# TRAILBLAZER PIPELINE CO — Notice of Amendment

**Citation:** CPF 320191001M  
**Type / status:** enforcement / historical  
**Agency:** Pipeline and Hazardous Materials Safety Administration  
**Effective:** Not stated  
**Published:** 2019-03-15

CLOSED notice of amendment citing 192.605(b)(1), 192.605(b)(2).

## Document text

Notice of Amendment involving TRAILBLAZER PIPELINE CO. PHMSA's enforcement data identifies the cited regulations as 192.605(b)(1),  192.605(b)(2). The case was opened on 2019-03-15 and is reported as closed as of 2022-07-19. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

320191001M_Closure Letter_07192022_(17-155390S).pdf: https://primis.phmsa.dot.gov/enforcement-documents/320191001M/320191001M_Closure%20Letter_07192022_(17-155390S).pdf

320191001M_Closure Letter_07192022_(17-155390S)_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/320191001M/320191001M_Closure%20Letter_07192022_(17-155390S)_text.pdf

320191001M_Notice of Amendment_03152019.pdf: https://primis.phmsa.dot.gov/enforcement-documents/320191001M/320191001M_Notice%20of%20Amendment_03152019.pdf

320191001M_Notice of Amendment_03152019_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/320191001M/320191001M_Notice%20of%20Amendment_03152019_text.pdf

320191001M_Operator Response to Notice_05022019.pdf: https://primis.phmsa.dot.gov/enforcement-documents/320191001M/320191001M_Operator%20Response%20to%20Notice_05022019.pdf

320191001M_Notice of Amendment_03152019_text.pdf

NOTICE OF AMENDMENT
CERTIFIED MAIL - RETURN RECEIPT REQUESTED
March 15, 2019
David Dehaemers
President
Tallgrass Energy, LLC
Trailblazer Pipeline
370 Van Gordon Street
Lakewood, CO 80228
CPF 3-2019-1001M
Dear Mr. Dehaemers:
From March 7, 2017, through August 31, 2017, representatives of the Pipeline and Hazardous
Materials Safety Administration (PHMSA) pursuant to Chapter 601 of 49 United States Code
inspected Tallgrass Trailblazer Pipeline procedures for operations, maintenance, and
emergencies in Lakewood, CO.
On the basis of the inspection, PHMSA has identified the apparent inadequacies found within
Tallgrass Energy, LLC’s (Tallgrass’) plans or procedures, as described below:
1. §192.605 Procedural manual for operations, maintenance, and emergencies
(b) Maintenance and normal operations. The manual required by paragraph (a) of this
section must include procedures for the following, if applicable, to provide safety
during maintenance and operations.
(1) Operating, maintaining, and repairing the pipeline in accordance with each of the
requirements of this subpart and Subpart M of this part.
Tallgrass did not have adequate procedures for operations and maintenance activities as
required by Subparts L & M, 49 CFR Part 192. The procedure to ensure the inspection of
transmission linebreak valves that might be required during any emergency in accordance to
§192.745 was inadequate. PHMSA inspectors reviewed Tallgrass Procedure O&M 301_G



titled, "Inspecting and Servicing Emergency Valves." The procedure stated, "Inspect and
service valves in conformance with manufacturers’ recommendations." PHMSA reviewed the
two manufacturer’s recommendations that were provided by Tallgrass for the linebreak valves-
“Automatic Linebreak Control Adjustment and Set-up Procedure ALBC 1983-Present” and the
“Shafer valve Company Adjustment and Setting Procedure for Shafer Automatic Line Break
Control.” A review of valve maintenance records found documentation where the rate of drop
was not in accordance with the manufacturers’ recommendations.
The Shafer Valve Company Adjustment and Setting Procedure for Shafer Automatic Line
Break Control and the Automatic Linebreak Control Adjustment and Set-up Procedure ALBC
1983-Present manufacturer’s recommendations require different ranges for rate of pressure
drop calibrations. The ALBC manufacturer’s recommendations require that the rate of drop for
the #72 orifice and 1640 cubic inch tank should never exceed 18 psi/min. Shafer manufacturer
recommendations were reported by Tallgrass for the #72 orifice and 1640 cubic inch tank to be
calibrated between 18-30 psi.
Tallgrass does not have a procedure to ensure that linebreak valves are properly maintained to
ensure pressure sensing systems will adapt to pressure and flow changes (rate of drop) in order
to minimize or eliminate accidental valve closures.
2. §192.605 Procedural manual for operations, maintenance, and emergencies.
(b) Maintenance and normal operations. The manual required by paragraph (a) of this
section must include procedures for the following, if applicable, to provide safety
during maintenance and operations.
(2) Controlling corrosion in accordance with the operations and maintenance
requirements of subpart I of this part.
At the time of the inspection, Tallgrass's O&M 903_GL titled, “External Corrosion Control for
Buried or Submerged Pipelines," procedures were inadequate because the procedures did not
describe how voltage (IR) drops - other than those across the structure electrolyte boundary -
would be calculated for valid interpretation of annual pipe-to-soil readings. As such, the
procedures do not provide for a level of cathodic protection (CP) that complies with one or
more of the applicable criteria contained in 49 CFR Part 192, Appendix D.
49 CFR §192.463 (a) requires that “[e]ach cathodic protection system required by this subpart
must provide a level of cathodic protection that complies with one or more of the applicable
criteria contained in Appendix D of this part. If none of these criteria is applicable, the cathodic
protection system must provide a level of cathodic protection at least equal to that provided by
compliance with one or more of these criteria.”
49 CFR 192, Appendix D,II - Interpretation of voltage measurement requires that “[v]oltage
(IR) drops other than those across the structure electrolyte boundary must be considered for
valid interpretation of the voltage measurement in paragraphs A(1) and (2) and paragraph B(1)
of section I of the appendix.”
Tallgrass’s O&M 903_GL states in Attachment 3, “Existing industry standards provide several
example methods in which the IR drop may be considered including measuring or calculating
2



the IR drop, reviewing the historical CP system performance, evaluating the physical and
electrical characteristics of the pipe and its environment, and determining whether there is
physical evidence of corrosion.” The procedure did not discuss how to calculate IR drop or
how to use the industry standards referenced in Attachment 3 to calculate IR Drop.
3. §192.605 Procedural manual for operations, maintenance, and emergencies.
(b) Maintenance and normal operations. The manual required by paragraph (a) of this
section must include procedures for the following, if applicable, to provide safety
during maintenance and operations.
(2) Controlling corrosion in accordance with the operations and maintenance
requirements of subpart I of this part.
At the time of the inspection, Tallgrass's O&M 903_GL titled, “External Corrosion Control for
Buried or Submerged Pipelines," procedure was inadequate because the procedure describes
interference tests as a desired action not a requirement, which does not minimize adverse
effects on existing adjacent underground metallic structures. 49 CFR § 192.473(b) requires
that “[e]ach impressed current type cathodic protection system or galvanic anode system must
be designed and installed so as to minimize any adverse effects on existing adjacent
underground metallic structures.”
Tallgrass's O&M 903_GL, Section 3.4.8. “Interference Test Surveys” states, “Conduct
interference tests on metallic structures in the immediate area after energizing new CP units or
after installing metallic structures in the area of influence of a CP unit if either party desires."
Tallgrass procedure does not ensure that interference testing is conducted to minimize any
adverse effects on existing adjacent underground metallic structures. The Tallgrass procedure
relies solely on the desires of either party after newly installed CP units or other metallic
structures.
Response to this Notice
This Notice is provided pursuant to 49 U.S.C. § 60108(a) and 49 C.F.R. § 190.206. Enclosed
as part of this Notice is a document entitled Response Options for Pipeline Operators in
Compliance Proceedings. Please refer to this document and note the response options. Be
advised that all material you submit in response to this enforcement action is subject to being
made publicly available. If you believe that any portion of your responsive material qualifies
for confidential treatment under 5 U.S.C. 552(b), along with the complete original document
you must provide a second copy of the document with the portions you believe qualify for
confidential treatment redacted and an explanation of why you believe the redacted
information qualifies for confidential treatment under 5 U.S.C. 552(b).
Following the receipt of this Notice, you have 30 days to submit written comments, revised
procedures, or a request for a hearing under §190.211. If you do not respond within 30 days of
receipt of this Notice, this constitutes a waiver of your right to contest the allegations in this
Notice and authorizes the Associate Administrator for Pipeline Safety to find facts as alleged in
this Notice without further notice to you and to issue an Order Directing Amendment. If your
plans or procedures are found inadequate as alleged in this Notice, you may be ordered to
amend your plans or procedures to correct the inadequacies (49 C.F.R. § 190.206). If you are
3



not contesting this Notice, we propose that you submit your amended procedures to my office
within 45 days of receipt of this Notice. This period may be extended by written request for
good cause. Once the inadequacies identified herein have been addressed in your amended
procedures, this enforcement action will be closed.
It is requested (not mandated) that Tallgrass Energy, LLC maintain documentation of the
safety improvement costs associated with fulfilling this Notice of Amendment
(preparation/revision of plans, procedures) and submit the total to Allan C. Beshore, Director,
Central Region, Pipeline and Hazardous Materials Safety Administration. In correspondence
concerning this matter, please refer to CPF 3-2019-1001M and, for each document you
submit, please provide a copy in electronic format whenever possible.
Sincerely,
Allan C. Beshore
Director, Central Region
Pipeline and Hazardous Materials Safety Administration
Enclosure: Response Options for Pipeline Operators in Enforcement Proceedings
4

320191001M_Closure Letter_07192022_(17-155390S)_text.pdf

VIA ELECTRONIC MAIL TO: bill.moler@tallgrassenergylp.com;
jennifer.eckels@tallgrassenergylp.com; crystal.heter@tallgrassenergylp.com
July 19, 2022
William Moler
President/CEO
Tallgrass Energy, LP
Trailblazer Pipeline Company
4200 W. 115th Street, Suite 350
Leawood, KS 66221
Re: CPF 3-2019-1001M
Dear Mr. Moler:
On March 7, 2017, through August 31, 2017, a representative from the Pipeline and Hazardous
Materials Safety Administration (PHMSA), pursuant to chapter 601 of 49 United States Code,
conducted an on-site pipeline safety inspection of Tallgrass Trailblazer Pipeline’s procedures in
Lakewood, Colorado. As a result of the inspection, Tallgrass Energy, LP (Tallgrass) was issued
a Notice of Amendment on March 15, 2019, which proposed amendments to Tallgrass’
procedures.
Tallgrass submitted its amended procedures on July 6, 2022. My staff has reviewed the amended
procedures, and it appears that the inadequacies outlined in the Notice of Amendment have been
corrected.
This letter is to inform you that no further action is necessary and this case is now closed. Thank
you for your cooperation
Sincerely,
Gregory A. Ochs
Director, Central Region, OPS
Pipeline and Hazardous Materials Safety Administration

## Provenance

- Official: Yes
- Source: <https://primis.phmsa.dot.gov/enforcement-data/case/320191001M>
- Source ID: `phmsa-enforcement`
- SHA-256: `0997523995a0d61e41880d6a2baac0477f5b124fdc74941b8175b213e7474f09`
- Retrieved: 2026-08-20T04:44:44.458Z
- Exported: 2026-08-22T01:41:41.570Z
- Document slug: `phmsa-enforcement-320191001m`

### Source metadata

```json
{
  "cpf": "320191001M",
  "operator": "TRAILBLAZER PIPELINE CO",
  "region": "Central",
  "pipelineType": "GAS INTERSTATE ONSHORE",
  "caseStatus": "CLOSED",
  "citedSections": [
    "192.605(b)(1)",
    "192.605(b)(2)"
  ],
  "dataAsOf": "08/04/2026 12PM",
  "caseDataAsOf": "2026-08-04",
  "attachmentCount": 5,
  "attachments": [
    {
      "name": "320191001M_Closure Letter_07192022_(17-155390S).pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/320191001M/320191001M_Closure%20Letter_07192022_(17-155390S).pdf",
      "bytes": 247649,
      "category": "agency_document"
    },
    {
      "name": "320191001M_Closure Letter_07192022_(17-155390S)_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/320191001M/320191001M_Closure%20Letter_07192022_(17-155390S)_text.pdf",
      "bytes": 80861,
      "category": "agency_document"
    },
    {
      "name": "320191001M_Notice of Amendment_03152019.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/320191001M/320191001M_Notice%20of%20Amendment_03152019.pdf",
      "bytes": 217644,
      "category": "agency_document"
    },
    {
      "name": "320191001M_Notice of Amendment_03152019_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/320191001M/320191001M_Notice%20of%20Amendment_03152019_text.pdf",
      "bytes": 120394,
      "category": "agency_document"
    },
    {
      "name": "320191001M_Operator Response to Notice_05022019.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/320191001M/320191001M_Operator%20Response%20to%20Notice_05022019.pdf",
      "bytes": 1300610,
      "category": "party_submission"
    }
  ],
  "extractedAgencyDocumentCount": 2,
  "attachmentPolicy": "Official attachment links are retained. Agency-issued documents may also include a verified local PDF and page-level text representation.",
  "jurisdiction": "US",
  "operatorName": "TRAILBLAZER PIPELINE CO"
}
```
