# TRES PALACIOS GAS STORAGE LLC — Notice of Amendment

**Citation:** CPF 12021012NOA  
**Type / status:** enforcement / historical  
**Agency:** Pipeline and Hazardous Materials Safety Administration  
**Effective:** Not stated  
**Published:** 2021-04-20

CLOSED notice of amendment citing 192.12(c).

## Document text

Notice of Amendment involving TRES PALACIOS GAS STORAGE LLC. PHMSA's enforcement data identifies the cited regulation as 192.12(c). The case was opened on 2021-04-20 and is reported as closed as of 2021-06-17. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

12021012NOA_Closure Letter_06172021_(20-173619).pdf: https://primis.phmsa.dot.gov/enforcement-documents/12021012NOA/12021012NOA_Closure%20Letter_06172021_(20-173619).pdf

12021012NOA_Closure Letter_06172021_(20-173619)_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/12021012NOA/12021012NOA_Closure%20Letter_06172021_(20-173619)_text.pdf

12021012NOA_Notice of Amendment_04202021_(20-173619).pdf: https://primis.phmsa.dot.gov/enforcement-documents/12021012NOA/12021012NOA_Notice%20of%20Amendment_04202021_(20-173619).pdf

12021012NOA_Notice of Amendment_04202021_(20-173619)_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/12021012NOA/12021012NOA_Notice%20of%20Amendment_04202021_(20-173619)_text.pdf

12021012NOA_Operator Response to Notice_05032021_(20-173619).pdf: https://primis.phmsa.dot.gov/enforcement-documents/12021012NOA/12021012NOA_Operator%20Response%20to%20Notice_05032021_(20-173619).pdf

12021012NOA_Notice of Amendment_04202021_(20-173619)_text.pdf

NOTICE OF AMENDMENT
VIA ELECTRONIC MAIL TO: Eric.Ormond@crestwoodlp.com
April 20, 2021
Mr. Eric Ormond
VP, Engineering & Project Management
Tres Palacios Gas Storage LLC
811 Main Street
Houston, Texas 77002
CPF 1-2021-012-NOA
Dear Mr. Ormond:
From July 14-16, 2020, a representative of the Pipeline and Hazardous Materials Safety
Administration (PHMSA) pursuant to Chapter 601 of 49 United States Code (U.S.C.) inspected
Tres Palacios Gas Storage LLC’s (TPGS) procedures1 for the Tres Palacios Gas Storage facility
in Markham, Texas.
On the basis of the inspection, PHMSA has identified the apparent inadequacies found within
TPGS’s plans or procedures, as described below:
1. § 192.12 Underground natural gas storage facilities.
(a) …
(c) Procedural manuals. Each operator of a UNGSF must prepare
and follow for each facility one or more manuals of written procedures
for conducting operations, maintenance, and emergency preparedness
and response activities under paragraphs (a) and (b) of this section.
Each operator must keep records necessary to administer such
procedures and review and update these manuals at intervals not
exceeding 15 months, but at least once each calendar year. Each
operator must keep the appropriate parts of these manuals accessible
at locations where UNGSF work is being performed. Each operator
must have written procedures in place before commencing operations
or beginning an activity not yet implemented.
1 Tres Palacios Gas Storage, LLC is a subsidiary of Crestwood Midstream Partners, LP and uses Crestwood’s
procedures.



CPF 1-2021-012-NOA
TPGS's written procedures for conducting operations, maintenance, and emergency preparedness
and response activities under §192.12(a)(3) were inadequate. Specifically, TPGS's UNGS OM did
not describe its operation and maintenance (O&M) processes in detail in accordance with API RP
1170, Section 9.7.1 Procedures (Section 9.7.1).
Section 192.12(a)(3) states in relevant part, for operators that use a solution-mined salt cavern for
natural gas storage, constructed on or before July 18, 2017, to meet the provisions of API RP 1170
(incorporated by reference, see §192.7), section 9, by January 18, 2018.
Section 9.7.1 states in relevant part:
All operators shall have or develop operation and maintenance (O&M) procedures. These
procedures should allow for the safe operation and necessary maintenance of the wellhead
and cavern to ensure integrity. Operators should have specific procedures for caverns and
wellheads that include routine operation and maintenance guidelines as well as workover
and emergency procedures.
At the time of the inspection, TPGS's UNGS OM did not describe the O&M processes with
specificity. Procedures presented to PHMSA at the time only re-stated the requirements of API
RP 1170. Therefore, TGPS’s procedures lacked details to thoroughly describe the O&M processes
used to maintain ongoing functional integrity of the storage facility. TPGS must revise its
procedures to include detailed O&M procedures.
2. § 192.12 Underground natural gas storage facilities.
(a) …
(c) Procedural manuals. Each operator of a UNGSF must prepare
and follow for each facility one or more manuals of written procedures
for conducting operations, maintenance, and emergency preparedness
and response activities under paragraphs (a) and (b) of this section.
Each operator must keep records necessary to administer such
procedures and review and update these manuals at intervals not
exceeding 15 months, but at least once each calendar year. Each
operator must keep the appropriate parts of these manuals accessible
at locations where UNGSF work is being performed. Each operator
must have written procedures in place before commencing operations
or beginning an activity not yet implemented.
TPGS’s written procedures for conducting operations, maintenance, and emergency preparedness
and response activities under § 192.12(a)(3) were inadequate. Specifically, TPGS's OM S2.29.1
procedures did not describe the process it uses to establish a maximum and minimum storage
operating pressure, or its process for converting maximum and minimum pressure at a casing seat
to a maximum and minimum wellhead pressure, in accordance with API RP 1170, Section 9.1-
Minimum and Maximum Operating Limits (Section 9.1).
As noted above, § 192.12(a)(3) requires operators that use a solution-mined salt cavern for natural
gas storage, constructed on or before July 18, 2017, to meet the provisions of API RP 1170
(incorporated by reference, see §192.7), section 9, by January 18, 2018.
12021012NOA_Notice of Amendment_04202021_(20-173619)_text Page 2 of 5



CPF 1-2021-012-NOA
Section 9.1 states in relevant part:
Maximum storage operating pressures shall be established by the operator.
…
The operator shall then convert the maximum and minimum pressure at the casing seat to a
maximum and minimum wellhead pressure if the wellhead is the monitoring point of record.
At the time of the inspection, TPGS's procedures restated Section 9.1 but did not describe the
processes that TPGS uses to establish a maximum and minimum storage operating pressure or its
process for converting casing seat pressures to wellhead pressures. TPGS must revise its
procedures to include its processes for complying with API RP 1170 Section 9.1, in accordance
with § 192.12(a)(3).
3. § 192.12 Underground natural gas storage facilities.
(a) …
(c) Procedural manuals. Each operator of a UNGSF must prepare
and follow for each facility one or more manuals of written procedures
for conducting operations, maintenance, and emergency preparedness
and response activities under paragraphs (a) and (b) of this section.
Each operator must keep records necessary to administer such
procedures and review and update these manuals at intervals not
exceeding 15 months, but at least once each calendar year. Each
operator must keep the appropriate parts of these manuals accessible
at locations where UNGSF work is being performed. Each operator
must have written procedures in place before commencing operations
or beginning an activity not yet implemented.
TPGS's written procedures for conducting operations, maintenance, and emergency preparedness
and response activities under §192.12(a)(3) were inadequate. Specifically, TPGS does not have
detailed procedures to describe its evaluation process for the applicability of integrity monitoring
methods in accordance with API RP 1170, Section 10.4 - Review of Integrity Monitoring Methods
(Section 10.4).
As noted above, § 192.12(a)(3) requires operators that use a solution-mined salt cavern for natural
gas storage, constructed on or before July 18, 2017, to meet the provisions of API RP 1170
(incorporated by reference, see §192.7), section 10, by January 18, 2018.
Section 10.4 states in relevant part:
Table 1 lists monitoring methods currently in use by salt cavern operators. Each operator
shall evaluate these methods for applicability and inclusion in their Integrity Monitoring
Program. These methods are found in Annex B.
At the time of the inspection, TPGS's procedures did not describe the evaluation processes for
integrity monitoring methods in detail. Therefore, TPGS did not develop evaluation processes for
integrity monitoring methods as required by Section 10.4. TPGS must revise its procedures to
12021012NOA_Notice of Amendment_04202021_(20-173619)_text Page 3 of 5



CPF 1-2021-012-NOA
include details on its integrity monitoring methods.
4. § 192.12 Underground natural gas storage facilities.
(a) …
(c) Procedural manuals. Each operator of a UNGSF must prepare
and follow for each facility one or more manuals of written procedures
for conducting operations, maintenance, and emergency preparedness
and response activities under paragraphs (a) and (b) of this section.
Each operator must keep records necessary to administer such
procedures and review and update these manuals at intervals not
exceeding 15 months, but at least once each calendar year. Each
operator must keep the appropriate parts of these manuals accessible
at locations where UNGSF work is being performed. Each operator
must have written procedures in place before commencing operations
or beginning an activity not yet implemented.
TPGS's written procedures for conducting operations, maintenance, and emergency preparedness
and response activities under §192.12(a)(3) were inadequate. Specifically, TPGS's UNGS OM
procedures did not describe the process for Lockout and Tagout (LOTO) operations in accordance
with API RP 1170, Section 9.6.8 - Lockout and Tagout Systems (Section 9.6.8).
As stated above, § 192.12(a)(3) requires operators that use a solution-mined salt cavern for natural
gas storage, constructed on or before July 18, 2017, to meet the provisions of API RP 1170
(incorporated by reference, see §192.7), section 9, by January 18, 2018.
Section 9.6.8 states in part:
Lockout and tagout (LOTO) systems shall be used at storage facilities to protect workers
from hazardous energy sources. A LOTO procedure shall be developed for each cavern
wellhead to allow for calibration, maintenance and workovers.
At the time of the inspection, TPGS's procedures did not include LOTO procedures, as required
by Section 9.6.8. TPGS must amend its procedures to include LOTO procedures.
Response to this Notice
This Notice is provided pursuant to 49 U.S.C. § 60108(a) and 49 C.F.R. § 190.206. Enclosed as
part of this Notice is a document entitled Response Options for Pipeline Operators in Enforcement
Proceedings. Please refer to this document and note the response options. Be advised that all
material you submit in response to this enforcement action is subject to being made publicly
available. If you believe that any portion of your responsive material qualifies for confidential
treatment under 5 U.S.C. 552(b), along with the complete original document you must provide a
second copy of the document with the portions you believe qualify for confidential treatment
redacted and an explanation of why you believe the redacted information qualifies for confidential
treatment under 5 U.S.C. 552(b).
12021012NOA_Notice of Amendment_04202021_(20-173619)_text Page 4 of 5



CPF 1-2021-012-NOA
Following the receipt of this Notice, you have 30 days to submit written comments, revised
procedures, or a request for a hearing under §190.211. If you do not respond within 30 days of
receipt of this Notice, this constitutes a waiver of your right to contest the allegations in this Notice
and authorizes the Associate Administrator for Pipeline Safety to find facts as alleged in this Notice
without further notice to you and to issue an Order Directing Amendment. If your plans or
procedures are found inadequate as alleged in this Notice, you may be ordered to amend your plans
or procedures to correct the inadequacies (49 C.F.R. § 190.206). If you are not contesting this
Notice, we propose that you submit your amended procedures to my office within 30 days of
receipt of this Notice. This period may be extended by written request for good cause. Once the
inadequacies identified herein have been addressed in your amended procedures, this enforcement
action will be closed.
It is requested (not mandated) that Tres Palacios Gas Storage, LLC maintain documentation of the
safety improvement costs associated with fulfilling this Notice of Amendment
(preparation/revision of plans, procedures) and submit the total to Robert Burrough, Director,
PHMSA Eastern Region, 840 Bear Tavern Road, Suite 300, West Trenton, NJ 08628. Please refer
to CPF 1-2021-012-NOA on each document you submit, and whenever possible provide a signed
PDF copy in electronic format. Smaller files may be emailed to robert.burrough@dot.gov. Larger
files should be sent on USB flash drive accompanied by the original paper copy to the Eastern
Region Office.
Additionally, if you choose to respond to this (or any other case), please ensure that any response
letter pertains solely to one CPF case number.
Sincerely,
Robert Burrough
Director, Eastern Region
Pipeline and Hazardous Materials Safety Administration
Enclosure: Response Options for Pipeline Operators in Enforcement Proceedings
12021012NOA_Notice of Amendment_04202021_(20-173619)_text Page 5 of 5

12021012NOA_Closure Letter_06172021_(20-173619)_text.pdf

OVERNIGHT EXPRESS DELIVERY
June 17, 2021
Mr. Eric Ormond
VP, Engineering & Project Management
Tres Palacios Gas Storage LLC
811 Main Street
Houston, Texas 77002
CPF 1-2021-012-NOA
Dear Mr. Ormond:
From July 14-16, 2020, a representative of the Pipeline and Hazardous Materials Safety
Administration (PHMSA) pursuant to Chapter 601 of 49 United States Code (U.S.C.) inspected
Tres Palacios Gas Storage LLC’s (TPGS) procedures1 for the Tres Palacios Gas Storage facility
in Markham, Texas. As a result of the inspection, TPGS was issued a Notice of Amendment on
April 20, 2021, which proposed amendment of your procedures.
TPGS submitted its amended procedures on May 3, 2021. My staff reviewed the amended
procedures, and it appears that the inadequacies outlined in this Notice of Amendment have been
corrected.
This letter is to inform you no further action is necessary and this case is now closed. Thank you
for your cooperation.
Sincerely,
Robert Burrough
Director, Eastern Region
Pipeline and Hazardous Materials Safety Administration
1 Tres Palacios Gas Storage, LLC is a subsidiary of Crestwood Midstream Partners, LP and uses Crestwood’s
procedures.

## Provenance

- Official: Yes
- Source: <https://primis.phmsa.dot.gov/enforcement-data/case/12021012NOA>
- Source ID: `phmsa-enforcement`
- SHA-256: `417f5394d571a7bb9dc33066536c4a0b6f3f85f37b7fefa7d5af54438ac1360c`
- Retrieved: 2026-08-20T04:44:44.458Z
- Exported: 2026-08-22T18:09:35.626Z
- Document slug: `phmsa-enforcement-12021012noa`

### Source metadata

```json
{
  "cpf": "12021012NOA",
  "operator": "TRES PALACIOS GAS STORAGE LLC",
  "region": "Eastern",
  "pipelineType": "INTERSTATE UNDERGROUND NG STORAGE",
  "caseStatus": "CLOSED",
  "citedSections": [
    "192.12(c)"
  ],
  "dataAsOf": "08/04/2026 12PM",
  "caseDataAsOf": "2026-08-04",
  "attachmentCount": 5,
  "attachments": [
    {
      "name": "12021012NOA_Closure Letter_06172021_(20-173619).pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/12021012NOA/12021012NOA_Closure%20Letter_06172021_(20-173619).pdf",
      "bytes": 353456,
      "category": "agency_document"
    },
    {
      "name": "12021012NOA_Closure Letter_06172021_(20-173619)_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/12021012NOA/12021012NOA_Closure%20Letter_06172021_(20-173619)_text.pdf",
      "bytes": 81117,
      "category": "agency_document"
    },
    {
      "name": "12021012NOA_Notice of Amendment_04202021_(20-173619).pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/12021012NOA/12021012NOA_Notice%20of%20Amendment_04202021_(20-173619).pdf",
      "bytes": 282045,
      "category": "agency_document"
    },
    {
      "name": "12021012NOA_Notice of Amendment_04202021_(20-173619)_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/12021012NOA/12021012NOA_Notice%20of%20Amendment_04202021_(20-173619)_text.pdf",
      "bytes": 164365,
      "category": "agency_document"
    },
    {
      "name": "12021012NOA_Operator Response to Notice_05032021_(20-173619).pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/12021012NOA/12021012NOA_Operator%20Response%20to%20Notice_05032021_(20-173619).pdf",
      "bytes": 537501,
      "category": "party_submission"
    }
  ],
  "extractedAgencyDocumentCount": 2,
  "attachmentPolicy": "Official attachment links are retained. Agency-issued documents may also include a verified local PDF and page-level text representation.",
  "jurisdiction": "US",
  "operatorName": "TRES PALACIOS GAS STORAGE LLC"
}
```
