# TRANSCONTINENTAL GAS PIPE LINE COMPANY — Warning Letter

**Citation:** CPF 120171012W  
**Type / status:** enforcement / historical  
**Agency:** Pipeline and Hazardous Materials Safety Administration  
**Effective:** Not stated  
**Published:** 2017-05-08

CLOSED warning letter citing 192.605(a).

## Document text

Warning Letter involving TRANSCONTINENTAL GAS PIPE LINE COMPANY. PHMSA's enforcement data identifies the cited regulation as 192.605(a). The case was opened on 2017-05-08 and is reported as closed as of 2017-05-08. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

120171012W_Warning Letter_05082017.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120171012W/120171012W_Warning%20Letter_05082017.pdf

120171012W_Warning Letter_05082017_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120171012W/120171012W_Warning%20Letter_05082017_text.pdf

120171012W_Warning Letter_05082017_text.pdf

WARNING LETTER
OVERNIGHT EXPRESS DELIVERY
May 8, 2017
Mr. Mark Cluff
VP Safety & Operational Discipline
Transcontinental Gas Pipe Line Company
One Williams Center
Tulsa, OK 74172
CPF 1-2017-1012W
Dear Mr. Cluff:
From August 1 – 5, 2016, representatives of the Pipeline and Hazardous Materials Safety
Administration (PHMSA), Office of Pipeline Safety, pursuant to Chapter 601 of 49 United States
Code, inspected Transcontinental Gas Pipe Line Company’s (Transco) VA-North District,
PHMSA Unit #891 in Manassas, VA.
As a result of the inspection, it appears that you have committed a probable violation of the Pipeline
Safety Regulations, Title 49, Code of Federal Regulations. The items inspected and the probable
violation is:
1. § 192. 605 Procedural Manual for operations, maintenance, and emergencies
(a) General. Each operator shall prepare and follow for each pipeline, a manual of
written procedures for conducting operations and maintenance activities and for
emergency response. For transmission lines, the manual must also include
procedures for handling abnormal operations. This manual must be reviewed and
updated by the operator at intervals not exceeding 15 months, but at least one
each calendar year. This manual must be prepared before operations of a pipeline
system commence. Appropriate parts of the manual must be kept at locations
where operations and maintenance activities are conducted.
Transco failed to follow for each pipeline, a manual of written procedures for conducting
operations and maintenance activities and for emergency response. Specifically, Transco failed to



CPF 1-2017-1012W
follow its written procedure 20.06.03, Cathodic Protection Criteria, Rev.13, dated 3/27/2013
(Procedure), pursuant to 192.463(a).
§192.463 (a) states “Each cathodic protection system required by this subpart must provide a level
of cathodic protection that complies with one or more of the applicable criteria contained in
Appendix D of this part. If none of these criteria is applicable, the cathodic protection system must
provide a level of cathodic protection at least equal to that provided by compliance with one or
more of these criteria.”
Transco’s Procedure establishes the CP protection criteria utilized to confirm adequate external
corrosion control on their facilities. The 3 criteria listed in this procedure are:
1. 2. -0.850 Volt Pipe-to-Soil (with IR drop considered),
100 mV Voltage Shift (Polarization Decay), and
3. 300 mV Shift.
Section 1.0. Using the -0.850 Volt Pipe-to-Soil Criteria, paragraph 1.3 states “Consider any voltage
(IR) drops according to WilSOP O&M 20.06.02 – Methods for IR Drop Correction.”
During the inspection, the PHMSA inspector reviewed annual CP survey records for 2014, 2015
and 2016 for test points within Transco’s Virginia - North district.
The 2014 records at relative station engineering numbers 76599+25, 76599+26 and 76599+27 (test
points 30, 31 and 32), located at the V-266 flow control valve within the Tenaska-Antioch M&R
station, indicated the following:
1. Inspection remarks: “Mags not interrupted.”
2. Structure P/S [Pipe to Soil] and Structure IRF [IR Free]:
a. Values recorded under the “Structure IRF” column were more negative than the
values in the “Structure P/S” column at test points 30 and 31, indicating that current
sources may have been interrupted and that IR drop had not been considered.
b. Transco Asset Integrity personnel indicated that there are uninterruptable anodes at
this location that are not detached during annual CP surveys.
3. The “Native P/S” column of the report was blank. The lack of native pipe-to-soil readings
in the “Native P/S” column prevents application of criterion other than the -0.850 Volt
Pipe-to-Soil criteria, such as the 100 mV Voltage Shift or 300 mV Criteria found in
Transco’s 20.06.03 procedure for CP criteria.
120171012W_Warning Letter_05082017_text Page 2 of 3



CPF 1-2017-1012W
Thus, Transco did not demonstrate that IR-drop was considered at these tests points, or that another
valid cathodic protection criterion was utilized at this location in accordance with their written
procedures.
Under 49 United States Code, § 60122, you are subject to a civil penalty not to exceed $205,638
per violation per day the violation persists up to a maximum of $2,056,380 for a related series of
violations. For violation occurring between January 4, 2012 to August 1, 2016, the maximum
penalty may not exceed $200,000 per violation per day, with a maximum penalty not to exceed
$2,000,000 for a related series of violations. For violations occurring prior to January 4, 2012, the
maximum penalty may not exceed $100,000 per violation per day, with a maximum penalty not to
exceed $1,000,000 for a related series of violations. We have reviewed the circumstances and
supporting documents involved in this case, and have decided not to conduct additional
enforcement action or penalty assessment proceedings at this time. We advise you to correct the
item identified in this letter. Failure to do so will result in Transco being subject to additional
enforcement action.
Be advised that all material you submit in response to this enforcement action is subject to being
made publicly available. If you believe that any portion of your responsive material qualifies for
confidential treatment under 5 U.S.C. 552(b), along with the complete original document, you
must provide a second copy of the document with the portions you believe qualify for confidential
treatment redacted and an explanation of why you believe the redacted information qualifies for
confidential treatment under 5 U.S.C. 552(b).
No reply to this letter is required. If you choose to reply, please submit all correspondence in this
matter to Robert Burrough, Acting Director, PHMSA Eastern Region, 820 Bear Tavern Road,
Suite 103, West Trenton, NJ 08628. Please refer to CPF 1- 2017-1012W on each document you
submit, and whenever possible provide a signed PDF copy in electronic format. Smaller files may
be emailed to robert.burrough@dot.gov. Larger files should be sent on a CD accompanied by the
original paper copy to the Eastern Region Office.
Additionally, if you choose to respond to this (or any other case), please ensure that any response
letter pertains solely to one CPF case number.
Sincerely,
Robert Burrough
Acting Director, Eastern Region
Pipeline and Hazardous Materials Safety Administration
120171012W_Warning Letter_05082017_text Page 3 of 3

## Provenance

- Official: Yes
- Source: <https://primis.phmsa.dot.gov/enforcement-data/case/120171012W>
- Source ID: `phmsa-enforcement`
- SHA-256: `b3693da9652bb161fa684e373ad5696cfe349ee1e1783e6a322fd04d3d6c1fd1`
- Retrieved: 2026-08-20T04:44:44.458Z
- Exported: 2026-08-23T09:31:14.494Z
- Document slug: `phmsa-enforcement-120171012w`

### Source metadata

```json
{
  "cpf": "120171012W",
  "operator": "TRANSCONTINENTAL GAS PIPE LINE COMPANY",
  "region": "Eastern",
  "pipelineType": "GAS INTERSTATE ONSHORE",
  "caseStatus": "CLOSED",
  "citedSections": [
    "192.605(a)"
  ],
  "dataAsOf": "08/04/2026 12PM",
  "caseDataAsOf": "2026-08-04",
  "attachmentCount": 2,
  "attachments": [
    {
      "name": "120171012W_Warning Letter_05082017.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/120171012W/120171012W_Warning%20Letter_05082017.pdf",
      "bytes": 266920,
      "category": "agency_document"
    },
    {
      "name": "120171012W_Warning Letter_05082017_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/120171012W/120171012W_Warning%20Letter_05082017_text.pdf",
      "bytes": 136239,
      "category": "agency_document"
    }
  ],
  "extractedAgencyDocumentCount": 1,
  "attachmentPolicy": "Official attachment links are retained. Agency-issued documents may also include a verified local PDF and page-level text representation.",
  "jurisdiction": "US",
  "operatorName": "TRANSCONTINENTAL GAS PIPE LINE COMPANY"
}
```
