# TESORO HIGH PLAINS PIPELINE COMPANY LLC — Notice of Probable Violation

**Citation:** CPF 320125028  
**Type / status:** enforcement / historical  
**Agency:** Pipeline and Hazardous Materials Safety Administration  
**Effective:** Not stated  
**Published:** 2012-12-27

CLOSED notice of probable violation citing 195.436, 195.579(a).

## Document text

Notice of Probable Violation involving TESORO HIGH PLAINS PIPELINE COMPANY LLC. PHMSA's enforcement data identifies the cited regulations as 195.436,  195.579(a). The case was opened on 2012-12-27 and is reported as closed as of 2015-05-20. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

320125028_Closure_05202015.pdf: https://primis.phmsa.dot.gov/enforcement-documents/320125028/320125028_Closure_05202015.pdf

320125028_Closure_05202015_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/320125028/320125028_Closure_05202015_text.pdf

320125028_Final Order_04042014.pdf: https://primis.phmsa.dot.gov/enforcement-documents/320125028/320125028_Final%20Order_04042014.pdf

320125028_Final Order_04042014_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/320125028/320125028_Final%20Order_04042014_text.pdf

320125028_NOPV PCO_12272012.pdf: https://primis.phmsa.dot.gov/enforcement-documents/320125028/320125028_NOPV%20PCO_12272012.pdf

320125028_NOPV PCO_12272012_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/320125028/320125028_NOPV%20PCO_12272012_text.pdf

320125028_Operator Response to Notice and Request for Time Extension_01252013.pdf: https://primis.phmsa.dot.gov/enforcement-documents/320125028/320125028_Operator%20Response%20to%20Notice%20and%20Request%20for%20Time%20Extension_01252013.pdf

320125028_Final Order_04042014_text.pdf

APRIL 4, 2014
Mr. Gregory J. Goff
President and Chief Executive Officer
Tesoro Corporation
19100 Ridgewood Parkway
San Antonio, TX 78259
Re: CPF No. 3-2012-5028
Dear Mr. Goff:
Enclosed please find the Final Order issued in the above-referenced case. It makes findings of
violation and specifies actions that need to be taken by Tesoro High Plains Pipeline Company to
comply with the pipeline safety regulations. When the terms of the compliance order have been
completed, as determined by the Director, Central Region, this enforcement action will be
closed. Service of the Final Order by certified mail is deemed effective upon the date of mailing,
or as otherwise provided under 49 C.F.R. § 190.5.
Thank you for your cooperation in this matter.
Sincerely,
Jeffrey D. Wiese
Associate Administrator
for Pipeline Safety
Enclosure
cc: Ms. Linda Daugherty, Director, Central Region, OPS
Mr. Rick Weyen, Vice President, Logistics, Tesoro High Plains Pipeline Company,
19100 Ridgewood Parkway, San Antonio, TX 78259
CERTIFIED MAIL - RETURN RECEIPT REQUESTED



U.S. DEPARTMENT OF TRANSPORTATION
PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION
OFFICE OF PIPELINE SAFETY
WASHINGTON, D.C. 20590
____________________________________
In the Matter of )
Tesoro High Plains Pipeline Company, ) )
)
)
Respondent. )
____________________________________)
CPF No. 3-2012-5028
FINAL ORDER
On August 23-27, 2010, and August 30-September 3, 2010, pursuant to 49 U.S.C. § 60117, a
representative of the Pipeline and Hazardous Materials Safety Administration (PHMSA), Office
of Pipeline Safety (OPS), conducted an on-site pipeline safety inspection of the facilities and
records of Tesoro High Plains Pipeline Company (Tesoro or Respondent) in North Dakota.
Tesoro Corporation, through various subsidiaries, operates six refineries in the United States
with a combined capacity of 850,000 barrels per day.1
As a result of the inspection, the Director, Central Region, OPS (Director), issued to Respondent,
by letter dated December 27, 2012, a Notice of Probable Violation and Proposed Compliance
Order (Notice). In accordance with 49 C.F.R. § 190.207, the Notice proposed finding that
Tesoro violated 49 C.F.R. §§ 195.436 and 195.579 and proposed ordering Respondent to take
certain measures to correct the alleged violations.
Tesoro responded to the Notice by letter dated January 25, 2013 (Response) and requested that
PHMSA make certain modifications to the facts alleged in the Notice. The company did not
contest the allegations of violation but provided written explanations and other materials related
to the alleged violations. Respondent did not request a hearing and therefore has waived its right
to one.
FINDINGS OF VIOLATION
In its Response, Tesoro did not contest the allegations in the Notice that it violated 49 C.F.R.
Part 195, as follows:
Item 1: The Notice alleged that Respondent violated 49 C.F.R. § 195.436, which states:
1 This statement was generally taken from the Tesoro website. http://phx.corporate-
ir.net/phoenix.zhtml?c=79122&p=irol-IRHome (last accessed on January 24, 2014)



2
§ 195.436 Security of facilities.
Each operator shall provide protection for each pumping station and
breakout tank area and other exposed facility (such as scraper traps) from
vandalism and unauthorized entry.
The Notice alleged that Respondent violated 49 C.F.R. § 195.436 by failing to provide adequate
protection for each pumping station and breakout tank area from vandalism and unauthorized
entry. Specifically, the Notice alleged that certain pump stations and breakout tank areas were
either inadequately fenced or without any adequate security.
2
Respondent did not contest this allegation of violation.
Accordingly, based upon a review of all of the evidence, I find that Respondent violated
49 C.F.R. § 195.436 by failing to provide adequate protection for each pumping station and
breakout tank area from vandalism and unauthorized entry.
Item 2: The Notice alleged that Respondent violated 49 C.F.R. § 195.579(a), which states:
§ 195.579 What must I do to mitigate internal corrosion?
(a) General. If you transport any hazardous liquid or carbon dioxide
that would corrode the pipeline, you must investigate the corrosive effect
of the hazardous liquid or carbon dioxide on the pipeline and take
adequate steps to mitigate internal corrosion.
The Notice alleged that Respondent violated 49 C.F.R. § 195.579(a) by failing to investigate the
corrosive effect of hazardous liquid or carbon dioxide on the pipeline and take adequate steps to
mitigate internal corrosion. Specifically, the Notice alleged that Tesoro failed to provide records
demonstrating that it investigated the corrosive effect of crude oil on its pipeline. During the
inspection, a PHMSA investigator noted that, during an internal line inspection, it discovered a
metal loss anomaly indicative of internal corrosion. However, Tesoro could not provide
documentation that it conducted any subsequent investigation or mitigation.
Respondent did not contest this allegation of violation.
Accordingly, based upon a review of all of the evidence, I find that Respondent violated
49 C.F.R. § 195.579(a) by failing to investigate the corrosive effect of hazardous liquid or carbon
dioxide on its pipeline and take adequate steps to mitigate internal corrosion.
These findings of violation will be considered prior offenses in any subsequent enforcement
action taken against Respondent.
2 The Black Slough Pump Station and Breakout Tank area was secured by a four-foot tall barbed wire fence
composed of 2-3 strands. The Tioga Pump station was similarly secured, and its breakout tank area was not fenced.
In addition, the Poker Jim Breakout Tank area had an open, 31-foot wide entrance, without a gate. Pipeline Safety
Violation Report (Violation Report), (December 27, 2012) (on file with PHMSA), at Exhibit B.



3
COMPLIANCE ORDER
The Notice proposed a compliance order with respect to Items 1 and 2 in the Notice for
violations of 49 C.F.R. §§ 195.436 and 195.579(a), respectively. Under 49 U.S.C. § 60118(a),
each person who engages in the transportation of hazardous liquids or who owns or operates a
pipeline facility is required to comply with the applicable safety standards established under
chapter 601. Pursuant to the authority of 49 U.S.C. § 60118(b) and 49 C.F.R. § 190.217,
Respondent is ordered to take the following actions to ensure compliance with the pipeline safety
regulations applicable to its operations:
1. With respect to the violation of § 195.436 (Item 1), Respondent must install
adequate security for the Black Slough Pump Station and Breakout Tank area, Tioga
Pump Station, and Poker Jim Breakout Tank Area.
2. With respect to the violation of § 195.579(a) (Item 2), Respondent must
investigate the cause of the internal corrosion (anomaly located at 142366.5) and take
adequate steps to mitigate the corrosion, as determined by the investigation.
3. With respect to Item 1, Respondent must submit documentation of the completion
of these installations within 15 days of receipt of this Final Order. The Director,
Central Region, will review the documents, and then specify any further actions that
Respondent must take to comply. With respect to Item 2, Respondent must submit
relevant records and a notice of completed action to the Director, Central Region,
OPS, 901 Locust Street, Suite 462, Kansas City, MO 64106-2641, within 15 days of
receipt of this Final Order.
4. It is requested (not mandated) that Respondent maintain documentation of the
safety improvement costs associated with fulfilling this Compliance Order and submit
the total to the Director. The costs should be reported in two categories: (1) total cost
associated with preparation and revision of plans, procedures, studies, and analyses;
and (2) total cost associated with replacements, additions, and other changes to the
pipeline infrastructure.
The Director may grant an extension of time to comply with any of the required items upon a
written request timely submitted by the Respondent and demonstrating good cause for an
extension.
Failure to comply with this Order may result in the administrative assessment of civil penalties
not to exceed $200,000 for each violation for each day the violation continues or in referral to the
Attorney General for appropriate relief in a district court of the United States.
The terms and conditions of this Final Order are effective upon service in accordance with
49 C.F.R. § 190.5.
___________________________________ __________________________
Jeffrey D. Wiese Date Issued
Associate Administrator for Pipeline Safety

320125028_Closure_05202015_text.pdf

CERTIFIED MAIL - RETURN RECEIPT REQUESTED
May 20, 2015
Mr. Don Sorensen
Senior Vice President
Tesoro Logistics GP, LLC
19100 Ridgewood Parkway
San Antonio, Texas 78259
CPF 3-2012-5028
Dear Mr. Sorensen:
On April 4, 2014, the Pipeline and Hazardous Materials Safety Administration (PHMSA)
issued to Tesoro High Plains Pipeline Company a Final Order in the above-referenced case.
This Order included a Compliance Order requirement to take corrective actions on your
pipeline. Based on our review of the documentation you provided, it has been determined that
you have complied with the terms of this Order.
Accordingly, this case is now closed and no further action is contemplated with respect to the
matters involved in this case. Thank you for your cooperation in this matter.
Sincerely,
Allan C. Beshore
Director, Central Region, OPS
Pipeline and Hazardous Materials Safety Administration

## Provenance

- Official: Yes
- Source: <https://primis.phmsa.dot.gov/enforcement-data/case/320125028>
- Source ID: `phmsa-enforcement`
- SHA-256: `c3c418f33d709a6d3a519b83a6184139a5ad4af2abaa2e8e72be8acc12a9f0ec`
- Retrieved: 2026-08-20T04:44:44.458Z
- Exported: 2026-08-22T23:16:54.575Z
- Document slug: `phmsa-enforcement-320125028`

### Source metadata

```json
{
  "cpf": "320125028",
  "operator": "TESORO HIGH PLAINS PIPELINE COMPANY LLC",
  "region": "Central",
  "pipelineType": "INTERSTATE LIQUID ONSHORE",
  "caseStatus": "CLOSED",
  "citedSections": [
    "195.436",
    "195.579(a)"
  ],
  "dataAsOf": "08/04/2026 12PM",
  "caseDataAsOf": "2026-08-04",
  "attachmentCount": 7,
  "attachments": [
    {
      "name": "320125028_Closure_05202015.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/320125028/320125028_Closure_05202015.pdf",
      "bytes": 349050,
      "category": "agency_document"
    },
    {
      "name": "320125028_Closure_05202015_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/320125028/320125028_Closure_05202015_text.pdf",
      "bytes": 4303,
      "category": "agency_document"
    },
    {
      "name": "320125028_Final Order_04042014.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/320125028/320125028_Final%20Order_04042014.pdf",
      "bytes": 212774,
      "category": "agency_document"
    },
    {
      "name": "320125028_Final Order_04042014_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/320125028/320125028_Final%20Order_04042014_text.pdf",
      "bytes": 15999,
      "category": "agency_document"
    },
    {
      "name": "320125028_NOPV PCO_12272012.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/320125028/320125028_NOPV%20PCO_12272012.pdf",
      "bytes": 299993,
      "category": "case_document"
    },
    {
      "name": "320125028_NOPV PCO_12272012_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/320125028/320125028_NOPV%20PCO_12272012_text.pdf",
      "bytes": 36320,
      "category": "case_document"
    },
    {
      "name": "320125028_Operator Response to Notice and Request for Time Extension_01252013.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/320125028/320125028_Operator%20Response%20to%20Notice%20and%20Request%20for%20Time%20Extension_01252013.pdf",
      "bytes": 282078,
      "category": "party_submission"
    }
  ],
  "extractedAgencyDocumentCount": 2,
  "attachmentPolicy": "Official attachment links are retained. Agency-issued documents may also include a verified local PDF and page-level text representation.",
  "jurisdiction": "US",
  "operatorName": "TESORO HIGH PLAINS PIPELINE COMPANY LLC"
}
```