# SG RESOURCES MISSISSIPPI, LLC — Corrective Action Order

**Citation:** CPF 22026004CAO  
**Type / status:** enforcement / current  
**Agency:** Pipeline and Hazardous Materials Safety Administration  
**Effective:** Not stated  
**Published:** 2026-02-06

OPEN corrective action order.

## Document text

Corrective Action Order involving SG RESOURCES MISSISSIPPI, LLC. The dataset does not identify a cited regulation for this case. The case was opened on 2026-02-06 and is reported as open. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

22026004CAO_Corrective Action Order (AMENDED)_03022026_(26-363868).pdf: https://primis.phmsa.dot.gov/enforcement-documents/22026004CAO/22026004CAO_Corrective%20Action%20Order%20(AMENDED)_03022026_(26-363868).pdf

22026004CAO_Corrective Action Order (AMENDED)_03022026_(26-363868)_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/22026004CAO/22026004CAO_Corrective%20Action%20Order%20(AMENDED)_03022026_(26-363868)_text.pdf

22026004CAO_Corrective Action Order_02062026_(26-363868).pdf: https://primis.phmsa.dot.gov/enforcement-documents/22026004CAO/22026004CAO_Corrective%20Action%20Order_02062026_(26-363868).pdf

22026004CAO_Corrective Action Order_02062026_(26-363868)_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/22026004CAO/22026004CAO_Corrective%20Action%20Order_02062026_(26-363868)_text.pdf

22026004CAO_Corrective Action Order_02062026_(26-363868)_text.pdf

U.S. Department
of Transportation
Pipeline and Hazardous
Materials Safety
Administration
1200 New Jersey Avenue, SE
Washington, DC 20590
February 6, 2026
VIA EMAIL TO: chad.zamarin@williams.com;matt.hastings@williams.com
Chad Zamarin
President/CEO
SG Resources, L.L.C.
One Williams Center
Tulsa, OK 74172
CPF 2-2026-004-CAO
Dear Mr. Zamarin:
Enclosed please find a Corrective Action Order (“CAO” or “Order”) issued by the Pipeline and
Hazardous Materials Safety Administration (PHMSA), Office of Pipeline Safety (OPS). The CAO
requires SG Resources Mississippi, L.L.C. (SGR), to take certain corrective actions with respect
to the pipeline failure that occurred on February 3, 2026, on its Southern Pines Natural Gas Line
300 near Leakesville, Mississippi. SGR is a subsidiary of The Williams Companies, Inc.
Service of the CAO by email is effective upon the date of transmission and acknowledgment of
receipt as provided under 49 CFR § 190.5. The terms and conditions of this Order are effective
upon completion of service.
Sincerely,
Linda G. Daugherty
Acting Associate Administrator
for Pipeline Safety
Enclosure: CAO
cc: James Urisko, Director, PHMSA, Office of Pipeline Safety, Southern Region,
james.urisko@dot.gov
Matt Hastings, VP HSEI, SG Resources Mississippi, L.L.C.,
matt.hastings@williams.com



DEPARTMENT OF TRANSPORTATION
PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION
OFFICE OF PIPELINE SAFETY
WASHINGTON, D.C. 20590
)
In the Matter of )
)
SG Resources Mississippi, LLC, ) CPF No. 2-2026-004-CAO
)
Respondent )
)
CORRECTIVE ACTION ORDER
Background and Purpose
The Pipeline and Hazardous Materials Safety Administration (PHMSA), Office of Pipeline
Safety (OPS), is issuing this Corrective Action Order (CAO or Order) pursuant to the authority
provided in 49 U.S.C. § 60112. The CAO requires SG Resources Mississippi, L.L.C. (SGR or
Respondent)1 to take certain necessary corrective actions to protect the public, property, and the
environment from the potential hazards associated with the continued operation of its Southern
Pines Natural Gas Pipeline System near Leakesville, Mississippi, in Greene County.
On February 3, 2026, at approximately 6:30 PM CST, the Southern Pines Natural Gas Pipeline
System Line 300 ruptured inside the Southern Pines Energy Center located near Leakesville,
Mississippi, in Greene County (hereinafter the “Failure”). The Failure resulted in the separation
of the 2-inch liquid extraction line from the Line 300, the formation of a crater within the
Southern Pines Energy Center, and the release of a currently undetermined volume of natural
gas.
Pursuant to 49 U.S.C. § 60117, PHMSA has initiated an investigation of the Failure. The
preliminary findings of PHMSA’s ongoing investigation are as follows:
1 SGR is a subsidiary of The Williams Companies, Inc. See SG Resources Mississippi,
https://www.gasnom.com/ip/SOUTHERNPINES/ (last accessed February 6, 2026).



Preliminary Findings
• At approximately 6:30 PM CST on February 3, 2026, the Southern Pines Natural Gas
Pipeline System Line 300 ruptured at the Southern Pines Energy Center, an underground
natural gas storage facility, near Leakesville, Mississippi, in Greene County.
• The Failure resulted in the separation of a 2-inch liquid extraction line from Line 300, the
formation of a crater within the Southern Pines Energy Center, and the release of a
currently undetermined volume of natural gas.
• The event did not impact the integrity of the underground storage, though the entire
facility is currently shut-in. The failure happened in a remote location within the
Southern Pines Energy Center facility. There were no reported injuries, fatalities, or
evacuations, and the escaped gas did not ignite.
• SGR attempted to isolate the suspected failed segment of Line 300 using facility valves,
but it discovered that one of the valves used to isolate the segment was leaking. In
response, SGR isolated the line by closing the upstream and downstream block valves
(the Southern Pines Energy Center Valve at mile post 0 and the Midway Valve at mile
post 11.75), which are thirteen miles apart, and blew down the section. SGR successfully
isolated the failed segment on February 4, 2026.
• A recovered portion of the failed pipeline shows indications of internal corrosion that is
believed to be microbiologically influenced corrosion. The Southern Pines Energy Center
facility has had prior corrosion issues.
• The Southern Pines Natural Gas Pipeline System consists of 26.14 miles of natural gas
transmission pipeline. The pipeline system includes Line 100 running to the west out of
the Southern Pine Energy Center with interconnects to multiple customers, including an
interconnect at Ranch Road, and Lines 300 and 400 running to the east out of the Center.
Lines 100 and 400 were not disturbed by the Failure; however, SGR also shut in these
pipelines.
• As a major provider of natural gas along the southern United States, the pipeline system
transports natural gas from Mississippi to Alabama. There will be impacts to the supply
of commercial natural gas until repairs are made.
• At the discharge side of Southern Pines Energy Center, at mile post 0, where the Failure
occurred, the Maximum Allowable Operating Pressure (MAOP) reported by Williams
personnel is 1480 psig and the Maximum Operating Pressure (MOP) is 1140 psig.
• The pipeline was constructed in 2008. The pipeline coating is Fusion Bonded Epoxy
(FBE) with an undetermined seam type.
Determination of Necessity for Corrective Action Order and Right to Hearing
Section 60112 of title 49, United States Code, authorizes PHMSA to determine that a pipeline
facility is or would be hazardous to life, property, or the environment and if there is a likelihood
of serious harm, to expeditiously order the operator of the facility to take necessary corrective



action, including suspended or restricted use of the facility, physical inspection, testing, repair,
replacement, or other appropriate action. An order issued expeditiously must provide an
opportunity for a hearing as soon as practicable after the order is issued.
In deciding whether to issue an order, PHMSA must consider the following, if relevant: (1) the
characteristics of the pipe and other equipment used in the pipeline facility, including the age,
manufacture, physical properties, and method of manufacturing, constructing, or assembling the
equipment; (2) the nature of the material the pipeline facility transports, the corrosive and
deteriorative qualities of the material, the sequence in which the material is transported, and the
pressure required for transporting the material; (3) the aspects of the area in which the pipeline
facility is located, including climatic and geologic conditions and soil characteristics; (4) the
proximity of the area in which the facility is located to environmentally sensitive areas; (5) the
population density and population and growth patterns of the area in which the pipeline facility is
located; (6) any recommendation of the National Transportation Safety Board made under another
law; and (7) any other factors PHMSA may consider as appropriate.
After evaluating the foregoing preliminary findings of fact, and having considered the
characteristics of the pipeline, the nature of the failure, to include the history of corrosion issues
at the facility; the hazardous nature of the material transported (natural gas); the existing and
potential additional impacts to life, property, or the environment; the still-unknown cause of the
Failure; and the possibility of additional failures on the pipeline system; it is hereby determined
that continued operation of the Affected Segment, as defined below, without corrective measures
is or would be hazardous to life, property, or the environment, and that failure to issue this Order
expeditiously would result in the likelihood of serious harm.
Accordingly, this Order mandating immediate corrective action is issued expeditiously without
prior notice and opportunity for a hearing. The terms and conditions of this Order are effective
upon completion of service.
Within 10 days of receipt of this Order, Respondent may request a hearing, to be held as soon as
practicable, by notifying the Associate Administrator for Pipeline Safety in writing, with a copy
to the Director, PHMSA, OPS Southern Region. If a hearing is requested, it will be held in
accordance with 49 CFR § 190.211.
After receiving and analyzing additional data in the course of this investigation, PHMSA may
identify other corrective measures that need to be taken. Respondent will be notified of any
additional measures required and, if appropriate, PHMSA will consider a further amended order.
To the extent consistent with safety, Respondent will be afforded notice and an opportunity for a
hearing prior to the imposition of any additional corrective measures.
Corrective Measures
Definitions
Affected Segment – The “Affected Segment” means the approximately three miles of Line 100
from the mainline valve at Ranch Road to the Midpoint Valves on Lines 300 and 400



(approximate Mile Posts 11.75 and 11.8, respectively). The Affected Segment includes the entire
Southern Pines Energy Center and all related facility piping.
The Failure – The “Failure” means the rupture of Line 300 that occurred at 6:30 PM CST on
February 3, 2026, at the Southern Pines Energy Center, an underground natural gas storage
facility, near Leakesville, Mississippi, in Greene County.
Isolated Segment – The “Isolated Segment” means the portion of Line 300 from the Southern
Pines Energy Center Compressor Station at mile post 0 to the Midpoint Valve at mile post 11.75.
Director – The “Director” means the Director, PHMSA, OPS Southern Region.
1. SGR must not operate the Isolated Segment until authorized to do so by the Director.
2. Operating Pressure Restriction. SGR must reduce and maintain a twenty percent
(20%) pressure reduction in the actual operating pressure along the entire length of the
Affected
Segment such that the operating pressure along the Affected Segment will not exceed eighty
percent (80%) of the actual operating pressure in effect immediately prior to the Failure on
February 3, 2026.
a. This pressure restriction is to remain in effect until written approval to increase the
pressure or return the pipeline to its pre-failure operating pressure is obtained from the
Director.
b. Within 15 days of receipt of this Order, SGR must provide the Director the actual
operating pressures of each pump/compressor station and each main line pressure
regulating station on the Affected Segment at the time of failure and the reduced
pressure restriction set-points at these same locations.
c. This pressure restriction requires any relevant remote or local alarm limits, software
programming set-points or control points, and mechanical over-pressure devices to be
adjusted accordingly.
d. When determining the pressure restriction set-points, SGR must take into account any
in-line inspection (ILI) features or anomalies present in the Affected Segment to
provide for continued safe operation while further corrective actions are completed.
e. SGR must review the pressure restriction monthly by analyzing the operating pressure
data. SGR must take into account any ILI features or anomalies present in the Affected
Segment and immediately reduce the operating pressure to maintain the safe operations
of the Affected Segment, if warranted by the monthly review. SGR must submit the
results of the monthly review to the Director. The results must include, at a minimum,
the current discharge set-points (including any additional pressure reductions), and any
pressure exceedance at discharge set-points.
3. Restart Plan. Prior to resuming operation of the Isolated Segment, SGR must develop and
submit a written Restart Plan to the Director for prior approval.
a. The Director may approve the Restart Plan incrementally without approving the
entire plan but the Isolated Segment cannot resume operation until the Restart Plan
is approved in its entirety.



b. Once approved by the Director, the Restart Plan will be incorporated by reference
into this Order.
c. The Restart Plan must provide for adequate patrolling of the Isolated Segment
during the restart process and must include incremental pressure increases during
start up, with each increment to be held for at least 2 hours.
d. The Restart Plan must include sufficient surveillance of the pipeline during each
pressure increment to ensure that no leaks are present when operation of the line
resumes.
e. The Restart Plan must specify a day-light restart and include advance
communications with local emergency response officials.
f. The Restart Plan must provide for a review of the Isolated Segment for conditions
similar to those of the Failure including a review of construction, operating and
maintenance (O&M) and integrity management records such as ILI results,
hydrostatic tests, root cause failure analysis of prior failures, aerial and ground
patrols, corrosion, cathodic protection, excavations and pipe replacements. SGR
must address any findings that require remedial measures to be implemented prior
to restart.
g. The Restart Plan must also include documentation of the completion of all
mandated actions, and a management of change plan to ensure that all procedural
modifications are incorporated into SGR’s operations and maintenance procedures
manual.
h. Prior to restart, SGR must submit to the Director a contingency plan to operate and
monitor the Isolated Segment during flooding conditions, including enhanced
patrolling and surveillance.
4. Return to Service. After the Director approves the Restart Plan, SGR may return the
Isolated Segment to service but the operating pressure must not exceed eighty percent (80%)
of the actual operating pressure in effect immediately prior to the Failure on February 3, 2026,
in accordance with Item 2 above.
5. Removal of Pressure Restriction. The Director may allow the removal or modification of
the pressure restriction upon a written request from SGR demonstrating that restoring the
pipeline to its pre-failure operating pressure is justified based on a reliable engineering analysis
showing that the pressure increase is safe considering all known defects, anomalies, and
operating parameters of the pipeline.
6. The Director may allow the temporary removal or modification of the pressure restrictions
upon a written request from SGR demonstrating that temporary mitigative and preventive
measures are implemented prior to and during the temporary removal or modification of the
pressure restriction. The Director's determination will be based on the Failure cause and
provision of evidence that preventative and mitigative actions taken by the operator provide
for the safe operation of the Affected Segment during the temporary removal or modification
of the pressure restriction. Appeals to determinations of the Director in this regard will be
decided by the Associate Administrator for Pipeline Safety.



7. Instrumented Leakage Survey. Within 30 days of receipt of this Order, SGR must perform
an aerial or ground instrumented leakage survey of the Affected Segment. SGR must
investigate all leak indications and remedy all leaks discovered. SGR must submit
documentation of this survey to the Director within 45 days of receipt of this Order.
8. Records Verification. As recommended in PHMSA Advisory Bulletin 2012-06, SGR must
verify the records for the Affected Segment to confirm the MAOP. SGR must submit
documentation of this record verification to the Director within 45 days of receipt of this Order.
9. Review of Prior Inline Inspection (ILI) Results. Within 30 days of receipt of this Order,
SGR must conduct a review of any previous ILI results of the Affected Segment; re-evaluate
all ILI results from the past 10 calendar years, to include a review of the ILI vendors' raw data
and analysis; and determine whether any features were present in the failed pipe joint and/or
any other pipe removed. SGR must also determine if any features with similar characteristics
are present elsewhere on the Affected Segment. SGR shall submit documentation of this ILI
review to the Director within 45 days of receipt of this Order as follows:
a. List all ILI tool runs, tool types, and the calendar years of the tool runs.
b. List, describe (type, size, wall loss, etc.), and identify the specific location of all ILI
features present in the failed joint and/or other pipe removed.
c. List, describe (type, size, wall loss, etc.), and identify the specific location of all ILI
features with similar characteristics present elsewhere on the Affected Segment.
d. Explain the process used to review the ILI results and the results of the reevaluation.
10. Mechanical and Metallurgical Testing. Within 45 days of receipt of this Order, SGR
must complete mechanical and metallurgical testing and failure analysis of the failed pipe,
including an analysis of soil samples and any foreign materials. The testing and analysis must
be completed as follows:
a. Document the chain-of-custody when handling and transporting the failed pipe
section and other evidence from the Failure site.
b. Within 10 days of receipt of this Order, develop and submit the testing protocol and
the proposed testing laboratory to the Director for prior approval.
c. Prior to beginning the mechanical and metallurgical testing, provide the Director
with the scheduled date, time, and location of the testing to allow for an OPS
representative to witness the testing.
d. Ensure the testing laboratory distributes all reports whether draft or final in their
entirety to the Director at the same time they are made available to SGR.
11. Root Cause Failure Analysis. Within 90 days following receipt of this Order, SGR must
complete a root cause failure analysis (RCFA) and submit a final report of this RCFA to the
Director. The RCFA must be supplemented or facilitated by an independent third-party
approved by the Director and must document the decision-making process and all factors
contributing to the failure. SGR must ensure that all reports, whether draft or final, are made
available in their entirety to the Director at the same time they are made available to SGR. The
final report must include findings and any lessons learned and whether the findings and any
lessons learned are applicable to other locations within SGR’s pipeline system.



12. Leak Detection Plan. Within 45 days of receipt of this Order, SGR shall perform a review
and submit to the Director a written plan to improve the leak detection capability on the
Affected Segment. The review must include a comprehensive analysis of any SCADA, leak
detection, surveillance, and other monitoring systems on the Affected Segment. The written
plan must include a schedule for improving the leak detection capability on the Affected
Segment through additional instrumentation, updated hardware or software, installation of a
computational pipeline monitoring system and associated software programming, additional
surveillance, pipeline control staffing, ongoing leak surveys, and any other appropriate
measures.
13. Emergency Response Plan and Training Review. SGR must review and assess the
effectiveness of its emergency response plan with regards to the Failure. The review and
assessment must include the on-scene response and support, coordination, and communication
with emergency responders and public officials. SGR must also include a review and
assessment of the effectiveness of its emergency training program. SGR must amend its
emergency response plan and emergency training, if necessary, to reflect the results of this
review. The documentation of this Emergency Response Plan and Training Review must be
available for inspection by OPS or provided to the Director, if requested.
14. Remedial Work Plan (RWP).
a. Within 90 days following receipt of this Order, SGR must submit a Remedial
Work Plan (RWP) to the Director for approval.
b. The Director may approve the RWP incrementally without approving the entire
RWP.
c. Once approved by the Director, the RWP will be incorporated by reference into this
Order.
d. The RWP must specify the tests, inspections, assessments, evaluations, and remedial
measures SGR will use to verify the integrity of the Affected Segment. It must
address all known or suspected factors and causes of the Failure identified by, but
not limited to, the results of the metallurgical and root cause failure analysis required
by this Order. SGR should consider both the risk of another failure and the
consequence of another failure to develop a prioritized schedule for RWP related
work along the Affected Segment.
e. The RWP must include a procedure or process to:
i. Identify pipe, both facility and mainline, in the Affected Segment with
characteristics similar to the contributing factors identified for the Failure,
to include operational or maintenance factors.
ii. Gather all data necessary to review the failure history (in service and
pressure test failures) of the Affected Segment and to prepare a written
report containing all the available information such as the locations, dates,
and causes of leaks and failures.
iii. Integrate the results of the metallurgical testing, root cause failure analysis,
and other corrective actions required by this Order with all relevant pre-
existing operational and assessment data for the Affected Segment. Pre-
existing operational data includes, but is not limited to, construction,



operations, maintenance, testing, repairs, prior metallurgical analyses, and
any third-party consultation information. Pre-existing assessment data
includes, but is not limited to, ILI tool runs, hydrostatic pressure testing,
direct assessments, close interval surveys, and Direct Current Voltage
Gradient/Alternating Current Voltage Gradient surveys.
iv. Determine if conditions similar to those contributing to the Failure, to
include operational or maintenance conditions, are likely to exist elsewhere
on the Affected Segment.
v. Conduct additional field tests, inspections, assessments, and evaluations to
determine whether, and to what extent, the conditions associated with the
Failure and other failures from the failure history (see (e)(ii) above) or any
other integrity threats are present elsewhere on the Affected Segment. At
a
minimum, this process must consider all failure causes and specify the use
of one or more of the following:
1) ILI tools that are technically appropriate for assessing the
pipeline system based on the cause of the Failure and that can
reliably detect and identify anomalies,
2) Hydrostatic pressure testing,
3) Close-interval surveys,
4) Cathodic protection surveys, to include interference surveys in
coordination with other utilities (e.g. underground utilities,
overhead power lines, etc.) in the area,
5) Coating surveys,
6) Stress corrosion cracking surveys,
7) Selective seam corrosion surveys; and,
8) Other tests, inspections, assessments, and evaluations appropriate
for the Failure causes.
Note: SGR may use the results of previous tests, inspections,
assessments, and evaluations if approved by the Director,
provided the results of the tests, inspections, assessments,
and evaluations are analyzed with regard to the factors
known or suspected to have caused the Failure.
vi. Describe the inspection and repair criteria SGR will use to prioritize,
excavate, evaluate, and repair anomalies, imperfections, and other
identified integrity threats. Include a description of how any defects will
be graded and a schedule for repairs or replacement.
vii. Based on the known history and condition of the Affected Segment
describe the methods SGR will use to repair, replace, or take other
corrective measures, to include measures to update maintenance or
operational procedures that may have been causal factors of the Failure,
in order to remediate the conditions associated with the February 3, 2026,
pipeline failure and to address other known integrity threats along the
Affected Segment. The repair, replacement, or other corrective measures
must meet the criteria specified in (d)(vi) above.



viii. Implement continuing long-term periodic testing and integrity
verification
measures to ensure the ongoing safe operation of the Affected Segment
considering the results of the analyses, inspections, evaluations, and
corrective measures undertaken pursuant to the Order.
f. Include a proposed schedule for completion of the RWP.
g. SGR must revise the RWP as necessary to incorporate new information obtained
during the failure investigation and remedial activities, to incorporate the results of
actions undertaken pursuant to this Order, and to incorporate modifications required
by the Director. SGR must submit any plan revisions to the Director for prior
approval. The Director may approve plan revisions incrementally. Any and all
revisions to the RWP after it has been approved and incorporated by reference into
this Order will be fully described and documented in the CAO Documentation
Report.
h. SGR must implement the RWP as it is approved by the Director, including any
revisions to the plan.
15. CAO Documentation Report (CDR). SGR must create and revise, as necessary, a
CAO Documentation Report (CDR). When SGR has concluded all the items in this Order
it will submit the final CDR in its entirety to the Director. This will allow the Director to
complete a thorough review of all actions taken by SGR with regards to this Order prior
to approving the closure of this Order. The intent is for the CDR to summarize all activities
and documentation associated with this Order in one document.
a. The Director may approve the CDR incrementally without approving the entire
CDR.
b. Once approved by the Director, the CDR will be incorporated by reference into this
Order.
c. The CDR must include but not be limited to:
i. Table of Contents;
ii. Summary of the pipeline failure of February 3, 2026, and the response
activities;
iii. Summary of pipe data and properties and all prior assessments of the
Affected Segment;
iv. Summary of all tests, inspections, assessments, evaluations, and analysis
required by the Order;
v. Summary of the Mechanical and Metallurgical Testing as required by
the Order;
vi. Summary of the RCFA with all root causes as required by the Order;
vii. Documentation of all actions taken by SGR to implement the RWP, the
results of those actions, and the inspection and repair criteria used;
viii. Documentation of any revisions to the RWP including those necessary
to incorporate the results of actions undertaken pursuant to this Order
and whenever necessary to incorporate new information obtained
during the failure investigation and remedial activities;
ix. Lessons learned while completing this Order;
x. A path forward describing specific actions SGR will take on its entire



pipeline system as a result of the lessons learned from work on this
Order; and
xi. Appendices (if required).
Other Requirements:
16. Approvals. With respect to each submission under this Order that requires the approval of
the Director, the Director may: (a) approve, in whole or part, the submission; (b) approve the
submission on specified conditions; (c) modify the submission to cure any deficiencies; (d)
disapprove in whole or in part, the submission, directing that Respondent modify the
submission, or (e) any combination of the above. In the event of approval, approval upon
conditions, or modification by the Director, Respondent shall proceed to take all action
required by the submission as approved or modified by the Director. If the Director
disapproves all or any portion of the submission, Respondent must correct all deficiencies
within the time specified by the Director and resubmit it for approval.
17. Extensions of Time. The Director may grant an extension of time for compliance with
any of the terms of this Order upon a written request timely submitted demonstrating good
cause for an extension.
18. Reporting. SGR must submit quarterly reports to the Director that: (1) include all
available data and results of the testing and evaluations required by this Order; and (2) describe
the progress of the repairs or other remedial actions being undertaken. The first quarterly report
is due on April 1, 2026, covering the period through March 15, 2026. The Director may change
the interval for the submission of these reports.
19. Documentation of the Costs. It is requested that Respondent maintain documentation of
the costs associated with implementation of this CAO. Include in each quarterly report
submitted the to-date total costs associated with: (1) preparation and revision of procedures,
studies, and analyses; (2) physical changes to pipeline infrastructure, including repairs,
replacements, and other modifications; and (3) environmental remediation, if applicable.
Be advised that all material submitted in response to this enforcement action is subject to being
made publicly available. If you believe that any portion of your responsive material qualifies for
confidential treatment under 5 U.S.C. § 552(b), along with the complete original document you
must provide a second copy of the document with the portions you believe qualify for confidential
treatment redacted and an explanation of why you believe the redacted information qualifies for
confidential treatment under 5 U.S.C. § 552(b).
In your correspondence on this matter, please refer to “CPF No. 2-2026-004-CAO” and for each
document you submit, please provide a copy in electronic format whenever possible. The actions
required by this Order are in addition to and do not waive any requirements that apply to
Respondent’s pipeline system under 49 CFR Parts 190 through 199, under any other order issued
to Respondent under authority of 49 U.S.C. Chapter 601, or under any other provision of federal
or state law.



Respondent may appeal any decision of the Director to the Associate Administrator for Pipeline
Safety. Decisions of the Associate Administrator shall be final.
Failure to comply with this Order may result in the assessment of civil penalties and in referral to
the Attorney General for appropriate relief in United States District Court pursuant to 49 U.S.C.
§ 60120.
The terms and conditions of this Order are effective upon service in accordance with 49 CFR
§ 190.5.
Linda Daugherty Date Issued
Acting Associate Administrator
for Pipeline Safety

22026004CAO_Corrective Action Order (AMENDED)_03022026_(26-363868)_text.pdf

U.S. Department
of Transportation
Pipeline and Hazardous
Materials Safety
Administration
1200 New Jersey Avenue, SE
Washington, DC 20590
March 2, 2026
VIA EMAIL TO: chad.zamarin@williams.com;matt.hastings@williams.com
Chad Zamarin
President/CEO
SG Resources, L.L.C.
One Williams Center
Tulsa, OK 74172
CPF 2-2026-004-CAO
Dear Mr. Zamarin:
Enclosed please find a Corrected Corrective Action Order (Corrected CAO) issued by the Pipeline
and Hazardous Materials Safety Administration (PHMSA), Office of Pipeline Safety (OPS). The
Corrected CAO corrects a typographical error in paragraph 14.e.vii. of the list of corrective actions
in the Corrective Action Order that was issued on February 6, 2026, regarding the pipeline failure
that occurred on February 3, 2026, on the Southern Pines Natural Gas Line 300 near Leakesville,
Mississippi. SGR is a subsidiary of The Williams Companies, Inc.
Service of the Corrected CAO by electronic mail is effective upon the date of transmission and
acknowledgment of receipt as provided under 49 CFR § 190.5.
Sincerely,
Linda G. Daugherty
Acting Associate Administrator
for Pipeline Safety
Enclosure: Corrected CAO
cc: James Urisko, Director, Southern Region, Office of Pipeline Safety, PHMSA
james.urisko@dot.gov
Matt Hastings, VP HSEI, SG Resources Mississippi, L.L.C.,
matt.hastings@williams.com
CONFIRMATION OF RECEIPT REQUESTED



DEPARTMENT OF TRANSPORTATION
PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION
OFFICE OF PIPELINE SAFETY
WASHINGTON, D.C. 20590
____________________________________
In the Matter of )
SG Resources Mississippi, LLC, ) CPF No. 2-2026-004-CAO
)
)
)
Respondent )
____________________________________)
CORRECTIVE ACTION ORDER
Background and Purpose
The Pipeline and Hazardous Materials Safety Administration (PHMSA), Office of Pipeline
Safety (OPS), is issuing this Corrective Action Order (CAO or Order) pursuant to the authority
provided in 49 U.S.C. § 60112. The CAO requires SG Resources Mississippi, L.L.C. (SGR or
Respondent)1 to take certain necessary corrective actions to protect the public, property, and the
environment from the potential hazards associated with the continued operation of its Southern
Pines Natural Gas Pipeline System near Leakesville, Mississippi, in Greene County.
On February 3, 2026, at approximately 6:30 PM CST, the Southern Pines Natural Gas Pipeline
System Line 300 ruptured inside the Southern Pines Energy Center located near Leakesville,
Mississippi, in Greene County (hereinafter the “Failure”). The Failure resulted in the separation
of the 2-inch liquid extraction line from the Line 300, the formation of a crater within the
Southern Pines Energy Center, and the release of a currently undetermined volume of natural
gas.
Pursuant to 49 U.S.C. § 60117, PHMSA has initiated an investigation of the Failure. The
preliminary findings of PHMSA’s ongoing investigation are as follows:
1 SGR is a subsidiary of The Williams Companies, Inc. See SG Resources Mississippi,
https://www.gasnom.com/ip/SOUTHERNPINES/ (last accessed February 6, 2026).



Preliminary Findings
• At approximately 6:30 PM CST on February 3, 2026, the Southern Pines Natural Gas
Pipeline System Line 300 ruptured at the Southern Pines Energy Center, an underground
natural gas storage facility, near Leakesville, Mississippi, in Greene County.
• The Failure resulted in the separation of a 2-inch liquid extraction line from Line 300, the
formation of a crater within the Southern Pines Energy Center, and the release of a
currently undetermined volume of natural gas.
• The event did not impact the integrity of the underground storage, though the entire
facility is currently shut-in. The failure happened in a remote location within the
Southern Pines Energy Center facility. There were no reported injuries, fatalities, or
evacuations, and the escaped gas did not ignite.
• SGR attempted to isolate the suspected failed segment of Line 300 using facility valves,
but it discovered that one of the valves used to isolate the segment was leaking. In
response, SGR isolated the line by closing the upstream and downstream block valves
(the Southern Pines Energy Center Valve at mile post 0 and the Midway Valve at mile
post 11.75), which are thirteen miles apart, and blew down the section. SGR successfully
isolated the failed segment on February 4, 2026.
• A recovered portion of the failed pipeline shows indications of internal corrosion that is
believed to be microbiologically influenced corrosion. The Southern Pines Energy Center
facility has had prior corrosion issues.
• The Southern Pines Natural Gas Pipeline System consists of 26.14 miles of natural gas
transmission pipeline. The pipeline system includes Line 100 running to the west out of
the Southern Pine Energy Center with interconnects to multiple customers, including an
interconnect at Ranch Road, and Lines 300 and 400 running to the east out of the Center.
Lines 100 and 400 were not disturbed by the Failure; however, SGR also shut in these
pipelines.
• As a major provider of natural gas along the southern United States, the pipeline system
transports natural gas from Mississippi to Alabama. There will be impacts to the supply
of commercial natural gas until repairs are made.
• At the discharge side of Southern Pines Energy Center, at mile post 0, where the Failure
occurred, the Maximum Allowable Operating Pressure (MAOP) reported by Williams
personnel is 1480 psig and the Maximum Operating Pressure (MOP) is 1140 psig.
• The pipeline was constructed in 2008. The pipeline coating is Fusion Bonded Epoxy
(FBE) with an undetermined seam type.
Determination of Necessity for Corrective Action Order and Right to Hearing
Section 60112 of title 49, United States Code, authorizes PHMSA to determine that a pipeline
facility is or would be hazardous to life, property, or the environment and if there is a likelihood
of serious harm, to expeditiously order the operator of the facility to take necessary corrective



action, including suspended or restricted use of the facility, physical inspection, testing, repair,
replacement, or other appropriate action. An order issued expeditiously must provide an
opportunity for a hearing as soon as practicable after the order is issued.
In deciding whether to issue an order, PHMSA must consider the following, if relevant: (1) the
characteristics of the pipe and other equipment used in the pipeline facility, including the age,
manufacture, physical properties, and method of manufacturing, constructing, or assembling the
equipment; (2) the nature of the material the pipeline facility transports, the corrosive and
deteriorative qualities of the material, the sequence in which the material is transported, and the
pressure required for transporting the material; (3) the aspects of the area in which the pipeline
facility is located, including climatic and geologic conditions and soil characteristics; (4) the
proximity of the area in which the facility is located to environmentally sensitive areas; (5) the
population density and population and growth patterns of the area in which the pipeline facility is
located; (6) any recommendation of the National Transportation Safety Board made under another
law; and (7) any other factors PHMSA may consider as appropriate.
After evaluating the foregoing preliminary findings of fact, and having considered the
characteristics of the pipeline, the nature of the failure, to include the history of corrosion issues
at the facility; the hazardous nature of the material transported (natural gas); the existing and
potential additional impacts to life, property, or the environment; the still-unknown cause of the
Failure; and the possibility of additional failures on the pipeline system; it is hereby determined
that continued operation of the Affected Segment, as defined below, without corrective measures
is or would be hazardous to life, property, or the environment, and that failure to issue this Order
expeditiously would result in the likelihood of serious harm.
Accordingly, this Order mandating immediate corrective action is issued expeditiously without
prior notice and opportunity for a hearing. The terms and conditions of this Order are effective
upon completion of service.
Within 10 days of receipt of this Order, Respondent may request a hearing, to be held as soon as
practicable, by notifying the Associate Administrator for Pipeline Safety in writing, with a copy
to the Director, PHMSA, OPS Southern Region. If a hearing is requested, it will be held in
accordance with 49 CFR § 190.211.
After receiving and analyzing additional data in the course of this investigation, PHMSA may
identify other corrective measures that need to be taken. Respondent will be notified of any
additional measures required and, if appropriate, PHMSA will consider a further amended order.
To the extent consistent with safety, Respondent will be afforded notice and an opportunity for a
hearing prior to the imposition of any additional corrective measures.
Corrective Measures
Definitions
Affected Segment – The “Affected Segment” means the approximately three miles of Line 100
from the mainline valve at Ranch Road to the Midpoint Valves on Lines 300 and 400



(approximate Mile Posts 11.75 and 11.8, respectively). The Affected Segment includes the entire
Southern Pines Energy Center and all related facility piping.
The Failure – The “Failure” means the rupture of Line 300 that occurred at 6:30 PM CST on
February 3, 2026, at the Southern Pines Energy Center, an underground natural gas storage
facility, near Leakesville, Mississippi, in Greene County.
Isolated Segment – The “Isolated Segment” means the portion of Line 300 from the Southern
Pines Energy Center Compressor Station at mile post 0 to the Midpoint Valve at mile post 11.75.
Director – The “Director” means the Director, PHMSA, OPS Southern Region.
1. SGR must not operate the Isolated Segment until authorized to do so by the Director.
2. Operating Pressure Restriction. SGR must reduce and maintain a twenty percent
(20%) pressure reduction in the actual operating pressure along the entire length of the
Affected
Segment such that the operating pressure along the Affected Segment will not exceed eighty
percent (80%) of the actual operating pressure in effect immediately prior to the Failure on
February 3, 2026.
a. This pressure restriction is to remain in effect until written approval to increase the
pressure or return the pipeline to its pre-failure operating pressure is obtained from the
Director.
b. Within 15 days of receipt of this Order, SGR must provide the Director the actual
operating pressures of each pump/compressor station and each main line pressure
regulating station on the Affected Segment at the time of failure and the reduced
pressure restriction set-points at these same locations.
c. This pressure restriction requires any relevant remote or local alarm limits, software
programming set-points or control points, and mechanical over-pressure devices to be
adjusted accordingly.
d. When determining the pressure restriction set-points, SGR must take into account any
in-line inspection (ILI) features or anomalies present in the Affected Segment to
provide for continued safe operation while further corrective actions are completed.
e. SGR must review the pressure restriction monthly by analyzing the operating pressure
data. SGR must take into account any ILI features or anomalies present in the Affected
Segment and immediately reduce the operating pressure to maintain the safe operations
of the Affected Segment, if warranted by the monthly review. SGR must submit the
results of the monthly review to the Director. The results must include, at a minimum,
the current discharge set-points (including any additional pressure reductions), and any
pressure exceedance at discharge set-points.
3. Restart Plan. Prior to resuming operation of the Isolated Segment, SGR must develop and
submit a written Restart Plan to the Director for prior approval.
a. The Director may approve the Restart Plan incrementally without approving the
entire plan but the Isolated Segment cannot resume operation until the Restart Plan
is approved in its entirety.



b. Once approved by the Director, the Restart Plan will be incorporated by reference
into this Order.
c. The Restart Plan must provide for adequate patrolling of the Isolated Segment
during the restart process and must include incremental pressure increases during
start up, with each increment to be held for at least 2 hours.
d. The Restart Plan must include sufficient surveillance of the pipeline during each
pressure increment to ensure that no leaks are present when operation of the line
resumes.
e. The Restart Plan must specify a day-light restart and include advance
communications with local emergency response officials.
f. The Restart Plan must provide for a review of the Isolated Segment for conditions
similar to those of the Failure including a review of construction, operating and
maintenance (O&M) and integrity management records such as ILI results,
hydrostatic tests, root cause failure analysis of prior failures, aerial and ground
patrols, corrosion, cathodic protection, excavations and pipe replacements. SGR
must address any findings that require remedial measures to be implemented prior
to restart.
g. The Restart Plan must also include documentation of the completion of all
mandated actions, and a management of change plan to ensure that all procedural
modifications are incorporated into SGR’s operations and maintenance procedures
manual.
h. Prior to restart, SGR must submit to the Director a contingency plan to operate and
monitor the Isolated Segment during flooding conditions, including enhanced
patrolling and surveillance.
4. Return to Service. After the Director approves the Restart Plan, SGR may return the
Isolated Segment to service but the operating pressure must not exceed eighty percent (80%)
of the actual operating pressure in effect immediately prior to the Failure on February 3, 2026,
in accordance with Item 2 above.
5. Removal of Pressure Restriction. The Director may allow the removal or modification of
the pressure restriction upon a written request from SGR demonstrating that restoring the
pipeline to its pre-failure operating pressure is justified based on a reliable engineering analysis
showing that the pressure increase is safe considering all known defects, anomalies, and
operating parameters of the pipeline.
6. The Director may allow the temporary removal or modification of the pressure restrictions
upon a written request from SGR demonstrating that temporary mitigative and preventive
measures are implemented prior to and during the temporary removal or modification of the
pressure restriction. The Director's determination will be based on the Failure cause and
provision of evidence that preventative and mitigative actions taken by the operator provide
for the safe operation of the Affected Segment during the temporary removal or modification
of the pressure restriction. Appeals to determinations of the Director in this regard will be
decided by the Associate Administrator for Pipeline Safety.



7. Instrumented Leakage Survey. Within 30 days of receipt of this Order, SGR must perform
an aerial or ground instrumented leakage survey of the Affected Segment. SGR must
investigate all leak indications and remedy all leaks discovered. SGR must submit
documentation of this survey to the Director within 45 days of receipt of this Order.
8. Records Verification. As recommended in PHMSA Advisory Bulletin 2012-06, SGR must
verify the records for the Affected Segment to confirm the MAOP. SGR must submit
documentation of this record verification to the Director within 45 days of receipt of this Order.
9. Review of Prior Inline Inspection (ILI) Results. Within 30 days of receipt of this Order,
SGR must conduct a review of any previous ILI results of the Affected Segment; re-evaluate
all ILI results from the past 10 calendar years, to include a review of the ILI vendors' raw data
and analysis; and determine whether any features were present in the failed pipe joint and/or
any other pipe removed. SGR must also determine if any features with similar characteristics
are present elsewhere on the Affected Segment. SGR shall submit documentation of this ILI
review to the Director within 45 days of receipt of this Order as follows:
a. List all ILI tool runs, tool types, and the calendar years of the tool runs.
b. List, describe (type, size, wall loss, etc.), and identify the specific location of all ILI
features present in the failed joint and/or other pipe removed.
c. List, describe (type, size, wall loss, etc.), and identify the specific location of all ILI
features with similar characteristics present elsewhere on the Affected Segment.
d. Explain the process used to review the ILI results and the results of the reevaluation.
10. Mechanical and Metallurgical Testing. Within 45 days of receipt of this Order, SGR
must complete mechanical and metallurgical testing and failure analysis of the failed pipe,
including an analysis of soil samples and any foreign materials. The testing and analysis must
be completed as follows:
a. Document the chain-of-custody when handling and transporting the failed pipe
section and other evidence from the Failure site.
b. Within 10 days of receipt of this Order, develop and submit the testing protocol and
the proposed testing laboratory to the Director for prior approval.
c. Prior to beginning the mechanical and metallurgical testing, provide the Director
with the scheduled date, time, and location of the testing to allow for an OPS
representative to witness the testing.
d. Ensure the testing laboratory distributes all reports whether draft or final in their
entirety to the Director at the same time they are made available to SGR.
11. Root Cause Failure Analysis. Within 90 days following receipt of this Order, SGR must
complete a root cause failure analysis (RCFA) and submit a final report of this RCFA to the
Director. The RCFA must be supplemented or facilitated by an independent third-party
approved by the Director and must document the decision-making process and all factors
contributing to the failure. SGR must ensure that all reports, whether draft or final, are made
available in their entirety to the Director at the same time they are made available to SGR. The
final report must include findings and any lessons learned and whether the findings and any
lessons learned are applicable to other locations within SGR’s pipeline system.



12. Leak Detection Plan. Within 45 days of receipt of this Order, SGR shall perform a review
and submit to the Director a written plan to improve the leak detection capability on the
Affected Segment. The review must include a comprehensive analysis of any SCADA, leak
detection, surveillance, and other monitoring systems on the Affected Segment. The written
plan must include a schedule for improving the leak detection capability on the Affected
Segment through additional instrumentation, updated hardware or software, installation of a
computational pipeline monitoring system and associated software programming, additional
surveillance, pipeline control staffing, ongoing leak surveys, and any other appropriate
measures.
13. Emergency Response Plan and Training Review. SGR must review and assess the
effectiveness of its emergency response plan with regards to the Failure. The review and
assessment must include the on-scene response and support, coordination, and communication
with emergency responders and public officials. SGR must also include a review and
assessment of the effectiveness of its emergency training program. SGR must amend its
emergency response plan and emergency training, if necessary, to reflect the results of this
review. The documentation of this Emergency Response Plan and Training Review must be
available for inspection by OPS or provided to the Director, if requested.
14. Remedial Work Plan (RWP).
a. Within 90 days following receipt of this Order, SGR must submit a Remedial
Work Plan (RWP) to the Director for approval.
b. The Director may approve the RWP incrementally without approving the entire
RWP.
c. Once approved by the Director, the RWP will be incorporated by reference into this
Order.
d. The RWP must specify the tests, inspections, assessments, evaluations, and remedial
measures SGR will use to verify the integrity of the Affected Segment. It must
address all known or suspected factors and causes of the Failure identified by, but
not limited to, the results of the metallurgical and root cause failure analysis required
by this Order. SGR should consider both the risk of another failure and the
consequence of another failure to develop a prioritized schedule for RWP related
work along the Affected Segment.
e. The RWP must include a procedure or process to:
i. Identify pipe, both facility and mainline, in the Affected Segment with
characteristics similar to the contributing factors identified for the Failure,
to include operational or maintenance factors.
ii. Gather all data necessary to review the failure history (in service and
pressure test failures) of the Affected Segment and to prepare a written
report containing all the available information such as the locations, dates,
and causes of leaks and failures.
iii. Integrate the results of the metallurgical testing, root cause failure analysis,
and other corrective actions required by this Order with all relevant pre-
existing operational and assessment data for the Affected Segment. Pre-
existing operational data includes, but is not limited to, construction,



operations, maintenance, testing, repairs, prior metallurgical analyses, and
any third-party consultation information. Pre-existing assessment data
includes, but is not limited to, ILI tool runs, hydrostatic pressure testing,
direct assessments, close interval surveys, and Direct Current Voltage
Gradient/Alternating Current Voltage Gradient surveys.
iv. Determine if conditions similar to those contributing to the Failure, to
include operational or maintenance conditions, are likely to exist elsewhere
on the Affected Segment.
v. Conduct additional field tests, inspections, assessments, and evaluations to
determine whether, and to what extent, the conditions associated with the
Failure and other failures from the failure history (see (e)(ii) above) or any
other integrity threats are present elsewhere on the Affected Segment. At a
minimum, this process must consider all failure causes and specify the use
of one or more of the following:
1) ILI tools that are technically appropriate for assessing the pipeline
system based on the cause of the Failure and that can reliably detect
and identify anomalies,
2) Hydrostatic pressure testing,
3) Close-interval surveys,
4) Cathodic protection surveys, to include interference surveys in
coordination with other utilities (e.g. underground utilities,
overhead power lines, etc.) in the area,
5) Coating surveys,
6) Stress corrosion cracking surveys,
7) Selective seam corrosion surveys; and,
8) Other tests, inspections, assessments, and evaluations appropriate
for the Failure causes.
Note: SGR may use the results of previous tests, inspections,
assessments, and evaluations if approved by the Director,
provided the results of the tests, inspections, assessments,
and evaluations are analyzed with regard to the factors
known or suspected to have caused the Failure.
vi. Describe the inspection and repair criteria SGR will use to prioritize,
excavate, evaluate, and repair anomalies, imperfections, and other
identified integrity threats. Include a description of how any defects will
be graded and a schedule for repairs or replacement.
vii. Based on the known history and condition of the Affected Segment
describe the methods SGR will use to repair, replace, or take other
corrective measures, to include measures to update maintenance or
operational procedures that may have been causal factors of the Failure,
in order to remediate the conditions associated with the February 3, 2026,
pipeline failure and to address other known integrity threats along the
Affected Segment. The repair, replacement, or other corrective measures
must meet the criteria specified in (e)(vi) above.



viii. Implement continuing long-term periodic testing and integrity
verification
measures to ensure the ongoing safe operation of the Affected Segment
considering the results of the analyses, inspections, evaluations, and
corrective measures undertaken pursuant to the Order.
f. Include a proposed schedule for completion of the RWP.
g. SGR must revise the RWP as necessary to incorporate new information obtained
during the failure investigation and remedial activities, to incorporate the results of
actions undertaken pursuant to this Order, and to incorporate modifications required
by the Director. SGR must submit any plan revisions to the Director for prior
approval. The Director may approve plan revisions incrementally. Any and all
revisions to the RWP after it has been approved and incorporated by reference into
this Order will be fully described and documented in the CAO Documentation
Report.
h. SGR must implement the RWP as it is approved by the Director, including any
revisions to the plan.
15. CAO Documentation Report (CDR). SGR must create and revise, as necessary, a
CAO Documentation Report (CDR). When SGR has concluded all the items in this Order
it will submit the final CDR in its entirety to the Director. This will allow the Director to
complete a thorough review of all actions taken by SGR with regards to this Order prior
to approving the closure of this Order. The intent is for the CDR to summarize all activities
and documentation associated with this Order in one document.
a. The Director may approve the CDR incrementally without approving the entire
CDR.
b. Once approved by the Director, the CDR will be incorporated by reference into this
Order.
c. The CDR must include but not be limited to:
i. Table of Contents;
ii. Summary of the pipeline failure of February 3, 2026, and the response
activities;
iii. Summary of pipe data and properties and all prior assessments of the
Affected Segment;
iv. Summary of all tests, inspections, assessments, evaluations, and analysis
required by the Order;
v. Summary of the Mechanical and Metallurgical Testing as required by
the Order;
vi. Summary of the RCFA with all root causes as required by the Order;
vii. Documentation of all actions taken by SGR to implement the RWP, the
results of those actions, and the inspection and repair criteria used;
viii. Documentation of any revisions to the RWP including those necessary
to incorporate the results of actions undertaken pursuant to this Order
and whenever necessary to incorporate new information obtained
during the failure investigation and remedial activities;
ix. Lessons learned while completing this Order;
x. A path forward describing specific actions SGR will take on its entire



pipeline system as a result of the lessons learned from work on this
Order; and
xi. Appendices (if required).
Other Requirements:
16. Approvals. With respect to each submission under this Order that requires the approval of
the Director, the Director may: (a) approve, in whole or part, the submission; (b) approve the
submission on specified conditions; (c) modify the submission to cure any deficiencies; (d)
disapprove in whole or in part, the submission, directing that Respondent modify the
submission, or (e) any combination of the above. In the event of approval, approval upon
conditions, or modification by the Director, Respondent shall proceed to take all action
required by the submission as approved or modified by the Director. If the Director
disapproves all or any portion of the submission, Respondent must correct all deficiencies
within the time specified by the Director and resubmit it for approval.
17. Extensions of Time. The Director may grant an extension of time for compliance with
any of the terms of this Order upon a written request timely submitted demonstrating good
cause for an extension.
18. Reporting. SGR must submit quarterly reports to the Director that: (1) include all
available data and results of the testing and evaluations required by this Order; and (2) describe
the progress of the repairs or other remedial actions being undertaken. The first quarterly report
is due on April 1, 2026, covering the period through March 15, 2026. The Director may change
the interval for the submission of these reports.
19. Documentation of the Costs. It is requested that Respondent maintain documentation of
the costs associated with implementation of this CAO. Include in each quarterly report
submitted the to-date total costs associated with: (1) preparation and revision of procedures,
studies, and analyses; (2) physical changes to pipeline infrastructure, including repairs,
replacements, and other modifications; and (3) environmental remediation, if applicable.
Be advised that all material submitted in response to this enforcement action is subject to being
made publicly available. If you believe that any portion of your responsive material qualifies for
confidential treatment under 5 U.S.C. § 552(b), along with the complete original document you
must provide a second copy of the document with the portions you believe qualify for confidential
treatment redacted and an explanation of why you believe the redacted information qualifies for
confidential treatment under 5 U.S.C. § 552(b).
In your correspondence on this matter, please refer to “CPF No. 2-2026-004-CAO” and for each
document you submit, please provide a copy in electronic format whenever possible. The actions
required by this Order are in addition to and do not waive any requirements that apply to
Respondent’s pipeline system under 49 CFR Parts 190 through 199, under any other order issued
to Respondent under authority of 49 U.S.C. Chapter 601, or under any other provision of federal
or state law.



Respondent may appeal any decision of the Director to the Associate Administrator for Pipeline
Safety. Decisions of the Associate Administrator shall be final.
Failure to comply with this Order may result in the assessment of civil penalties and in referral to
the Attorney General for appropriate relief in United States District Court pursuant to 49 U.S.C.
§ 60120.
The terms and conditions of this Order are effective upon service in accordance with 49 CFR
§ 190.5.
__________________________ _______________________
Linda Daugherty Date Issued
Acting Associate Administrator
for Pipeline Safety

## Provenance

- Official: Yes
- Source: <https://primis.phmsa.dot.gov/enforcement-data/case/22026004CAO>
- Source ID: `phmsa-enforcement`
- SHA-256: `96805f344419b018150463318b67277e9d989a1934109a8303347ad857985b15`
- Retrieved: 2026-08-20T04:44:44.458Z
- Exported: 2026-08-23T16:26:42.342Z
- Document slug: `phmsa-enforcement-22026004cao`

### Source metadata

```json
{
  "cpf": "22026004CAO",
  "operator": "SG RESOURCES MISSISSIPPI, LLC",
  "region": "Southern",
  "pipelineType": "INTERSTATE GAS TRANSMISSION",
  "caseStatus": "OPEN",
  "citedSections": [],
  "dataAsOf": "08/04/2026 12PM",
  "caseDataAsOf": "2026-08-04",
  "attachmentCount": 4,
  "attachments": [
    {
      "name": "22026004CAO_Corrective Action Order (AMENDED)_03022026_(26-363868).pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/22026004CAO/22026004CAO_Corrective%20Action%20Order%20(AMENDED)_03022026_(26-363868).pdf",
      "bytes": 311017,
      "category": "agency_document"
    },
    {
      "name": "22026004CAO_Corrective Action Order (AMENDED)_03022026_(26-363868)_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/22026004CAO/22026004CAO_Corrective%20Action%20Order%20(AMENDED)_03022026_(26-363868)_text.pdf",
      "bytes": 284431,
      "category": "agency_document"
    },
    {
      "name": "22026004CAO_Corrective Action Order_02062026_(26-363868).pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/22026004CAO/22026004CAO_Corrective%20Action%20Order_02062026_(26-363868).pdf",
      "bytes": 267301,
      "category": "agency_document"
    },
    {
      "name": "22026004CAO_Corrective Action Order_02062026_(26-363868)_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/22026004CAO/22026004CAO_Corrective%20Action%20Order_02062026_(26-363868)_text.pdf",
      "bytes": 282175,
      "category": "agency_document"
    }
  ],
  "extractedAgencyDocumentCount": 2,
  "attachmentPolicy": "Official attachment links are retained. Agency-issued documents may also include a verified local PDF and page-level text representation.",
  "jurisdiction": "US",
  "operatorName": "SG RESOURCES MISSISSIPPI, LLC"
}
```