CLOSED warning letter citing 195.452(f)(3), 195.452(g), 195.452(i)(4), 195.571.

## Document text

Warning Letter involving MOBIL  PIPE  LINE COMPANY. PHMSA's enforcement data identifies the cited regulations as 195.452(f)(3),  195.452(g),  195.452(i)(4),  195.571. The case was opened on 2019-03-15 and is reported as closed as of 2019-03-15. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

320195014W_Warning Letter_03152019.pdf: https://primis.phmsa.dot.gov/enforcement-documents/320195014W/320195014W_Warning%20Letter_03152019.pdf

320195014W_Warning Letter_03152019_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/320195014W/320195014W_Warning%20Letter_03152019_text.pdf

320195014W_Warning Letter_03152019_text.pdf

WARNING LETTER
CERTIFIED MAIL - RETURN RECEIPT REQUESTED
March 15, 2019
Mr. Gerald S. Frey
President
ExxonMobil Pipeline Company
P.O. Box 2220
Houston, Texas 77252-2220
3-2019-5014W
Dear Mr. Frey:
On July 31st through August 4th and November 27th through December 1st 2017, a
representative of the Pipeline and Hazardous Materials Safety Administration (PHMSA)
pursuant to Chapter 601 of 49 United States Code (U.S.C.) inspected your Lockport Products
Terminal, Mokena-Joliet Refinery 30”(MOJO) pipeline and Mustang pipeline in central
Illinois.
As a result of the inspection, it is alleged that you have committed probable violations of the
Pipeline Safety Regulations, Title 49, Code of Federal Regulations (CFR). The items
inspected and the probable violation(s) are:



1. 195.452 Pipeline integrity management in high consequence areas.
(a) . . . .
(f) What are the elements of an integrity management program?
An integrity management program begins with the initial framework. An operator
must continually change the program to reflect operating experience, conclusions
drawn from results of the integrity assessments, and other maintenance and
surveillance data, and evaluation of consequences of a failure on the high
consequence area. An operator must include, at minimum, each of the following
elements in its written integrity management program:
(1) . . . .
(3) An analysis that integrates all available information about the integrity of the
entire pipeline and the consequences of a failure (see paragraph (g) of this section);
§195.452(g) What is an information analysis? In periodically evaluating the integrity
of each pipeline segment (paragraph (j) of this section), an operator must analyze all
available information about the integrity of the entire pipeline and the consequences
of a failure. This information includes:
(1) Information critical to determining the potential for, and preventing, damage
due to excavation, including current and planned damage prevention activities, and
development or planned development along the pipeline segment;
(2) Data gathered through the integrity assessment required under this section;
(3) Data gathered in conjunction with other inspections, tests, surveillance and
patrols required by this Part, including, corrosion control monitoring and cathodic
protection surveys; and
(4) Information about how a failure would affect the high consequence area, such as
location of the water intake.
Units 43163 and 64233:
ExxonMobil’s integrity management program (IMP) does not include an analysis that
integrates all available information about the integrity of pipeline facilities and the
consequences of a failure. ExxonMobil performed several facility integrity management
activities such as: Facility Risk Assessment (FRA) for critical control devices, a review of
overfill protection systems, and API 570 inspections of select pipeline and storage facilities.
However, ExxonMobil has not developed an information analysis for each facility or a
comprehensive facility integrity risk analysis to consistently identify and evaluate risks in
accordance with 195.452(g).
2. §195.571 What criteria must I use to determine the adequacy of cathodic
protection? Cathodic protection required by this Subpart must comply with one or
more of the applicable criteria and other considerations for cathodic protection
contained in paragraphs 6.2 and 6.3 of NACE SP 0169 (incorporated by reference,
see § 195.3).
2



Unit 87704:
ExxonMobil failed to comply with one or more of the applicable criteria and other
considerations for cathodic protection contained in paragraphs 6.2 and 6.3 of NACE SP 0169.
Permanent reference electrodes (both zinc & copper copper-sulfate types) have been installed
between the double tank bottoms on breakout tanks 902, 904, 905, 907, 909 at Lockport
terminal. Based on the cathodic protection survey data, the tank-to-soil potential readings
taken using the permanent reference electrodes installed between the tank bottoms is suspect.
There is no other method in place for testing the cathodic protection (CP) effectiveness on the
primary containment tank bottom.
3. §195.571 What criteria must I use to determine the adequacy of cathodic
protection? Cathodic protection required by this Subpart must comply with one or
more of the applicable criteria and other considerations for cathodic protection
contained in paragraphs 6.2 and 6.3 of NACE SP 0169 (incorporated by reference,
see § 195.3).
Units 43163 and 64233:
ExxonMobil has not adequately considered IR drop in the determination of adequate cathodic
protection in accordance with NACE criteria. ExxonMobil uses “ON” pipe-to-soil-potential
measurements to determine adequacy of cathodic protection which does not consider IR drop.
4. §195.452 Pipeline integrity management in high consequence areas.
(a) . . . .
(i) What preventive and mitigative measures must an operator take to protect the
high consequence area ?
(1) . . . .
(4) Emergency Flow Restricting Devices (EFRD ). If an operator determines that an
EFRD is needed on a pipeline segment to protect a high consequence area in the
event of a hazardous liquid pipeline release, an operator must install the EFRD. In
making this determination, an operator must, at least, consider the following factors
- the swiftness of leak detection and pipeline shutdown capabilities, the type of
commodity carried, the rate of potential leakage, the volume that can be released,
topography or pipeline profile, the potential for ignition, proximity to power
sources, location of nearest response personnel, specific terrain between the pipeline
segment and the high consequence area, and benefits expected by reducing the spill
size.
Units 64233:
3



ExxonMobil performed a study of its 18” Mustang pipeline in 2014 that identified a potential
EFRD location at MP 24.22. The type of EFRD considered was a remotely operated valve
(ROV). Per ExxonMobil’s IM process, the potential EFRD candidate was submitted to their
LRMT (Local Risk Management Team) for consideration. ExxonMobil used Form 6.2
(Ver.2013) to document the data reviewed and the results of their EFRD evaluation for this site
(EMPCo 2017 CRA EFRD Lockport to Patoka 001). The LMRT review determined that the
installation of a ROV would not provide significant risk reduction and the descision was made
not to install the ROV. However, section 7 of form 6.2 for this site had several variables listed
as N/A including Risk Reduction Score, Segment Risk Matrix, Threat Classification and
Consequence. The Significant Change box was also left unchecked which indicates whether
the EFRD should be considered as a possible risk reduction strategy. In addition, comments
within the form did not adequately document or describe the decision why not to install an
EFRD device at MP 24.22.
Under 49 U.S.C. § 60122 and 49 CFR § 190.223, you are subject to a civil penalty not to
exceed $213,268 per violation per day the violation persists, up to a maximum of $2,132,679
for a related series of violations. For violation occurring on or after November 2, 2015 and
before November 27, 2018, the maximum penalty may not exceed $209,002 per violation per
day, with a maximum penalty not to exceed $2,090,022. For violations occurring prior to
November 2, 2015, the maximum penalty may not exceed $200,000 per violation per day, with
a maximum penalty not to exceed $2,000,000 for a related series of violations. We have
reviewed the circumstances and supporting documents involved in this case, and have decided
not to conduct additional enforcement action or penalty assessment proceedings at this time.
We advise you to correct the item(s) identified in this letter. Failure to do so will result in
ExxonMobil Pipeline Company being subject to additional enforcement action.
No reply to this letter is required. If you choose to reply, in your correspondence please refer
to 3-2019-5014W. Be advised that all material you submit in response to this enforcement
action is subject to being made publicly available. If you believe that any portion of your
responsive material qualifies for confidential treatment under 5 U.S.C. 552(b), along with the
complete original document you must provide a second copy of the document with the portions
you believe qualify for confidential treatment redacted and an explanation of why you believe
the redacted information qualifies for confidential treatment under 5 U.S.C. 552(b).
Sincerely,
Allan C. Beshore, P.E.
Director, Central Region
Pipeline and Hazardous Materials Safety Administration
4

## Provenance

- Official: Yes
- Source: <https://primis.phmsa.dot.gov/enforcement-data/case/320195014W>
- Source ID: `phmsa-enforcement`
- SHA-256: `6be9802301f85c5052428eb3f5a388652871f5d9c1f04195fe0db98857e79d78`
- Retrieved: 2026-08-20T04:44:44.458Z
- Exported: 2026-08-22T23:18:42.196Z
- Document slug: `phmsa-enforcement-320195014w`

### Source metadata

```json
{
  "cpf": "320195014W",
  "operator": "MOBIL  PIPE  LINE COMPANY",
  "region": "Central",
  "pipelineType": "INTERSTATE LIQUID ONSHORE",
  "caseStatus": "CLOSED",
  "citedSections": [
    "195.452(f)(3)",
    "195.452(g)",
    "195.452(i)(4)",
    "195.571"
  ],
  "dataAsOf": "08/04/2026 12PM",
  "caseDataAsOf": "2026-08-04",
  "attachmentCount": 2,
  "attachments": [
    {
      "name": "320195014W_Warning Letter_03152019.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/320195014W/320195014W_Warning%20Letter_03152019.pdf",
      "bytes": 200970,
      "category": "agency_document"
    },
    {
      "name": "320195014W_Warning Letter_03152019_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/320195014W/320195014W_Warning%20Letter_03152019_text.pdf",
      "bytes": 171786,
      "category": "agency_document"
    }
  ],
  "extractedAgencyDocumentCount": 1,
  "attachmentPolicy": "Official attachment links are retained. Agency-issued documents may also include a verified local PDF and page-level text representation.",
  "jurisdiction": "US",
  "operatorName": "MOBIL  PIPE  LINE COMPANY"
}
```