# ALGONQUIN GAS TRANSMISSION, L.L.C. (SPECTRA ENERGY PARTNERS, LP) — Corrective Action Order

**Citation:** CPF 12020014CAO  
**Type / status:** enforcement / historical  
**Agency:** Pipeline and Hazardous Materials Safety Administration  
**Effective:** Not stated  
**Published:** 2020-10-01

CLOSED corrective action order.

## Document text

Corrective Action Order involving ALGONQUIN GAS TRANSMISSION, L.L.C. (SPECTRA ENERGY PARTNERS, LP). The dataset does not identify a cited regulation for this case. The case was opened on 2020-10-01 and is reported as closed as of 2021-11-17. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

12020014CAO_Amended Corrective Action Order_10302020_(20-172418).pdf: https://primis.phmsa.dot.gov/enforcement-documents/12020014CAO/12020014CAO_Amended%20Corrective%20Action%20Order_10302020_(20-172418).pdf

12020014CAO_Amended Corrective Action Order_10302020_(20-172418)_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/12020014CAO/12020014CAO_Amended%20Corrective%20Action%20Order_10302020_(20-172418)_text.pdf

12020014CAO_Closure Letter_11172021_(20-172418).pdf: https://primis.phmsa.dot.gov/enforcement-documents/12020014CAO/12020014CAO_Closure%20Letter_11172021_(20-172418).pdf

12020014CAO_Closure Letter_11172021_(20-172418)_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/12020014CAO/12020014CAO_Closure%20Letter_11172021_(20-172418)_text.pdf

12020014CAO_Corrective Action Order_10012020_(20-172418).pdf: https://primis.phmsa.dot.gov/enforcement-documents/12020014CAO/12020014CAO_Corrective%20Action%20Order_10012020_(20-172418).pdf

12020014CAO_Corrective Action Order_10012020_(20-172418)_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/12020014CAO/12020014CAO_Corrective%20Action%20Order_10012020_(20-172418)_text.pdf

12020014CAO_Operator Hearing Request Withdrawn_11042020_(20-172418).pdf: https://primis.phmsa.dot.gov/enforcement-documents/12020014CAO/12020014CAO_Operator%20Hearing%20Request%20Withdrawn_11042020_(20-172418).pdf

12020014CAO_Operator Request for Hearing and Statement of Issues_10132020_(20-172418).pdf: https://primis.phmsa.dot.gov/enforcement-documents/12020014CAO/12020014CAO_Operator%20Request%20for%20Hearing%20and%20Statement%20of%20Issues_10132020_(20-172418).pdf

12020014CAO_Amended Corrective Action Order_10302020_(20-172418)_text.pdf

October 30, 2020
VIA ELECTRONIC MAIL TO: bill.yardley@enbridge.com
Mr. William T. Yardley
President, Gas Transmission and Midstream
Enbridge, Inc.
5400 Westheimer Court
Houston, Texas 77056
CPF No. 1-2020-014-CAO
Dear Mr. Yardley:
Enclosed please find an Amended Corrective Action Order (ACAO) issued by the Pipeline and
Hazardous Materials Safety Administration (PHMSA), Office of Pipeline Safety (OPS), in the
above-referenced case. It requires Algonquin Gas Transmission, LLC, a subsidiary of Enbridge
Inc., to take certain corrective actions with respect to Algonquin’s Weymouth Compressor Station
in Weymouth, Massachusetts.
Service of the ACAO by electronic mail is deemed complete upon transmission and
acknowledgement of receipt, or as otherwise provided under 49 C.F.R. § 190.5. The terms and
conditions of this Order are effective upon completion of service.
Sincerely,
Alan K. Mayberry
Associate Administrator
for Pipeline Safety
Enclosure: ACAO
cc: Ms. Linda Daugherty, Deputy Associate Administrator for Field Operations, OPS
Mr. Robert Burrough, Director, Eastern Region, OPS
Ms. Michele Harradence, SVP & Chief Operating Officer, Gas Transmission and
Midstream, michele.harradence@enbridge.com
Mr. Nathan Atanu, Manager, Operational Compliance, Algonquin Gas Transmission, LLC,
nathan.atanu@enbridge.com
CONFIRMATION OF RECEIPT REQUESTED



U.S. DEPARTMENT OF TRANSPORTATION
PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION
OFFICE OF PIPELINE SAFETY
WASHINGTON, D.C. 20590
____________________________________
In the Matter of )
Algonquin Gas Transmission, LLC, ) CPF No. 1-2020-014-CAO
a subsidiary of Enbridge, Inc., )
)
)
)
Respondent. )
____________________________________)
AMENDED CORRECTIVE ACTION ORDER
Purpose and Background:
This Amended Corrective Action Order (ACAO or Order) is being issued under the authority of
49 U.S.C. § 60112 to require Algonquin Gas Transmission, LLC (AGT or Respondent), a
subsidiary of Enbridge, Inc.,1 to take the necessary corrective actions to protect the public,
property, and the environment from potential hazards associated with the unplanned emergency
shutdown events at its Weymouth Compressor Station in Weymouth, Massachusetts (Station).
On September 11, 2020, the Station experienced an O-ring gasket failure on a sump tank during
the Station’s commissioning activities (Event 1). The failure triggered the manual operation of the
emergency shutdown system and the release of approximately 169 thousand cubic feet (mscf) of
natural gas. On September 30, 2020, at approximately 10:30 AM, the Station experienced an
unplanned emergency shutdown, resulting in the release of approximately 195 mscf of natural gas
(Event 2). The circumstances surrounding the failure of the O-ring gasket in Event 1, as well as
the cause for the emergency shutdown in Event 2 (collectively, Events), are under investigation.
Pursuant to 49 U.S.C. § 60117, PHMSA, Office of Pipeline Safety (OPS), initiated an investigation
of the Events. As a result of our investigation and additional information provided by AGT,
PHMSA is issuing this ACAO to clarify a few of the preliminary facts and to modify the
definitions. The ACAO does not make any substantive changes to the corrective actions prescribed
in the CAO.
The preliminary findings of the agency’s ongoing investigation are as follows:
1 Enbridge, Inc. website, National Gas Transmission and Midstream, available at
https://www.enbridge.com/About-Us/Natural-Gas-Transmission-and-Midstream.aspx (last accessed September 30,
2020).



CPF No. 1-2020-014-CAO
Page 2
Preliminary Findings:
 The Station is the final part of AGT’s Atlantic Bridge Pipeline Project (Project). The
Project involved replacing a 6.3-mile (10-kilometer) 26-inch-diameter pipe section
with a 42-inch pipe in New York and Connecticut. The Project also involved installing
a new meter station in Connecticut, modifications to various metering stations spread
across several states, installation of four new compressor units at existing facilities, and
a new compressor station in Weymouth, Massachusetts. The Project was designed to
provide an additional 132,700 dekatherms of capacity on the AGT pipeline system and
the Maritimes & Northeast pipeline system.
 Weymouth, Massachusetts, is a heavily populated suburb outside of Boston,
Massachusetts. The Station is in a high consequence area, and is located near Fore
River Bridge, a heavily trafficked commuter road.
 The Station has a station design pressure of 1440 pounds per square inch gauge (psig).
 The Station experienced a gasket failure that triggered the manual activation of its
emergency shutdown system, as well as an unplanned emergency shutdown due to
unknown reasons, less than three weeks apart.
 There were no injuries or fatalities associated with the Events; however, the release of
large quantities of pressurized natural gas in a heavily populated area carries a
substantial risk of fire, explosion, and personal injury or death, and releases natural gas
into the environment.
 On September 30, 2020, the inlet pressure at the Station was 683 psig; the discharge
pressure at the time of the emergency shutdown was 707 psig.
 AGT is performing a root cause failure analysis on the O-ring gasket failure that caused
Event 1.
 The reason for Event 2 is unknown and under investigation.
 The Station is currently shut-in.
Determination of Necessity for Corrective Action Order and Right to Hearing:
Section 60112 of title 49, United States Code, authorizes PHMSA to determine that a pipeline
facility is or would be hazardous to life, property, or the environment and, if there is a likelihood
of serious harm, to expeditiously order the operator of the facility to take necessary corrective
action, including suspended or restricted use of the facility, physical inspection, testing, repair,
replacement, or other appropriate action. An order issued expeditiously must provide an
opportunity for a hearing as soon as practicable after the order is issued.



CPF No. 1-2020-014-CAO
Page 3
In deciding whether to issue an order, PHMSA must consider the following, if relevant: (1) the
characteristics of the pipe and other equipment used in the pipeline facility, including the age,
manufacture, physical properties, and method of manufacturing, constructing, or assembling the
equipment; (2) the nature of the material the pipeline facility transports, the corrosive and
deteriorative qualities of the material, the sequence in which the material are transported, and the
pressure required for transporting the material; (3) the aspects of the area in which the pipeline
facility is located, including climatic and geologic conditions and soil characteristics; (4) the
proximity of the area in which the hazardous liquid pipeline facility is located to environmentally
sensitive areas; (5) the population density and population and growth patterns of the area in
which the pipeline facility is located; (6) any recommendation of the National Transportation
Safety Board made under another law; and (7) any other factors PHMSA may consider
appropriate.
After evaluating the foregoing preliminary findings of fact, and having considered that the
Station had an O-ring gasket failure that triggered the manual operation of its emergency
shutdown system and an unplanned emergency shutdown for unknown reasons within three
weeks of each other; the uncertainties as to the cause of Event 2; and the Station’s location in a
High Consequence Area, and proximity to populated areas and highly-trafficked public roads, I
find that continued operation of the Station without corrective measures is or would be hazardous
to life, property, or the environment, and that failure to issue this Order expeditiously would
result in the likelihood of serious harm.
Accordingly, this Amended Corrective Action Order mandating immediate corrective action is
issued without prior notice and opportunity for a hearing. The terms and conditions of this Order
are effective upon receipt.
Within 10 days of receipt of this Order, Respondent may request a hearing, to be held as soon as
practicable, by notifying the Associate Administrator for Pipeline Safety in writing, with a copy
to the Director, Eastern Region, PHMSA (Director). If a hearing is requested, it will be held in
accordance with 49 C.F.R. § 190.211.
After receiving and analyzing additional data in the course of this investigation, PHMSA may
identify other corrective measures that need to be taken. Respondent will be notified of any
additional measures required and, if appropriate, PHMSA will consider amending or withdrawing
this Order, if warranted by new supporting information. To the extent consistent with safety,
Respondent will be afforded notice and an opportunity for a hearing prior to the imposition of any
additional corrective measures.
Required Corrective Actions:
Definitions:
Isolated Segment – Means the Weymouth Compressor Station, from inlet valves to outlet
valves.



CPF No. 1-2020-014-CAO
Page 4
Director – Means the Director, Pipeline and Hazardous Materials Safety Administration
(PHMSA), Office of Pipeline Safety, Eastern Region. The Director’s address is 840 Bear
Tavern Road, Suite 300, West Trenton, NJ 08626.
Pursuant to 49 U.S.C. 60112, I hereby order AGT to immediately take the following corrective
actions for the Isolated Segment:
1. Shutdown of the Isolated Segment. The Isolated Segment is currently shut-in and not in
operation. AGT must not operate the Isolated Segment until authorized to do so by the
Director.
2. Restart Plan. Prior to resuming operation of the Isolated Segment, AGT must develop and
submit a written Restart Plan to the Director for approval.
a. The Director may approve the Restart Plan incrementally without approving the
entire plan but the Isolated Segment cannot resume operation until the Restart Plan
is approved in its entirety.
b. Once approved by the Director, the Restart Plan will be incorporated by reference
into this Order.
c. The Restart Plan must provide for adequate patrolling of the Isolated Segment
during the restart process and must include incremental pressure increases during
start-up, with each increment to be held for at least two hours.
d. The Restart Plan must include sufficient surveillance of the Isolated Segment
during each pressure increment to ensure that no leaks are present when operation
of the pipeline facility resumes.
e. The Restart Plan must specify a day-light restart and include advance
communications with local emergency response officials.
f. The Restart Plan must provide for a review of the Isolated Segment for conditions
similar to those that caused the Events, including a review of construction and
commissioning records. AGT must address any findings that require remedial
measures to be implemented prior to restart.
g. The Restart Plan must also include documentation of the completion of all
mandated actions, and a management of change plan to ensure that all procedural
modifications are incorporated into AGT’s operations and maintenance procedures
manual.
3. Return to Service. After the Director approves the Restart Plan, AGT may return the
Isolated Segment to service but the operating pressure must not exceed eighty percent
(80%) of the actual operating pressure in effect immediately prior to Event 2, in accordance
with Item 2 above.
4. Removal of Pressure Restriction. The Director may allow the removal or modification of
the pressure restriction upon a written request from AGT demonstrating that restoring the



CPF No. 1-2020-014-CAO
Page 5
Isolated Segment to its pre-Event 2 operating pressure is justified based on a reliable
engineering analysis showing that the pressure increase is safe, considering all known
defects, anomalies, and operating parameters of the Isolated Segment.
5. Temporary Removal of Pressure Restriction. The Director may allow the temporary
removal or modification of the pressure restrictions upon a written request from AGT
demonstrating that temporary mitigative and preventive measures are being implemented
prior to and during the temporary removal or modification of the pressure restriction. The
Director's determination will be based on the known or suspected cause of Event 2 and the
provision of evidence that preventive and mitigative actions taken by the operator provide
for the safe operation of the Isolated Segment during the temporary removal or
modification of the pressure restriction. Appeals to determinations of the Director in this
regard will be decided by the Associate Administrator for Pipeline Safety.
6. Root Cause Failure Analysis. Within 90 days following receipt of this Order, complete a
root cause failure analysis (RCFA) and submit a final report of this RCFA to the
Director. The RCFA must be supplemented or facilitated by an independent third-party
acceptable to the Director and must document the decision-making process and all factors
contributing to Event 2. The final report must include findings and any lessons learned and
whether the findings and any lessons learned are applicable to other locations within AGT’s
pipeline system.
Other Requirements:
7. Approvals. With respect to each submission that under this Order requires the approval of
the Director, the Director may: (a) approve, in whole or part, the submission; (b) approve
the submission on specified conditions; (c) modify the submission to cure any deficiencies;
(d) disapprove in whole or in part, the submission, directing that Respondent modify the
submission, or (e) any combination of the above. In the event of approval, approval upon
conditions, or modification by the Director, Respondent shall proceed to take all action
required by the submission as approved or modified by the Director. If the Director
disapproves all or any portion of the submission, Respondent must correct all deficiencies
within the time specified by the Director, and resubmit it for approval.
8. Extensions of Time. The Director may grant an extension of time for compliance with any
of the terms of this Order upon a written request timely submitted demonstrating good
cause for an extension.
9. Reporting. Submit monthly reports to the Director that: (1) include all available data and
results of the testing and evaluations required by this Order; and (2) describe the progress
of the repairs or other remedial actions being undertaken. The first monthly report is due
on November 27, 2020. The Director may change the interval for the submission of these
reports.
10. Documentation of the Costs. It is requested but not required that Respondent maintain
documentation of the costs associated with implementation of this Corrective Action
Order. Include in each monthly report submitted, the to-date total costs associated with:



CPF No. 1-2020-014-CAO
Page 6
(1) preparation and revision of procedures, studies and analyses; (2) physical changes to
pipeline infrastructure, including repairs, replacements and other modifications; and (3)
environmental remediation, if applicable.
Be advised that all material you submit in response to this enforcement action is subject to being
made publicly available. If you believe that any portion of your responsive material qualifies for
confidential treatment under 5 U.S.C. § 552(b), along with the complete original document you
must provide a second copy of the document with the portions you believe qualify for confidential
treatment redacted and an explanation of why you believe the redacted information qualifies for
confidential treatment under 5 U.S.C. § 552(b).
In your correspondence on this matter, please refer to “CPF No. 1-2020-014-CAO” and for each
document you submit, please provide a copy in electronic format whenever possible. The actions
required by this Order are in addition to and do not waive any requirements that apply to
Respondent’s pipeline system under 49 C.F.R. Parts 190 through 199, under any other order issued
to Respondent under authority of 49 U.S.C. Chapter 601, or under any other provision of Federal
or State law.
Respondent may appeal any decision of the Director to the Associate Administrator for Pipeline
Safety. Decisions of the Associate Administrator shall be final.
Failure to comply with this Order may result in the assessment of civil penalties and in referral to
the Attorney General for appropriate relief in United States District Court pursuant to
49 U.S.C. § 60120.
The terms and conditions of this Order are effective upon service in accordance with 49 C.F.R.
§ 190.5.
October 30, 2020
_________________________________ ________________________
Alan K. Mayberry Date Issued
Associate Administrator
for Pipeline Safety

12020014CAO_Corrective Action Order_10012020_(20-172418)_text.pdf

October 1, 2020
VIA ELECTRONIC MAIL TO: bill.yardley@enbridge.com
Mr. William T. Yardley
President, Gas Transmission and Midstream
Enbridge, Inc.
5400 Westheimer Court
Houston, Texas 77056
CPF No. 1-2020-014-CAO
Dear Mr. Yardley:
Enclosed please find a Corrective Action Order (CAO) issued by the Pipeline and Hazardous
Materials Safety Administration (PHMSA), Office of Pipeline Safety (OPS), in the above-
referenced case. It requires Algonquin Gas Transmission, LLC, a subsidiary of Enbridge Inc., to
take certain corrective actions with respect to Algonquin’s Weymouth Compressor Station in
Weymouth, Massachusetts.
Service of the CAO by electronic mail is deemed complete upon transmission and
acknowledgement of receipt, or as otherwise provided under 49 C.F.R. § 190.5. The terms and
conditions of this Order are effective upon completion of service.
Sincerely,
Alan K. Mayberry
Associate Administrator
for Pipeline Safety
Enclosure: CAO
cc: Ms. Linda Daugherty, Deputy Associate Administrator for Field Operations, OPS
Mr. Robert Burrough, Director, Eastern Region, OPS
Ms. Michele Harradence, SVP & Chief Operating Officer, Gas Transmission and
Midstream, michele.harradence@enbridge.com
Mr. Nathan Atanu, Manager, Operational Compliance, Algonquin Gas Transmission, LLC,
nathan.atanu@enbridge.com
CONFIRMATION OF RECEIPT REQUESTED



U.S. DEPARTMENT OF TRANSPORTATION
PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION
OFFICE OF PIPELINE SAFETY
WASHINGTON, D.C. 20590
____________________________________
In the Matter of )
Algonquin Gas Transmission, LLC, ) CPF No. 1-2020-014-CAO
a subsidiary of Enbridge, Inc., )
)
)
)
Respondent. )
____________________________________)
CORRECTIVE ACTION ORDER
Purpose and Background:
This Corrective Action Order (CAO or Order) is being issued under the authority of 49 U.S.C.
§ 60112 to require Algonquin Gas Transmission, LLC (AGT or Respondent), a subsidiary of
Enbridge, Inc.,1 to take the necessary corrective actions to protect the public, property, and the
environment from potential hazards associated with the multiple unplanned emergency shutdown
events at its Weymouth Compressor Station in Weymouth, Massachusetts (Station).
On September 11, 2020, the Station experienced an O-ring gasket failure on a sump tank during
the Station’s commissioning activities (Incident 1). The failure triggered the manual operation of
the emergency shutdown system and the release of approximately 169 thousand cubic feet (mscf)
of natural gas. On September 30, 2020, at approximately 10:30 AM, the Station experienced an
unplanned emergency shutdown, resulting in the release of approximately 275 mscf of natural gas
(Incident 2). The circumstances surrounding the failure of the O-ring gasket in Incident 1, as well
as the cause for the emergency shutdown in Incident 2 (collectively, Incidents) are under
investigation.
Pursuant to 49 U.S.C. § 60117, PHMSA, Office of Pipeline Safety (OPS), initiated an investigation
of the Incidents. The preliminary findings of the agency’s ongoing investigation are as follows:
Preliminary Findings:
 The Station is part of the AGT’s Atlantic Bridge Pipeline Project (Project). The Project
involves replacing a 6.3-mile (10-kilometer) 26-inch-diameter pipe section with a 42-
inch pipe in New York and Connecticut. The Project also involves installing a new
1 Enbridge, Inc. website, National Gas Transmission and Midstream, available at
https://www.enbridge.com/About-Us/Natural-Gas-Transmission-and-Midstream.aspx (last accessed September 30,
2020).



CPF No. 1-2020-014-CAO
Page 2
meter station in Connecticut, modifications to various metering stations spread across
several states, installation of four new compressor units at existing facilities, and a new
compressor station in Weymouth, Massachusetts. When completed, the Project will
provide an additional 132,700 dekatherms of capacity on the AGT pipeline system and
the Maritimes & Northeast pipeline system.
 Weymouth, Massachusetts, is a heavily populated suburb outside of Boston,
Massachusetts. The Station is in a high consequence area, and is located near Fore
River Bridge, a heavily trafficked commuter road.
 The Station has a station design pressure of 1440 pounds per square inch gauge (psig).
 The Station experienced a gasket failure that triggered the manual activation of its
emergency shutdown system, as well as an unplanned emergency shutdown due to
unknown reasons, less than three weeks apart.
 There were no injuries or fatalities associated with the Incidents; however, the release
of large quantities of pressurized natural gas in a heavily populated area carries a
substantial risk of fire, explosion, and personal injury or death and releases harmful
methane into the environment.
 On September 30, 2020, the inlet pressure at the Station was 683 psig; the discharge
pressure at the time of the emergency shutdown was 707 psig.
 AGT is performing a root cause failure analysis on the O-ring gasket failure that caused
Incident 1.
 The reason for Incident 2 is unknown and under investigation.
 The Station is currently shut-in.
Determination of Necessity for Corrective Action Order and Right to Hearing:
Section 60112 of title 49, United States Code, authorizes PHMSA to determine that a pipeline
facility is or would be hazardous to life, property, or the environment and, if there is a likelihood
of serious harm, to expeditiously order the operator of the facility to take necessary corrective
action, including suspended or restricted use of the facility, physical inspection, testing, repair,
replacement, or other appropriate action. An order issued expeditiously must provide an
opportunity for a hearing as soon as practicable after the order is issued.
In deciding whether to issue an order, PHMSA must consider the following, if relevant: (1) the
characteristics of the pipe and other equipment used in the pipeline facility, including the age,
manufacture, physical properties, and method of manufacturing, constructing, or assembling the
equipment; (2) the nature of the material the pipeline facility transports, the corrosive and



CPF No. 1-2020-014-CAO
Page 3
deteriorative qualities of the material, the sequence in which the material are transported, and the
pressure required for transporting the material; (3) the aspects of the area in which the pipeline
facility is located, including climatic and geologic conditions and soil characteristics; (4) the
proximity of the area in which the hazardous liquid pipeline facility is located to environmentally
sensitive areas; (5) the population density and population and growth patterns of the area in
which the pipeline facility is located; (6) any recommendation of the National Transportation
Safety Board made under another law; and (7) any other factors PHMSA may consider
appropriate.
After evaluating the foregoing preliminary findings of fact, and having considered that the
Station had an O-ring gasket failure that triggered the manual operation of its emergency
shutdown system and an unplanned emergency shutdown for unknown reasons within the past
three weeks; the uncertainties as to the cause of Incident 2; and the Station’s location in a High
Consequence Area, and proximity to populated areas and highly-trafficked public roads, I find
that continued operation of the Station without corrective measures is or would be hazardous to
life, property, or the environment, and that failure to issue this Order expeditiously would result
in the likelihood of serious harm.
Accordingly, this Corrective Action Order mandating immediate corrective action is issued
without prior notice and opportunity for a hearing. The terms and conditions of this Order are
effective upon receipt.
Within 10 days of receipt of this Order, Respondent may request a hearing, to be held as soon as
practicable, by notifying the Associate Administrator for Pipeline Safety in writing, with a copy
to the Director, Southwest Region, PHMSA (Director). If a hearing is requested, it will be held in
accordance with 49 C.F.R. § 190.211.
After receiving and analyzing additional data in the course of this investigation, PHMSA may
identify other corrective measures that need to be taken. Respondent will be notified of any
additional measures required and, if appropriate, PHMSA will consider amending or withdrawing
this Order, if warranted by new supporting information. To the extent consistent with safety,
Respondent will be afforded notice and an opportunity for a hearing prior to the imposition of any
additional corrective measures.
Required Corrective Actions:
Definitions:
Affected Pipeline – The Weymouth Compressor Station, including incoming pipeline, I-
10, back to first upstream mainline valve.
Isolated Segment – Means the Weymouth Compressor Station, from inlet valves to outlet
valves.
Director – Means the Director, Pipeline and Hazardous Materials Safety Administration
(PHMSA), Office of Pipeline Safety, Eastern Region. The Director’s address is 840 Bear
Tavern Road, Suite 300, West Trenton, NJ 08626.



CPF No. 1-2020-014-CAO
Page 4
Pursuant to 49 U.S.C. 60112, I hereby order AGT to immediately take the following corrective
actions for the Affected Pipeline and Isolated Segment:
1. Shutdown of the Isolated Segment. The Isolated Segment is currently shut-in and not in
operation. AGT must not operate the Isolated Segment until authorized to do so by the
Director.
2. Restart Plan. Prior to resuming operation of the Isolated Segment, AGT must develop and
submit a written Restart Plan to the Director for approval.
a. The Director may approve the Restart Plan incrementally without approving the
entire plan but the Isolated Segment cannot resume operation until the Restart Plan
is approved in its entirety.
b. Once approved by the Director, the Restart Plan will be incorporated by reference
into this Order.
c. The Restart Plan must provide for adequate patrolling of the Isolated Segment
during the restart process and must include incremental pressure increases during
start-up, with each increment to be held for at least two hours.
d. The Restart Plan must include sufficient surveillance of the Isolated Segment
during each pressure increment to ensure that no leaks are present when operation
of the line resumes.
e. The Restart Plan must specify a day-light restart and include advance
communications with local emergency response officials.
f. The Restart Plan must provide for a review of the Isolated Segment for conditions
similar to those that caused the Incidents, including a review of construction and
commissioning records. AGT must address any findings that require remedial
measures to be implemented prior to restart.
g. The Restart Plan must also include documentation of the completion of all
mandated actions, and a management of change plan to ensure that all procedural
modifications are incorporated into AGT’s operations and maintenance procedures
manual.
h. Prior to restart, AGT must submit to the Director a contingency plan to operate and
monitor the Isolated Segment during flooding conditions, including enhanced
patrolling and surveillance.
3. Return to Service. After the Director approves the Restart Plan, AGT may return the
Isolated Segment to service but the operating pressure must not exceed eighty percent
(80%) of the actual operating pressure in effect immediately prior to Incident 2, in
accordance with Item 2 above.



CPF No. 1-2020-014-CAO
Page 5
4. Removal of Pressure Restriction. The Director may allow the removal or modification of
the pressure restriction upon a written request from AGT demonstrating that restoring the
pipeline to its pre-Incident 2 operating pressure is justified based on a reliable engineering
analysis showing that the pressure increase is safe, considering all known defects,
anomalies, and operating parameters of the pipeline.
The Director may allow the removal or modification of the pressure restriction upon a
written request from AGT demonstrating that restoring the Affected Segment to its pre-
Incident 2 operating pressure is justified, based on a reliable engineering analysis showing
that the pressure increase is safe, considering all known defects, anomalies, and operating
parameters of the pipeline.
5. Temporary Removal of Pressure Restriction. The Director may allow the temporary
removal or modification of the pressure restrictions upon a written request from AGT
demonstrating that temporary mitigative and preventive measures are being implemented
prior to and during the temporary removal or modification of the pressure restriction. The
Director's determination will be based on the known or suspected cause of Incident 2 and
the provision of evidence that preventive and mitigative actions taken by the operator
provide for the safe operation of the Affected Segment during the temporary removal or
modification of the pressure restriction. Appeals to determinations of the Director in this
regard will be decided by the Associate Administrator for Pipeline Safety.
6. Root Cause Failure Analysis. Within 90 days following receipt of this Order, complete a
root cause failure analysis (RCFA) and submit a final report of this RCFA to the
Director. The RCFA must be supplemented or facilitated by an independent third-party
acceptable to the Director and must document the decision-making process and all factors
contributing to Incident 2. The final report must include findings and any lessons learned
and whether the findings and any lessons learned are applicable to other locations within
AGT’s pipeline system.
Other Requirements:
7. Approvals. With respect to each submission that under this Order requires the approval of
the Director, the Director may: (a) approve, in whole or part, the submission; (b) approve
the submission on specified conditions; (c) modify the submission to cure any deficiencies;
(d) disapprove in whole or in part, the submission, directing that Respondent modify the
submission, or (e) any combination of the above. In the event of approval, approval upon
conditions, or modification by the Director, Respondent shall proceed to take all action
required by the submission as approved or modified by the Director. If the Director
disapproves all or any portion of the submission, Respondent must correct all deficiencies
within the time specified by the Director, and resubmit it for approval.
8. Extensions of Time. The Director may grant an extension of time for compliance with any
of the terms of this Order upon a written request timely submitted demonstrating good
cause for an extension.
9. Reporting. Submit quarterly reports to the Director that: (1) include all available data and
results of the testing and evaluations required by this Order; and (2) describe the progress



CPF No. 1-2020-014-CAO
Page 6
of the repairs or other remedial actions being undertaken. The first quarterly report is due
on January 4, 2021. The Director may change the interval for the submission of these
reports.
10. Documentation of the Costs. It is requested but not required that Respondent maintain
documentation of the costs associated with implementation of this Corrective Action
Order. Include in each monthly report submitted, the to-date total costs associated with:
(1) preparation and revision of procedures, studies and analyses; (2) physical changes to
pipeline infrastructure, including repairs, replacements and other modifications; and (3)
environmental remediation, if applicable.
Be advised that all material you submit in response to this enforcement action is subject to being
made publicly available. If you believe that any portion of your responsive material qualifies for
confidential treatment under 5 U.S.C. § 552(b), along with the complete original document you
must provide a second copy of the document with the portions you believe qualify for confidential
treatment redacted and an explanation of why you believe the redacted information qualifies for
confidential treatment under 5 U.S.C. § 552(b).
In your correspondence on this matter, please refer to “CPF No. 1-2020-014-CAO” and for each
document you submit, please provide a copy in electronic format whenever possible. The actions
required by this Order are in addition to and do not waive any requirements that apply to
Respondent’s pipeline system under 49 C.F.R. Parts 190 through 199, under any other order issued
to Respondent under authority of 49 U.S.C. Chapter 601, or under any other provision of Federal
or State law.
Respondent may appeal any decision of the Director to the Associate Administrator for Pipeline
Safety. Decisions of the Associate Administrator shall be final.
Failure to comply with this Order may result in the assessment of civil penalties and in referral to
the Attorney General for appropriate relief in United States District Court pursuant to
49 U.S.C. § 60120.
The terms and conditions of this Order are effective upon service in accordance with 49 C.F.R.
§ 190.5.
October 1, 2020
_________________________________ ________________________
Alan K. Mayberry Date Issued
Associate Administrator
for Pipeline Safety

12020014CAO_Closure Letter_11172021_(20-172418)_text.pdf

VIA ELECTRONIC MAIL TO: Bill.Yardley@enbridge.com
November 17, 2021
Mr. William T. Yardley
President, Gas Transmission and Midstream
Enbridge, Inc.
5400 Westheimer Court
Houston, Texas 77056
CPF 1-2020-014-CAO
Dear Mr. Yardley:
On October 1, 2020, and on October 30, 2020, the Pipeline and Hazardous Materials Safety
Administration (PHMSA) issued a Corrective Action Order (CAO) and an Amended Corrective
Action Order (ACAO), respectively, to Algonquin Gas Transmission, LLC (AGT), a subsidiary
of Enbridge, Inc., with regard to the September 11, 2020 and September 30, 2020 events at
Weymouth Compressor Station. The ACAO included a list of various required Corrective Actions.
We have received a final monthly report, dated August 13, 2021, from Mr. Nathan Atanu,
Manager, Operational Compliance. We have also received eight earlier monthly reports, submitted
as part of the final Corrective Action deliverable, required under item 9 of the ACAO.
Subsequently, a letter from Mr. Atanu was received on August 18, 2021 requesting closure of the
ACAO.
During our review of the documentation, a PHMSA investigator performed multiple on-site visits
to verify completion of corrective actions. The investigator was on site to view Phase 1 through
Phase 4 of the approved Restart Plan from December 4 to 7, 2020. The Weymouth Compressor
Station was operating at 683 pounds per square inch gauge (psig) at the time of Event 2. Leakage
surveys of the Isolated Segment of Weymouth Compressor Station were performed and reviewed
during the two (2) hour hold periods of each phase. After receiving appropriate approval to proceed
to Phase 5 of the Restart Plan, AGT completed a Temporary Removal of Pressure Restriction,
which was also verified by the investigator.
The Root Cause Failure Analysis (RCFA) was received by PHMSA on December 22, 2020. The
ACAO requires that all recommendations from the RCFA be incorporated into AGT’s Operations
and Maintenance Manual. This was completed and subsequently reviewed and verified by the
PHMSA investigator on August 18, 2021.
PHMSA reminds AGT of the requirements enacted by Congress and described in Section 114 of
the “Protecting our Infrastructure of Pipelines and Enhancing Safety Act of 2020” (PIPES Act of
2020), which requires all pipeline operators to address the elimination of hazardous leaks and
minimization of releases of natural gas. Please refer to PHMSA Advisory Bulletin ADB-2021-
01, for more information on this self-executing provision. PHMSA will be conducting
inspections of these modified plans in 2022.



CPF 1-2020-014-CAO
PHMSA also requests that AGT continue to maintain relationships and open communication with
state and local authorities such as the Massachusetts Department of Environmental Protection, the
Town of Weymouth, the Town of Braintree, and the City of Quincy.
PHMSA is also aware that AGT has initiated and completed additional safety measures in addition
to the requirements of the ACAO. For example, AGT has utilized Pipeline Safety Management
System (PSMS) principles to perform additional risk assessments to Weymouth Compressor
Station systems outside the scope of the ACAO and have incorporated the lessons learned. AGT
had a third party review the Emergency Shutdown (ESD) system and have incorporated all the
recommended enhancements into policies and procedures. Finally, AGT continues to perform
weekly leakage surveys throughout the compressor station, a practice which started back in
November 2020.
Based on our review of the documentation you provided, it has been determined that you have
complied with the terms of this Order. Accordingly, this CAO is now closed. It is our expectation
that AGT will aggressively implement methane emission reduction strategies at this facility and
other locations along its pipeline systems. As noted previously, PHMSA will be inspecting all
pipeline facilities across the country to ensure alignment with statutory requirements for reducing
methane emissions. Thank you for your cooperation in this matter.
Sincerely,
Robert Burrough
Director, Eastern Region
Pipeline and Hazardous Materials Safety Administration
cc: Ms. Linda Daugherty, Deputy Associate Administrator for Field Operations, OPS
(PHMSA)
Mr. Thomas Wooden, Vice President, Northeast Transmission (Enbridge)
Mr. Nathan Atanu, Manager, Operational Compliance (Enbridge)
12020014CAO_Closure Letter_11172021_(20-172418)_text Page 2 of 2

## Provenance

- Official: Yes
- Source: <https://primis.phmsa.dot.gov/enforcement-data/case/12020014CAO>
- Source ID: `phmsa-enforcement`
- SHA-256: `4240c4ad78257763def554cf195687d1d422afc1e193b31e738c5dbdad3bf407`
- Retrieved: 2026-08-20T04:44:44.458Z
- Exported: 2026-08-23T02:39:27.571Z
- Document slug: `phmsa-enforcement-12020014cao`

### Source metadata

```json
{
  "cpf": "12020014CAO",
  "operator": "ALGONQUIN GAS TRANSMISSION, L.L.C. (SPECTRA ENERGY PARTNERS, LP)",
  "region": "Eastern",
  "pipelineType": "INTERSTATE GAS TRANSMISSION",
  "caseStatus": "CLOSED",
  "citedSections": [],
  "dataAsOf": "08/04/2026 12PM",
  "caseDataAsOf": "2026-08-04",
  "attachmentCount": 8,
  "attachments": [
    {
      "name": "12020014CAO_Amended Corrective Action Order_10302020_(20-172418).pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/12020014CAO/12020014CAO_Amended%20Corrective%20Action%20Order_10302020_(20-172418).pdf",
      "bytes": 231725,
      "category": "agency_document"
    },
    {
      "name": "12020014CAO_Amended Corrective Action Order_10302020_(20-172418)_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/12020014CAO/12020014CAO_Amended%20Corrective%20Action%20Order_10302020_(20-172418)_text.pdf",
      "bytes": 222446,
      "category": "agency_document"
    },
    {
      "name": "12020014CAO_Closure Letter_11172021_(20-172418).pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/12020014CAO/12020014CAO_Closure%20Letter_11172021_(20-172418).pdf",
      "bytes": 224035,
      "category": "agency_document"
    },
    {
      "name": "12020014CAO_Closure Letter_11172021_(20-172418)_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/12020014CAO/12020014CAO_Closure%20Letter_11172021_(20-172418)_text.pdf",
      "bytes": 101953,
      "category": "agency_document"
    },
    {
      "name": "12020014CAO_Corrective Action Order_10012020_(20-172418).pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/12020014CAO/12020014CAO_Corrective%20Action%20Order_10012020_(20-172418).pdf",
      "bytes": 282483,
      "category": "agency_document"
    },
    {
      "name": "12020014CAO_Corrective Action Order_10012020_(20-172418)_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/12020014CAO/12020014CAO_Corrective%20Action%20Order_10012020_(20-172418)_text.pdf",
      "bytes": 225910,
      "category": "agency_document"
    },
    {
      "name": "12020014CAO_Operator Hearing Request Withdrawn_11042020_(20-172418).pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/12020014CAO/12020014CAO_Operator%20Hearing%20Request%20Withdrawn_11042020_(20-172418).pdf",
      "bytes": 48798,
      "category": "party_submission"
    },
    {
      "name": "12020014CAO_Operator Request for Hearing and Statement of Issues_10132020_(20-172418).pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/12020014CAO/12020014CAO_Operator%20Request%20for%20Hearing%20and%20Statement%20of%20Issues_10132020_(20-172418).pdf",
      "bytes": 149649,
      "category": "party_submission"
    }
  ],
  "extractedAgencyDocumentCount": 3,
  "attachmentPolicy": "Official attachment links are retained. Agency-issued documents may also include a verified local PDF and page-level text representation.",
  "jurisdiction": "US",
  "operatorName": "ALGONQUIN GAS TRANSMISSION, L.L.C. (SPECTRA ENERGY PARTNERS, LP)"
}
```
