# PHILADELPHIA ENERGY SOLUTIONS REFINING AND MARKETING, LLC — Warning Letter

**Citation:** CPF 120176006W  
**Type / status:** enforcement / historical  
**Agency:** Pipeline and Hazardous Materials Safety Administration  
**Effective:** Not stated  
**Published:** 2017-09-12

CLOSED warning letter citing 195.412(b), 195.452(b)(5), 195.452(j)(5)(iv), 195.452(l)(ii).

## Document text

Warning Letter involving PHILADELPHIA ENERGY SOLUTIONS REFINING AND MARKETING, LLC. PHMSA's enforcement data identifies the cited regulations as 195.412(b),  195.452(b)(5),  195.452(j)(5)(iv),  195.452(l)(ii). The case was opened on 2017-09-12 and is reported as closed as of 2017-09-12. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

120176006W_Operator Response to Notice_10042017.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120176006W/120176006W_Operator%20Response%20to%20Notice_10042017.pdf

120176006W_Warning Letter_09122017.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120176006W/120176006W_Warning%20Letter_09122017.pdf

120176006W_Warning Letter_09122017_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120176006W/120176006W_Warning%20Letter_09122017_text.pdf

120176006W_Warning Letter_09122017_text.pdf

WARNING LETTER
OVERNIGHT EXPRESS DELIVERY
September 12, 2017
John Pickering
Senior Vice President, Manufacturing
Philadelphia Energy Solutions Refining and Marketing, LLC
3144 Passyunk Avenue
Philadelphia, PA 19145
CPF 1-2017-6006W
Dear Mr. Pickering:
Between October 14 and November 16, 2015, a representative of the Pipeline and Hazardous
Materials Safety Administration (PHMSA), Office of Pipeline Safety (OPS) pursuant to Chapter
601 of 49 United States Code (U.S.C.) inspected certain procedures of Philadelphia Energy
Solutions Refining and Marketing, LLC’s (PES) operation and maintenance manual and integrity
management program along with associated records in Philadelphia, Pennsylvania.
As a result of the inspection, it is alleged that you have committed probable violations of the
Pipeline Safety Regulations, Title 49, Code of Federal Regulations (CFR). The items inspected
and the probable violations are:
1. §195.412 Inspection of rights-of-way and crossings under navigable waters.
(b) Except for offshore pipelines, each operator shall, at intervals not exceeding
5 years, inspect each crossing under a navigable waterway to determine the condition
of the crossing.
PES failed to inspect each crossing under navigable waterways to determine the condition of the
crossing at intervals not exceeding 5 years.
During this inspection, the PHMSA representative requested to review the most recent and
previous navigable waterway inspection reports, respectively



CPF 1-2017-6006W
1) PES presented a report titled Summary of Inspection Findings dated December 22, 2014
for an inspection conducted from September 18-19, 2014 at four Schuylkill River
Crossings in Philadelphia, Pennsylvania.
2) PES presented a report titled Summary of Inspection Findings dated July 22, 2009 for
an inspection conducted on March 11 and 23, 2009 at four Schuylkill River Crossings
in Philadelphia, Pennsylvania.
The PHMSA representative requested a copy of the referenced drawings titled Sunoco Dwg.
No. 1-0-3H/85001D in the report. PES produced the drawings that showed the location and names
of the jurisdictional pipelines at the four crossings.
The time interval between the September 19, 2014 and March 23, 2009 inspection of crossing
under four navigable waterways exceeded 5 years by 180 days. Therefore, PES failed to inspect
each crossing under navigable waterways to determine the condition of the crossing at intervals
not exceeding 5 years as prescribed in § 195.412(b).
2. §195.452 Pipeline integrity management in high consequence areas.
(b) What program and practices must operators use to manage pipeline integrity? Each
operator of a pipeline covered by this section must:…
(5) Implement and follow the program.
PES failed to implement and follow its written integrity management program. Specifically, PES
did not utilize a leak detection system for detecting leaks on its FM1 pipeline between Schuylkill
River Tank Farm (SRFT) and West Yard for 2 years and # 7 Line for an undetermined time frame
in accordance with its Pipeline Integrity Management Plan, Revision Date: 3/6/2015, 5.6.2.
Preventive and Mitigative Measures, 3) Leak Detection (Procedure).
Pursuant to § 195.452(f)(6), an operator must include the element of identifying preventive and
mitigative measures to protect the high consequence area as seen in § 195.452(i). Section
195.452(i)(3) states an operator must have a means to detect leaks on its pipeline system.
According to the Procedure, PES utilizes a computational pipeline monitoring (computer based)
system which was referred to as Siemens/Controlotron to, among other things, detect leaks on its
pipelines.
During this inspection, the PHMSA representative requested PES to produce records of its leak
detection to review. Subsequently, PES presented an e-mail dated October 29, 2015 from the SRFT
lead operator to the Inspection Superintendent stating, “[t]he following lines need to be addressed
to repair the leak detection system at SRTF: 1) The FM1 line is not working at SRTF. Strap on
equipment not functioning both at SRTF and N1 (Has not worked for 2 years)… 4) 7 Line reading
bad….” PES’s Inspection Superintendent sent an e-mail to GP Instrument Reliability Engineer on
November 13, 2015 stating “What do we need to do to correct these issues?” Therefore, PES was
not able to utilize a leak detection system to detect leaks on the pipeline FM1 and # 7 Line in
accordance with the Procedure Section 5.6.2. Preventive and Mitigative Measures, 3) Leak
Detection.
120176006W_Warning Letter_09122017_text
Page 2 of 5



CPF 1-2017-6006W
Therefore, PES failed to implement and follow its Procedure as prescribed in § 195.452(b)(5) and
in accordance with § 195.452(f)(6).
3. §195.452 Pipeline integrity management in high consequence areas.
(j) What is a continual process of evaluation and assessment to maintain a pipeline's
integrity? –
(5) Assessment methods. An operator must assess the integrity of the line pipe by any
of the following methods. The methods an operator selects to assess low frequency
electric resistance welded pipe or lap welded pipe susceptible to longitudinal seam
failure must be capable of assessing seam integrity and of detecting corrosion and
deformation anomalies.
(iv) Other technology that the operator demonstrates can provide an equivalent
understanding of the condition of the line pipe. An operator choosing this option must
notify OPS 90 days before conducting the assessment, by sending a notice to the
address or facsimile number specified in paragraph (m) of this section.
PES failed to notify OPS 90 days before conducting an assessment using “other technology”, by
sending a notice to the address or facsimile number specified in § 195.452(m).
During this inspection, the PHSMA inspector requested to review PES’s integrity assessment
schedule for its pipelines which are located in a high consequence area (HCA). PES provided the
PHMSA representative with a copy of its DOT Inspection Schedule spreadsheet. The PHMSA
representative noted that the in-service Line ID Nos. 11178 and 11179 was assessed using guided
wave ultrasonic (GWUT) in 2010 and then in 2015. GWUT is considered to be “other technology.”
Subsequently, the PHMSA representative requested PES to provide records of submitting the
notification for using an “other technology” assessment method for Line ID Nos. 11178 and 11179
in 2015. PES did not provide records to show it submitted notification to OPS 90 days prior to
using GWUT. In addition, the PHMSA representative confirmed with OPS that it did not receive
a notification from PES for using an “other technology” assessment method in 2015.
Therefore, PES failed to notify OPS 90 days before conducting an assessment using “other
technology”, by sending a notice to the address or facsimile number specified in § 195.452(m), as
prescribed in § 195.452(j)(5)(iv).
4. §195.452 Pipeline integrity management in high consequence areas.
(l) What records must an operator keep to demonstrate compliance? (1) An operator
must maintain, for the useful life of the pipeline, records that demonstrate compliance
with the requirements of this subpart. At a minimum, an operator must maintain the
following records for review during an inspection:
(ii) Documents to support the decisions and analyses, including any modifications,
justifications, deviations and determinations made, variances, and actions taken, to
implement and evaluate each element of the integrity management program listed in
paragraph (f) of this section.
120176006W_Warning Letter_09122017_text
Page 3 of 5



CPF 1-2017-6006W
PES failed to maintain, for the useful life of the pipeline, documents that support the decisions and
analyses, including any modifications, justifications, deviations and determinations made,
variances, and actions taken, to implement and evaluate each element of the integrity management
program. Specifically, PES failed to maintain adequate documentation to support its decision for
determining whether an emergency flow restricting device (EFRD) was needed, to implement and
evaluate preventive and mitigative measures pursuant to § 195.452(f)(6).
Pursuant to § 195.452(f)(6), an operator must include in its written integrity management program
identification of preventive and mitigative measures to protect the high consequence area as seen
in § 195.452(i).
According to § 195.452(i)(4), an operator must determine whether an EFRD is needed on a
pipeline segment to protect a high consequence area in an event of a hazardous liquid pipeline
release. The operator must, at least, consider the following factors in making the determination if
a EFRD is needed — the swiftness of leak detection and pipeline shutdown capabilities, the type
of commodity carried, the rate of potential leakage, the volume that can be released, topography
or pipeline profile, the potential for ignition, proximity to power sources, location of nearest
response personnel, specific terrain between the pipeline segment and the high consequence area,
and benefits expected by reducing the spill size.
During this inspection, the PHMSA requested PES to produce records of the EFRD evaluation.
Subsequently, PES presented its Pipeline Integrity Management Plan, Revision Date: 3/6/2015,
5.6.2. Preventive and Mitigative Measures, a. Emergency Flow Restricting Devices which states
in part:
“Sunoco, Inc. R&M, and subsequently PES, considered the use of EFRD’s but
determined the use of EFRD’s are not an appropriate course of action since they
could potentially cause more problems than they can solve. For this reason this
specific action is not included in the Risk Model. Most of the lines are within five
miles of the refinery, and a majority of the lines are short river crossings linking
one part of the refinery to the other. The closeness of the lines to the refinery and
refinery operations means that they are monitored frequently.”
The document did not include details about the consideration made to the factors listed in
§ 195.452(i)(4). For instance, this document did not include information about considering type of
commodity carried, potential ignition, or proximity to power source. In addition, this document
did not include a detailed explaination for why EFRD was not needed or needed; instead of stating
it will “cause more problems.” Furthermore, the document did not describe when the evaluation
was done, who was involved in the decision making, and other pertinent information.
Therefore, PES failed to maintain adequate documentation to support its decision for determining
whether an EFRD was needed, to implement and evaluate § 195.452(f)(6), as prescribed in
§ 195.452(l)(1)(ii).
As of April 27, 2017, under 49 U.S.C. § 60122 and 49 CFR § 190.223, you are subject to a civil
penalty not to exceed $209,002 per violation per day the violation persists up to a maximum of
$2,090,022 for a related series of violations. We have reviewed the circumstances and supporting
documents involved in this case, and have decided not to conduct additional enforcement action120176006W_Warning Letter_09122017_text
Page 4 of 5



CPF 1-2017-6006W
or penalty assessment proceedings at this time. We advise you to correct the items identified in
this letter. Failure to do so will result in Philadelphia Energy Solutions Refining and Marketing,
LLC being subject to additional enforcement action.
No reply to this letter is required. If you choose to reply, please submit all correspondence in this
matter to Robert Burrough, Acting Director, PHMSA Eastern Region, 820 Bear Tavern Road,
Suite 103, West Trenton, NJ 08628. Please refer to CPF 1- 2017-6006W on each document you
submit, and whenever possible provide a signed PDF copy in electronic format. Smaller files may
be emailed to robert.burrough@dot.gov. Larger files should be sent on a CD accompanied by the
original paper copy to the Eastern Region Office.
Be advised that all material you submit in response to this enforcement action is subject to being
made publicly available. If you believe that any portion of your responsive material qualifies for
confidential treatment under 5 U.S.C. 552(b), along with the complete original document you must
provide a second copy of the document with the portions you believe qualify for confidential
treatment redacted and an explanation of why you believe the redacted information qualifies for
confidential treatment under 5 U.S.C. 552(b).
Sincerely,
Robert Burrough
Acting Director, Eastern Region
Pipeline and Hazardous Materials Safety Administration
120176006W_Warning Letter_09122017_text
Page 5 of 5

## Provenance

- Official: Yes
- Source: <https://primis.phmsa.dot.gov/enforcement-data/case/120176006W>
- Source ID: `phmsa-enforcement`
- SHA-256: `3ee1053fe26e5bb9acc2261486cbaa08b7c126f7d099b88da379d081d90c926b`
- Retrieved: 2026-08-20T04:44:44.458Z
- Exported: 2026-08-22T01:41:33.248Z
- Document slug: `phmsa-enforcement-120176006w`

### Source metadata

```json
{
  "cpf": "120176006W",
  "operator": "PHILADELPHIA ENERGY SOLUTIONS REFINING AND MARKETING, LLC",
  "region": "Eastern",
  "pipelineType": "INTRASTATE LIQUID ONSHORE",
  "caseStatus": "CLOSED",
  "citedSections": [
    "195.412(b)",
    "195.452(b)(5)",
    "195.452(j)(5)(iv)",
    "195.452(l)(ii)"
  ],
  "dataAsOf": "08/04/2026 12PM",
  "caseDataAsOf": "2026-08-04",
  "attachmentCount": 3,
  "attachments": [
    {
      "name": "120176006W_Operator Response to Notice_10042017.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/120176006W/120176006W_Operator%20Response%20to%20Notice_10042017.pdf",
      "bytes": 86011,
      "category": "party_submission"
    },
    {
      "name": "120176006W_Warning Letter_09122017.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/120176006W/120176006W_Warning%20Letter_09122017.pdf",
      "bytes": 479353,
      "category": "agency_document"
    },
    {
      "name": "120176006W_Warning Letter_09122017_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/120176006W/120176006W_Warning%20Letter_09122017_text.pdf",
      "bytes": 135923,
      "category": "agency_document"
    }
  ],
  "extractedAgencyDocumentCount": 1,
  "attachmentPolicy": "Official attachment links are retained. Agency-issued documents may also include a verified local PDF and page-level text representation.",
  "jurisdiction": "US",
  "operatorName": "PHILADELPHIA ENERGY SOLUTIONS REFINING AND MARKETING, LLC"
}
```