# SUNOCO PIPELINE L.P. — Warning Letter

**Citation:** CPF 12021040WL  
**Type / status:** enforcement / historical  
**Agency:** Pipeline and Hazardous Materials Safety Administration  
**Effective:** Not stated  
**Published:** 2021-06-08

CLOSED warning letter citing 195.202.

## Document text

Warning Letter involving SUNOCO PIPELINE L.P.. PHMSA's enforcement data identifies the cited regulation as 195.202. The case was opened on 2021-06-08 and is reported as closed as of 2021-06-08. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

12021040WL_Warning Letter_06082021_(20-172473).pdf: https://primis.phmsa.dot.gov/enforcement-documents/12021040WL/12021040WL_Warning%20Letter_06082021_(20-172473).pdf

12021040WL_Warning Letter_06082021_(20-172473)_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/12021040WL/12021040WL_Warning%20Letter_06082021_(20-172473)_text.pdf

12021040WL_Warning Letter_06082021_(20-172473)_text.pdf

WARNING LETTER
OVERNIGHT EXPRESS DELIVERY
June 8, 2021
Mr. Greg McIlwain
Sr Vice President, Operations
Sunoco Pipeline, LP
1300 Main Street
Houston, TX 77002
CPF 1-2021-040-WL
Dear Mr. McIlwain:
From July 28, 2020 to July 29, 2020, a representative of the Pipeline and Hazardous Materials
Safety Administration (PHMSA) pursuant to Chapter 601 of 49 United States Code (U.S.C.)
inspected Sunoco Pipeline, LP’s (Sunoco) Mariner East 2 Project in East Goshen Township, PA.
As a result of the inspection/investigation, it is alleged that you have committed a probable
violation of the Pipeline Safety Regulations, Title 49, Code of Federal Regulations (CFR). The
item inspected and the probable violation is:
1. § 195.202 Compliance with specifications or standards.
Each pipeline system must be constructed in accordance with
comprehensive written specifications or standards that are consistent
with the requirements of this part.
Sunoco failed to construct its Mariner East 2 pipeline in accordance with its comprehensive written
specifications or standards consistent with Part 195. Specifically, Sunoco failed to follow Sunoco
Pipeline L.P. and Affiliates CONSTRUCTION STANDARDS - Coating of Underground Steel Pipe,
Revision: 3, Number: 0502, Date: 9/1/15, subsection 3.1.1 (Construction Standard) regarding
specified anchor patterns.



CPF 1-2021-040-WL
Sunoco’s Construction Standard required a “specified anchor pattern (surface profile)” when
preparing underground steel pipe for coating. To assess the anchor profile, Sunoco utilized
calibrated anchor profile gauges.
During the July 28, 2020 inspection, the PHMSA inspector discovered that Sunoco used an expired
anchor profile gauge (ID # 217363, last calibration date was 3/6/2017 and due date was 3/6/2018)
to assess the surface profile for coating on pipe that was being installed. The anchor profile gauge
in use had a history of being calibrated; however, the calibration was expired.
Thus, by using an anchor profile gauge with an exceeded calibration due date, Sunoco failed to
confirm the “specified anchor pattern (surface profile)” as required by its Construction Standard.
Under 49 U.S.C. § 60122 and 49 CFR § 190.223, you are subject to a civil penalty not to exceed
$225,134 per violation per day the violation persists, up to a maximum of $2,251,334 for a related
series of violations. For violation occurring on or after January 11, 2021 and before May 3, 2021,
the maximum penalty may not exceed $222,504 per violation per day the violation persists, up to
a maximum of $2,225,034 for a related series of violations. For violation occurring on or after
July 31, 2019 and before January 11, 2021, the maximum penalty may not exceed $218,647 per
violation per day the violation persists, up to a maximum of $2,186,465 for a related series of
violations. For violation occurring on or after November 27, 2018 and before July 31, 2019, the
maximum penalty may not exceed $213,268 per violation per day, with a maximum penalty not to
exceed $2,132,679. For violation occurring on or after November 2, 2015 and before November
27, 2018, the maximum penalty may not exceed $209,002 per violation per day, with a maximum
penalty not to exceed $2,090,022.
We have reviewed the circumstances and supporting documents involved in this case, and have
decided not to conduct additional enforcement action or penalty assessment proceedings at this
time. We advise you to correct the item identified in this letter. Failure to do so will result in
Sunoco Pipeline, LP being subject to additional enforcement action.
No reply to this letter is required. If you choose to reply, in your correspondence please refer to
CPF 1-2021-040-WL. Be advised that all material you submit in response to this enforcement
action is subject to being made publicly available. If you believe that any portion of your
responsive material qualifies for confidential treatment under 5 U.S.C. 552(b), along with the
complete original document you must provide a second copy of the document with the portions
you believe qualify for confidential treatment redacted and an explanation of why you believe the
redacted information qualifies for confidential treatment under 5 U.S.C. 552(b).
Sincerely,
Robert Burrough
Director, Eastern Region, Office of Pipeline Safety
Pipeline and Hazardous Materials Safety Administration
12021040WL_Warning Letter_06082021_(20-172473)_text Page 2 of 2

## Provenance

- Official: Yes
- Source: <https://primis.phmsa.dot.gov/enforcement-data/case/12021040WL>
- Source ID: `phmsa-enforcement`
- SHA-256: `291819b1d22976a044c4d44a360fb8b11f483c93ea2ae8b59740830c7eef3060`
- Retrieved: 2026-08-20T04:44:44.458Z
- Exported: 2026-08-22T16:48:02.537Z
- Document slug: `phmsa-enforcement-12021040wl`

### Source metadata

```json
{
  "cpf": "12021040WL",
  "operator": "SUNOCO PIPELINE L.P.",
  "region": "Eastern",
  "pipelineType": "INTERSTATE LIQUID",
  "caseStatus": "CLOSED",
  "citedSections": [
    "195.202"
  ],
  "dataAsOf": "08/04/2026 12PM",
  "caseDataAsOf": "2026-08-04",
  "attachmentCount": 2,
  "attachments": [
    {
      "name": "12021040WL_Warning Letter_06082021_(20-172473).pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/12021040WL/12021040WL_Warning%20Letter_06082021_(20-172473).pdf",
      "bytes": 116619,
      "category": "agency_document"
    },
    {
      "name": "12021040WL_Warning Letter_06082021_(20-172473)_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/12021040WL/12021040WL_Warning%20Letter_06082021_(20-172473)_text.pdf",
      "bytes": 111339,
      "category": "agency_document"
    }
  ],
  "extractedAgencyDocumentCount": 1,
  "attachmentPolicy": "Official attachment links are retained. Agency-issued documents may also include a verified local PDF and page-level text representation.",
  "jurisdiction": "US",
  "operatorName": "SUNOCO PIPELINE L.P."
}
```