# ENMARK ENERGY, INC — Notice of Probable Violation

**Citation:** CPF 220136011  
**Type / status:** enforcement / historical  
**Agency:** Pipeline and Hazardous Materials Safety Administration  
**Effective:** Not stated  
**Published:** 2013-10-25

CLOSED notice of probable violation citing 192.465(d), 192.517(a), 192.745(b).

## Document text

Notice of Probable Violation involving ENMARK ENERGY, INC. PHMSA's enforcement data identifies the cited regulations as 192.465(d),  192.517(a),  192.745(b). The case was opened on 2013-10-25 and is reported as closed as of 2015-03-04. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

220136011_Closure Letter_03042015.pdf: https://primis.phmsa.dot.gov/enforcement-documents/220136011/220136011_Closure%20Letter_03042015.pdf

220136011_Closure Letter_03042015_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/220136011/220136011_Closure%20Letter_03042015_text.pdf

220136011_Final Order_04042014.pdf: https://primis.phmsa.dot.gov/enforcement-documents/220136011/220136011_Final%20Order_04042014.pdf

220136011_Final Order_04042014_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/220136011/220136011_Final%20Order_04042014_text.pdf

220136011_nopv_pco_10252013.pdf: https://primis.phmsa.dot.gov/enforcement-documents/220136011/220136011_nopv_pco_10252013.pdf

220136011_nopv_pco_10252013_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/220136011/220136011_nopv_pco_10252013_text.pdf

220136011_Operator Response to Notice_11222013.pdf: https://primis.phmsa.dot.gov/enforcement-documents/220136011/220136011_Operator%20Response%20to%20Notice_11222013.pdf

220136011_Closure Letter_03042015_text.pdf

CERTIFIED MAIL - RETURN RECEIPT REQUESTED
March 4, 2015
Mr. Connell R. Rader
President
Enmark Energy, Inc.
104 First Choice Drive, Suite A
Madison, MS 39110
CPF 2-2013-6011
Dear Mr. Rader:
The PHMSA Southern Region, Office of Pipeline Safety (OPS) received a letter from
Mr. M. Benjamin Machlis dated March 2, 2015, an attorney with Holland & Hart, which
represents Rentech, Inc. (Rentech). Enmark Energy, Inc. (Enmark) is the operator of record
and Gulf Coast Synthetic Fuel Center, LLC (Gulf Coast), a subsidiary of Rentech, is the
owner of the Rentech 6-inch natural gas pipeline and pipeline facilities in Louisiana and
Mississippi, subject to the above referenced Final Order issued on April 4, 2014.
The letter included a copy of FERC’s “Order Approving Abandonment” issued on February
6, 2015, which grants Gulf Coast the authority to abandon the referenced pipeline and
associated appurtenances. Moreover, the Order clearly explains that the U.S. Army Corps of
Engineers required Gulf Coast to either upgrade or remove the pipeline portions atop three of
its jurisdictional levees.
Since abandonment of the pipeline makes the compliance items in the Final Order moot, this
case is now closed and no further action is necessary with respect to the matters involved in
this case. Notwithstanding the closure of this Final Order, it is must be noted that should Gulf
Coast not abandon the pipeline and associated appurtenances, the pipeline owner and operator
could be subject to further enforcement actions.
Sincerely,
Wayne T. Lemoi
Director, Office of Pipeline Safety
PHMSA Southern Region

220136011_Final Order_04042014_text.pdf

APRIL 4, 2014
Mr. Connell R. Rader
President
Enmark Energy, Inc.
104 First Choice Drive, Suite A
Madison, MS 39110
Re: CPF No. 2-2013-6011
Dear Mr. Rader:
Enclosed please find the Final Order issued in the above-referenced case. It makes findings of
violation and specifies actions that need to be taken by Enmark Energy, Inc., to comply with the
pipeline safety regulations. When the terms of the compliance order have been completed, as
determined by the Director, Southern Region, this enforcement action will be closed. Service of
the Final Order by certified mail is deemed effective upon the date of mailing, or as otherwise
provided under 49 C.F.R. § 190.5.
Thank you for your cooperation in this matter.
Sincerely,
Jeffrey D. Wiese
Associate Administrator
for Pipeline Safety
Enclosure
cc: Mr. Wayne T. Lemoi, Director, Southern Region, OPS
CERTIFIED MAIL - RETURN RECEIPT REQUESTED



U.S. DEPARTMENT OF TRANSPORTATION
PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION
OFFICE OF PIPELINE SAFETY
WASHINGTON, D.C. 20590
____________________________________
)
In the Matter of )
)
Enmark Energy, Inc., ) CPF No. 2-2013-6011
)
Respondent. )
____________________________________)
FINAL ORDER
On August 16, 2013, pursuant to 49 U.S.C. § 60117, a representative of the Pipeline and
Hazardous Materials Safety Administration (PHMSA), Office of Pipeline Safety (OPS),
conducted an on-site pipeline safety inspection of the facilities and records of Enmark Energy,
Inc. (Enmark or Respondent), in Louisiana and Mississippi. Enmark operates a 6-inch natural
gas pipeline (Rentech Pipeline) and related facilities in multiple States.
1
As a result of the inspection, the Director, OPS Southern Region, issued to Respondent, by letter
dated October 25, 2013, a Notice of Probable Violation and Proposed Compliance Order
(Notice). In accordance with 49 C.F.R. § 190.207, the Notice proposed finding that Enmark had
committed various violations of 49 C.F.R. Part 192, and ordering Respondent to take certain
measures to correct the alleged violations.
Enmark responded to the Notice by letter dated November 22, 2013 (Response). The company
did not contest the allegations of violation but requested that the Proposed Compliance Order
(PCO) be modified due to Respondent’s intent to abandon the pipeline. Respondent did not
request a hearing and therefore has waived its right to one.
FINDINGS OF VIOLATION
In its Response, Enmark did not contest the allegations in the Notice that it violated
49 C.F.R. Part 192, as follows:
Item 1: The Notice alleged that Respondent violated 49 C.F.R. § 192.465(d), which states:
1 See http://www.enmarkenergy.com/Projects html (Current as of March 10, 2014).



2
§ 192.465 External corrosion control: Monitoring
(a) Each pipeline that is under cathodic protection must be tested at
least once each calendar year, but with intervals not exceeding 15
months, to determine whether the cathodic protection meets the
requirements of § 192.463. . . .
(d) Each operator shall take prompt remedial action to correct any
deficiencies indicated by the monitoring.
The Notice alleged that Respondent violated 49 C.F.R. § 192.465(d) by failing to take prompt
remedial action to correct deficiencies indicated by the company’s external corrosion control
monitoring program. Specifically, the Notice alleged that Enmark had noted inadequate pipe-to-
soil readings at its cathodic protection test stations at Mile Posts 15.5 and 17.7 during its annual
external corrosion control testing in 2010, 2011 and 2012, but had failed to take any remedial
action to correct such deficiencies.
Respondent did not contest this allegation of violation. Accordingly, based upon a review of all
of the evidence, I find that Respondent violated 49 C.F.R. § 192.465(d) by failing to take prompt
remedial action to correct deficiencies identified by the company’s external corrosion control
monitoring program.
Item 2: The Notice alleged that Respondent violated 49 C.F.R. § 192.517(a), which states, in
relevant part:
§ 192.517 Records.
(a) Each operator shall make, and retain for the useful life of the
pipeline, a record of each test performed under §§192.505 and 192.507.
The record must contain at least the following information: . . .
(5) Pressure recording charts, or other record of pressure readings; . . .
The Notice alleged that Respondent violated 49 C.F.R. § 192.517(a) by failing to make, and
retain for the useful life of the Rentech Pipeline, adequate records for each test performed under
§§ 192.505 and 192.507. Specifically, the Notice alleged that Enmark could not provide pipeline
pressure recording charts or other records of pressure readings for a 1985 hydrostatic pressure
test. The 1985 test was memorialized only by a “Memo to File,” which stated only: 1) the test
pressure; 2) the dates of the test; and 3) several other bits of information.
Respondent did not contest this allegation of violation. Accordingly, based upon a review of all
of the evidence, I find that Respondent violated 49 C.F.R. § 192.517(a) by failing to make, and
retain for the useful life of the Rentech Pipeline, adequate records for each test performed under
§§ 192.505 and 192.507.
Item 3: The Notice alleged that Respondent violated 49 C.F.R. § 192.745(b), which states:
§ 192.745 Valve maintenance: Transmission lines.
(a) Each transmission line valve that might be required during any
emergency must be inspected and partially operated at intervals not



3
exceeding 15 months, but at least once each calendar year.
(b) Each operator must take prompt remedial action to correct any
valve found inoperable, unless the operator designates an alternative
valve.
The Notice alleged that Respondent violated 49 C.F.R. § 192.745(b) by failing to take prompt
remedial action to correct any “critical transmission line valve” (i.e., a transmission line that may
be necessary during an emergency) found to be inoperable during a regular valve inspection
required under § 192.745(a). Specifically, the Notice alleged that in July 2009, Enmark
discovered four critical valves to be inoperable during a regular inspection but failed to take any
corrective action. The same four valves were found to be inoperable in subsequent November
2009, November 2010, October 2011 and August 2012 Critical Valve Inspections, but the
company failed to take any remedial action following those inspections.
Respondent did not contest this allegation of violation. Accordingly, based upon a review of all
of the evidence, I find that Respondent violated 49 C.F.R. § 192.745(b) by failing to take prompt
remedial action to correct multiple critical transmission line valves that were found to be
inoperable.
These findings of violation will be considered prior offense in any subsequent enforcement
action taken against Enmark.
COMPLIANCE ORDER
The Notice proposed a compliance order with respect to Items 1, 2, and 3 in the Notice for
violations of 49 C.F.R. §§ 192.465(d), 192.517(a), and 192.745(b), respectively. Under
49 U.S.C. § 60118(a), each person who engages in the transportation of gas or who owns or
operates a pipeline facility is required to comply with the applicable safety standards established
under chapter 601.
In its Response, Enmark requested that the PCO be modified to reflect the company’s intention
to abandon the Rentech Pipeline. However, since Respondent has apparently not yet filed the
necessary paperwork with the Federal Energy and Regulatory Commission to formally abandon
the pipeline, nor specified what (if any) modifications should be made to the PCO, this request is
denied.
Accordingly, pursuant to the authority of 49 U.S.C. § 60118(b) and 49 C.F.R. § 190.217,
Respondent is ordered to take the following actions to ensure compliance with the pipeline safety
regulations applicable to its operations:
1. With respect to the violation of § 192.465(d) (Item 1), Enmark must:
a. Identify all deficiencies on its Rentech Pipeline indicated by external
corrosion control monitoring in 2010, 2011, 2012, and 2013; and
b. Correct any deficiencies that do not meet external corrosion control
cathodic protection criteria per § 192.463.



4
2. 3. 4. 5. With respect to the violation of § 192.517(a) (Item 2), Enmark must:
a. Locate the original pressure recording charts or other original records of
pressure readings for the February 13-14, 1985 hydrostatic pressure test of
the Rentech Pipeline; or
b. Complete a hydrostatic pressure test of the Rentech Pipeline.
With respect to the violation of § 192.745(b) (Item 3), Enmark must:
a. Repair or replace all four faulty critical transmission valves identified in
the 2009 to 2012 Critical Valve Inspection Reports; or
b. Designate alternative valves, as allowed under §192.745(b).
Enmark must notify the Director, OPS Southern Region, within 150 days
following the date of issuance of the Final Order that Compliance Order Items 1,
2, and 3 have been completed.
It is requested (not mandated) that Enmark maintain documentation of the safety
improvement costs associated with fulfilling this Compliance Order, and submit
the total to Wayne T. Lemoi, Director, OPS Southern Region. It is requested that
these costs be reported in two categories: 1) total cost associated with
preparation/revision of plans, procedures, studies and analyses; and 2) total costs
associated with replacements, additions and other changes to pipeline
infrastructure.
The Director, OPS Southern Region, may grant an extension of time to comply with any of the
required items upon a written request: 1) timely submitted by the Respondent; and 2)
demonstrating good cause for an extension. Failure to comply with this Order may result in the
administrative assessment of civil penalties not to exceed $200,000 for each violation for each
day the violation continues or in referral to the Attorney General for appropriate relief in a
district court of the United States.
The terms and conditions of this Final Order are effective upon service in accordance with
49 C.F.R. § 190.5.
___________________________________ __________________________
Jeffrey D. Wiese Date Issued
Associate Administrator
for Pipeline Safety

## Provenance

- Official: Yes
- Source: <https://primis.phmsa.dot.gov/enforcement-data/case/220136011>
- Source ID: `phmsa-enforcement`
- SHA-256: `714f030689d9e7af6dcebd2b856f253300d453475dd3a03dd252779cd882122e`
- Retrieved: 2026-08-20T04:44:44.458Z
- Exported: 2026-08-25T00:34:49.663Z
- Document slug: `phmsa-enforcement-220136011`

### Source metadata

```json
{
  "cpf": "220136011",
  "operator": "ENMARK ENERGY, INC",
  "region": "Southern",
  "pipelineType": "GAS INTRASTATE ONSHORE",
  "caseStatus": "CLOSED",
  "citedSections": [
    "192.465(d)",
    "192.517(a)",
    "192.745(b)"
  ],
  "dataAsOf": "08/04/2026 12PM",
  "caseDataAsOf": "2026-08-04",
  "attachmentCount": 7,
  "attachments": [
    {
      "name": "220136011_Closure Letter_03042015.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/220136011/220136011_Closure%20Letter_03042015.pdf",
      "bytes": 93570,
      "category": "agency_document"
    },
    {
      "name": "220136011_Closure Letter_03042015_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/220136011/220136011_Closure%20Letter_03042015_text.pdf",
      "bytes": 5216,
      "category": "agency_document"
    },
    {
      "name": "220136011_Final Order_04042014.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/220136011/220136011_Final%20Order_04042014.pdf",
      "bytes": 248049,
      "category": "agency_document"
    },
    {
      "name": "220136011_Final Order_04042014_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/220136011/220136011_Final%20Order_04042014_text.pdf",
      "bytes": 21382,
      "category": "agency_document"
    },
    {
      "name": "220136011_nopv_pco_10252013.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/220136011/220136011_nopv_pco_10252013.pdf",
      "bytes": 2876128,
      "category": "case_document"
    },
    {
      "name": "220136011_nopv_pco_10252013_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/220136011/220136011_nopv_pco_10252013_text.pdf",
      "bytes": 18791,
      "category": "case_document"
    },
    {
      "name": "220136011_Operator Response to Notice_11222013.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/220136011/220136011_Operator%20Response%20to%20Notice_11222013.pdf",
      "bytes": 882743,
      "category": "party_submission"
    }
  ],
  "extractedAgencyDocumentCount": 2,
  "attachmentPolicy": "Official attachment links are retained. Agency-issued documents may also include a verified local PDF and page-level text representation.",
  "jurisdiction": "US",
  "operatorName": "ENMARK ENERGY, INC"
}
```
