# TPM, INC — Warning Letter

**Citation:** CPF 220076003W  
**Type / status:** enforcement / historical  
**Agency:** Pipeline and Hazardous Materials Safety Administration  
**Effective:** Not stated  
**Published:** 2007-02-22

CLOSED warning letter citing 195.406, 195.573(a)(2), 195.575(a), 195.577.

## Document text

Warning Letter involving TPM, INC. PHMSA's enforcement data identifies the cited regulations as 195.406,  195.573(a)(2),  195.575(a),  195.577. The case was opened on 2007-02-22 and is reported as closed as of 2007-02-22. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

220076003W_operator response to notice_03302007.pdf: https://primis.phmsa.dot.gov/enforcement-documents/220076003W/220076003W_operator%20response%20to%20notice_03302007.pdf

220076003W_Warning Letter_02222007.pdf: https://primis.phmsa.dot.gov/enforcement-documents/220076003W/220076003W_Warning%20Letter_02222007.pdf

220076003W_Warning Letter_02222007.pdf

@
U.S. Deportment
of Trqnsportolion
Plpeline ond
Hdzordous frlqlerisls Sotely
Admlnistrotlon
233 Peachtree Stred Ste. 600
Atlanta. GA 30303
WARNING LETTER
CERTIFIED MAIL - RETIIRN RECEIPT REQUESTED
February 22,2007
Mr. Lany Clynch
Company Executive Offi cer
TPM.Inc.
P.O. Box 486
Alpharetta, GA 30009
cPF 2-2007-6003W
Dear Mr. Clynch:
On June 5 - 7,2006, a representative of the Pipeline and Hazardous Materials Safety
Administration (PHMSA) pursuant to Chapter 601 of 49 United States Code inspected your
Hazardous Liquid Pipeline facilities and reviewed records in Memphis, Tennessee.
As a result of the inspection, it appears that you have committed probable violations of the
Pipeline Safety Regulations Title 49, Code of Federal Regulations. The items inspected and the
probable violations are:
1. $195.573 What must I do to monitor external corrosion control?
(a) Protected pipelines. You must do fhe following to determine whether cathodic
protection required by this subpart complies with $195.571:
(2) Identify before December 2912003 or not more than 2 years after cathodic
protection is installed, whichever comes later, the circumstances in which a close-
interyal survey or comparable technology is practicable and necessary to accomplish
the otrjectives of paragraph 10.1.1.3 of NACE Standard RP0169-96 (incorporated by
reference, see $195.3).



)
J .
4.
TPM personnel did not provide a record of this evaluation. Operator personnel asserted
they had plans to address this code requirement.
$195.575 Which facilities must I electrically isolate and what inspections, tests, and
safeguards are required?
(a) You must electrically isolate each buried or submerged pipeline from other
metallic structures, unless you electrically interconnect and cathodically protect the
pipeline and the other structures as a single unit.
TPM personnel did not provide a record verifying inspection of its electrical isolations.
In addition, operator personnel asserted the Dupont station isolation is not working and they
have plans to frx it.
$195.577 What must I do to alleviate interference currents?
(a) For pipelines exposed to stray currents, you must have a program to identiff' test
for, and minimize the detrimental effects of such currents.
(b) You must design and install each impressed current or galvanic anode system to
minimize any adverse effects on existing adjacent metallic structures.
TPM personnel did not provide a record which verified testing for interference curents or
no need for due to analysis of non-exposure to stray currents.
$195.406 Maximum operating pressure.
(a) Except for surge pressures and other variations from normal operations' no
operator may operate a pipeline at a pressure that exceeds any of the following:
(1) The internal design pressure of the pipe determined in accordance with $195.106.
However, for steel pipe in pipelines being converted under $195.5' if one or more
factors of the design formula (Sf 95.106) are unknown, one of the following pressures
is to be used as design pressure:
(i) Eighty percent ofthe first test pressure that produces yield under section N5.0 of
appendix N of ASME 831.8, rdduced by the appropriate factors in $$195.106(a) and
(e); or
(ii) If the pipe is 121/nin (324 mm) or less outside diameter and is not tested to yield
under this paragraph,200 p.s.i. (1379 kPa) gage.
(2) The design pressure of any other component of the pipeline.
(3) Eighty percent of the test pressure for any part of the pipeline which has been
pressure tested under Subpart E ofthis part.
(a) Eighty percent of the factory test pressure or of the protofype test pressure for any
individually installed component which is excepted from testing under $195.305.
(5) X'or pipelines under $$195.302 (bX1) and (b)(z)(i) that have not been pressure
tested under subpart E ofthis part,80 percent ofthe test pressure or highest



'.
operating pressure to which the pipeline was subjected for 4 or more continuous hours
that can be demonstrated by recording charts or logs made at the time the test or
operations were conducted.
(b) No operator may permit the pressure in a pipeline during surges or other
variations from normal operations to exceed 110 percent of the operating pressure
limit established under paragraph (a) of this section. Each operator must provide
adequate controls and protective equipment to control the pressure within this limit.
TPM personnel did not provide a record of MOP calculation for its pipeline.
Under 49 United States Code, § 60122, you are subject to a civil penalty not to exceed
for any related series of violations. We have reviewed the circumstances and supporting
$100,000 for each violation for each day the violations persists up to a maximum of $1,000,000
documents involved in this case, and have decided not to conduct additional enforcement action
or penalty assessment proceedings at this time. We advise you to correct the items identified in
this letter. Be advised that failure to do so will result in TPM being subject to additional
enforcement action.
No reply to this letter is required. If you choose to reply, in your correspondence please refer to
CPF 2-2007-6003 W.
Sincerely,
Sanada Daughuty
Linda Daugherty
Director, Southern Region
Pipeline and Hazardous Materials Safety Administration

## Provenance

- Official: Yes
- Source: <https://primis.phmsa.dot.gov/enforcement-data/case/220076003W>
- Source ID: `phmsa-enforcement`
- SHA-256: `a91e991186775bbc2d048e74955b092acb9b8f370502112aed0e112834f5719e`
- Retrieved: 2026-08-20T04:44:44.458Z
- Exported: 2026-08-22T16:46:34.194Z
- Document slug: `phmsa-enforcement-220076003w`

### Source metadata

```json
{
  "cpf": "220076003W",
  "operator": "TPM, INC",
  "region": "Southern",
  "pipelineType": "INTRASTATE LIQUID ONSHORE",
  "caseStatus": "CLOSED",
  "citedSections": [
    "195.406",
    "195.573(a)(2)",
    "195.575(a)",
    "195.577"
  ],
  "dataAsOf": "08/04/2026 12PM",
  "caseDataAsOf": "2026-08-04",
  "attachmentCount": 2,
  "attachments": [
    {
      "name": "220076003W_operator response to notice_03302007.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/220076003W/220076003W_operator%20response%20to%20notice_03302007.pdf",
      "bytes": 110066,
      "category": "party_submission"
    },
    {
      "name": "220076003W_Warning Letter_02222007.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/220076003W/220076003W_Warning%20Letter_02222007.pdf",
      "bytes": 120289,
      "category": "agency_document"
    }
  ],
  "extractedAgencyDocumentCount": 1,
  "attachmentPolicy": "Official attachment links are retained. Agency-issued documents may also include a verified local PDF and page-level text representation.",
  "jurisdiction": "US",
  "operatorName": "TPM, INC"
}
```