# TRANSCANADA NORTHERN BORDER INC — Warning Letter

**Citation:** CPF 320111002W  
**Type / status:** enforcement / historical  
**Agency:** Pipeline and Hazardous Materials Safety Administration  
**Effective:** Not stated  
**Published:** 2011-03-21

CLOSED warning letter citing 192.328(a)(1), 192.328(a)(2), 192.807.

## Document text

Warning Letter involving TRANSCANADA NORTHERN BORDER INC. PHMSA's enforcement data identifies the cited regulations as 192.328(a)(1),  192.328(a)(2),  192.807. The case was opened on 2011-03-21 and is reported as closed as of 2011-03-21. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

320111002W_Warning Letter_03212011.pdf: https://primis.phmsa.dot.gov/enforcement-documents/320111002W/320111002W_Warning%20Letter_03212011.pdf

320111002W_Warning Letter_03212011_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/320111002W/320111002W_Warning%20Letter_03212011_text.pdf

320111002W_Warning Letter_03212011_text.pdf

WARNING LETTER
CERTIFIED MAIL - RETURN RECEIPT REQUESTED
March 21, 2011
Mr. Vern Meier
Vice President, US Pipeline Operations
TransCanada
717 Texas Avenue
Houston, TX, 77002-2761
CPF 3-2011-1002W
Dear Mr. Meier:
During the second half of 2010, a representative of the Pipeline and Hazardous Materials Safety
Administration (PHMSA) pursuant to Chapter 601 of 49 United States Code inspected your
activities related to the TransCanada - Bison Project near Dickinson, North Dakota.
During the course of our construction inspections, the need for improvements in the quality
assurance plan, including personnel qualification, were identified. While no construction
activities affecting safety appeared to have gone uncorrected prior to placing the Bison pipeline
in service, it was apparent that an improved quality management system, if properly
implemented, would reduce the need for remedial work and improve overall quality during
construction.
Therefore, as a result of the inspection, it appears that you have committed probable violations of
the Pipeline Safety Regulations, Title 49, Code of Federal Regulations. The items inspected and
the probable violation(s) are:
1. § 192.328 Additional construction requirements for steel pipe using alternative
maximum allowable operating pressure. For a new or existing pipeline segment to
be eligible for operation at the alternative maximum allowable operating pressure
calculated under § 192.620, a segment must meet the following additional



construction requirements. Records must be maintained, for the useful life of the
pipeline, demonstrating compliance with these requirements:
(a)(1) Quality assurance. The construction of the pipeline segment must be done
under a quality assurance plan addressing pipe inspection, hauling and stringing,
field bending, welding, non-destructive examination of girth welds, applying and
testing field applied coating, lowering of the pipeline into the ditch, padding and
backfilling, and hydrostatic testing.
The document management procedures established for the project were not
followed completely. Various inspection procedures were modified throughout
the project, but not all construction inspectors received these documents. Assuring
all personnel are working with the most current procedures is an important aspect
of quality assurance to maintain consistency and repeatability.
The quality assurance plan in place for project was basically limited to inspection.
In addition to inspection activities the plan should have included elements
whereby “non-conformances”, when identified, would be analyzed to understand
the root causes so that improvements could be made to processes or procedures to
prevent recurrence. Additionally, lessons learned from previous TransCanada
construction projects should be considered when developing a quality assurance
plan.
The quality assurance plan did not include specific numerical acceptance criteria
for defect/repair rates. When unacceptable rates are noted this should initiate a re-
evaluation of processes and procedures and necessary modifications to maintain
consistent quality. In addition to acceptance criteria, the quality assurance plan
should include controls to reduce the variations in working conditions on a larger
scale construction project to maintain consistency and repeatability.
2. § 192.328 Additional construction requirements for steel pipe using alternative
maximum allowable operating pressure.
(a)(2) The quality assurance plan for applying and testing field applied coating to
girth welds must be:
(i) Equivalent to that required under § 192.112(f)(3) for pipe; and
(ii) Performed by an individual with the knowledge, skills, and ability to
assure effective coating application.
2



§ 192.112(f)(3) A quality assurance inspection and testing program for
the coating must cover the surface quality of the bare pipe, surface
cleanliness and chlorides, blast cleaning, application temperature
control, adhesion, cathodic disbondment, moisture permeation,
bending, coating thickness, holiday detection, and repair.
The construction project did not have an adequate quality inspection and testing
procedure for holiday detection of coatings during field construction. PHMSA
communicated expectations regarding holiday detection for Alternate Maximum
Operating Pressure pipelines on the publicly accessible website, “Standards for
Implementing Alternative MAOP for Gas Transmission Pipelines” at
http://primis.phmsa.dot.gov/maop/index.htm. The website included holiday
detection testing (revised June 11, 2010) to verify the quality of pipe coating.
TransCanada was aware of these expectations, yet continued to perform holiday
detection at lower than recommended voltages until September 9, 2010.
3. § 192.807 Recordkeeping. Each operator shall maintain records that demonstrate
compliance with this subpart.
(a) Qualification records shall include:
(1) Identification of qualified individual(s);
(2) Identification of the covered tasks the individual is qualified to perform;
(3) Date(s) of current qualification; and
(4) Qualification method(s).requirements for steel pipe using alternative
maximum allowable operating pressure.
The quality and accuracy of qualification records for individuals performing
covered tasks during the construction of an alternate MAOP pipeline were
deficient. During the field operator qualification (OQ) inspection, performed by a
PHMSA inspector on September 28, 2010, records of individuals provided by
representatives of Price Gregory, Pegasus and TransCanada personnel were
reviewed at the time of the inspection. During the review of OQ records, there
were discrepancies between those individuals who may have performed covered
tasks to those individuals qualified to perform covered tasks. A comprehensive
program began September 29, 2010 to correct these deficiencies.
Under 49 United States Code, § 60122, you are subject to a civil penalty not to exceed $100,000
for each violation for each day the violation persists up to a maximum of $1,000,000 for any
related series of violations. We have reviewed the circumstances and supporting documents
involved in this case, and have decided not to conduct additional enforcement action or penalty
assessment proceedings at this time. We advise you to correct the item(s) identified in this letter.
Failure to do so will result in TransCanada Bison Pipeline being subject to additional
enforcement action.
3



No reply to this letter is required. If you choose to reply, in your correspondence please refer to
CPF 3-2011-1002W. Be advised that all material you submit in response to this enforcement
action is subject to being made publicly available. If you believe that any portion of your
responsive material qualifies for confidential treatment under 5 U.S.C. 552(b), along with the
complete original document you must provide a second copy of the document with the portions
you believe qualify for confidential treatment redacted and an explanation of why you believe
the redacted information qualifies for confidential treatment under 5 U.S.C. 552(b).
Sincerely,
David Barrett
Director, Central Region
Pipeline and Hazardous Materials Safety Administration
4

## Provenance

- Official: Yes
- Source: <https://primis.phmsa.dot.gov/enforcement-data/case/320111002W>
- Source ID: `phmsa-enforcement`
- SHA-256: `f6b90c1719dea24847163917355a2da19f1a940e3201e71f5c4743c973b58c04`
- Retrieved: 2026-08-20T04:44:44.458Z
- Exported: 2026-08-22T05:27:01.042Z
- Document slug: `phmsa-enforcement-320111002w`

### Source metadata

```json
{
  "cpf": "320111002W",
  "operator": "TRANSCANADA NORTHERN BORDER INC",
  "region": "Central",
  "pipelineType": "GAS INTERSTATE ONSHORE",
  "caseStatus": "CLOSED",
  "citedSections": [
    "192.328(a)(1)",
    "192.328(a)(2)",
    "192.807"
  ],
  "dataAsOf": "08/04/2026 12PM",
  "caseDataAsOf": "2026-08-04",
  "attachmentCount": 2,
  "attachments": [
    {
      "name": "320111002W_Warning Letter_03212011.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/320111002W/320111002W_Warning%20Letter_03212011.pdf",
      "bytes": 418278,
      "category": "agency_document"
    },
    {
      "name": "320111002W_Warning Letter_03212011_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/320111002W/320111002W_Warning%20Letter_03212011_text.pdf",
      "bytes": 30530,
      "category": "agency_document"
    }
  ],
  "extractedAgencyDocumentCount": 1,
  "attachmentPolicy": "Official attachment links are retained. Agency-issued documents may also include a verified local PDF and page-level text representation.",
  "jurisdiction": "US",
  "operatorName": "TRANSCANADA NORTHERN BORDER INC"
}
```
