK was not inspected between
September 5, 2006, and January 12, 2007, an interval that exceeded 2½ months.
In its Response, BPL only contested the portion of the allegation relating to the rectifiers on the
Harristown Shell system. The company asserted that during the March and July inspections, the
Harristown rectifiers were out of service due to tank projects and were noted as “locked



6
out/tagged out” on the company’s inspection records.
documents included comments for the Harristown rectifiers for the March and July inspections.
In March, the rectifiers were noted as “Locked out – Due to cleaning tank” and in July they were
listed as “Down – Due to construction.” Based on these records and BPL’s explanation for them,
it is plausible that the rectifiers were out of service during these inspections.
13 BPL’s rectifier output-history
To remain in compliance with the regulation, however, BPL was obliged to check the rectifiers
before they were put back into service. The company failed to inspect them until the next
scheduled inspection two months later, resulting in a four-month interval between inspections.
BPL stated that it had subsequently revised its procedures to require that rectifiers be checked
both prior to and after being locked out and that the company had added a field in its work order
system to show when an inspection would be out of compliance with § 195.573(c).14
Accordingly, after considering all of the evidence, I find that Respondent violated
49 C.F.R. § 195.573(c) by failing to check several rectifiers for proper performance within the
required intervals.
Item 9: The Notice alleged that Respondent violated 49 C.F.R. § 195.571, which states:
§ 195.571 What criteria must I use to determine the adequacy of
cathodic protection?
Cathodic protection required by [Subpart H] must comply with one or
more of the applicable criteria and other considerations for cathodic
protection contained in paragraphs 6.2 and 6.3 of NACE SP 0169
(incorporated by reference, see § 195.3).
The Notice alleged that BPL violated 49 C.F.R. § 195.571 by failing to ensure that cathodic
protection for the company’s facilities at the Philadelphia Airport (Airport) complied with one or
more of the applicable criteria and other considerations for cathodic protection contained in
paragraphs 6.2 and 6.3 of NACE Standard SP 0169 (NACE Standard). Specifically, it alleged
that BPL had failed to take any pipe-to-soil readings at the Airport since October 2006 and that
therefore the adequacy of cathodic protection at these locations was unknown.
In its Response, BPL acknowledged that it did not take pipe-to-soil readings at the Airport test
points, but contended that it had been unable to gain access to the Airport in 2007 and that the
test points at the Airport represented only a small fraction of the points on its entire system.
15
BPL stated that all the other test points had been tested in 2007 and that the Airport points were
accessed and tested in October 2008. The company also stated that it had now arranged a new
method for arranging security escorts at the Airport and that it had made arrangements for the
2009 inspection within the required interval.
16
13 Response at 4.
14 Id.
15 Response at 4.
16 Response at 4-5.



7
BPL is obligated to ensure that cathodic protection is adequate and complies with the NACE
Standard at all times. BPL’s failure to gain access to the Airport does not serve to refute the
allegation of violation. Accordingly, after considering all of the evidence, I find that Respondent
violated 49 C.F.R. § 195.571 by failing to ensure that cathodic protection on its pipeline
complied with the applicable criteria and other considerations for cathodic protection contained
in the NACE Standard.
Item 11: The Notice alleged that Respondent violated 49 C.F.R. § 195.573(e), which states:
§ 195.573 What must I do to monitor external corrosion control?
(a) . . .
(e) Corrective action. You must correct any identified deficiency in
corrosion control as required by § 195.401(b). However, if the deficiency
involves a pipeline in an integrity management program under § 195.452,
you must correct the deficiency as required by § 195.452(h).
The Notice alleged that BPL violated 49 C.F.R. § 195.573(e) by failing to correct identified
deficiencies in corrosion control, as required by § 195.401(b), which states that an operator must
correct, within a reasonable time, any deficiency that could adversely affect the safe operation of
the pipeline. Specifically, the Notice alleged that the company’s own work orders showed that
several locations along the pipeline with low cathodic protection readings had been scheduled for
work between 2005 and 2007, but that the work had not been completed by the time of the
PHMSA inspections in 2008.
BPL did not contest this allegation and explained that it had improved its process for remediating
low cathodic protection readings by adding a field in its work order system to show when
of the evidence, I find that Respondent violated 49 C.F.R. § 195.573(e) by failing to correct
proposed remediation efforts would fail to be in compliance.17 Accordingly, after considering all
identified deficiencies in corrosion control within a reasonable time.
Integrity Management Program (IMP) Items
Item 14: The Notice alleged that Respondent violated 49 C.F.R. § 195.452(j)(2), which states:
§ 195.452 Pipeline integrity management in high consequence areas.
(a) . . .
(j) What is a continual process of evaluation and assessment to
maintain a pipeline’s integrity?—
(1) General. After completing the baseline integrity assessment, an
operator must continue to assess the line pipe at specified intervals and
periodically evaluate the integrity of each pipeline segment that could
affect a high consequence area.
(2) Evaluation. An operator must conduct a periodic evaluation as
frequently as needed to assure pipeline integrity. An operator must base
17 Response at 5.



8
the frequency of evaluation on risk factors specific to its pipeline,
including the factors specified in paragraph (e) of this section. The
evaluation must consider the results of the baseline and periodic integrity
assessments, information analysis (paragraph (g) of this section), and
decisions about remediation, and preventive and mitigative actions
(paragraphs (h) and (i) of this section).
The Notice alleged that BPL violated 49 C.F.R. § 195.452(j)(2) by failing to conduct periodic
evaluations as frequently as needed to assure pipeline integrity. Specifically, the Notice alleged
that “BPL could not demonstrate that periodic evaluations of the pipeline integrity program were
performed as required by the integrity management regulations.”18 BPL contested the allegation,
stating that the company’s “process for periodic evaluation of the integrity of BPL’s pipelines
and compliance with integrity regulations involves its Risk Management Team.”19 The
Response broadly described the responsibilities and activities of the team, including ensuring
“[c]ompliance with all regulatory requirements regarding operational risk management” and a
“[c]ontinuous improvement process for BPL’s integrity management program.”20 BPL also
stated that minutes and “action items” from the team’s meetings documented the company’s
periodic evaluation process.
21
BPL did not offer any documentation or evidence of any of its integrity program evaluations. The
meeting minutes and actions items which BPL referenced in its Response were not provided, nor
did BPL demonstrate that results of any evaluations were used to make decisions about
remediation and preventive and mitigative (P&M) actions. BPL offered examples of “programs
that were recommended through the periodic evaluations” but did not offer any documentation of
the evaluations or the recommendations that they had claimed to have made.22
Neither party has presented sufficient proof to prove its position, but OPS bears the burden of
proving that BPL has committed the violation. Section 195.452(j) requires continuous
evaluation and assessment of an operator’s individual pipeline segments, not simply its overall
IMP. The evidence presented by OPS in the Violation Report and Notice are insufficient to
prove that Respondent’s IMP failed to include periodic pipe segment evaluations under §
195.452(j). The record contains no documents, procedures, interview notes or any other
evidence to support the allegation that the company’s IMP was devoid of the sort of continuous
evaluations required by the regulation. Accordingly, based upon the foregoing, I find that OPS
has failed to meet its burden of proof and hereby order that Item 14 be withdrawn.
Item 17: The Notice alleged that Respondent violated 49 C.F.R. § 195.452(f)(6), which states:
18 Notice at 7.
19 Response at 6.
20 Id.
21 Response at 7.
22 Id.



9
§ 195.452 Pipeline integrity management in high consequence areas.
(a) . . .
(f) What are the elements of an integrity management program? An
integrity management program begins with the initial framework. An
operator must continually change the program to reflect operating
experience, conclusions drawn from results of the integrity assessments,
and other maintenance and surveillance data, and evaluation of
consequences of a failure on the high consequence area. An operator must
include, at minimum, each of the following elements in its written
integrity management program:
(1) …
(6) Identification of preventive and mitigative measures to protect the
high consequence area (see paragraph (i) of this section).
The Notice alleged that BPL violated 49 C.F.R. § 195.452(f)(6) by failing to include in its IMP a
process for identifying (P&M) measures to protect HCAs. Under
§ 195.452(f), an operator’s IMP must contain eight separate elements, including a process for
identifying HCAs, a baseline assessment plan, an information-integration analysis, criteria for
taking remedial action, a continual process of periodic assessments of line pipe segments (see
Item 14 above), the identification of P&M measures tailored to the operator’s unique system, and
methods to measure the IMP’s overall effectiveness.
The Violation Report stated that the OPS inspection team had found no indication that BPL had
ever developed a process within its IMP for identifying P&M measures that would reduce the
likelihood and consequences of pipeline releases, had ever identified specific P&M measures to
protect HCAs, or had compiled any documentation to show such processes were in place. The
Violation Report also noted that BPL’s integrity manager had stated that BPL would be
developing such procedures in the future.
In its Response, BPL contested the alleged violation, stating that its Integrity Management
Manual (IMM) did indeed contain a process for identifying potential P&M measures and
summarizing the process. It claimed that Section 6 of its IMM fully described the company’s
process for identifying P&M measures, including the use of a Risk Model to identify high-risk
areas, the use of subject matter expert teams to develop and test “various preventive and
mitigative scenarios that potentially will provide positive impacts to reducing the identified risk,”
the selection and evaluation of “physically feasible” measures, and the implementation of those
measures having the greatest benefit in terms of risk reduction and financial feasibility.
23 In
addition, the company contended that the “Exhibit A-01A flowchart in Buckeye’s IMM and
referenced in Section 6 clearly shows that preventive and mitigative measures are an integral part
procedures or any other documentation in either its Response or Supplemental Response.
of the Continual Assessment Program.” 24 The company, however, did not submit any of these
23 Response at 8.
24 Response at 8.



10
Such general statements do not constitute credible evidence that BPL actually had a process for
identifying P&M measures or that it had actually developed specific measures to reduce the
likelihood or consequences of failures on HCAs. Not only did BPL fail to produce
documentation of a P&M process that was in effect as of the date of the OPS inspection in May
2008, but it also failed to provide any evidence showing that any specific P&M measures had ever
been actually identified, evaluated by its subject matter expert team, or implemented by the
company.
While BPL may indeed have had some general framework of a process for identifying P&M
measures, the company failed to produce any evidence that it had implemented any such process
or that it had met the requirements of the regulation. Accordingly, based upon a review of all of
the evidence, I find that BPL violated 49 C.F.R. § 195.452(f)(6) by failing to include a process
for identifying P&M measures to protect HCAs in its written IMP.
Item 19: The Notice alleged that Respondent violated 49 C.F.R. § 195.452(i)(4), which states:
§ 195.452 Pipeline integrity management in high consequence areas.
(a) . . .
(i) What preventive and mitigative measures must an operator take to
protect the high consequence area?-
(1) ….
(4) Emergency Flow Restricting Devices (EFRD). If an operator
determines that an EFRD is needed on a pipeline segment to protect a high
consequence area in the event of a hazardous liquid pipeline release, an
operator must install the EFRD. In making this determination, an operator
must, at least, consider the following factors—the swiftness of leak
detection and pipeline shutdown capabilities, the type of commodity
carried, the rate of potential leakage, the volume that can be released,
topography or pipeline profile, the potential for ignition, proximity to
power sources, location of nearest response personnel, specific terrain
between the pipeline segment and the high consequence area, and benefits
expected by reducing the spill size.
The Notice alleged that BPL violated 49 C.F.R. § 195.452(i)(4) by failing to determine whether
EFRDs were needed to protect against failures that could affect HCAs along its pipeline and, if
so, to install them. Specifically, the Notice alleged that, since 2005, BPL had failed to conduct
annual EFRD analyses of pipeline segments scheduled for integrity re-assessments, as required
by § 195.452(i) and Section 15 of the company’s own IMM. The Notice also alleged that BPL
had failed to install certain EFRDs that had been recommended as a result of a 2002 evaluation.
In its Response, BPL noted that pipelines scheduled for integrity assessments between 2002 and
2005 had been analyzed for EFRDs and that the recommended devices had been included in
BPL’s capital plan. The company claimed, however, that it had ultimately decided to allocate
funds to other risk-management projects instead.25
BPL also noted that its spending on pipeline
maintenance had drastically increased since 2000 and that EFRDs were “still being considered
25 Response at 8-9.



11
and installed when the benefits match the expenditure.
”26 For example, it cited the example of a
block valve that had been installed as a “risk mitigation project,” which showed that BPL was
the allegation.
“not opposed to adding EFRDs.”27 The company, however, did not contest the facts set out in
BPL’s spending on other maintenance projects does not lessen the potential consequences of the
violation at hand, nor do budgetary considerations absolve BPL of its obligation to comply with
the regulation and its own IMP. Accordingly, after considering all of the evidence, I find that
Respondent violated 49 C.F.R. § 195.452(i)(4) by failing to determine whether EFRDs were
needed on its pipeline to protect against failures, and, if so, to install them.
These findings of violation will be considered prior offenses in any subsequent enforcement
action taken against Respondent.
ASSESSMENT OF PENALTY
Under 49 U.S.C. § 60122, Respondent is subject to an administrative civil penalty not to exceed
$100,000 per violation for each day of the violation, up to a maximum of $1,000,000 for any
related series of violations. In determining the amount of a civil penalty under
49 U.S.C. § 60122 and 49 C.F.R. § 190.225, I must consider the following criteria: the nature,
circumstances, and gravity of the violation, including adverse impact on the environment; the
degree of Respondent’s culpability; the history of Respondent’s prior offenses; the Respondent’s
ability to pay the penalty and any effect that the penalty may have on its ability to continue doing
business; and the good faith of Respondent in attempting to comply with the pipeline safety
regulations. In addition, I may consider the economic benefit gained from the violation without
any reduction because of subsequent damages, and such other matters as justice may require.
The Notice proposed a total civil penalty of $645,200 for the violations cited above.
Item 3: The Notice proposed a civil penalty of $41,500 for Respondent’s violation of
49 C.F.R. § 195.402(a), for failing to follow its own manual of written procedures for conducting
normal O&M activities and handling abnormal operations and emergencies. As noted above, I
found that BPL failed to conduct root cause analyses in 25 accident reports, as required by its
O&M procedures. Respondent argued, however, that the penalty should be “rescinded” because
BPL had recognized the need to ensure root cause analyses were done, and had created a job
position for this purpose two years before the OPS inspection. I fail to see any basis for
rescission or reduction of the penalty. Recognizing a need to comply and actually complying are
two different things. Respondent’s arguments do not mitigate the fact that BPL prepared 25
accident reports during 2002–2007 that did not include a root cause analysis, as required by its
own procedures.
A root cause analysis is an important tool for identifying safety problems before they cause
accidents. Presumably, this is the very reason BPL included the requirement in its O&M
manual. The gravity of the violation is not mitigated by the fact that BPL recognized the
26 Response at 9.
27 Id.



12
problem and made plans to correct it. On the contrary, it is troubling to see that the violation
continued for years because the company apparently did not place a high enough priority on
investigating the root causes of 25 separate accidents or complying with its own internal
procedures. BPL has not presented any evidence or argument that would justify a reduction or
elimination of the proposed penalty. Accordingly, having reviewed the record and considered
the assessment criteria, I assess Respondent a civil penalty of $41,500 for violation of
49 C.F.R. § 195.402(a).
Item 4: The Notice proposed a civil penalty of $29,000 for Respondent’s violation of
49 C.F.R. § 195.403(b), for failing to review with company personnel their performance in
meeting the objectives of BPL’s emergency response training program, at intervals not
exceeding 15 months but at least once each calendar year. I found that, while Respondent used a
form to document employee responses to emergencies, it did not document such reviews on the
forms and did not provide PHMSA with copies of any completed forms to demonstrate that the
required reviews had actually been conducted.
Adequate emergency response training is essential to the safety of the public and protection of
the environment in the event of emergencies. Respondent’s failure to review or document the
performance of its personnel reduced the safety of its operations insofar as the company had no
established method of regularly reviewing employee performance that was related specifically to
emergency response. Accordingly, having reviewed the record and considered the assessment
criteria, I assess Respondent a civil penalty of $29,000 for violations of 49 C.F.R. § 195.403(b).
Item 7: The Notice proposed a civil penalty of $14,000 for Respondent’s violation of
49 C.F.R. § 195.583(a), for failing to inspect the above-ground pipeline facilities at the Mantua
Station for atmospheric corrosion at least once every three calendar years, but at intervals not
exceeding 39 months. BPL neither contested the allegation nor presented any evidence or
argument justifying a reduction in the proposed penalty; therefore, I found that Respondent failed
to inspect each pipeline exposed to the atmosphere for atmospheric corrosion at the required
intervals. Atmospheric corrosion at the Mantua Station could result in a release of hazardous
liquids, thus posing a risk to life, property and the environment. Accordingly, having reviewed
the record and considered the assessment criteria, I assess Respondent a civil penalty of $14,000
for violation of 49 C.F.R. § 195.583(a).
Item 8: The Notice proposed a civil penalty of $14,000 for Respondent’s violation of
49 C.F.R. § 195.573(c), for failing to check several rectifiers for proper performance at the
required frequency. Respondent contested the allegations relating to the Harristown Shell
system but not the others. As discussed above, I found that Respondent was required to check
the locked-out rectifiers before putting them back into service. The proposed penalty amount
reflects the fact that neither pipeline integrity nor safe operations were seriously affected by the
violations. Based upon the foregoing, I assess Respondent a civil penalty of $14,000 for
violation of 49 C.F.R. § 195.573(c).
Item 9: The Notice proposed a civil penalty of $35,300 for Respondent’s violation of
49 C.F.R. § 195.571, for failing to ensure that cathodic protection for the company’s pipeline
facilities at the Airport complied with the NACE Standard. BPL failed to take any pipe-to-soil
readings at the Airport from October 2006 until October 2008, and therefore the adequacy of the



13
cathodic protection at this location was unknown. As noted above, I found that BPL’s failure to
gain access to the Airport did not serve to refute the allegation of violation.
BPL has a responsibility to ensure that its facilities can be operated safely, which includes
maintaining adequate cathodic protection. The potential failure of this pipeline in an HCA near
the Airport could jeopardize the safety and operation of an important facility where the public
often congregates in large numbers. The importance of ensuring adequate cathodic protection at
such a facility increases the gravity of the violation, as does its duration. BPL has not presented
any evidence or argument justifying a reduction or elimination of the proposed penalty.
Accordingly, having reviewed the record and considered the assessment criteria, I assess
Respondent a civil penalty of $35,300 for violation of 49 C.F.R. § 195.571.
Item 11: The Notice proposed a civil penalty of $29,000 for Respondent’s violation of
49 C.F.R. § 195.573(e), for failing to correct, within a reasonable time, identified deficiencies in
corrosion control. Respondent’s work orders showed that several locations having low cathodic
protection readings along the pipeline had been scheduled for work between 2005 and 2007 but
the work had not been completed by the time of the PHMSA inspections in 2008. BPL neither
contested the allegation nor presented any evidence or argument justifying a reduction in the
proposed penalty. Inadequate cathodic protection can result in pipeline leaks and the release of
hazardous liquid. Two of the identified deficiencies were located within an HCA, thus
aggravating the gravity of the violation. Accordingly, having reviewed the record and
considered the assessment criteria, I assess Respondent a civil penalty of $29,000 for violation of
49 C.F.R. § 195.573(e).
Item 13: The Notice proposed a civil penalty of $41,500 for Respondent’s violation of
49 C.F.R. § 195.402(a), for failing to follow its own manual of written procedures for conducting
normal O&M activities and for handling abnormal operations and emergencies. BPL neither
contested the allegation nor presented any evidence or argument justifying a reduction in the
proposed penalty. As noted above, I found that Respondent failed on two occasions to repair
abnormal conditions, as required by its written procedures. These conditions potentially affected
HCAs, meaning the safety of the public and the environment were at increased risk. Therefore,
the gravity of the violation supports the proposed penalty. Accordingly, having reviewed the
record and considered the assessment criteria, I assess Respondent a civil penalty of $41,500 for
violation of 49 C.F.R. § 195.402(a).
Item 14: The Notice proposed a civil penalty of $120,300 for Respondent’s violation of
49 C.F.R. § 195.452(j)(2), for failing to conduct periodic evaluations as frequently as needed to
assure pipeline integrity. As discussed above, the allegation is withdrawn. Therefore, I also
withdraw the proposed penalty for violation of 49 C.F.R. § 195.452(j)(2).
Item 17: The Notice proposed a civil penalty of $200,300 for Respondent’s violation of
49 C.F.R. § 195.452(f)(6), for failing to include a process in its IMP for identifying P&M
measures to protect HCAs. As noted above, I found that BPL failed to produce evidence of a
P&M process that was in effect as of the date the PHMSA inspection began in May 2008.
Early identification and implementation of P&M measures can help prevent some or all of the
damage that can result from a pipeline failure. The unique features of each pipeline, the terrain



14
and environment around the pipeline, and the particular features of the surrounding community
mean that each operator must implement a process uniquely tailored to its own individual
system. This process is a critical element of the IMP and helps to ensure its efficacy. Such a
process was required to be in BPL’s written IMP no later than March 2002, but there is no
evidence that it was in place by the time of the inspection in May 2008.
More than half of BPL’s pipelines are either located within or could affect HCAs. The company
is therefore required to implement and maintain a complete IMP to protect the public and the
environment in HCAs from potentially dangerous pipeline failures. The failure to do so is a
serious violation of the integrity management regulations, as a pipeline failure in or near an HCA
could have catastrophic consequences for the public and the environment. Therefore the nature
and gravity of the violation and BPL’s culpability justify the proposed penalty.
This violation continued for years, yet the amount of the proposed penalty is far below the limit
of $100,000 per violation per day. BPL has not presented any other evidence or argument
justifying a reduction or elimination of the proposed penalty. Accordingly, having reviewed the
record and considered the assessment criteria, I assess Respondent a civil penalty of $200,300 for
violation of 49 C.F.R. § 195.452(f)(6).
Item 19: The Notice proposed a civil penalty of $120,300 for Respondent’s violation of
49 C.F.R. § 195.452(i)(4), for failing to determine whether EFRDs were needed on its pipeline to
protect against failures that could affect HCAs. Specifically, it alleged that BPL had failed to
conduct annual EFRD analyses of pipeline segments scheduled for integrity re-assessments and
to install EFRDs that the company had previously determined were needed.
BPL’s defense was that instead of installing the EFRDs, the company had allocated funds to
other repairs with greater risk-mitigation benefits. In addition, Respondent noted that it had
dramatically increased spending on pipeline maintenance between 2000 and 2008.
EFRDs have been shown to be effective in mitigating the consequences of many hazardous
liquid pipeline releases. If the need for EFRDs is not assessed and appropriate action taken, a
pipeline failure can cause additional damage that could have been prevented, thereby putting the
environment and public safety at unnecessary risk. Spending on other maintenance activities,
while commendable, does not mitigate an operator’s duty to conduct EFRD evaluations and
install them as needed, as required under both § 195.452(i)(4) and the company’s own
procedures. That BPL did not complete the EFRD installations that were recommended in its
own 2002 evaluation is particularly troubling because the company recognized a safety hazard
but consciously decided to forego action that could mitigate the effects of a spill. Therefore, the
nature and gravity of the violation and the culpability of the operator justify the proposed penalty
amount.
BPL has not presented any other evidence or argument justifying a reduction or elimination of
the proposed penalty. Accordingly, having reviewed the record and considered the assessment
criteria, I assess Respondent a civil penalty of $120,300 for violation of
49 C.F.R. § 195.452(i)(4).



15
In summary, having reviewed the record and considered the assessment criteria for each of the
Items cited above, I assess Respondent a total civil penalty of $524,900.
Payment of the civil penalty must be made within 20 days of service. Federal regulations
(49 C.F.R. § 89.21(b)(3)) require such payment to be made by wire transfer through the Federal
Reserve Communications System (Fedwire), to the account of the U.S. Treasury. Detailed
instructions are contained in the enclosure. Questions concerning wire transfers should be
directed to: Financial Operations Division (AMZ-341), Federal Aviation Administration, Mike
Monroney Aeronautical Center, P.O. Box 269039, Oklahoma City, Oklahoma 73125. The
Financial Operations Division telephone number is (405) 954-8893.
Failure to pay the $524,900 civil penalty will result in accrual of interest at the current annual
rate in accordance with 31 U.S.C. § 3717, 31 C.F.R. § 901.9 and 49 C.F.R. § 89.23. Pursuant to
those same authorities, a late penalty charge of six percent (6%) per annum will be charged if
payment is not made within 110 days of service. Furthermore, failure to pay the civil penalty
may result in referral of the matter to the Attorney General for appropriate action in a district
court of the United States.
COMPLIANCE ORDER
The Notice proposed a compliance order with respect to Items 3, 9, 17, and 19 in the Notice for
violations of 49 C.F.R. §§ 195.402(a), 195.571, 195.452(f)(6), and 195.452(i)(4), respectively.
Under 49 U.S.C. § 60118(a), each person who engages in the transportation of hazardous liquids
or who owns or operates a pipeline facility is required to comply with the applicable safety
standards established under chapter 601. Pursuant to the authority of 49 U.S.C. § 60118(b) and
49 C.F.R. § 190.217, Respondent is ordered to take the following actions to ensure compliance
with the pipeline safety regulations applicable to its operations:
1. With respect to the violation of § 195.402(a) (Item 3), Respondent must develop a
plan to ensure that a root cause analysis is conducted and documented for all
accidents, as required by BPL’s O&M Manual, and that any corrective actions
recommended by each analysis are implemented.
2. With respect to the violation of § 195.571 (Item 9), Respondent must establish and
implement a plan to gain access to BPL facilities at the Philadelphia Airport in order
to ensure its cathodic protection complies with paragraphs 6.2 and 6.3 of NACE
Standard SP 0169.
3. With respect to the violation of § 195.452(f)(6) (Item 17), Respondent must establish
and implement processes to evaluate its pipeline segments for additional P&M
measures. Upon completion of the evaluation of pipeline segments, a schedule for
implementing any needed P&M actions must be submitted.
4. With respect to the violation of § 195.452(i)(4) (Item 19), Respondent must establish
an improved process to evaluate the need for additional EFRDs. Upon establishment
of the improved process, Respondent must perform EFRD evaluations on its pipeline



16
segments, develop a schedule for installing EFRDs where necessary, and document
the reasoning for why EFRDs are not necessary for all locations Respondent
considered.
5. Respondent must submit a plan and schedule for completing the Compliance Order
items listed above to PHMSA for review and approval within 60 days after receipt of
the Final Order. Upon receiving approval of the plan and schedule, Respondent must
submit evidence of completion for the Compliance Order items listed above to
PHMSA within 180 days after receipt of the Final Order. Submit all correspondence
for review and approval to the Director, Eastern Region, Office of Pipeline Safety,
PHMSA, 820 Bear Tavern Road, Suite 306, West Trenton, NJ 08628.
6. It is requested that Respondent maintain documentation of the safety improvement
costs associated with fulfilling this Compliance Order and submit that total to the
Director, Eastern Region, PHMSA. It is requested that costs be reported in two
categories: (1) total cost associated with preparation and revision of plans,
procedures, studies and analyses; and (2) total cost associated with replacements,
additions and other changes to pipeline infrastructure.
The Director may grant an extension of time to comply with any of the required items upon a
written request timely submitted by the Respondent and demonstrating good cause for an
extension.
Failure to comply with this Order may result in the administrative assessment of civil penalties
not to exceed $100,000 per violation for each day the violation continues or in referral to the
Attorney General for appropriate relief in a district court of the United States.
WARNING ITEMS
With respect to Items 1, 2, 5, 6, 10, 12, 15, 16, 18, 20, 21, and 22, the Notice alleged probable
violations of Part 195 but did not propose a civil penalty or compliance order for these items.
Therefore, these are considered to be warning items. The warnings were for:
49 C.F.R. § 195.401(b) (Item 1) – Respondent’s alleged failure to correct four
conditions that could have adversely affected the safe operation of its pipeline within a
reasonable time.
49 C.F.R. § 195.402(a) (Item 2) – Respondent’s alleged failure to review and update its
operations, maintenance, and emergency manuals at intervals not exceeding 15 months,
but at least once each calendar year. Respondent claimed that its manual review process
satisfied the requirements of § 195.402(a) and that it had revised its procedures to
include a documented annual review of its manuals.28
However, Respondent did not
provide any evidence that the reviews had been conducted at the required intervals.
28 Response at 2.



17
49 C.F.R. § 195.412(a) (Item 5) – Respondent’s alleged failure to inspect the surface
conditions on or adjacent to each pipeline right-of-way at intervals not exceeding 3
weeks, but at least 26 times a year.
49 C.F.R. § 195.557 (Item 6) – Respondent’s alleged failure to provide coating for
external corrosion control as required for certain pipelines.
49 C.F.R. § 195.573(e) (Item 10) – Respondent’s alleged failure to correct identified
deficiencies in external corrosion control within a reasonable time period. Cathodic
protection survey test results in 2006 and 2007 identified inadequate levels of cathodic
protection, but this condition was not addressed until 2008. In its Response, BPL
claimed these test results were not indicative of a deficiency in corrosion control, but
were simply the result of defective test leads.29
Regardless of the cause of the test
results, the condition needed to be corrected before the next annual test.
49 C.F.R. § 195.438 (Item 12) – Respondent’s alleged failure to prohibit smoking and
open flames at each pump station and breakout tank area where there was a possibility
of leakage of a flammable hazardous liquid or the presence of flammable vapors. BPL
had “No Smoking” signs at some, but not all, tank areas, and not at the entrance to tank
dikes at the Booth Station, an inconsistency that could confuse workers and visitors
regarding where it was safe to smoke within the facility. In its Response, BPL claimed
that signs were not required at each tank dike since the company had signs on its
perimeter fences and its written policy prohibited smoking inside the fenced areas.
30
While it is necessary and appropriate for operators to have written policies prohibiting
smoking and open flames in pump station areas, the existence of such procedures alone
does not constitute compliance with the regulation.31
In addition, the presence of “No
Smoking” signs at some, but not all, tank areas could lead to confusion and an
ineffective implementation of the “no smoking” policy.
49 C.F.R. § 195.452(b)(2) (Items 15 and 16) – Respondent’s alleged failure to identify
all pipelines that could affect a HCA.
49 C.F.R. § 195.452(i)(2) (Item 18) – Respondent’s alleged failure to properly consider
all relevant risk factors in its evaluation of what P&M measures were needed to protect
HCAs in the event of a pipeline release.
49 C.F.R. § 195.452(f)(3) (Item 20) – Respondent’s alleged failure to continually update
its IMP to reflect relevant operating experience.
29 Response at 5.
30 Response at 6.
31 See In the Matter of Nustar Logistics, L.P., F/K/A Valero Logistics Operations, L.P., CPF No. 4-2005-5048
(March 11, 2009). Final orders are generally available on PHMSA website at
http://primis.phmsa.dot.gov/comm/reports/enforce/Actions_opid_0.html?nocache=8998#_TP_1_tab_2.



18
49 C.F.R. § 195.561(b) (Item 21) – Respondent’s alleged failure to properly repair any
coating damage discovered during an inspection of external pipe.
49 C.F.R. § 195.406(b) (Item 22) – Respondent’s alleged failure to provide adequate
controls and protective equipment to keep the surge pressure on the pipeline below
110% of the operating pressure limit established under § 195.406(a). The Notice listed
three documented events where the surge pressure exceeded 110% of the MOP. In its
Response, BPL stated that in two of these instances, the pressure did not actually exceed
110% of the MOP, and that the company’s Abnormal Operating Event forms had
mismarked the pressure due to an employee’s miscalculation. However, BPL did not
provide any evidence to substantiate this explanation. The third event was not
disputed.32
BPL presented information in its Response showing that it had taken certain actions to address
the cited items. Accordingly, having considered such information, I find, pursuant to
49 C.F.R. § 190.205, that probable violations of 49 C.F.R. § 195.401(b) (Item 1), § 195.402(a)
(Item 2), § 195.412(a) (Item 5), § 195.557 (Item 6), § 195.573(e) (Item 10), § 195.438 (Item 12),
§ 195.452(b)(2) (Items 15 and 16), § 195.452(i)(2) (Item 18), § 195.452(f) (Item 20),
§ 195.561(b) (Item 21), and § 195.406(b) (Item 22) have occurred and Respondent is hereby
advised to correct such conditions. In the event that OPS finds a violation of any of these items
in a subsequent inspection, Respondent may be subject to future enforcement action.
Under 49 C.F.R. § 190.215, Respondent has a right to submit a Petition for Reconsideration of
this Final Order. The petition must be sent to: Associate Administrator, Office of Pipeline
Safety, PHMSA, 1200 New Jersey Avenue, SE, East Building, 2nd Floor, Washington, DC
20590, with a copy sent to the Office of Chief Counsel, PHMSA, at the same address. PHMSA
will accept petitions received no later than 20 days after receipt of service of this Final Order by
the Respondent, provided they contain a brief statement of the issue(s) and meet all other
requirements of 49 C.F.R. § 190.215. The filing of a petition automatically stays the payment of
any civil penalty assessed. Unless the Associate Administrator, upon request, grants a stay, all
other terms and conditions of this Final Order are effective upon service in accordance with
49 C.F.R. § 190.5.
___________________________________ __________________________
Jeffrey D. Wiese Date Issued
Associate Administrator
for Pipeline Safety
32 Response at 10.

## Provenance

- Official: Yes
- Source: <https://primis.phmsa.dot.gov/enforcement-data/case/120095002>
- Source ID: `phmsa-enforcement`
- SHA-256: `c321ace1c4d2027cf3b62819c57a3e47b801ca2c78606bd9beecc52685e2e302`
- Retrieved: 2026-08-20T04:44:44.458Z
- Exported: 2026-08-22T11:49:26.160Z
- Document slug: `phmsa-enforcement-120095002`

### Source metadata

```json
{
  "cpf": "120095002",
  "operator": "BUCKEYE PARTNERS, LP",
  "region": "Eastern",
  "pipelineType": "INTERSTATE LIQUID ONSHORE",
  "caseStatus": "CLOSED",
  "citedSections": [
    "195.401(b)",
    "195.402(a)",
    "195.403(b)",
    "195.406(b)",
    "195.412(a)",
    "195.438",
    "195.452(b)(2)",
    "195.452(f)(3)",
    "195.452(f)(6)",
    "195.452(i)(2)",
    "195.452(i)(4)",
    "195.452(j)(2)",
    "195.557(a)",
    "195.561",
    "195.571",
    "195.573(c)",
    "195.573(e)",
    "195.583(a)"
  ],
  "dataAsOf": "08/04/2026 12PM",
  "caseDataAsOf": "2026-08-04",
  "attachmentCount": 7,
  "attachments": [
    {
      "name": "120095002_ Operator Response to Notice letter_09252009.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/120095002/120095002_%20Operator%20Response%20to%20Notice%20letter_09252009.pdf",
      "bytes": 2666313,
      "category": "party_submission"
    },
    {
      "name": "120095002_Closure Letter_06172013.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/120095002/120095002_Closure%20Letter_06172013.pdf",
      "bytes": 219394,
      "category": "agency_document"
    },
    {
      "name": "120095002_Closure Letter_06172013_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/120095002/120095002_Closure%20Letter_06172013_text.pdf",
      "bytes": 12736,
      "category": "agency_document"
    },
    {
      "name": "120095002_Final Order _05302012.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/120095002/120095002_Final%20Order%20_05302012.pdf",
      "bytes": 1035446,
      "category": "agency_document"
    },
    {
      "name": "120095002_Final_Order_05302012_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/120095002/120095002_Final_Order_05302012_text.pdf",
      "bytes": 109650,
      "category": "agency_document"
    },
    {
      "name": "120095002_NOPV-PCP-PCO_06262009.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/120095002/120095002_NOPV-PCP-PCO_06262009.pdf",
      "bytes": 1296280,
      "category": "agency_document"
    },
    {
      "name": "120095002_NOPV-PCP-PCO_06262009_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/120095002/120095002_NOPV-PCP-PCO_06262009_text.pdf",
      "bytes": 79029,
      "category": "agency_document"
    }
  ],
  "extractedAgencyDocumentCount": 4,
  "attachmentPolicy": "Official attachment links are retained. Agency-issued documents may also include a verified local PDF and page-level text representation.",
  "jurisdiction": "US",
  "operatorName": "BUCKEYE PARTNERS, LP"
}
```
