# RH ENERGYTRANS, LLC — Notice of Amendment

**Citation:** CPF 120201022M  
**Type / status:** enforcement / historical  
**Agency:** Pipeline and Hazardous Materials Safety Administration  
**Effective:** Not stated  
**Published:** 2020-06-12

CLOSED notice of amendment citing 192.303.

## Document text

Notice of Amendment involving RH ENERGYTRANS, LLC. PHMSA's enforcement data identifies the cited regulation as 192.303. The case was opened on 2020-06-12 and is reported as closed as of 2020-08-25. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

120201022M_Closure Letter_08252020.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120201022M/120201022M_Closure%20Letter_08252020.pdf

120201022M_Closure Letter_08252020_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120201022M/120201022M_Closure%20Letter_08252020_text.pdf

120201022M_Notice of Amendment_06122020.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120201022M/120201022M_Notice%20of%20Amendment_06122020.pdf

120201022M_Notice of Amendment_06122020_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120201022M/120201022M_Notice%20of%20Amendment_06122020_text.pdf

120201022M_Operator Response to Notice_07082020.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120201022M/120201022M_Operator%20Response%20to%20Notice_07082020.pdf

120201022M_Closure Letter_08252020_text.pdf

OVERNIGHT EXPRESS DELIVERY
August 25, 2020
Kyle Rhoades
Chief Operating Officer
RH energytrans, LLC
558 West 6th Street
Suite 200
Erie, PA 16507
CPF 1-2020-1022M
Dear Mr. Rhoades:
From April 30, 2019 to May 2, 2019, August 7, 2019 to August 8, 2019, and December 3, 2019 to
December 5, 2019, a representative from the Pipeline and Hazardous Materials Safety
Administration (PHMSA), pursuant to Chapter 601 of 49 United States Code, conducted an on-
site pipeline safety inspection of RH energytrans, LLC’s (RH energytrans) Risberg Project in
Kingsville, Ohio. As a result of the inspection, RH energytrans was issued a Notice of Amendment
on June 12, 2020, which proposed amendment of your procedures.
RH energytrans submitted its amended procedures on July 8, 2020. My staff reviewed the amended
procedures, and it appears that the inadequacies outlined in this Notice of Amendment have been
corrected.
This letter is to inform you no further action is necessary and this case is now closed. Thank you
for your cooperation.
Sincerely,
Robert Burrough
Director, Eastern Region
Pipeline and Hazardous Materials Safety Administration

120201022M_Notice of Amendment_06122020_text.pdf

NOTICE OF AMENDMENT
OVERNIGHT EXPRESS DELIVERY
June 12, 2020
Kyle Rhoades
Chief Operating Officer
RH energytrans, LLC
558 West 6th Street, Erie, PA 16507
CPF 1-2020-1022M
Dear Mr. Rhoades:
From April 30, 2019 to May 2, 2019, August 7, 2019 to August 8, 2019, and December 3, 2019 to
December 5, 2019, a representative of the Pipeline and Hazardous Materials Safety
Administration (PHMSA) pursuant to Chapter 601 of 49 United States Code (U.S.C.) performed
an inspection on RH energytrans, LLC’s (RH energytrans) Risberg Project in Kingsville, Ohio.
On the basis of the inspection, PHMSA has identified apparent inadequacies found within RH
energytrans’ plans or procedures, as described below:
1. § 192.303 Compliance with specifications or standards.
Each transmission line or main must be constructed in accordance
with comprehensive written specifications or standards that are
consistent with this part.
RH energytrans’ written specifications or standards for constructing each transmission line were
inadequate. Specifically, RH energytrans' General Conditions and Specifications for Pipeline-
Construction, undated (Construction Specification), failed to include training and experience
requirements for individuals who perform visual inspection of welding, as prescribed in
§ 192.241(a).
Section 192.241(a), Inspection and test of welds, states:



CPF 1-2020-1022M
(a) Visual inspection of welding must be conducted by an individual qualified by
appropriate training and experience to ensure that:
(1) The welding is performed in accordance with the welding procedure; and
(2) The weld is acceptable under paragraph (c) of this section.
During an inspection of the Risberg Project in Kingsville, Ohio from April 30, 2019 to May 2,
2019, a PHMSA Inspector reviewed the Construction Specification. The Construction
Specification did not contain requirements prescribed in § 192.241(a), including what appropriate
training and experience is required of an individual who performs visual inspection of welds. When
asked about the missing requirement, RH energytrans personnel acknowledged that the details
were not recorded in the Construction Specifications at the time of the inspection.
Thus, RH energytrans’ written specifications and standards required by § 192.303 were inadequate
as it pertains to § 192.241(a).
2. § 192.303 Compliance with specifications or standards.
Each transmission line or main must be constructed in accordance
with comprehensive written specifications or standards that are
consistent with this part.
RH energytrans’ written specifications or standards for constructing each transmission line were
inadequate. Specifically, RH energytrans’ General Conditions and Specifications for Pipeline-
Construction, undated (Construction Specification) failed to include the requirements for the
limitations on welders and welding operators prescribed in § 192.229(b).
Section 192.229(b), Limitations on welders and welding operators, states:
A welder or welding operator may not weld with a particular welding process
unless, within the preceding 6 calendar months, the welder or welding operator
was engaged in welding with that process.
During an inspection of the Risberg Project in Kingsville, Ohio from April 30, 2019 to May 2,
2019, a PHMSA Inspector reviewed the Construction Specification. It was noted during the review
that details regarding limitations on welders and welding operators were not included in the
Welding Procedures regarding § 192.229(b). When asked about the missing requirement, RH
energytrans personnel acknowledged that the details were not recorded in the Construction
Specifications at the time of the inspection.
Thus, RH energytrans’ written specifications and standards required by § 192.303 were inadequate
as it pertains to § 192.229(b).
120201022M_Notice of Amendment_06122020_text Page 2 of 5



CPF 1-2020-1022M
3. § 192.303 Compliance with specifications or standards.
Each transmission line or main must be constructed in accordance
with comprehensive written specifications or standards that are
consistent with this part.
RH energytrans’ written specifications or standards for constructing each transmission line were
inadequate. Specifically, RH energytrans' General Conditions and Specifications for Pipeline-
Construction, undated (Construction Specification) failed to specify requirements for pressure test
records as prescribed in § 192.517(a).
Section 192.517(a), Records, states:
(a) Each operator shall make, and retain for the useful life of the pipeline, a record of each
test performed under §§192.505 and 192.507. The record must contain at least the following
information:
(1) The operator's name, the name of the operator's employee responsible for making the
test, and the name of any test company used.
(2) Test medium used.
(3) Test pressure.
(4) Test duration.
(5) Pressure recording charts, or other record of pressure readings.
(6) Elevation variations, whenever significant for the particular test.
(7) Leaks and failures noted and their disposition.
During an inspection of the Risberg Project in Kingsville, Ohio from April 30, 2019 to May 2,
2019, a PHMSA Inspector reviewed the Hydrostatic Pressure Test Procedures. It was noted during
the review that no specific requirements for pressure test records as prescribed in § 192.517(a)
were contained in the Construction Specification. When asked about the missing requirements,
RH energytrans personnel noted that the company did not have a procedure during the time of the
inspection regarding the records requirement in § 192.517(a).
Thus, RH energytrans’ written specifications and standards required by § 192.303 were inadequate
as it pertains to § 192.517(a).
4. § 192.303 Compliance with specifications or standards.
Each transmission line or main must be constructed in accordance
with comprehensive written specifications or standards that are
consistent with this part.
RH energytrans’ written specifications and standards for constructing each transmission line were
inadequate. Specifically, RH energytrans’ construction standards for coating inspection failed to
adequately address the requirements of § 192.307 regarding pipe that was installed via horizontal
directional drilling (HDD).
120201022M_Notice of Amendment_06122020_text Page 3 of 5



CPF 1-2020-1022M
Section 192.307, Inspection of materials, states:
Each length of pipe and each other component must be visually inspected at the
site of installation to ensure that it has not sustained any visually determinable
damage that could impair its serviceability.
During an inspection of the Risberg Project in Kingsville, Ohio from August 7, 2019 to August 8,
2019, a PHMSA inspector requested procedures for assessing and remediating coating that may
have been damaged as a result of installation via HDD. RH energytrans provided its Policy and
Procedure Manual, Pipeline Operations, Northeast Division, Section: Pipeline, Sub Section:
Protective Coating, Date Issued/Revised: 5/1/2019 and Document Number: 461-1 (Protective
Coating Procedures). However, the Protective Coating Procedures did not address inspecting
piping that was installed via HDD at the site of installation, including entry and exit pits in order
to ensure that it did not sustain any visually determinable damage that could impair its
serviceability as required by § 192.307.
Thus, RH energytrans’ written specifications and standards required by § 192.303 were inadequate
as it pertains to § 192.307.
5. § 192.303 Compliance with specifications or standards.
Each transmission line or main must be constructed in accordance
with comprehensive written specifications or standards that are
consistent with this part.
RH energytrans’ written specifications and standards for constructing each transmission line were
inadequate. Specifically, RH energytrans’ construction standards for coating inspection failed to
adequately address the requirements of § 192.461(e) regarding pipe that was installed via HDD.
Section 192.461(e), External corrosion control: Protective coating, states:
If coated pipe is installed by boring, driving, or other similar method, precautions
must be taken to minimize damage to the coating during installation.
During an inspection of the Risberg Project in Kingsville, Ohio from August 7, 2019 to August 8,
2019, a PHMSA inspector requested procedures for minimizing damage to protective coatings
during pipe installation via HDD. RH energytrans provided its Protective Coating Procedures.
The Protective Coating Procedures did not address precautions and remediation requirements that
may be necessary to satisfy the requirements of § 192.461(e).
Thus, RH energytrans’ written specifications and standards required by § 192.303 were inadequate
as it pertains to § 192.461(e).
120201022M_Notice of Amendment_06122020_text Page 4 of 5



CPF 1-2020-1022M
Response to this Notice
This Notice is provided pursuant to 49 U.S.C. § 60108(a) and 49 C.F.R. § 190.206. Enclosed as
part of this Notice is a document entitled Response Options for Pipeline Operators in Enforcement
Proceedings. Please refer to this document and note the response options. Be advised that all
material you submit in response to this enforcement action is subject to being made publicly
available. If you believe that any portion of your responsive material qualifies for confidential
treatment under 5 U.S.C. 552(b), along with the complete original document you must provide a
second copy of the document with the portions you believe qualify for confidential treatment
redacted and an explanation of why you believe the redacted information qualifies for confidential
treatment under 5 U.S.C. 552(b).
Following the receipt of this Notice, you have 30 days to submit written comments, revised
procedures, or a request for a hearing under §190.211. If you do not respond within 30 days of
receipt of this Notice, this constitutes a waiver of your right to contest the allegations in this Notice
and authorizes the Associate Administrator for Pipeline Safety to find facts as alleged in this Notice
without further notice to you and to issue an Order Directing Amendment. If your plans or
procedures are found inadequate as alleged in this Notice, you may be ordered to amend your plans
or procedures to correct the inadequacies (49 C.F.R. § 190.206). If you are not contesting this
Notice, we propose that you submit your amended procedures to my office within 30 days of
receipt of this Notice. This period may be extended by written request for good cause. Once the
inadequacies identified herein have been addressed in your amended procedures, this enforcement
action will be closed.
It is requested (not mandated) that RH energytrans, LLC maintain documentation of the safety
improvement costs associated with fulfilling this Notice of Amendment (preparation/revision of
plans, procedures) and submit the total to Robert Burrough, Director, PHMSA Eastern Region,
840 Bear Tavern Road, Suite 300, West Trenton, NJ 08628. Please refer to CPF 1-2020-1022M
on each document you submit, and whenever possible provide a signed PDF copy in electronic
format. Smaller files may be emailed to robert.burrough@dot.gov. Larger files should be sent on
USB flash drive accompanied by the original paper copy to the Eastern Region Office.
Additionally, if you choose to respond to this (or any other case), please ensure that any response
letter pertains solely to one CPF case number.
Sincerely,
Robert Burrough
Director, Eastern Region
Pipeline and Hazardous Materials Safety Administration
Enclosure: Response Options for Pipeline Operators in Enforcement Proceedings
120201022M_Notice of Amendment_06122020_text Page 5 of 5

## Provenance

- Official: Yes
- Source: <https://primis.phmsa.dot.gov/enforcement-data/case/120201022M>
- Source ID: `phmsa-enforcement`
- SHA-256: `dc1cb9b3661af51f86a54f4410212b231ae2da512f5df635afd81615e10b4835`
- Retrieved: 2026-08-20T04:44:44.458Z
- Exported: 2026-08-22T04:24:35.853Z
- Document slug: `phmsa-enforcement-120201022m`

### Source metadata

```json
{
  "cpf": "120201022M",
  "operator": "RH ENERGYTRANS, LLC",
  "region": "Eastern",
  "pipelineType": "GAS INTERSTATE ONSHORE",
  "caseStatus": "CLOSED",
  "citedSections": [
    "192.303"
  ],
  "dataAsOf": "08/04/2026 12PM",
  "caseDataAsOf": "2026-08-04",
  "attachmentCount": 5,
  "attachments": [
    {
      "name": "120201022M_Closure Letter_08252020.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/120201022M/120201022M_Closure%20Letter_08252020.pdf",
      "bytes": 891812,
      "category": "agency_document"
    },
    {
      "name": "120201022M_Closure Letter_08252020_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/120201022M/120201022M_Closure%20Letter_08252020_text.pdf",
      "bytes": 80187,
      "category": "agency_document"
    },
    {
      "name": "120201022M_Notice of Amendment_06122020.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/120201022M/120201022M_Notice%20of%20Amendment_06122020.pdf",
      "bytes": 631721,
      "category": "agency_document"
    },
    {
      "name": "120201022M_Notice of Amendment_06122020_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/120201022M/120201022M_Notice%20of%20Amendment_06122020_text.pdf",
      "bytes": 123575,
      "category": "agency_document"
    },
    {
      "name": "120201022M_Operator Response to Notice_07082020.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/120201022M/120201022M_Operator%20Response%20to%20Notice_07082020.pdf",
      "bytes": 149751,
      "category": "party_submission"
    }
  ],
  "extractedAgencyDocumentCount": 2,
  "attachmentPolicy": "Official attachment links are retained. Agency-issued documents may also include a verified local PDF and page-level text representation.",
  "jurisdiction": "US",
  "operatorName": "RH ENERGYTRANS, LLC"
}
```