# COLUMBIA GAS TRANSMISSION, LLC — Corrective Action Order

**Citation:** CPF 120121025H  
**Type / status:** enforcement / historical  
**Agency:** Pipeline and Hazardous Materials Safety Administration  
**Effective:** Not stated  
**Published:** 2012-12-20

CLOSED corrective action order.

## Document text

Corrective Action Order involving COLUMBIA GAS TRANSMISSION, LLC. The dataset does not identify a cited regulation for this case. The case was opened on 2012-12-20 and is reported as closed as of 2014-04-02. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

120121025H_Closure Letter_04022014.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120121025H/120121025H_Closure%20Letter_04022014.pdf

120121025H_Closure Letter_04022014_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120121025H/120121025H_Closure%20Letter_04022014_text.pdf

120121025H_Corrective Action Order_12202012.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120121025H/120121025H_Corrective%20Action%20Order_12202012.pdf

120121025H_Corrective Action Order_12202012_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120121025H/120121025H_Corrective%20Action%20Order_12202012_text.pdf

120121025H_Corrective Action Order_12202012_text.pdf

DECEMBER 20 2012
VIA CERTIFIED MAIL AND FAX TO: (304) 357-2644
Mr. Robert C. Skaggs, Jr.
President and Chief Executive Officer
Columbia Gas Transmission, L.L.C
1700 MacCorkle Avenue SE
Charleston, WV 25314
Mr. Shawn Patterson
President, Operations and Project Delivery
Columbia Gas Transmission, L.L.C.
1700 MacCorkle Avenue
P.O. Box 1273
Charleston, WV 25314
Re: CPF No. 1-2012-1025H
Dear Mr. Skaggs and Mr. Patterson:
Enclosed is a Corrective Action Order issued in the above-referenced case. It finds that
operation of the 20-inch diameter Columbia Gas Transmission, L.L.C., natural gas transmission
pipeline, SM-80, is hazardous to life, property, and the environment without immediate
corrective action. The Corrective Action Order requires you to take immediate action to protect
the public, property, and the environment in connection with the December 11, 2012 failure of
the SM-80 Pipeline in Kanawha County, West Virginia. This segment is 26.2 miles long, from
Lanham Station to the Broad Run Meter facility. Service is being made by certified mail and
facsimile. Your receipt of this Corrective Action Order constitutes service of that document
under 49 C.F.R. § 190.5. The terms and conditions of this Order are effective upon receipt.
We look forward to a successful resolution of the concerns arising out of this failure to ensure
the safe operation of the pipeline. Please direct any questions on this matter to Byron Coy,
Director, Eastern Region, OPS, at (609) 989-2171.
Sincerely,
Jeffrey D. Wiese
Associate Administrator for Pipeline Safety



Enclosure: Corrective Action Order and Copy of 49 C.F.R. §190.233
cc: Mr. Byron Coy, Director, Eastern Region, PHMSA
Mr. David Hippchem, Manager Pipeline Safety, West Virginia Public Service
Commission



2
U.S. DEPARTMENT OF TRANSPORTATION
PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION
OFFICE OF PIPELINE SAFETY
WASHINGTON, D.C. 20590
____________________________________
In the Matter of )
Columbia Gas Transmission L.L.C., ) CPF No. 1-2012-1025H
a subsidiary of NiSource Gas )
Transmission & Storage )
)
)
)
Respondent )
____________________________________)
CORRECTIVE ACTION ORDER
Purpose and Background
This Corrective Action Order (Order) is being issued, under authority of 49 U.S.C. § 60112, to
Columbia Gas Transmission L.L.C.1 (Columbia Gas or Respondent), the operator of the 20-inch
natural gas transmission line, SM-80 (Affected Pipeline). On December 11, 2012, a pipeline
rupture and fire occurred on the SM-80 pipeline, approximately 4.7 miles downstream of the
Lanham Compressor Station near Sissonville, WV. This Order finds that operation of the
pipeline without corrective action is hazardous to life, property, or the environment and requires
Respondent to take immediate action to ensure the safe operation of the pipeline.
On December 11, 2012, Respondent experienced a failure on the Affected Pipeline requiring
shutdown, and reported a natural gas pipeline failure to the National Response Center (NRC
#1032935). Columbia Gas operates two additional pipelines, SM-86 Loop2 and SM-863, which
run parallel to the SM-80 pipeline in the incident area.
Pursuant to 49 U.S.C. § 60117, the Pipeline and Hazardous Materials Safety Administration
(PHMSA), Office of Pipeline Safety (OPS), joined the National Transportation Safety Board
(NTSB) and the Public Service Commission of West Virginia (PSCWV), acting as Agent for the
1 Columbia Gas Transmission L.L.C., a subsidiary of NiSource Inc., owns and operates approximately 11,453 miles
of pipeline in Delaware, Kentucky, Maryland, New Jersey, New York, North Carolina, Ohio, Pennsylvania,
Virginia, and West Virginia.
2 SM-86 Loop (Lanham Compressor Station to Broad Run) consists of approximately 26.0 miles of 30” diameter
pipeline.
3 Line SM-86 (Lanham Compressor Station to Broad Run) consists of approximately 25.8 miles of 26” diameter
pipeline.



3
PHMSA, in the investigation of the Failure. OPS determined that the explosion and fire
originated in the Affected Pipeline, but the cause of the Failure is still under investigation. The
preliminary findings of the investigation are as follows:
Preliminary Findings
• At approximately 12:43 p.m. EST, on December 11, 2012, Respondent experienced a
failure, in which a 15-foot section of pipe separated entirely from the Affected Pipeline
and was ejected from the ground.
• The NTSB noted at a December 14, 2012 press conference that evidence at the failure
site is consistent with external corrosion.4
• The Failure site is located at Mile Post (M.P.) 4.7, in Sissonville, West Virginia,
approximately two miles from the town center and 10 miles north of Charleston, West
Virginia.5
• The Failure resulted in the release and ignition of an undetermined amount of gas and
created two flame plumes. As a result of the explosion and ensuing fire, Interstate 77 was
damaged and closed. In addition, the fire destroyed three neighbouring homes, severely
damaged another, and inflicted some damage to other residences.
• Following the Failure, Respondent isolated the failed pipe by closing the Rocky Hollow
valve (13:20 p.m.) and the Lanham valve (13:40 p.m.). Currently, the failed segment is
blocked off at upstream and downstream block valves, has not been repaired, or returned
to service.
• Respondent notified the National Response Center (Report # 1032935) at approximately
1:45 p.m.
• Due to its proximity to the Failure Site, Interstate 77 was closed by the West Virginia
Highway Department. The highway surfaces sustained thermal damage, causing the
highway to be closed for approximately 18 hours while repairs were made.
• Line SM-80 was originally installed in 1951, from Lanham to Broad Run (26.2 miles). In
1955, it was extended from Lanham to Leach. Since that time, various segments of the
pipeline have been replaced, resulting in a line with various vintages of pipe, the newest
of which stems from a 1992 project.
• Columbia Gas operates two additional pipelines, SM-86 Loop and SM-86, which run
parallel to the Affected Pipeline in the incident area. Following the explosion, service
from Lanham Compressor Station to Patterson Fork was curtailed as a precautionary
measure. After shut-in, Lines SM-86 Loop and SM-86 maintained a static pressure of
approximately 520 psig.
4 http://www.youtube.com/watch?v=DDK80Orr2hE&feature=youtu.be.
5 See Map of Failure Site.



4
• At the incident location, SM-86 and the Affected Pipeline are separated by approximately
183 feet. Through consultation with an independent engineering firm, Det Norske
Veritas (DNV), the Respondent concluded that the incident did not affect Line SM-86
and restored pressure slowly over a 2.5 hour period. Line SM-86 was returned to full
service in the early morning hours of December 12, 2012. No leaks were detected on the
pipeline during foot or aerial leakage surveys that were performed on start-up.
• At the incident location, Line SM-86 Loop and the Affected Pipeline are separated by
approximately 53 feet. DNV6 also concluded that SM-86 Loop was not adversely
impacted by the SM-80 accident. However, since SM-86 Loop is closer to SM-80,
Columbia Gas developed a Return to Service Plan, dated December 15, 2012, for SM-86
Loop, which OPS reviewed and approved. The Return to Service Plan for SM-86 Loop
pipeline was successfully implemented on December 19, 2012.
• OPS observed general wall thinning on the underside of the Affected Pipeline at the
Failure location, OPS has preliminarily concluded that general wall thinning is a major
factor in the cause of the Failure.
• The Affected Pipeline pipe at the failure location was constructed in 1967. Preliminary
data from the pipe at the Failure location shows a general wall thickness of 0.281 inches,
20 inches in diameter and has an electric resistance weld (ERW) long seam.
Determination of Necessity for Corrective Action Order and Right to Hearing
Under 49 U.S.C. § 60112 and 49 C.F.R. § 190.233, the Associate Administrator for Pipeline
Safety (Associate Administrator) may issue a corrective action order (CAO) after providing
reasonable notice and the opportunity for a hearing if he finds that a particular pipeline facility is
or would be hazardous to life, property, or the environment. The terms of such an order may
include the suspended or restricted use of a pipeline facility, physical inspection, testing, repair,
replacement, or any other action as appropriate. The Associate Administrator may also issue a
corrective action order without providing any notice or the opportunity for a hearing if he finds
that a failure to do so expeditiously will result in likely serious harm to life, property or the
environment. The opportunity for a hearing will be provided as soon as practicable after the
issuance of the CAO in such cases.
After evaluating the foregoing preliminary findings of fact, I find that the continued operation of
the pipeline without corrective measures would be hazardous to life, property and the
environment. Additionally, after considering the age of the pipe, circumstances surrounding this
Failure, the proximity of the pipeline to populated areas, and public roadways the hazardous
nature of the product the pipeline transports, the uncertainties as to the cause of the failure, and
the ongoing investigation to determine the cause of the failure, I find that a failure to issue this
Order expeditiously to require immediate corrective action would result in likely serious harm to
life, property, and the environment. Accordingly, this Order mandating immediate corrective
6 Exhibit A. DNV Study.



5
action is issued without prior notice and opportunity for a hearing. The terms and conditions of
this Order are effective upon receipt.
Within 10 days of receipt of this Order, Respondent may request a hearing, to be held as soon as
practicable, by notifying the Associate Administrator for Pipeline Safety in writing, delivered
personally, by mail or by telecopy at (202) 366-4566. The hearing will be held in the Eastern
Region on a date that is mutually convenient to PHMSA and Respondent.
After receiving and analyzing additional data in the course of this investigation, OPS may
identify other corrective measures that need to be taken. Respondent will be notified of any
additional measures required and amendment of this Order will be considered. To the extent
consistent with safety, Respondent will be afforded notice and an opportunity for a hearing prior
to the imposition of any additional corrective measures.
Required Corrective Action
Pursuant to 49 U.S.C. § 60112, Columbia Gas is ordered to immediately take the following
corrective actions to ensure the safe operation of the Affected Pipeline, from Lanham Station to
the Broad Run Meter facility:
I. PHASE I: RETURN LINE TO RESTRICTED OPERATION
a. Create Plan. Respondent must establish a written Phase I plan, and then seek written
approval from the Director, Eastern Region, prior to the initiation of the plan.
b. Repairs. Conduct repairs based on Respondent’s established written procedures. These
procedures are to be identified in the plan.
c. d. e. f. Cathodic Protection (CP). Verify that all CP equipment and test stations are operating
properly, on all three pipelines, three miles up and down stream of the incident location.
Critical Valves. Inspect and partially operate all critical valves that might be required
during any emergency to ensure they can be completely closed. Take prompt remedial
action to correct any deficiencies.
Discharge Pressure. Analyze and validate the actual discharge pressure at Lanham
compressor station for the Affected Pipeline at the time of the failure.
Temporary Maximum Allowable Operating Pressure.
1. 2. 3. Use the lower of 741 or 80% of the validated Lanham compressor station pressure
in Item I.e. above.
Set the temporary maximum allowable operating pressure, to the pressure
determined in Item I.f.1.
Step increase the pressure in SM-80, in quarter increments up to the pressure
determined in Item I.f.1.



6
II. a. b. c. d. e. f. g. h. 4. 5. 6. 7. 8. 9. Set any and all pressure control and relief devices to insure the temporary
maximum allowable operating pressure will not be exceeded.
Each quarter step is to be followed by a 30-minute idle period.
Conduct a leak survey over the entire segment with either foot or aerial patrol, but
ensure that an on-ground foot leak patrol with hydrogen flame ionization devices
are conducted for 300 feet up and down stream of the incident location.
Investigate and resolve any discovered leaks before continuing the quarter step
process.
Conduct another set of leak surveys, as set forth in Item I.f.6 above, 24 hours after
the fourth quarter pressure increment is completed.
Investigate and resolve any discovered leaks within 24 hours.
PHASE II: LONG TERM ASSESSMENT AND REMEDIATION
Create Plan. Respondent must establish a written Phase II plan, and then seek written
approval from the Director, Eastern Region, prior to the initiation of the plan.
Data. Review pipe data to ascertain records reflect actual pipe specifications, including
representative sampling with bell hole validation.
Records. Review MAOP records to ascertain MAOP does not exceed related records. If
records do not support the current normal MAOP, arrange to reset normal MAOP to
match records.
In-Line Inspection (ILI). Conduct an ILI inspection for High Resolution Deformation and
Metal Loss within 30 days of completing Phase I. Submit to the Director, Eastern
Region, copies of the preliminary ILI reports, which would delineate any and all
immediate conditions that could jeopardize the temporary maximum allowable operating
pressure, from successful tool runs within 40 days of running the tools, directly from the
tool vendors.
Analysis. Analyze all data, including field digs for tool results validation.
Excavation. Excavate to investigate anomalies and make repairs as though the entire
Affected Pipeline was in an HCA, using the criteria established in 49 C.F.R. Subpart O.
Cathodic Potential Survey. Perform close interval survey, investigate, and correct
deficiencies.
Coating Integrity. Assess the integrity of the coating using direct current voltage gradient
(DCVG) or alternating current voltage gradient (ACVG). Within 30 days of completing
the CIS. Perform a DCVG or ACVG survey in accordance with NACE RP 0502-2002,
Appendix A, of all pipe locations where CIS results reveal CP levels below the
requirements of 49 CFR Part 192, Subpart I. Correct any deficiencies identified.



7
III. PHASE III: CRITERIA
a. Criteria. Complete assessment and all necessary repairs in Phase II within 365 days of
issuance of this Order.
b. Summarize Work. Operator is to maintain records of work performed and prepare a
complete package of information for presentation to OPS when they believe the work in
complete. Operator is to use this information to seek OPS approval to return the line to
full and normal pressure.
c. Restore Pressure. Pressure can only be returned to normal MAOP after all work is
successfully completed and approved by the Director.
IV. PHASE IV: CONCLUSION CRITERIA
a. Monthly Reports for Phase I. Submit monthly reports to the Director, Eastern Region,
that: (1) include all available data and results of the testing and evaluations required by
this Order; and (2) describe the progress of the repairs or other corrective and/or remedial
actions being undertaken. The first monthly report is due by the third week of each
month until Phase I has been completed. The Director may adjust the reporting period
upon written request of the Respondent.
b. Quarterly Reports for Phase II. Submit quarterly reports to the Director, Eastern Region,
that: (1) include all available data and results of the testing and evaluations required by
this CAO; and (2) describe the progress of the repairs or other corrective and/or remedial
actions being undertaken. The first calendar quarterly report are due once Phase I has
been determined by the Director to be completed. There should be four quarterly report
submissions while this Order is still in effect.
c. Summary Report for Phase II. When the Operator believes Phase II has been completed,
a composite summary of all work performed is to be assembled, regardless of what may
have been provided earlier, and presented to the Director. The Director will review the
summary as part of the consideration for approval to return to normal MAOP.
d. Documentation. It is requested but not required that Respondent maintain documentation
of the costs associated with implementation of this Corrective Action Order. Include in
each monthly report submitted, the to-date total costs associated with: (1) preparation and
revision of procedures, studies and analyses; (2) physical changes to pipeline
infrastructure, including repairs, replacements and other modifications; and (3)
environmental remediation, if applicable.
The Director may grant an extension of time for compliance with any of the terms of this Order
upon a written request timely submitted demonstrating good cause for an extension.
With respect to each submission that under this Order requires the approval of the Director, the
Director may: (a) approve, in whole or part, the submission; (b) approve the submission on



8
specified conditions; (c) modify the submission to cure any deficiencies; (d) disapprove in whole
or in part, the submission, directing that Respondent modify the submission, or (e) any
combination of the above. In the event of approval, approval upon conditions, or modification
by the Director, Respondent must take all actions required by the submission, as approved or
modified by the Director. If the Director disapproves all or any portion of the submission,
Respondent must correct all deficiencies within the time specified by the Director, and resubmit
it for approval. If a resubmitted item is disapproved in whole or in part, the Director may again
require Respondent to correct the deficiencies in accordance with the foregoing procedure, and
the Director may otherwise proceed to enforce the terms of this Order.
Be advised that all material you submit in response to this enforcement action is subject to being
made publicly available. If you believe that any portion of your responsive material qualifies for
confidential treatment under 5 U.S.C. 552(b), you must provide, along with the complete original
document, a second copy of the document with those portions you believe qualify for
confidential treatment redacted, along with an explanation of why you believe the redacted
information qualifies for confidential treatment under 5 U.S.C. 552(b).
In your correspondence on this matter, please refer to “CPF No. 1-2012-1025H” and for each
document you submit, please provide a copy in electronic format whenever possible. The
actions required by this Corrective Action Order are in addition to and do not waive any
requirements that apply to Respondent’s pipeline system under 49 C.F.R. Part 195, under any
other order issued to Respondent under authority of 49 U.S.C. § 60101 et seq., or under any other
provision of Federal or State law.
Respondent may appeal any decision of the Director to the Associate Administrator for Pipeline
Safety. Decisions of the Associate Administrator shall be final.
Failure to comply with this Order may result in the assessment of civil penalties and in referral to
the Attorney General for appropriate relief in United States District Court pursuant to
49 U.S.C. § 60120.
The terms and conditions of this Corrective Action Order are effective upon receipt.
__________________________________ __________________
Jeffrey D. Wiese Date Issued
Associate Administrator
for Pipeline Safety

120121025H_Closure Letter_04022014_text.pdf

U.S. Department Of Transportation Pipeline and 609.989.2171
Hazardous Materials
Safety Administration
820 Bear Tavern Road, Suite 103
West Trenton, NJ 08628
OVERNIGHT EXPRESS DELIVERY
April 2, 2014
Shawn Patterson
President, Engineering and Project Delivery
Columbia Gas Transmission, L.L.C.
1700 MacCorkle Avenue, SE
Charleston, WV 25314
CPF 1-2012-1025H
Dear Mr. Patterson:
On December 20, 2012, the Pipeline and Hazardous Materials Safety Administration, Office of
Pipeline Safety, issued to Columbia Gas Transmission, L.L.C. (Columbia) a Corrective Action
Order following a pipeline rupture and fire that occurred on its SM-80 pipeline in Sissonville,
West Virginia. This Order included requirements to take corrective actions on the SM-80
pipeline from Lanham Station to the Broad Run Meter facility.
Based on our review of the documentation you provided, it has been determined that you have
complied with the terms of this Order.
Accordingly, this case is now closed and no further action is contemplated with respect to the
matters involved in this case. Thank you for your cooperation in this matter.
Sincerely,
Byron Coy, PE
Director, Eastern Region
Pipeline and Hazardous Materials Safety Administration

## Provenance

- Official: Yes
- Source: <https://primis.phmsa.dot.gov/enforcement-data/case/120121025H>
- Source ID: `phmsa-enforcement`
- SHA-256: `4e1cc5d43673b804ffcd31c15d2ce4fc20b076c17b6536f90529fb3796bf42d8`
- Retrieved: 2026-08-20T04:44:44.458Z
- Exported: 2026-08-24T14:22:54.657Z
- Document slug: `phmsa-enforcement-120121025h`

### Source metadata

```json
{
  "cpf": "120121025H",
  "operator": "COLUMBIA GAS TRANSMISSION, LLC",
  "region": "Eastern",
  "pipelineType": "GAS INTERSTATE ONSHORE",
  "caseStatus": "CLOSED",
  "citedSections": [],
  "dataAsOf": "08/04/2026 12PM",
  "caseDataAsOf": "2026-08-04",
  "attachmentCount": 4,
  "attachments": [
    {
      "name": "120121025H_Closure Letter_04022014.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/120121025H/120121025H_Closure%20Letter_04022014.pdf",
      "bytes": 83270,
      "category": "agency_document"
    },
    {
      "name": "120121025H_Closure Letter_04022014_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/120121025H/120121025H_Closure%20Letter_04022014_text.pdf",
      "bytes": 12828,
      "category": "agency_document"
    },
    {
      "name": "120121025H_Corrective Action Order_12202012.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/120121025H/120121025H_Corrective%20Action%20Order_12202012.pdf",
      "bytes": 3751340,
      "category": "agency_document"
    },
    {
      "name": "120121025H_Corrective Action Order_12202012_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/120121025H/120121025H_Corrective%20Action%20Order_12202012_text.pdf",
      "bytes": 45912,
      "category": "agency_document"
    }
  ],
  "extractedAgencyDocumentCount": 2,
  "attachmentPolicy": "Official attachment links are retained. Agency-issued documents may also include a verified local PDF and page-level text representation.",
  "jurisdiction": "US",
  "operatorName": "COLUMBIA GAS TRANSMISSION, LLC"
}
```