# EASTERN GAS TRANSMISSION AND STORAGE, INC. — Notice of Probable Violation

**Citation:** CPF 120121015  
**Type / status:** enforcement / historical  
**Agency:** Pipeline and Hazardous Materials Safety Administration  
**Effective:** Not stated  
**Published:** 2012-05-29

CLOSED notice of probable violation citing 192.163(e), 192.603(b).

## Document text

Notice of Probable Violation involving EASTERN GAS TRANSMISSION AND STORAGE, INC.. PHMSA's enforcement data identifies the cited regulations as 192.163(e),  192.603(b). The case was opened on 2012-05-29 and is reported as closed as of 2013-09-27. Proposed civil penalty: $174,500. Assessed civil penalty: $43,700. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

120121015_Closure Letter_09272013.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120121015/120121015_Closure%20Letter_09272013.pdf

120121015_Closure letter_09272013_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120121015/120121015_Closure%20letter_09272013_text.pdf

120121015_Final Order_07262013.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120121015/120121015_Final%20Order_07262013.pdf

120121015_Final Order_07262013_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120121015/120121015_Final%20Order_07262013_text.pdf

120121015_NOPV_PCP_PCO_05292012.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120121015/120121015_NOPV_PCP_PCO_05292012.pdf

120121015_NOPV_PCP_PCO_05292012_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120121015/120121015_NOPV_PCP_PCO_05292012_text.pdf

120121015_Operator Response_06282012.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120121015/120121015_Operator%20Response_06282012.pdf

120121015_Final Order_07262013_text.pdf

JULY 26, 2013
Mr. Thomas F. Farrell, II
President
Dominion Resources Services, Inc.
701 East Cary St.
Richmond, VA 23219
Re: CPF No. 1-2012-1015
Dear Mr. Farrell:
Enclosed please find the Final Order issued in the above-referenced case. It makes a finding of
violation, assesses a reduced civil penalty of $43,700, and specifies actions that need to be taken
by Dominion Transmission, Inc., to comply with the pipeline safety regulations. It also
withdraws several other allegations of violation in the Notice of Probable Violation.
The penalty payment terms are set forth in the Final Order. When the civil penalty has been paid
and the terms of the compliance order completed, as determined by the Director, Eastern Region,
this enforcement action will be closed. Service of the Final Order by certified mail is deemed
effective upon the date of mailing, or as otherwise provided under 49 C.F.R. § 190.5.
Thank you for your cooperation in this matter.
Sincerely,
Jeffrey D. Wiese
Associate Administrator
for Pipeline Safety
Enclosure
cc: Mr. Byron Coy, Director, Eastern Region, OPS
Mr. Alan Mayberry, Deputy Associate Administrator for Field Operations, OPS
Mr. Jeffrey Barger, Senior Vice President, Dominion Transmission, Inc., 445 West Main
Street, Clarksburg, WV 26301
CERTIFIED MAIL - RETURN RECEIPT REQUESTED



U.S. DEPARTMENT OF TRANSPORTATION
PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION
OFFICE OF PIPELINE SAFETY
WASHINGTON, D.C. 20590
____________________________________
In the Matter of )
Dominion Transmission, Inc., ) CPF No. 1-2012-1015
)
)
)
Respondent. )
____________________________________)
FINAL ORDER
Between August 4-6, 2009, and June 22, 2010, pursuant to 49 U.S.C. § 60117, a representative
of the West Virginia Public Service Commission, as agent for the Pipeline and Hazardous
Materials Safety Administration (PHMSA), Office of Pipeline Safety (OPS), conducted an on-
site pipeline safety inspection of the facilities and records of Dominion Transmission, Inc.
(Dominion or Respondent), in Clarksburg, West Virginia. Dominion is a subsidiary of
Dominion Resources Services, Inc., and operates approximately 7,800 miles of pipeline in six
states — Ohio, West Virginia, Pennsylvania, New York, Maryland and Virginia.1
As a result of the inspection, the Director, Eastern Region, OPS (Director), issued to Respondent,
by letter dated May 29, 2012, a Notice of Probable Violation, Proposed Civil Penalty, and
Proposed Compliance Order (Notice). In accordance with 49 C.F.R. § 190.207, the Notice
proposed finding that Dominion had committed various violations of 49 C.F.R. Part 192 and
proposed assessing a civil penalty of $174,500 for the alleged violations. The Notice also
proposed ordering Respondent to take certain measures to correct the alleged violations.
Dominion responded to the Notice by letters dated June 28, 2012, and July 16, 2012
(collectively, Response). The company contested the allegations, offered additional information
in response to the Notice, and requested that the proposed civil penalty be eliminated.
Respondent did not request a hearing and therefore has waived its right to one.
FINDING OF VIOLATION
The Notice alleged that Respondent violated 49 C.F.R. Part 192, as follows:
Item 2: The Notice alleged that Respondent violated 49 C.F.R. § 192.163(e), which states:
§ 192.163 Compressor stations: Design and construction.
(a) . . .
1 See https://www.dom.com/business/gas-transmission/ (last accessed on May 10, 2013).



2
(e) Electrical facilities. Electrical equipment and wiring installed in
compressor stations must conform to the National Electrical Code,
ANSI/NFPA 70, so far as that code is applicable.
The Notice alleged that Respondent violated 49 C.F.R. § 192.163(e) by failing to install
electrical equipment and wiring at the company’s Bridgeport Compressor Station in
conformance with the National Electrical Code (NEC), ANSI/NFPA 70. Specifically, the Notice
alleged that Dominion failed to comply with NEC Article 501.5(b), which requires operators to
install a conduit seal within 18 inches of the explosion-proof housing for the breaker/starter
switch associated with the jacket water circulation pump.
In its Response, Dominion argued that Article 501.5(b) is not applicable to the equipment cited
in the Notice because that article was not included in the 2008 version of the NEC. The 2008
edition is the version currently incorporated by reference in the pipeline safety standards.
Therefore, Dominion requested that PHMSA withdraw this item.
I have reviewed the Notice, the Violation Report, and the Response. The equipment covered by
this alleged violation was installed prior to 2000. 2 At the time of the installation, the 1996
edition of the NEC controlled, as it was the version of the NEC incorporated in the pipeline
safety regulations at that time.
3 Therefore, Dominion was required to comply with the 1996
edition of the National Electrical Code when it installed the conduit seal, not the 2008 edition.
Regardless, the two editions are quite similar. Article 501.5(b)(l) of NEC (1996) states: “For
connections to explosion proof enclosures that are required to be approved for Class 1 locations,
seals shall be provided in accordance with [501.5](a)(1), (a)(2), and (a)(3) above.” Further,
Article 501.5(a)(l) states that "[i]n each conduit run entering an enclosure for switches, circuit
breakers, fuses, relays, resistors, or other apparatus that may produce enclosure for switches,
circuit breakers, fuses, relays, resistors, or other apparatus that may produce arcs, sparks, or high
temperatures in normal operation, seals shall be installed within 18 in (457 mm) from such
enclosures..." Article 501.15(A)(l) of NEC (2008) states that "[f]actory-sealed enclosures shall
not be considered to serve as a seal for another adjacent explosion proof enclosure that is
required to have a conduit seal. Conduit seals shall be installed within 450 mm (18 in.) from the
enclosure..."
The record shows that Dominion failed to follow NEC, ANSI/NFPA70 (1996), which was in
effect at the time the Bridgeport Compressor Station was designed and constructed, and required
that seals be installed within 450 mm (18 in.) from the enclosure. Accordingly, based upon a
review of all of the evidence, I find that Respondent violated 49 C.F.R. § 192.163(e) by failing to
install electrical equipment and wiring at the company’s Bridgeport Compressor Station in
conformance with the NEC, ANSI/NFPA 70.
2 Dominion personnel informed OPS during the inspection that the conduit seal was installed prior to 2000. See
Pipeline Safety Violation Report (Violation Report), (May 29, 2012) (on file with PHMSA).
3 The agency incorporated the 1996 version by Final Rule on June 24, 1996. This particular standard was not
updated in Part 192 until 2006, at which time, the agency incorporated the 2005 version of the National Electrical
Code. In 2010, the agency incorporated the 2008 edition of the NEC.



3
This finding of violation will be considered a prior offense in any subsequent enforcement action
taken against Respondent.
WITHDRAWAL OF ITEMS
Item 1: The Notice alleged that Respondent violated 49 C.F.R. § 192.163(e), as quoted above,
by failing to install electrical equipment and wiring at the Bridgeport Compressor Station in
conformance with the NEC, ANSI/NFPA 70. Specifically, it alleged that Dominion failed to
install proper grounding conductors and systems in conformance with Articles 250.5(b),
250.42(a), (d), and (f), and 250.81(b) of the NEC. In the Notice, OPS alleged that at the time of
its inspection, there were no grounding conductors for the micro-turbine generators at the station.
Respondent contested this probable violation, arguing that the Articles referenced in this Item
were not present in NEC (2008), which is the edition currently incorporated by reference in the
pipeline safety regulations. In addition, Dominion stated that it did perform an evaluation of the
two micro-turbine generators and determined that these devices were indeed equipped with
grounding conductors. As a result, Dominion requested that this item be withdrawn.
After reviewing the materials submitted with the Response, I agree that Respondent complied
with § 192.163(e) because the devices were properly equipped with grounding conductors at the
estimated date of installation. Accordingly, based upon a review of all the evidence, I am
withdrawing Item # 1.
Item 3: The Notice alleged that Respondent violated 49 C.F.R. § 192.163(e), as quoted above,
by failing to install electrical equipment and wiring at the Bridgeport Compressor Station in
conformance with the NEC, ANSI/NFPA 70. Specifically, it alleged that Dominion failed to
comply with NEC Article 230.95(c), which requires a performance test when the ground fault
protection system is first installed on site, and requires a written record of the test be created.
OPS alleged that at the time of its inspection, the operator was unable to produce any records of
this post-construction performance test.
Dominion first acknowledged that it had been unable to locate the records associated with the
performance tests. However, in its supplementary Response dated July 16, 2012, Dominion
contended that Article 230.95 was not applicable to the Bridgeport Compressor Station because
(1) the micro-turbines providing power to the Bridgeport Compressor Station did not deliver
power from a “serving utility,” as defined in Article 230.1, and (2) the combined rating of the
micro-turbines was 200 amperes. Dominion argued that Article 230.95 only requires ground
fault protection systems for systems rated at 1000 amperes or more. As a result, Dominion
requested that this item be withdrawn.
After reviewing the materials submitted with the Response, I agree that this requirement applies
only to facilities with a minimum combined rating of 1000 amperes. Dominion’s facility had a
rating of 200 amperes. Therefore, I am withdrawing Item # 3.
Item 4: The Notice alleged that Respondent violated 49 C.F.R. § 192.163(e), as quoted above,
by failing to install electrical equipment and wiring at the Bridgeport Compressor Station in
conformance with the NEC, ANSI/NFPA 70. Specifically, it alleged that Dominion failed to



4
have grounding conductors with a continuous outer finish that was either solid green or green
with one or more yellow stripes. NEC Article 230.57(b) requires that such conductors either be
solid green or green with one or more yellow stripes. The grounding wires for the Dominion
motor control center for the suction, discharge, and bypass of compressor engine number 1 at the
Bridgeport Compressor Station allegedly had a red continuous outer finish.
Respondent contested this probable violation, arguing that Article 230.57(b) is not included in
NEC (2008) and therefore is not applicable to Dominion. In addition, the company confirmed
that the wires in question are marked with green tape in compliance with NEC 230.57(b). As a
result, Dominion requested that this item be withdrawn.
After reviewing the materials and photographic evidence submitted with the Response, I agree
that Respondent has complied with 49 C.F.R. § 192.163(e) because the wires are marked with
green tape. Therefore, I am withdrawing Item # 4.
Item 5: The Notice alleged that Respondent violated 49 C.F.R. § 192.603(b), which states:
§ 192.603 General provisions.
(a) . . .
(b) Each operator shall keep records necessary to administer the
procedures established under § 192.605.
The Notice alleged that Respondent violated 49 C.F.R. § 192.603(b) by failing to keep records
necessary to administer the procedures established under § 192.605. Dominion had replaced all
segments of pipeline TL-260 except for two segments. During the OPS inspection, Dominion
staff had stated that the maximum allowable operating pressure (MAOP) for the two segments
had been determined in accordance with § 192.619(c), but had been unable to provide the
relevant MAOP records.
Respondent contested this alleged violation. Dominion confirmed that the MAOP for the entire
pipeline line was 460 psig, as established under § 192.619(c), and that the supporting MAOP
records were in fact provided to the West Virginia inspector during the inspection. In its
Response, Dominion provided PHMSA with an additional copy of the records.
The records show a discharge pressure of 460 psig that was attained multiple times between
November 4-5, 1969. This documentation substantiates a 460 psig MAOP during the prescribed
five-year period required by § 192.619(c)(3). Upon reviewing the materials submitted with the
Response, including the MAOP records, I agree that Respondent has complied with
49 C.F.R. § 192.603(b). Therefore, I am withdrawing Item #5.
ASSESSMENT OF PENALTY
As discussed above, I have withdrawn Items #1, 3, 4, and 5. Therefore, the proposed civil
penalty amounts associated with those items are also withdrawn.
Under 49 U.S.C. § 60122, Respondent is subject to an administrative civil penalty not to exceed
$100,000 per violation for each day of the violation, up to a maximum of $1,000,000 for any



5
related series of violations. In determining the amount of a civil penalty under
49 U.S.C. § 60122 and 49 C.F.R. § 190.225, I must consider the following criteria: the nature,
circumstances, and gravity of the violation, including adverse impact on the environment; the
degree of Respondent’s culpability; the history of Respondent’s prior offenses; the Respondent’s
ability to pay the penalty and any effect that the penalty may have on its ability to continue doing
business; and the good faith of Respondent in attempting to comply with the pipeline safety
regulations. In addition, I may consider the economic benefit gained from the violation without
any reduction because of subsequent damages, and such other matters as justice may require.
The Notice proposed a total civil penalty of $43,700 for Item #2.
Item 2: The Notice proposed a civil penalty of $43,700 for Respondent’s violation of
49 C.F.R. § 192.163(e), for failing to install a conduit seal within 18 inches of the explosion-
proof housing for the breaker switch at the jacket water circulation pump. I have reviewed the
proposed civil penalty amount and find that the amount is appropriate, given that non-
compliance persisted over nine years (dating back to 2000), and that Dominion’s history of prior
offenses shows the company had committed eight other violations of the pipeline safety
regulations in the five years preceding the date of the Notice.4
Accordingly, having reviewed the record and considered the assessment criteria, I assess
Respondent a civil penalty of $43,700 for violation of 49 C.F.R. § 192.163(e).
In summary, having reviewed the record and considered the assessment criteria for the Item cited
above, I assess Respondent a total civil penalty of $43,700.
Payment of the civil penalty must be made within 20 days of service. Federal regulations
(49 C.F.R. § 89.21(b)(3)) require such payment to be made by wire transfer through the Federal
Reserve Communications System (Fedwire), to the account of the U.S. Treasury. Detailed
instructions are contained in the enclosure. Questions concerning wire transfers should be
directed to: Financial Operations Division (AMZ-341), Federal Aviation Administration, Mike
Monroney Aeronautical Center, P.O. Box 269039, Oklahoma City, Oklahoma 73125. The
Financial Operations Division telephone number is (405) 954-8893.
Failure to pay the $43,700 civil penalty will result in accrual of interest at the current annual rate
in accordance with 31 U.S.C. § 3717, 31 C.F.R. § 901.9 and 49 C.F.R. § 89.23. Pursuant to
those same authorities, a late penalty charge of six percent (6%) per annum will be charged if
payment is not made within 110 days of service. Furthermore, failure to pay the civil penalty
may result in referral of the matter to the Attorney General for appropriate action in a district
court of the United States.
COMPLIANCE ORDER
As discussed above, I have withdrawn Items 1, 3, 4, and 5 and therefore the proposed
compliance items associated with these items are also withdrawn.
4 The eight violations are listed in Part D of the Pipeline Safety Violation Report (History of Prior Offenses). See
also, CPF No. 1-2011-1011 and CPF No. 1-2010-1006.



6
The Notice proposed a compliance order with respect to Item #2 in the Notice for violation of
49 C.F.R. § 192.163(e), respectively. Under 49 U.S.C. § 60118(a), each person who engages in
the transportation of gas or who owns or operates a pipeline facility is required to comply with
the applicable safety standards established under chapter 601. Pursuant to the authority of
49 U.S.C. § 60118(b) and 49 C.F.R. § 190.217, Respondent is ordered to take the following
actions to ensure compliance with the pipeline safety regulations applicable to its operations:
1. With respect to the violation of § 192.163(e) (Item 2), Respondent must install a
conduit seal for the breaker/starter switch for the jacket water circulation pump
that complies with Article 501.15(A)(1) of the National Electrical Code,
ANSI/NFPA 70 (2008) within 120 days of receipt of the Final Order. The seal
must be installed within 450 mm (18 inches) from the enclosure.5
The Director may grant an extension of time to comply with any of the required items upon a
written request timely submitted by the Respondent and demonstrating good cause for an
extension.
Failure to comply with this Order may result in the administrative assessment of civil penalties
not to exceed $100,000 for each violation for each day the violation continues or in referral to the
Attorney General for appropriate relief in a district court of the United States.
Under 49 C.F.R. § 190.215, Respondent has a right to submit a Petition for Reconsideration of
this Final Order. The petition must be sent to: Associate Administrator, Office of Pipeline
Safety, PHMSA, 1200 New Jersey Avenue, SE, East Building, 2nd Floor, Washington, DC
20590, with a copy sent to the Office of Chief Counsel, PHMSA, at the same address. PHMSA
will accept petitions received no later than 20 days after receipt of service of this Final Order by
the Respondent, provided they contain a brief statement of the issue(s) and meet all other
requirements of 49 C.F.R. § 190.215. The filing of a petition automatically stays the payment of
any civil penalty assessed.
Unless the Associate Administrator, upon request, grants a stay, all other terms and conditions of
this Final Order are effective upon service in accordance with 49 C.F.R. § 190.5.
___________________________________ __________________________
Jeffrey D. Wiese Date Issued
Associate Administrator
for Pipeline Safety
5 Although Dominion failed to comply with NEC Article 501.5(b) (1996) at the time of the installation, the
Compliance Order addresses current regulations. Therefore, the conduit seal must be installed in accordance with
current pipeline safety requirements, namely, Article 501.15(A)(1) of the National Electrical Code, ANSI/NFPA 70
(2008). As discussed in the Findings section, the requirements of NEC (2008) and NEC (1996), in terms of the
conduit seal, are largely the same.

120121015_Closure letter_09272013_text.pdf

U.S. Department Of Transportation Pipeline and 609.989.2171
Hazardous Materials
Safety Administration
820 Bear Tavern Road, Suite 103
West Trenton, NJ 08628
OVERNIGHT EXPRESS MAIL
September 27, 2013
Mr. Jeffrey Barger, Sr. VP
Dominion Transmission, Inc.
445 West Main Street
Clarksburg, WV 26301
CPF 1-2012-1015
Dear Mr. Barger:
On July 26, 2013, the Pipeline and Hazardous Materials Safety Administration (PHMSA) issued
to Dominion Transmission, Inc. a Final Order in the above-referenced case. This Order included
a Compliance Order and Civil Penalty assessment. Based on our review of the documentation
you provided, and confirmation of payment of the civil penalty, it has been determined that you
have complied with the terms of this Order.
Accordingly, this case is now closed and no further action is contemplated with respect to the
matters involved in this case. Thank you for your cooperation in this matter.
Sincerely,
Byron Coy, PE
Director, Eastern Region
Pipeline and Hazardous Materials Safety Administration
Cc: David Hippchen, WV PSC

## Provenance

- Official: Yes
- Source: <https://primis.phmsa.dot.gov/enforcement-data/case/120121015>
- Source ID: `phmsa-enforcement`
- SHA-256: `f457587267263bd6ca76bd0814e79c88a954535b2272c9d710c5bc4098e43e57`
- Retrieved: 2026-08-20T04:44:44.458Z
- Exported: 2026-08-24T19:05:17.837Z
- Document slug: `phmsa-enforcement-120121015`

### Source metadata

```json
{
  "cpf": "120121015",
  "operator": "EASTERN GAS TRANSMISSION AND STORAGE, INC.",
  "region": "Eastern",
  "pipelineType": "GAS INTERSTATE ONSHORE",
  "caseStatus": "CLOSED",
  "citedSections": [
    "192.163(e)",
    "192.603(b)"
  ],
  "dataAsOf": "08/04/2026 12PM",
  "caseDataAsOf": "2026-08-04",
  "attachmentCount": 7,
  "attachments": [
    {
      "name": "120121015_Closure Letter_09272013.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/120121015/120121015_Closure%20Letter_09272013.pdf",
      "bytes": 84014,
      "category": "agency_document"
    },
    {
      "name": "120121015_Closure letter_09272013_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/120121015/120121015_Closure%20letter_09272013_text.pdf",
      "bytes": 12665,
      "category": "agency_document"
    },
    {
      "name": "120121015_Final Order_07262013.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/120121015/120121015_Final%20Order_07262013.pdf",
      "bytes": 462973,
      "category": "agency_document"
    },
    {
      "name": "120121015_Final Order_07262013_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/120121015/120121015_Final%20Order_07262013_text.pdf",
      "bytes": 34474,
      "category": "agency_document"
    },
    {
      "name": "120121015_NOPV_PCP_PCO_05292012.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/120121015/120121015_NOPV_PCP_PCO_05292012.pdf",
      "bytes": 1061558,
      "category": "case_document"
    },
    {
      "name": "120121015_NOPV_PCP_PCO_05292012_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/120121015/120121015_NOPV_PCP_PCO_05292012_text.pdf",
      "bytes": 38567,
      "category": "case_document"
    },
    {
      "name": "120121015_Operator Response_06282012.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/120121015/120121015_Operator%20Response_06282012.pdf",
      "bytes": 1847945,
      "category": "party_submission"
    }
  ],
  "extractedAgencyDocumentCount": 2,
  "attachmentPolicy": "Official attachment links are retained. Agency-issued documents may also include a verified local PDF and page-level text representation.",
  "jurisdiction": "US",
  "operatorName": "EASTERN GAS TRANSMISSION AND STORAGE, INC."
}
```
