# NEW YORK STATE ELECTRIC & GAS CORP — Notice of Probable Violation

**Citation:** CPF 120141001  
**Type / status:** enforcement / historical  
**Agency:** Pipeline and Hazardous Materials Safety Administration  
**Effective:** Not stated  
**Published:** 2014-01-02

CLOSED notice of probable violation citing 192.491(c), 192.709.

## Document text

Notice of Probable Violation involving NEW YORK STATE ELECTRIC & GAS CORP. PHMSA's enforcement data identifies the cited regulations as 192.491(c),  192.709. The case was opened on 2014-01-02 and is reported as closed as of 2015-04-07. Proposed civil penalty: $20,000. Assessed civil penalty: $10,000. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

120141001_Closure Letter_04072015.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120141001/120141001_Closure%20Letter_04072015.pdf

120141001_Closure Letter_04072015_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120141001/120141001_Closure%20Letter_04072015_text.pdf

120141001_Final Order_09102014.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120141001/120141001_Final%20Order_09102014.pdf

120141001_Final Order_09102014_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120141001/120141001_Final%20Order_09102014_text.pdf

120141001_NOPV PCP PCO_01022014.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120141001/120141001_NOPV%20PCP%20PCO_01022014.pdf

120141001_NOPV PCP PCO_01022014_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120141001/120141001_NOPV%20PCP%20PCO_01022014_text.pdf

120141001_Operator Response_01312014.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120141001/120141001_Operator%20Response_01312014.pdf

120141001_NOPV PCP PCO_01022014_text.pdf

U.S. Department Of Transportation Pipeline and 609.989.2171
Hazardous Materials
Safety Administration
820 Bear Tavern Road, Suite 103
West Trenton, NJ 08628
NOTICE OF PROBABLE VIOLATION
PROPOSED CIVIL PENALTY
and
PROPOSED COMPLIANCE ORDER
EXPRESS OVERNIGHT MAIL
January 2, 2014
Mr. Barry Cigich, VP Operations
Crestwood Midstream LLC.
Two Brush Creek Blvd., Suite 200
Kansas City, MO 64112
CPF 1-2014-1001
Dear Mr. Cigich:
Between October 15 and November 7, 2012, inspectors from the New York State Department of Public
Service (NYSDPS), acting as agents for the Pipeline and Hazardous Materials Safety Administration
(PHMSA) pursuant to Chapter 601 of 49 United States Code inspected the Arlington Storage Company, LLC
(ASC) Seneca Lake Storage facilities in Watkins Glen, NY.
As a result of the inspection, it appears that you have committed probable violations of the Pipeline Safety
Regulations, Title 49, Code of Federal Regulations. The items inspected and the probable violations are:
1. § 192.709 Transmission lines: Record keeping.
Each operator shall maintain the following records for transmission lines for the periods specified:
(c) A record of each patrol, survey, inspection, and test required by subparts L and M of this part
must be retained for at least 5 years or until the next patrol, survey, inspection, or test is completed,
whichever is longer.
ASC failed to maintain a record of each patrol, survey, inspection, and test required by subparts L and M of
this part. Specifically, ASC could not produce any documents or capacity test reviews or calculations as
required by §192.743(a) for any of the relief devices on the Seneca Storage and Seneca West Pipeline
facilities.
2. § 192.491 Corrosion control records.
(c) Each operator shall maintain a record of each test, survey, or inspection required by this subpart in
sufficient detail to demonstrate the adequacy of corrosion control measures or that a corrosive
condition does not exist. These records must be retained for at least 5 years, except that records
related to §§ 192.465 (a) and (e) and 192.475(b) must be retained for as long as the pipeline remains in
service.
ASC failed to maintain a record of each test, survey, or inspection required by this subpart in sufficient detail
to demonstrate the adequacy of corrosion control measures or that a corrosive condition does not exist.



1-2014-1001
Specifically, ASC failed to document the required internal corrosion check upon removal of a section of 16-
inch pipe from the Seneca West Pipeline during tie-in of “Project 415: Interconnection with Millennium
Pipeline” in 2012, as required by §192.475(b).
Proposed Civil Penalty
Under 49 United States Code, § 60122, you are subject to a civil penalty not to exceed $200,000 per
violation per day the violation persists up to a maximum of $2,000,000 for a related series of violations. For
violations occurring prior to January 4, 2012, the maximum penalty may not exceed $100,000 per violation
per day, with a maximum penalty not to exceed $1,000,000 for a related series of violations. The
Compliance Officer has reviewed the circumstances and supporting documentation involved in the above
probable violations and has recommended that you be preliminarily assessed a civil penalty of $20,000 as
follows:
Item number PENALTY
1 $10,000
2 $10,000
Proposed Compliance Order
With respect to items 1 and 2 pursuant to 49 United States Code § 60118, the Pipeline and Hazardous
Materials Safety Administration proposes to issue a Compliance Order to Arlington Storage Company, LLC.
Please refer to the Proposed Compliance Order, which is enclosed and made a part of this Notice.
Response to this Notice
Enclosed as part of this Notice is a document entitled Response Options for Pipeline Operators in
Compliance Proceedings. Please refer to this document and note the response options. All material you
submit in response to this enforcement action may be made publicly available. If you believe that any
portion of your responsive material qualifies for confidential treatment under 5 U.S.C. 552(b), along with the
complete original document you must provide a second copy of the document with the portions you believe
qualify for confidential treatment redacted and an explanation of why you believe the redacted information
qualifies for confidential treatment under 5 U.S.C. 552(b). If you do not respond within 30 days of receipt of
this Notice, this constitutes a waiver of your right to contest the allegations in this Notice and authorizes the
Associate Administrator for Pipeline Safety to find facts as alleged in this Notice without further notice to
you and to issue a Final Order.
Please submit all correspondence in this matter to Byron Coy, PE, Director, PHMSA Eastern Region, 820
Bear Tavern Road, Suite 103, W. Trenton, NJ 08628. Please refer to CPF 1-2014-1001 on each document
you submit and please, whenever possible, provide a signed PDF copy in electronic format. Smaller files
may be emailed to Byron.Coy@dot.gov. Larger files should be sent on a CD accompanied by the original
paper copy to the Eastern Region Office.
Additionally, if you choose to respond to this (or any other case), please ensure that any response letter
pertains solely to one CPF case number.
Sincerely,
Byron Coy, PE
Director, Eastern Region
Pipeline and Hazardous Materials Safety Administration
Cc: Kevin Speicher NYSDPS
Enclosures: Proposed Compliance Order
Response Options for Pipeline Operators in Compliance Proceedings
120141001_NOPV_PCP_PCO_01022014 Page 2 of 3



1-2014-1001
PROPOSED COMPLIANCE ORDER
Pursuant to 49 United States Code § 60118, the Pipeline and Hazardous Materials Safety Administration
(PHMSA) proposes to issue to Arlington Storage Company, LLC (ASC) a Compliance Order incorporating
the following remedial requirements to ensure the compliance of ASC with the pipeline safety regulations:
1. 2. 3. 4. In regard to Item Number 1 of the Notice pertaining to ASC not providing records to verify
sizing of relief valves at the Seneca Lake Storage facilities, ASC must perform relief
capacity analysis on all associated devices that do not have adequate records, and make any
changes, if necessary, to establish adequate capacity.
In regard to Item Number 2 of the Notice pertaining to ASC not documenting the required
internal corrosion checks on a section of 16-inch pipe removed from service,
a. ASC must perform an internal inspection in the vicinity of the project noted in Item
Number 2, either by temporarily removing a component such as a valve, or spool piece,
a meter, a flanged section, or cutting out a section for inspection.
b. Any new segment of pipe that is used to restore the inspection area would have to meet
records and MAOP requirements.
c. ASC must modify their Internal Corrosion Control Procedure 906 to provide detailed
guidance for documenting an internal corrosion inspection when no corrosion is found.
ASC shall have 120 days from the receipt of a Final Order to complete the requirements for
Item Number 1 and Item Number 2 of the Notice.
It is requested (not mandated) that ASC maintain documentation of the safety improvement
costs associated with fulfilling this Compliance Order and submit the total to Byron Coy,
PE, Director, Eastern Region, Pipeline and Hazardous Materials Safety Administration. It is
requested that these costs be reported in two categories: 1) total cost associated with
preparation/revision of plans, procedures, studies and analyses, and 2) total cost associated
with replacements, additions and other changes to pipeline infrastructure.
120141001_NOPV_PCP_PCO_01022014 Page 3 of 3

120141001_Final Order_09102014_text.pdf

SEPTEMBER 10, 2014
Mr. Robert G. Phillips
Chairman, President and Chief Executive Officer
Crestwood Midstream GP, LLC
Two Brush Creek Boulevard, Suite 200
Kansas City, MO 64112
Re: CPF No. 1-2014-1001
Dear Mr. Phillips:
Enclosed please find the Final Order issued in the above-referenced case. It withdraws one of
the allegations of violation, makes one other finding of violation, assesses a reduced civil penalty
of $10,000, and specifies actions that need to be taken by your subsidiary, Arlington Storage
Company, LLC, to comply with the pipeline safety regulations. The penalty payment terms are
set forth in the Final Order. When the civil penalty has been paid and the terms of the
compliance order completed, as determined by the Director, Eastern Region, this enforcement
action will be closed. Service of the Final Order by certified mail is deemed effective upon the
date of mailing, or as otherwise provided under 49 C.F.R. § 190.5.
Thank you for your cooperation in this matter.
Sincerely,
Jeffrey D. Wiese
Associate Administrator
for Pipeline Safety
Enclosure
cc: Mr. Byron E. Coy, P.E., Director, Eastern Region, OPS
Mr. Matthew Norton, Director of PSM and Pipeline Compliance, Crestwood Midstream
GP, 801 Cherry Street, Suite 3800 – Unit 20, Fort Worth, Texas 76135
CERTIFIED MAIL - RETURN RECEIPT REQUESTED



U.S. DEPARTMENT OF TRANSPORTATION
PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION
OFFICE OF PIPELINE SAFETY
WASHINGTON, D.C. 20590
____________________________________________
)
In the Matter of )
)
Arlington Storage Company, LLC, ) CPF No. 1-2014-1001
a subsidiary of Crestwood Midstream GP, LLC, )
)
Respondent. )
____________________________________________)
FINAL ORDER
Between October 15 and November 7, 2012, pursuant to 49 U.S.C. § 60117, inspectors from the
New York State Department of Public Service (NYSDPS), acting as agents for the Pipeline and
Hazardous Materials Safety Administration (PHMSA), Office of Pipeline Safety (OPS),
conducted an on-site pipeline safety inspection of the facilities and records of Arlington Storage
Company, LLC (ASC or Respondent), at the company’s Seneca Lake storage facilities in
Watkins Glen, New York. This facility is operated by ASC, a subsidiary of Crestwood
Midstream GP, LLC, and includes an 18.6-mile, 16-inch diameter welded pipeline system and a
cavern with a storage capacity of 2.1 billion cubic feet of active working gas.1
As a result of the inspection, the Director, Eastern Region, OPS (Director), issued to Respondent,
by letter dated January 2, 2014, a Notice of Probable Violation, Proposed Civil Penalty, and
Proposed Compliance Order (Notice). In accordance with 49 C.F.R. § 190.207, the Notice
proposed finding that ASC had committed two violations of 49 C.F.R. Part 192 and proposed
assessing a civil penalty of $20,000 for the alleged violations. The Notice also proposed
ordering Respondent to take certain measures to correct the alleged violations.
ASC responded to the Notice by letter dated January 31, 2014 (Response). The company
contested one allegation, offered additional information in response to the Notice, and requested
that the proposed civil penalty be eliminated.
Respondent did not request a hearing and therefore has waived its right to one.
1 http://ceqpinvestor.crestwoodlp.com/phoenix.zhtml?c=132026&p=irol-newsArticle&ID=1585221&highlight=
(last accessed July 14, 2014); Pipeline Safety Violation Report (Violation Report), dated January 2, 2014 (on file
with PHMSA), at 1.



2
FINDING OF VIOLATION
In its Response, ASC did not contest the allegation in the Notice that it violated 49 C.F.R.
§ 192.709, as follows:
Item 1: The Notice alleged that Respondent violated 49 C.F.R. § 192.709, which states, in
relevant part:
§ 192.709 Transmission lines: Record keeping.
Each operator shall maintain the following records for transmission
lines for the periods specified:
(a) …
(c) A record of each patrol, survey, inspection, and test required by
subparts L and M of this part must be retained for at least 5 years or
until the next patrol, survey, inspection, or test is completed,
whichever is longer.
The Notice alleged that Respondent violated 49 C.F.R. § 192.709 by failing to maintain a record
of each patrol, survey, inspection, and test required by Subparts L and M of 49 C.F.R. Part 192.
Specifically, the Notice alleged that ASC could not produce any documents or capacity test
reviews or calculations, as required by § 192.743(a), for any of the relief devices on the Seneca
Storage and Seneca West Pipeline facilities.
Respondent did not contest this allegation of violation. Accordingly, based upon a review of all
of the evidence, I find that Respondent violated 49 C.F.R. § 192.709 by failing to maintain a
record of each patrol, survey, inspection, and test required by Subparts L and M of 49 C.F.R.
Part 192.
This finding of violation will be considered a prior offense in any subsequent enforcement action
taken against Respondent.
Item 2: The Notice alleged that Respondent violated 49 C.F.R. § 192.491(c), which states:
§ 192.491 Corrosion control records.
(a) …
(c) Each operator shall maintain a record of each test, survey, or
inspection required by this subpart in sufficient detail to demonstrate the
adequacy of corrosion control measures or that a corrosive condition does
not exist. These records must be retained for at least 5 years, except that
records related to §§ 192.465(a) and 192.475(b) must be retained for as
long as the pipeline remains in service.
The Notice alleged that Respondent violated 49 C.F.R. § 192.491(c) by failing to maintain a
record of each test, survey, or inspection required by this subpart in sufficient detail to
demonstrate the adequacy of corrosion control measures or that a corrosive condition does not
exist. Specifically, the Notice alleged that ASC failed to document the internal corrosion



3
inspection required under 49 C.F.R. § 192.495(b) when the company removed a section of 16-
inch pipe from the Seneca West Pipeline during tie-in of “Project 415: Interconnection with
Millennium Pipeline” in 2012.
In its Response, ASC challenged the allegation that it failed to document the internal corrosion
inspection and requested that the proposed civil penalty and compliance order requirement
associated with this Item be eliminated. ASC contended that NYSDPS did not request a record
of the internal corrosion inspection. Also, ASC argued that an internal corrosion inspection was
indeed conducted at the time of the tie-in project and was recorded on an “Information Report”
form dated April 17, 2012. ASC indicated that this “Information Report,” which was attached to
the Response, had been available at the time of the PHMSA inspection.
The NYSDPS disputed ASC’s statement that NYDPS did not ask for the internal corrosion
inspection records, stating that it did indeed request the records both during and after the
inspection. Additionally, Section 3.2 of Arlington Storage Procedure 907 states: “[W]henever
any pipe is removed from a pipeline for any reason, inspect the internal surface for evidence of
corrosion. If internal corrosion is found: Investigate the adjacent pipe to determine the extent of
internal corrosion and document on O&M Form OM200-02 Pipeline Examination Report. . . .”2
There are several problems with the documentation provided by ASC in its Response. First, the
“Information Report” is not the same record as the “Form OM200-2 Pipe Examination Report”
required by Arlington Storage Procedure 906 and does not reference said procedure. Second,
the “Information Report” has “Form S-10 02-08-2002” at the bottom of the page and only
references procedures numbered 301, 303, 304, and 508 at the top of the page but not procedure
906. Finally, the “Information Report” has no description indicating it was to be used for
recording an internal corrosion inspection, but instead was used for recording external surface
corrosion if a pipeline were exposed.
Nevertheless, after considering all of the evidence, I find that the information therein is sufficient
to show that an internal corrosion inspection did indeed occur. The “Information Report”
provided by ASC states expressly: “No corrosion detected internally!” and is dated and signed by
the inspector. Under the circumstances, I am willing to accept this as proof that ASC did
maintain an adequate record of an internal corrosion inspection for the section of pipe in
question.
Based upon the foregoing, I withdraw Item 2.
ASSESSMENT OF PENALTY
Under 49 U.S.C. § 60122, Respondent is subject to an administrative civil penalty not to exceed
$200,000 per violation for each day of the violation, up to a maximum of $2,000,000 for any
2 Violation Report, Exhibit A-01.



4
related series of violations.3 In determining the amount of a civil penalty under 49 U.S.C.
§ 60122 and 49 C.F.R. § 190.225, I must consider the following criteria: the nature,
circumstances, and gravity of the violation, including adverse impact on the environment; the
degree of Respondent’s culpability; the history of Respondent’s prior offenses; and any effect
that the penalty may have on its ability to continue doing business; and the good faith of
Respondent in attempting to comply with the pipeline safety regulations. In addition, I may
consider the economic benefit gained from the violation without any reduction because of
subsequent damages, and such other matters as justice may require. The Notice proposed a total
civil penalty of $20,000 for the violations cited above.
Item 1: The Notice proposed a civil penalty of $10,000 for Respondent’s violation of 49 C.F.R.
§ 192.709, for failing to maintain a record of each patrol, survey, inspection, and test required by
subparts L and M of Part 192. ASC did not contest this allegation, but did request that the
proposed civil penalty be reduced or waived. In its Response, ASC indicated that it completed a
relief capacity analysis on all associated relief devices following the inspection.
Respondent stated that the post-inspection analysis indicated all pressure-relief devices had
sufficient capacity; no device required resetting or physical change. Respondent believed that
the proposed penalty should be reduced despite the company’s failure to maintain records of a
capacity test. The company argued that its ability to easily conduct a capacity test demonstrated
the adequacy of both the original design and ASC’s on-going annual device relief testing
program. Respondent argued in its Response that the relief capacity analysis performed after the
NYSDPS inspection warrants a penalty reduction. I disagree. The fact that Respondent reacted
to the NYSDPS inspection by conducting an analysis does not warrant a penalty reduction, as it
is Respondent’s responsibility to ensure it has all the necessary records available at all times.
Respondent must maintain all necessary records regardless of whether its relief valves, or other
equipment, are adequate. The regulation specifically requires operators to maintain records for a
certain amount of time. Accordingly, having reviewed the record and considered the assessment
criteria, I assess Respondent a civil penalty of $10,000 for violation of 49 C.F.R. § 192.709.
Item 2: The Notice proposed a civil penalty of $10,000 for Respondent’s violation of 49 C.F.R.
§ 192.491(c), for failing to maintain a record of each test, survey, or inspection required by this
subpart in sufficient detail to demonstrate the adequacy of corrosion control measures or that a
corrosive condition does not exist. Based on the discussion above, I withdraw the proposed
penalty for violation of 49 C.F.R. § 192.491(c).
In summary, having reviewed the record and considered the assessment criteria for Item 1 cited
above, I assess Respondent a reduced civil penalty of $10,000.
Payment of the civil penalty must be made within 20 days of service. Federal regulations
(49 C.F.R. § 89.21(b)(3)) require such payment to be made by wire transfer through the Federal
Reserve Communications System (Fedwire), to the account of the U.S. Treasury. Detailed
instructions are contained in the enclosure. Questions concerning wire transfers should be
3 The Pipeline Safety, Regulatory Certainty, and Job Creation Act of 2011, Pub. L. No. 112-90, § 2(a)(1), 125 Stat.
1904, January 3, 2012, increased the civil penalty liability for violating a pipeline safety standard to $200,000 per
violation for each day of the violation, up to a maximum of $2,000,000 for any related series of violations.



5
directed to: Financial Operations Division (AMK-325), Federal Aviation Administration, Mike
Monroney Aeronautical Center, P.O. Box 269039, Oklahoma City, Oklahoma 73125. The
Financial Operations Division telephone number is (405) 954-8845.
Failure to pay the $10,000 civil penalty will result in accrual of interest at the current annual rate
in accordance with 31 U.S.C. § 3717, 31 C.F.R. § 901.9 and 49 C.F.R. § 89.23. Pursuant to
those same authorities, a late penalty charge of six percent (6%) per annum will be charged if
payment is not made within 110 days of service. Furthermore, failure to pay the civil penalty
may result in referral of the matter to the Attorney General for appropriate action in a district
court of the United States.
COMPLIANCE ORDER
The Notice proposed a compliance order with respect to Item 1 in the Notice for violation of
49 C.F.R. § 192.709. Under 49 U.S.C. § 60118(a), each person who engages in the
transportation of gas or who owns or operates a pipeline facility is required to comply with the
applicable safety standards established under chapter 601. Pursuant to the authority of 49 U.S.C.
§ 60118(b) and 49 C.F.R. § 190.217, Respondent is ordered to take the following actions to
ensure compliance with the pipeline safety regulations applicable to its operations:
1. With respect to the violation of § 192.709 (Item 1), Respondent must perform a
relief capacity analysis on all associated devices that do not have adequate records
and make any changes, if necessary, to establish adequate capacity.
2. Respondent shall have 120 days from the receipt of a Final Order to complete the
requirements for Item 1 of the Notice.
3. It is requested (not mandated) that Respondent maintain documentation of the
safety improvement costs associated with fulfilling this Compliance Order and
submit the total to Byron Coy, PE, Director, Eastern Region, Pipeline and
Hazardous Materials Safety Administration. It is requested that these costs be
reported in two categories: 1) total cost associated with preparation/revision of
plans, procedures, studies, and analyses; and 2) total cost associated with
replacements, additions, and other changes to pipeline infrastructure.
The Director may grant an extension of time to comply with any of the required items upon a
written request timely submitted by the Respondent and demonstrating good cause for an
extension.
Failure to comply with this Order may result in the administrative assessment of civil penalties
not to exceed $200,000 for each violation for each day the violation continues or in referral to the
Attorney General for appropriate relief in a district court of the United States.
Under 49 C.F.R. § 190.215, Respondent has a right to submit a Petition for Reconsideration of
this Final Order. The petition must be sent to: Associate Administrator, Office of Pipeline



6
Safety, PHMSA, 1200 New Jersey Avenue, SE, East Building, 2nd Floor, Washington, DC
20590, with a copy sent to the Office of Chief Counsel, PHMSA, at the same address. PHMSA
will accept petitions received no later than 20 days after receipt of service of this Final Order by
the Respondent, provided they contain a brief statement of the issue(s) and meet all other
requirements of 49 C.F.R. § 190.215. The filing of a petition automatically stays the payment of
any civil penalty assessed. Unless the Associate Administrator, upon request, grants a stay, all
other terms and conditions of this Final Order are effective upon service in accordance with
49 C.F.R. § 190.5.
___________________________________ __________________________
Jeffrey D. Wiese Date Issued
Associate Administrator
for Pipeline Safety

120141001_Closure Letter_04072015_text.pdf

U.S. Department Of Transportation Pipeline and 609.989.2171
Hazardous Materials
Safety Administration
820 Bear Tavern Road, Suite 103
West Trenton, NJ 08628
OVERNIGHT EXPRESS DELIVERY
April 7, 2015
Ms. Miranda Jones, VP ESR
Crestwood Midstream GP, LLC
801 Cherry St, Suite 3800, Unit 20
Fort Worth TX, 76102
CPF 1-2014-1001
Dear Ms. Jones:
On September 10, 2014, the Pipeline and Hazardous Materials Safety Administration (PHMSA)
issued to Arlington Storage Company, LLC (Arlington Storage), a subsidiary of Crestwood
Midstream GP, LLC, a Final Order in the above-referenced case. This Order included a
Compliance Order and Civil Penalty assessment. Based on our review of the documentation
Arlington Storage provided, and confirmation of payment of the civil penalty, it has been
determined that Arlington Storage has complied with the terms of this Order.
Accordingly, this case is now closed and no further action is contemplated with respect to the
matters involved in this case. Thank you for your cooperation in this matter.
Sincerely,
Byron Coy, PE
Director, Eastern Region
Pipeline and Hazardous Materials Safety Administration
Cc: Mr. Kevin Speicher, NYSDPS

## Provenance

- Official: Yes
- Source: <https://primis.phmsa.dot.gov/enforcement-data/case/120141001>
- Source ID: `phmsa-enforcement`
- SHA-256: `36790cd04e45638e5f49c7d2bf499ae1a26660641ed2ab42a9d46894566c11b8`
- Retrieved: 2026-08-20T04:44:44.458Z
- Exported: 2026-08-23T22:27:02.555Z
- Document slug: `phmsa-enforcement-120141001`

### Source metadata

```json
{
  "cpf": "120141001",
  "operator": "NEW YORK STATE ELECTRIC & GAS CORP",
  "region": "Eastern",
  "pipelineType": "GAS INTERSTATE ONSHORE",
  "caseStatus": "CLOSED",
  "citedSections": [
    "192.491(c)",
    "192.709"
  ],
  "dataAsOf": "08/04/2026 12PM",
  "caseDataAsOf": "2026-08-04",
  "attachmentCount": 7,
  "attachments": [
    {
      "name": "120141001_Closure Letter_04072015.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/120141001/120141001_Closure%20Letter_04072015.pdf",
      "bytes": 59162,
      "category": "agency_document"
    },
    {
      "name": "120141001_Closure Letter_04072015_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/120141001/120141001_Closure%20Letter_04072015_text.pdf",
      "bytes": 14742,
      "category": "agency_document"
    },
    {
      "name": "120141001_Final Order_09102014.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/120141001/120141001_Final%20Order_09102014.pdf",
      "bytes": 390469,
      "category": "agency_document"
    },
    {
      "name": "120141001_Final Order_09102014_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/120141001/120141001_Final%20Order_09102014_text.pdf",
      "bytes": 30144,
      "category": "agency_document"
    },
    {
      "name": "120141001_NOPV PCP PCO_01022014.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/120141001/120141001_NOPV%20PCP%20PCO_01022014.pdf",
      "bytes": 378795,
      "category": "agency_document"
    },
    {
      "name": "120141001_NOPV PCP PCO_01022014_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/120141001/120141001_NOPV%20PCP%20PCO_01022014_text.pdf",
      "bytes": 27413,
      "category": "agency_document"
    },
    {
      "name": "120141001_Operator Response_01312014.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/120141001/120141001_Operator%20Response_01312014.pdf",
      "bytes": 761605,
      "category": "party_submission"
    }
  ],
  "extractedAgencyDocumentCount": 3,
  "attachmentPolicy": "Official attachment links are retained. Agency-issued documents may also include a verified local PDF and page-level text representation.",
  "jurisdiction": "US",
  "operatorName": "NEW YORK STATE ELECTRIC & GAS CORP"
}
```
