# TENNESSEE GAS PIPELINE COMPANY — Safety Order

**Citation:** CPF 320111001S  
**Type / status:** enforcement / historical  
**Agency:** Pipeline and Hazardous Materials Safety Administration  
**Effective:** Not stated  
**Published:** 2011-03-11

CLOSED safety order.

## Document text

Safety Order involving TENNESSEE GAS PIPELINE COMPANY. The dataset does not identify a cited regulation for this case. The case was opened on 2011-03-11 and is reported as closed as of 2016-04-01. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

320111001S_Closure Letter_04012016.pdf: https://primis.phmsa.dot.gov/enforcement-documents/320111001S/320111001S_Closure%20Letter_04012016.pdf

320111001S_Closure Letter_04012016_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/320111001S/320111001S_Closure%20Letter_04012016_text.pdf

320111001S_Consent Agreement_03312011.pdf: https://primis.phmsa.dot.gov/enforcement-documents/320111001S/320111001S_Consent%20Agreement_03312011.pdf

320111001S_Consent Agreement_03312011_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/320111001S/320111001S_Consent%20Agreement_03312011_text.pdf

320111001S_Consent Order_03312011.pdf: https://primis.phmsa.dot.gov/enforcement-documents/320111001S/320111001S_Consent%20Order_03312011.pdf

320111001S_Consent Order_03312011_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/320111001S/320111001S_Consent%20Order_03312011_text.pdf

320111001S_NOPSO_03112011.pdf: https://primis.phmsa.dot.gov/enforcement-documents/320111001S/320111001S_NOPSO_03112011.pdf

320111001S_NOPSO_03112011_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/320111001S/320111001S_NOPSO_03112011_text.pdf

320111001S_Closure Letter_04012016_text.pdf

CERTIFIED MAIL - RETURN RECEIPT REQUESTED
April 1, 2016
Mr. Gary Buchler
Chief Operating Officer (COO)
Natural Gas Pipelines Group
Tennessee Gas Pipeline Company
1001 Louisiana Street
Suite 1000
Houston, Texas 77002
CPF 3-2011-1001S
Dear Mr. Buchler:
On March 11, 2011, the Pipeline and Hazardous Materials Safety Administration (PHMSA)
issued to Tennessee Gas Pipeline Company (TGP) a Notice of Proposed Safety Order in the
above-referenced case. PHMSA and TGP then entered into a Consent Agreement and
Order (Order) on March 31, 2011. This Order included required actions to be taken on and
along your pipeline. Based on our review of the documentation you provided, it has been
determined that you have complied with the terms of this Order.
Accordingly, this case is now closed. Thank you for your cooperation in this matter.
Sincerely,
Allan C. Beshore
Director, Central Region, OPS
Pipeline and Hazardous Materials Safety Administration

320111001S_Consent Agreement_03312011_text.pdf

MAR 31 2011
DEPARTMENT OF TRANSPORTATION
PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION
OFFICE OF PIPELINE SAFETY
WASHINGTON, DC 20590
____________________________________
In the Matter of )
Tennessee Gas Pipeline Company ) CPF No. 3-2011-1001S
)
)
)
Respondent )
____________________________________)
CONSENT AGREEMENT
On March 11, 2011, the Pipeline and Hazardous Materials Safety Administration
(PHMSA), U.S. Department of Transportation, issued a Notice of Proposed Safety Order
(Notice) to Tennessee Gas Pipeline Company (Respondent). The Notice alleges that
certain segments of Respondent’s natural gas pipeline system designated as the Line 200
Pipeline System have an apparent condition or conditions that, without corrective
measures, would pose a pipeline integrity risk to public safety, property, or the
environment. Specifically, the Notice alleges that the conditions that caused the February
10, 2011 failure on Line 200-4 in mainline valve section 214 (Line Section 214-4)
approximately 2.5 miles southeast of the town of Hanoverton, Ohio, and the March 1,
2011 failure on Line 200-1 in mainline valve section 209 (Line Section 209-1)
approximately ½ mile downstream of Compressor Station 209 demonstrate the presence
of integrity risks on those segments of Lines 200-1, 200-2, 200-3, and 200-4 running
from Compressor Station 200 to Compressor Station 219 including the Pittsburg Spur
(the “Affected Segments”).
Between March 1 and March 18, 2011, Respondent and PHMSA engaged in good faith
settlement discussions resulting in this Consent Agreement (the “Agreement”).
Having agreed that settlement of this proceeding will avoid further administrative
proceedings or litigation and that entry of this Consent Agreement is the most appropriate
means of resolving the Notice, pursuant to 49 C.F.R. Part 190, without adjudication of
any issue of fact or law, and upon consent and agreement of Respondent and PHMSA
(“the Parties”), the Parties agree as follows:



I. General Provisions
1. Respondent acknowledges that as operator of the Line 200 Pipeline System,
Respondent and its pipeline system are subject to the jurisdiction of the Federal pipeline
safety laws, 49 U.S.C. 60101 et seq., and the regulations and administrative orders issued
thereunder. For purposes of this Consent Agreement, Respondent acknowledges that it
received proper notice of PHMSA’s action in this proceeding and that the Notice states
claims upon which relief may be granted pursuant to 49 U.S.C. 60101 et seq. and the
regulations and orders issued thereunder.
2. Respondent agrees, for purposes of this proceeding, that the integrity risk
identified in the Notice exists in the Affected Segments and agrees to address it by
completing the actions specified in Section II of this Consent Agreement (“Work to be
Performed”), including the actions set forth in any work plans and schedules each of
which shall automatically be incorporated into this agreement upon approval. This
Consent Agreement does not constitute a finding of violation of any Federal law or
regulation and may not be used in any civil proceeding of any kind as evidence or proof
of any fact, fault or liability, or as evidence of the violation of any law, rule, regulation or
requirement, except in a proceeding to enforce the provisions of this Agreement.
3. After Respondent returns this signed Consent Agreement, PHMSA’s
representative will present it to the Associate Administrator for Pipeline Safety
recommending that the Associate Administrator adopt the terms of this Agreement by
issuing an administrative order (Consent Order) incorporating the terms of this Consent
Agreement. The terms of this Consent Agreement constitute an offer of settlement until
accepted by the Associate Administrator. Upon the effective date of this Agreement, any
request for a hearing submitted by Respondent shall be automatically withdrawn.
4. Respondent consents to the issuance of the Consent Order, and hereby waives any
further procedural requirements with respect to its issuance. Except as provided in Item
27 and Section IV of this Agreement, Respondent waives all rights to contest the
adequacy of notice, or the validity of the Consent Order or this Consent Agreement,
including all rights to administrative or judicial hearings or appeals.
5. This Consent Agreement shall apply to and be binding upon PHMSA, and upon
Respondent, its officers, directors, and employees, and its successors, assigns, or other
entities or persons otherwise bound by law. Respondent agrees to provide a copy of this
Consent Agreement and any incorporated work plans and schedules to all of
Respondent’s officers, employees, and agents whose duties might reasonably include
compliance with this Agreement.
6. For all transfers of ownership or operating responsibility of the Affected
Segments, Respondent shall provide a copy of this Consent Agreement to the prospective
transferee at least 30 days prior to such transfer and simultaneously provide written
notice of the prospective transfer to the PHMSA Central Region Director (Director).2



7. This Consent Agreement constitutes the final, complete and exclusive agreement
and understanding between the Parties with respect to the settlement embodied in this
Agreement, and the Parties acknowledge that there are no representations, agreements or
understandings relating to the settlement other than those expressly contained in this
Agreement, except that the terms of this Agreement may be construed by reference to the
Notice.
8. Nothing in this Consent Agreement affects or relieves Respondent of its
responsibility to comply with all applicable requirements of the Federal pipeline safety
laws, 49 U.S.C. § 60101 et seq., and the regulations and orders issued thereunder.
Nothing in this Consent Agreement alters PHMSA’s right of access, entry, inspection,
and information gathering or PHMSA’s authority to bring enforcement actions against
Respondent pursuant to the Federal pipeline safety laws, the regulations and orders issued
thereunder, or any other provision of Federal or State law.
9. This Consent Agreement does not waive or modify any Federal, State, or local
laws or regulations that are applicable to Respondent’s pipeline systems. This Consent
Agreement is not a permit, or a modification of any permit, under any Federal, State, or
local laws or regulations. Respondent remains responsible for achieving and maintaining
compliance with all applicable Federal, State, and local laws, regulations and permits.
10. This Consent Agreement does not create rights in, or grant any cause of action to,
any third party not party to this Agreement. The U.S. Department of Transportation is
not liable for any injuries or damages to persons or property arising from acts or
omissions of Respondent or its officers, employees, or agents carrying out the work
required by this Consent Agreement. Respondent agrees to indemnify and hold harmless
the U.S. Department of Transportation, its officers, employees, agents, and
representatives form any and all causes of action arising from any acts or omissions of
Respondent or its contractors in carrying out the work required by this Agreement.
II. Work to be Performed
11. Prior to resuming operation of Line 200-4 from MLV 214-4 to MLV 216-4,
develop and submit a written restart plan for approval by the Director for this segment.
The restart plan must provide for adequate patrolling of the pipeline during the restart
process, specify a daylight restart, include a hydrostatic test of section MLV 214-4 to
MLV 215-4, and detail advance communications with local emergency response officials.
The restart plan must include actions taken prior to restart by Respondent to confirm the
integrity of pipeline facilities that were damaged, or were suspected to be damaged, as a
result of the incident.
12. After receiving approval from the Director to restart, the Line 200-4 operating
pressure from MLV 214-4 to MLV 216-4 must not exceed 80% of the actual operating
pressure in effect immediately prior to the February 10, 2011, failure. Specifically, the
discharge pressure at the Carrollton Compressor Station into Line 200-4 must not exceed3



586 psig. This pressure reduction requires any relevant remote or local alarm limits,
software programming set-points or control points, and mechanical over pressure devices
to be adjusted accordingly. Prior to restart, identification of all auto-close valve locations
will be communicated to the controllers. The pressure restriction must remain in effect
until written approval to increase the pressure or return the pipeline to its pre-failure
operating pressure is obtained from the Director as set forth in Item 25. If the results of
any action undertaken pursuant to this Agreement necessitate a reduction in the operating
pressure permitted by the Agreement, Respondent must further reduce the operating
pressure accordingly and notify the Director.
13. Prior to resuming operation of the Line 200-1 from MLV 209-1 to MLV 210-1,
develop and submit a written restart plan for approval by the Director for this segment.
The restart plan must provide for adequate patrolling of the pipeline during the restart
process, specify a daylight restart, and detail advance communications with local
emergency response officials.
14. After receiving approval from the Director to restart, the Line 200-1 operating
pressure from MLV 209-1 to MLV 210-1 must not exceed 80% of the actual operating
pressure in effect immediately prior to the March 1, 2011, failure. Specifically, the
discharge pressure at the Station 209 into Line 200-1 must not exceed 567 psig. This
pressure reduction requires any relevant remote or local alarm limits, software
programming set-points or control points, and mechanical over pressure devices to be
adjusted accordingly. Prior to restart, identification of all auto-close valve locations will
be communicated to the controllers. The pressure restriction must remain in effect until
written approval to increase the pressure or return the pipeline to its pre-failure operating
pressure is obtained from the Director as set forth in Item 25. If the results of any action
undertaken pursuant to this Consent Agreement necessitate a reduction in the operating
pressure permitted by this Agreement, Respondent must further reduce the operating
pressure accordingly and notify the Director.
15. Within 15 days of receipt of the Consent Order, submit a written plan to conduct
an airborne instrumented leak survey of the Affected Segments to the Director detailing
the schedule for the expeditious completion of the leak survey within 30 days of initiating
the survey. The plan must include a summary report detailing the findings of the leak
survey to be provided directly from the airborne instrumented leak survey provider to the
Director. This summary report must include a description of any elements affecting the
leak survey data, area covered and associated ranges of the leak survey findings (height
of flight and width of area surveyed), verification that all of the pipeline corridors
traversed by the Affected Segments including the areas associated with crossover piping
located between the Affected Segments has been reviewed, and any other items of
significance such as accuracy of the instrumentation or malfunction of equipment. The
Director is to receive distribution of all resulting reports in their entirety, including all
media, whether draft or final, at the same time they are made available to Respondent.
Submit a separate report detailing the schedule of planned maintenance activities to
occur as a result of the leak survey for the Affected Segments.4



Continue to perform patrol surveillance activities at periods of 2 times per month for
pipe Sections MLV 209-1 to MLV 214-1 and MLV 214-4 to MLV 219-4 until approved
otherwise by the Director.
16. Within 45 days of the Director’s approval of testing protocols, complete third-
party mechanical and metallurgical testing and failure analysis of the Line 200-4 failed
pipe and the additional girth weld containing a crack-like indication (606+35.8) that was
located upstream of the failed weld. The Line 200-1 failed girth weld and 2 additional
girth welds adjacent to the failed weld shall also be subjected to metallurgical testing and
failure analysis. The testing and analysis must be completed as follows:
(A) Document the chain of custody when handling and transporting the failed pipe
section and other evidence originating from the failure site;
(B) Utilize mechanical and metallurgical testing protocols, including selection of the
testing laboratory, approved by the Director;
(C) Prior to commencing the mechanical and metallurgical testing, provide the
Director with the scheduled date, time, and location of the testing to allow a
PHMSA representative to witness the testing; and
(D) Ensure that the testing laboratory distributes all resulting reports in their entirety,
including all media, whether draft or final, to the Director at the same time they
are made available to Respondent.
17. Conduct an evaluation of previous in-line inspection (ILI) results (including raw
data) of the failed girth weld and the girth weld with a crack-like indication (606+35.8) to
establish ILI capability for detecting and identifying girth weld features or anomalies
include review and reporting by the ILI vendors’ analysts as follows:
(A) Within 30 days of receipt of the Consent Order, re-evaluate the 2005 in-line
inspection results from MLV 214-4 to MLV 219-4 to determine whether any
features with similar characteristics to the feature at the failure site is present
elsewhere in this portion of Line 200-4.
(B) Within 60 days of receipt of the Consent Order, re-evaluate all ILI data available
for the Affected Segments to determine if any features with similar characteristics
to those at the failure sites are present elsewhere on the Affected Segments.
18. Within 60 days of receipt of the Consent Order, perform in-line inspection on
Line 200-1 from MLV 209-1 to MLV 214-1 and specifically evaluate girth weld ILI data.
The data analysis must be completed within 30 days of successful completion of the ILI.
The ILI vendor shall evaluate the results per a performance specification specific to girth
weld anomalies.
5



19. Within 90 days of receipt of the Consent Order, submit a report to the Director
that provides a detailed review of all SCADA activities on Lines 200-1 and 200-4 that
relate to the March 1 and February 10, 2011, incidents. SCADA enhancements identified
during this review shall be included in the report, which will include approximate
timelines for implementation of such enhancements. Activities reviewed and summarized
in the report must include, but may not be limited to: controller actions on the day before
the incident, day of the incident, and day after the incident; maintenance activities (same
three days); controller notes or logs (same three days); actual and calculated
instrumentation readings (same three days); available communication statistics (same
three days, including pressure and flow value poll times); other SCADA equipment
functions (same three days); and SCADA maintenance requests and status (during the 6
months preceding the incident). The report should also include a review of 30 days of
detailed pressure information to document any changes in operating conditions since
February 10, 2011. The report should provide a specific summary regarding whether or
not the controllers had adequate information to recognize an abnormal operating
condition on either event date in the control room. If adequate information did not exist
to recognize these conditions, identify enhancements for the SCADA activities that could
provide the necessary data and allow for controller recognition.
20. Within 120 days of receipt of the Consent Order, develop and submit to the
Director for prior approval a Remedial Work Plan (“Work Plan”) that includes corrective
measures. The work plan must provide for the verification of the integrity of the
Affected Segments and must fully address all known or suspected factors that caused or
contributed to the February 10, and March 1, 2011, incidents, including, but not limited
to:
(A) The integration of the information developed from the actions required by this
Consent Agreement with all historical construction, operating, maintenance,
testing, and assessment data for the Affected Segments as follows:
(i) Within 90 days of receipt of the Consent Order complete a root cause
failure analysis for the February 10, 2011 (Line 200-4), and March 1, 2011
(Line 200-1) incidents that is supplemented and facilitated by an
independent third-party acceptable to the Director. Elements of the root
cause analysis must include, but may not be limited to: scoping document
of the root cause analysis; procedures associated with root cause analysis;
multiple methods used for the analysis and updates on each method as it
progresses; contributory factors; documentation of the decision making
process; and a final report of the root cause process results including any
lessons learned and whether the findings are applicable to other locations
within the Respondent’s system. To the extent that the findings from the
root cause analysis or other analysis conducted pursuant to this Agreement
are applicable to other segments or facilities processes, procedures, or
programs across the Respondent’s systems (including Respondent’s gas
control processes or SCADA system), Respondent shall develop and
submit a plan with activity identified timelines to apply the lessons learned6



and implement any applicable remedial actions taken on the Affected
Segments to those other segments, facilities, systems processes,
procedures or programs.
(ii) No longer than 30 days after the completion of the root cause failure
analysis, integrate the findings of the root cause failure analysis into other
data integration efforts and the remedial work plan.
(B) The performance of additional field testing, inspections, and evaluations to
determine whether and to what extent the conditions associated with the failures,
or any other integrity-threatening conditions are present elsewhere on theAffected
Segments. Data-gathering activities must include a review of the failure history
(in service and pressure test failures) of the Affected Segments and development
of a written report containing all available information regarding locations, dates,
and causes of failures. Include a detailed description of Respondent’s plan to
confirm the integrity of the applicable sections of the Affected Segments,
including the criteria to be used for the evaluation and prioritization of any
integrity threats and anomalies that are identified. Make the results of the actions
required by this provision available to the Director;
(C) The performance of repairs or other corrective measures that fully remediate the
condition(s) associated with the pipeline failures and any other integrity-
threatening condition everywhere along the Affected Segments where such
conditions are identified by the evaluation process. Include a detailed description
of the repair criteria and method(s) to be used in undertaking any repairs or other
remedial actions;
(D) Provisions for continuing long-term periodic testing and integrity verification
measures to ensure the ongoing safe operation of the Affected Segments
considering the results of the analyses, inspections, and corrective measures
undertaken pursuant to the Consent Order; and
(E) A proposed risk based schedule for completion of the actions required by
paragraphs (A) through (D) of this Item, including a schedule associated with all
elements of the internal root cause analysis. Provide the Director with reasonable
advance notice of scheduled repairs.
21. The remedial work plan becomes incorporated into this Consent Agreement and
must be revised as necessary to incorporate the results of actions undertaken pursuant to
this Agreement and whenever necessary to incorporate new information obtained during
the failure investigation and remedial activities. Submit any such plan revisions to the
Director for prior approval. The Director may approve plan elements incrementally.
22. Implement the Remedial Work Plan as it is approved by the Director, including
any revisions to the plan. The results of all actions taken in accordance with the
approved plan must be available for review by PHMSA or its representative.7



23. Submit monthly reports to the Director that: (1) include available data and results
of the testing and evaluations required by this Consent Agreement; and (2) describe the
progress of the repairs and other actions being undertaken as a result of this Agreement.
The first monthly report is due on the last day of the month following receipt of the
Consent Order. The regular intervals for submitting reports may be adjusted with prior
approval of the Director.
24. Respondent agrees to maintain documentation of the costs associated with
implementation of this Consent Agreement, and include in each report submitted
pursuant to Item 23, the to-date total costs associated with: (1) preparation and revision of
procedures, studies and analyses; (2) physical changes to pipeline infrastructure,
including repairs, replacements and other modifications; and (3) environmental
remediation, if applicable.
25. The Director may allow the removal or modification of the pressure restriction set
forth in Items 12 and 14 upon a written request from Respondent demonstrating that the
hazard has been abated and that restoring the pipeline, or portion thereof, to its pre-failure
operating pressure is justified based on a reliable engineering analysis showing that the
pressure increase is safe considering all known defects, anomalies, and operating
parameters of the pipeline.
26. The Director may grant an extension of time for compliance with any of the terms
of this Consent Agreement upon a written request timely submitted demonstrating good
cause for an extension.
27. Respondent may appeal any decision of the Director to the Associate
Administrator for Pipeline Safety. Decisions of the Associate Administrator are final.
III. Review and Approval Process
28. With respect to any submission under Section II of this Consent Agreement that
requires the approval of the Director, the Director may: (a) approve, in whole or in part,
the submission, (b) approve the submission on specified conditions, (c) disapprove, in
whole or in part, the submission, or (d) any combination of the foregoing. In the event of
approval, approval in part, or approval upon conditions, Respondent will proceed to take
all action required by the submission as approved by the Director, subject to
Respondent’s right to invoke the dispute resolution procedures in Section IV with respect
to any conditions identified by the Director. In the event that the Director disapproves all
or any portion of the submission, the Director will provide Respondent with a written
notice of the deficiencies. Respondent will correct all deficiencies within the time
specified by the Director and resubmit it for approval.
IV. Dispute Resolution
8



29. The Director and Respondent will informally attempt to resolve any disputes
arising under this Consent Agreement. If Respondent and the Director are unable to
informally resolve the dispute within 15 days, Respondent may request in writing, within
10 days, a written determination resolving the dispute from the Associate Administrator
for Pipeline Safety providing all information that Respondent believes is relevant to the
dispute. If the request is submitted as provided herein, the Associate Administrator will
issue a determination in writing which shall be final. The existence of a dispute and
PHMSA’s consideration of matters placed in dispute shall not excuse, toll, or suspend
any term or timeframe for completion of any work to be performed under this Consent
Agreement during the pendency of the dispute resolution process except as agreed by the
Director or the Associate Administrator in writing.
V. Enforcement
30. This Consent Agreement, as adopted by the Consent Order, is subject to all
enforcement authorities available to PHMSA under 49 U.S.C. § 60101 et seq. and 49
C.F.R. Part 190, including administrative civil penalties under § 60122 of up to $100,000
per violation for each day the non-compliance continues, if PHMSA determines that
Respondent is not materially proceeding in accordance with terms of this Agreement,
with determinations made by the Director, or if such determinations are appealed with
decisions of the Associate Administrator. All work plans and associated schedules set
forth or referenced in Section II shall be automatically incorporated into this Consent
Agreement and are enforceable in the same manner.
VI. Record Keeping and Information Disclosure
31. Respondent agrees to maintain records demonstrating compliance with all
requirements of this Consent Agreement for a period of at least five years following
completion of all work to be performed. For any reports, plans, or other deliverables
required to be submitted to PHMSA pursuant to this Consent Agreement, Respondent
may assert a claim of business confidentiality or other protections applicable to the
release of information by PHMSA, covering part or all of the information required to be
submitted to PHMSA pursuant to this Agreement in accordance with 49 C.F.R. Part 7.
The claim of confidentiality shall be marked in writing on each page, and shall include a
statement specifying the grounds for each claim of confidentially. PHMSA shall
determine release of any information submitted pursuant to this Consent Agreement in
accordance with 49 C.F.R. Part 7, the Freedom of Information Act, 5 U.S.C. § 552, DOT
and/or PHMSA policies, and other applicable regulations and Executive Orders.
VII. Effective Date
32. The “Effective Date” as used herein is the date on which this Consent Agreement
has been signed by both Respondent and PHMSA. Unless specified to the contrary, all
deadlines for actions required by this Agreement run from the Effective Date of this
Agreement.
9



VIII. Modification
33. The terms of this Consent Agreement may be modified by mutual agreement of
the Parties. Such modifications shall be in writing and shall be signed by both Parties.
IX. Termination
34. This Consent Agreement shall terminate upon the completion of all terms set
forth in Section II (Work to Be Performed). Respondent may request written
confirmation from PHMSA when this Agreement is terminated. To the extent ongoing
monitoring is required, PHMSA may terminate this Agreement with respect to all other
requirements with the exception of such monitoring. Nothing in this Agreement prevents
Respondent from completing any of the obligations earlier than the deadlines provided
for herein.
X. Ratification
35. The Parties’ undersigned representatives certify that they are fully authorized to
enter into the terms and conditions of this Consent Agreement and to execute and legally
bind such party to this document.
36. The Parties hereby agree to all conditions and terms of this Consent Agreement:
For PHMSA: For Respondent:
___________________________ ____________________________
Mr. David Barrett Mr. Jesus Soto, Jr.
Director, Central Region Vice-President
Pipeline and Hazardous Materials Tennessee Gas Pipeline Company
Safety Administration
_____________________ _____________________
Date Date
10

320111001S_Consent Order_03312011_text.pdf

MAR 31 2011
Mr. Jesus Soto, Jr.
Vice President, Operations Services
Tennessee Gas Pipeline Company
1001 Louisiana Street
P.O. Box 2511
Houston, TX 77252-2511
Re: CPF No. 3-2011-1001S
Dear Mr. Soto:
Enclosed please find a Consent Order incorporating the terms of the Consent Agreement that you
signed on March 24, 2011. Service of the Consent Order and Consent Agreement by certified
mail is deemed effective upon the date of mailing, or as otherwise provided under 49 C.F.R. §
190.5.
Thank you for your cooperation in this matter.
Sincerely,
Jeffrey D. Wiese
Associate Administrator
for Pipeline Safety
Enclosure
cc: Mr. David Barrett, Director, Central Region, PHMSA
Mr. Bill Cope, Vice President Eastern Operations, Tennessee Gas Pipeline Company
Ms. Elizabeth Herdes, Counsel for Tennessee Gas Pipeline Company
CERTIFIED MAIL - RETURN RECEIPT REQUESTED [7005 1160 0001 0073 9833]



DEPARTMENT OF TRANSPORTATION
PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION
OFFICE OF PIPELINE SAFETY
WASHINGTON, DC 20590
____________________________________
In the Matter of )
Tennessee Gas Pipeline Company, ) CPF No. 3-2011-1001S
)
)
)
Respondent. )
____________________________________)
CONSENT ORDER
On March 11, 2011, the Pipeline and Hazardous Materials Safety Administration (PHMSA)
Office of Pipeline Safety issued a Notice of Proposed Safety Order (Notice) to Tennessee Gas
Pipeline Company (Respondent) in this case.
In accordance with 49 C.F.R. § 190.239, the Notice alleged that certain segments of
Respondent’s natural gas pipeline system designated as the Line 200 Pipeline System have an
apparent condition or conditions that, without corrective measures, would pose a pipeline
integrity risk to public safety, property, or the environment. Specifically, the Notice alleged that
the conditions that caused the February 10, 2011 failure on Line 200-4 in mainline valve section
214 (Line Section 214-4) approximately 2.5 miles southeast of the town of Hanoverton, Ohio,
and the March 1, 2011 failure on Line 200-1 in mainline valve section 209 (Line Section 209-1)
approximately 0.5 miles downstream of Compressor Station 209, demonstrated the presence of
integrity risks on those segments of Lines 200-1, 200-2, 200-3, and 200-4 running from
Compressor Station 200 to Compressor Station 219 including the Pittsburg Spur (the “Affected
Segments”). The Notice proposed that Respondent take certain actions to address these
conditions.
In response to the Notice, Respondent and PHMSA engaged in good faith settlement discussions
resulting in the Consent Agreement attached to this Order that settles all of the allegations in the
Notice.
Accordingly, the foregoing Consent Agreement is hereby approved and incorporated by
reference into this Order. Tennessee Gas Pipeline Company is hereby ordered to comply with
the terms of the Consent Agreement, effective immediately.



Pursuant to 49 U.S.C. 60101 et seq. and 49 C.F.R. § 190.221, failure to comply with this Consent
Order may result in the assessment of administrative civil penalties of up to $100,000 per
violation per day, or in the referral of the case for judicial enforcement. The terms and
conditions of this Consent Order are effective upon service in accordance with 49 C.F.R.
§ 190.5.
____________________________________ _________________
Jeffrey D. Wiese Date Issued
Associate Administrator
for Pipeline Safety

## Provenance

- Official: Yes
- Source: <https://primis.phmsa.dot.gov/enforcement-data/case/320111001S>
- Source ID: `phmsa-enforcement`
- SHA-256: `cbe5a3a5679d906caf14aa7d0d42bb719ff98a1aec6e8d634158e768492c6628`
- Retrieved: 2026-08-20T04:44:44.458Z
- Exported: 2026-08-23T16:16:35.220Z
- Document slug: `phmsa-enforcement-320111001s`

### Source metadata

```json
{
  "cpf": "320111001S",
  "operator": "TENNESSEE GAS PIPELINE COMPANY",
  "region": "Central",
  "pipelineType": "GAS INTERSTATE ONSHORE",
  "caseStatus": "CLOSED",
  "citedSections": [],
  "dataAsOf": "08/04/2026 12PM",
  "caseDataAsOf": "2026-08-04",
  "attachmentCount": 8,
  "attachments": [
    {
      "name": "320111001S_Closure Letter_04012016.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/320111001S/320111001S_Closure%20Letter_04012016.pdf",
      "bytes": 329099,
      "category": "agency_document"
    },
    {
      "name": "320111001S_Closure Letter_04012016_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/320111001S/320111001S_Closure%20Letter_04012016_text.pdf",
      "bytes": 4488,
      "category": "agency_document"
    },
    {
      "name": "320111001S_Consent Agreement_03312011.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/320111001S/320111001S_Consent%20Agreement_03312011.pdf",
      "bytes": 520757,
      "category": "agency_document"
    },
    {
      "name": "320111001S_Consent Agreement_03312011_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/320111001S/320111001S_Consent%20Agreement_03312011_text.pdf",
      "bytes": 51735,
      "category": "agency_document"
    },
    {
      "name": "320111001S_Consent Order_03312011.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/320111001S/320111001S_Consent%20Order_03312011.pdf",
      "bytes": 106782,
      "category": "agency_document"
    },
    {
      "name": "320111001S_Consent Order_03312011_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/320111001S/320111001S_Consent%20Order_03312011_text.pdf",
      "bytes": 14765,
      "category": "agency_document"
    },
    {
      "name": "320111001S_NOPSO_03112011.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/320111001S/320111001S_NOPSO_03112011.pdf",
      "bytes": 1056840,
      "category": "case_document"
    },
    {
      "name": "320111001S_NOPSO_03112011_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/320111001S/320111001S_NOPSO_03112011_text.pdf",
      "bytes": 69534,
      "category": "case_document"
    }
  ],
  "extractedAgencyDocumentCount": 3,
  "attachmentPolicy": "Official attachment links are retained. Agency-issued documents may also include a verified local PDF and page-level text representation.",
  "jurisdiction": "US",
  "operatorName": "TENNESSEE GAS PIPELINE COMPANY"
}
```
