# PANHANDLE EASTERN PIPELINE CO — Notice of Probable Violation

**Citation:** CPF 320201005  
**Type / status:** enforcement / historical  
**Agency:** Pipeline and Hazardous Materials Safety Administration  
**Effective:** Not stated  
**Published:** 2020-09-09

CLOSED notice of probable violation citing 192.167(a)(4)(ii), 192.605(b)(3), 192.709(c), 192.745(a), 192.905(c), 192.937(b).

## Document text

Notice of Probable Violation involving PANHANDLE EASTERN PIPELINE CO. PHMSA's enforcement data identifies the cited regulations as 192.167(a)(4)(ii),  192.605(b)(3),  192.709(c),  192.745(a),  192.905(c),  192.937(b). The case was opened on 2020-09-09 and is reported as closed as of 2020-12-10. Proposed civil penalty: $226,500. Assessed civil penalty: $226,500. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

320201005_Closure Letter_12102020.pdf: https://primis.phmsa.dot.gov/enforcement-documents/320201005/320201005_Closure%20Letter_12102020.pdf

320201005_Closure Letter_12102020_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/320201005/320201005_Closure%20Letter_12102020_text.pdf

320201005_Final Order_12042020.pdf: https://primis.phmsa.dot.gov/enforcement-documents/320201005/320201005_Final%20Order_12042020.pdf

320201005_Final Order_12042020_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/320201005/320201005_Final%20Order_12042020_text.pdf

320201005_NOPV PCP PCO_09092020.pdf: https://primis.phmsa.dot.gov/enforcement-documents/320201005/320201005_NOPV%20PCP%20PCO_09092020.pdf

320201005_NOPV PCP PCO_09092020_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/320201005/320201005_NOPV%20PCP%20PCO_09092020_text.pdf

320201005_Operator Response to Notice_10262020.pdf: https://primis.phmsa.dot.gov/enforcement-documents/320201005/320201005_Operator%20Response%20to%20Notice_10262020.pdf

320201005_Final Order_12042020_text.pdf

December 4, 2020
VIA ELECTRONIC MAIL TO: matthew.ramsey@energytransfer.com
Mr. Matthew Ramsey
Chief Operating Officer
Energy Transfer, LP
8111 Westchester Drive
Dallas, Texas 75225
Re: CPF No. 3-2020-1005
Dear Mr. Ramsey:
Enclosed please find the Final Order issued in the above-referenced case. It makes findings of
violation against your subsidiary, Panhandle Eastern Pipeline Company, LP, finds that the civil
penalty amount of $226,500 has been paid in full, and specifies actions that need to be taken to
comply with the pipeline safety regulations. When the terms of the compliance order are completed,
as determined by the Director, Central Region, this enforcement action will be closed. Service of the
Final Order by electronic mail is effective upon the date of mailing as provided under 49 C.F.R. §
190.5.
Thank you for your cooperation in this matter.
Sincerely,
Alan K. Mayberry
Associate Administrator
for Pipeline Safety
Enclosures (Final Order and NOPV)
cc: Mr. Gregory Ochs, Director, Central Region, Office of Pipeline Safety, PHMSA
Mr. Kelcy Warren, Chief Executive Officer, Energy Transfer,
kelcy.warren@energytransfer.com
Mr. Eric Amundsen, Senior Vice President, Operations, Energy Transfer,
eric.amundsen@energytransfer.com
Mr. Todd Nardozzi, Director, Regulatory Compliance, Energy Transfer,
todd.nardozzi@energytransfer.com
CONFIRMATION OF RECEIPT REQUESTED



U.S. DEPARTMENT OF TRANSPORTATION
PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION
OFFICE OF PIPELINE SAFETY
WASHINGTON, D.C. 20590
__________________________________________
In the Matter of )
Panhandle Eastern Pipeline Company, LP, ) CPF No. 3-2020-1005
a subsidiary of Energy Transfer, LP, )
)
)
)
Respondent. )
__________________________________________)
FINAL ORDER
On September 9, 2020, pursuant to 49 C.F.R. § 190.207, the Director, Central Region, Office of
Pipeline Safety (OPS), issued a Notice of Probable Violation (Notice) to Panhandle Eastern
Pipeline Company, LP (Respondent). The Notice proposed finding that Respondent had violated
the pipeline safety regulations in 49 C.F.R. Part 192. The Notice also proposed certain measures
to correct the violations. Respondent did not contest the allegations of violation or corrective
measures, and paid the proposed civil penalty on November 3, 2020.
Based upon a review of all of the evidence, pursuant to § 190.213, I find Respondent violated the
pipeline safety regulations listed below, as more fully described in the enclosed Notice, which is
incorporated by reference:
49 C.F.R. § 192.167(a)(4)(ii) (Item 1) ─ Respondent failed to failed to provide
operable emergency shutdown (ESD) systems in at least two locations, each of
which was outside the gas area of the compressor station and near the exit gates of
the fenced stations;
49 C.F.R. § 192.709(c) (Item 3) ─ Respondent failed to retain records of each
patrol, survey, inspection, and test required by subpart M of Part 192 for at least 5
years or until the next patrol, survey, inspection, or test is completed, or
whichever is longer;
49 C.F.R. § 192.745(a) (Item 4) ─ Respondent failed to inspect and partially
operate transmission line valves that might be required during an emergency at
intervals not exceeding 15 months, but at least once each calendar year; and
49 C.F.R. § 192.937(b) (Item 6) ─ Respondent failed to follow its integrity
management plan for performing a continual process of evaluation and
assessment to maintain its pipeline integrity.



CPF No. 3-2020-1005
Page 2
These findings of violation will be considered prior offenses in any subsequent enforcement
action taken against Respondent. In accordance with 49 C.F.R. § 190.223, Respondent is
assessed the proposed civil penalty amount of $226,500, which Respondent has already paid in
full.
COMPLIANCE ACTIONS
Pursuant to 49 U.S.C. § 60118(b) and 49 C.F.R. § 190.217, Respondent is ordered to take the
actions proposed in the enclosed Notice to correct the violations. The Director may grant an
extension of time to comply with any of the required items upon a written request timely
submitted by the Respondent and demonstrating good cause for an extension. Upon completion
of ordered actions, Respondent may request that the Director close the case. Failure to comply
with this Order may result in the assessment of civil penalties under 49 C.F.R. § 190.223 or in
referral to the Attorney General for appropriate relief in a district court of the United States.
WARNING ITEMS
With respect to Items 2 and 5, the Notice alleged probable violations of 49 C.F.R. §§
192.605(b)(3) and 192.905(c), respectively, but did not propose a civil penalty or compliance
order for these items. Therefore, these are considered to be warning items. If OPS finds a
violation of any of these items in a subsequent inspection, Respondent may be subject to future
enforcement action.
The terms and conditions of this order are effective upon service in accordance with 49 C.F.R.
§ 190.5.
December 4, 2020
___________________________________ _________________________
Alan K. Mayberry Date Issued
Associate Administrator
for Pipeline Safety

320201005_Closure Letter_12102020_text.pdf

VIA ELECTRONIC MAIL TO: Mathew.Ramsey@energytransfer.com,
Eric.Amundsen@energytransfer.com, and Jim.Wright@energytransfer.com
December 10, 2020
Mr. Matthew Ramsey
Chief Operating Officer
Energy Transfer
8111 Westchester Drive
Dallas, Texas 75225
Re: CPF 3-2020-1005
Dear Mr.Ramsey:
On December 4, 2020, the Pipeline and Hazardous Materials Administration (PHMSA) issued to
Panhandle Eastern Pipeline Company, LP, a Final Order in the above referenced case. This
Order included a Compliance Order and Civil Penalty assessment. Based on our review of the
documentation provided and confirmation of payment of the civil penalty, it has been determined
that you have complied with the terms of the Order.
This letter is to inform you no further action is necessary and this case is now closed. Thank you
for your cooperation.
Sincerely,
Gregory A. Ochs
Director, Central Region, OPS
Pipeline and Hazardous Materials Safety Administration
cc: Mr. Eric Amundsen, Senior Vice President, Energy Transfer, dba Panhandle Eastern
Pipeline Company, 1300 Main Street, Houston, TX 77002 Eric.Amundsen@energytransfer.com
Jim Wright, Chief Compliance Officer and EVP Legal, Energy Transfer,
Jim.Wright@energytransfer.com

320201005_NOPV PCP PCO_09092020_text.pdf

NOTICE OF PROBABLE VIOLATION
PROPOSED CIVIL PENALTY
and
PROPOSED COMPLIANCE ORDER
VIA ELECTRONIC MAIL TO: kelcy.warren@energytransfer.com ,
ryan.coffey@energytransfer.com and Eric.Amundsen@energytransfer.com
September 9, 2020
Mr. Kelcy Warren
Chief Executive Officer
Energy Transfer, LP
8111 Westchester Drive
Dallas, Texas 75225
CPF 3-2020-1005
Dear Mr. Warren:
On various dates from March 4, 2019 through September 20, 2019, representatives of the Pipeline
and Hazardous Materials Safety Administration (PHMSA), Office of Pipeline Safety (OPS),
pursuant to Chapter 601 of 49 United States Code (U.S.C.), inspected your Panhandle Eastern
Pipeline Company (PEPL) records and procedures in Houston, Texas and conducted records,
facilities, and right of way inspections in Oklahoma, Kansas, Missouri, and Illinois.
As a result of the inspection, it is alleged that you have committed Probable violations of the
Pipeline Safety Regulations, Title 49, Code of Federal Regulations (CFR). The items inspected
and the probable violations are:



1. 2. §192.167 Compressor stations: Emergency shutdown.
(a) Except for unattended field compressor stations of 1,000 horsepower (746
kilowatts) or less, each compressor station must have an emergency shutdown
system that meets the following:
(1) . . .
(4) It must be operable from at least two locations, each of which is:
(i) (ii) Outside the gas area of the station;
Near the exit gates, if the station is fenced, or near the
emergency exits, if not fenced; and
(iii) Not more than 500 feet (153 meters) from the limits of the
station
PEPL failed to provide operable emergency shutdown (ESD) systems in at least two
locations, each of which was outside the gas area of the compressor station and near the
exit gates of the fenced stations as required by §192.167(a)(4)(ii). PEPL’s Olpe
compressor station had new units installed after 1970 and therefore, PEPL, which is
currently fenced in, should have modified the ESD system to meet the requirements of
having two ESD switches outside the gas area near the exit gates. During PHMSA’s
inspection of the Olpe compressor station, the inspectors observed one of the ESD
switches located near a vehicle gate that was kept open during occupation and had a
nearby man gate that could be opened with a crash bar, and the other ESD switch was
located near a vehicle gate that was kept locked and had no man gate nearby. The
location of these ESDs were not compliant with §192.167(a)(4)(ii) because one the ESDs
was not located near an exit gate, and instead, by a vehicle gate that was locked.
Therefore, PEPL is in violation of §192.167(a)(4)(ii) because it failed to have ESDs in at
least two locations at the Olpe compressor station, each of which was outside the gas area
of the fenced in station and near the exit gates.
§192.605 Procedural manual for operations, maintenance, and emergencies
(a) . . .
(b) Maintenance and normal operations. The manual required by paragraph (a) of
this section must include procedures for the following, if applicable, to provide
safety during maintenance and operations.
(1) . . .
(3) Making construction records, maps, and operating history available to
appropriate operating personnel.
PEPL failed to follow its operation and maintenance (O&M) manual to ensure it made
available accurate maps to appropriate operating personnel. During the inspection,
PHMSA inspectors observed that the field maps and the electronic database that PEPL
made available to field employees had incorrect mapping at four locations.
2



3. Two major inaccuracies were indentified on PEPL’s mapping records. First, PEPL’s map
showed over half of the Preston lateral, which is approximately 2 miles long, was located
on the wrong side of the road. Second, PEPL’s map for the Bowling Green lateral, which
was less in length than the Preston lateral, showed a pipeline crossing to the west side of
the road that stayed there for a few hundred feet before returning to the east side of the
road. However, the Preston lateral never crossed the road in this area as shown when
PEPL located the line during the field inspection.
Additionally, two minor inaccuracies were also identified on PEPL’s mapping records for
the Windsor lateral. PEPL’s mapping record did not reflect that the pipeline had been
rerouted to maintain distance from a shop that was constructed by the land owner, and at
a location known as Bison Station, associated piping being had been removed.
Furthermore, the new pipe laid to reconnect the pipeline was not added to the maps.
§192.709 Transmission lines: Record keeping.
(a) . . .
(c) A record of each patrol, survey, inspection, and test required by subparts L and
M of this part must be retained for at least 5 years or until the next patrol,
survey, inspection, or test is completed, whichever is longer.
PEPL failed to retain records of each patrol, survey, inspection, and test required by
subpart M of part 192 for at least 5 years or until the next patrol, survey, inspection, or
test is completed, or whichever is longer. Specifically, PEPL failed to retain records
showing inspection and testing of pressure-limiting and regulating stations completed in
2017 per requirements of §192.739(a) for the Guymon Hansford Unit and Liberal (DCP)
Unit.
During the inspection, PEPL was unable to produce the 2017 inspection and testing
records for 78 pressure limiting and regulating devices at these locations. PEPL
explained that a contractor was used to perform relief valve and regulating station
inspections and testing, but the contracting company went out of business and the records
of their work completed for the year 2017 could not be obtained by PEPL. The only
records that PEPL could produce were records for the work performed prior to 2017 and
an invoice for work completed in the year 2017. Therefore, PEPL failed to retain
inspection and test records for pressure-limiting and regulating devices for at least five
years as required by §192.706(c).
3



4. 5. §192.745 Valve maintenance: Transmission lines.
(a) Each transmission line valve that might be required during any emergency must
be inspected and partially operated at intervals not exceeding 15 months, but at
least once each calendar year.
PEPL failed to inspect and partially operate transmission line valves that might be
required during an emergency at intervals not exceeding 15 months, but at least once
each calendar year. PHMSA inspectors identified during the records inspection that in
the Guymon/Hansford Area (Unit 18904), there were 80 valves which were not inspected
at least once each calendar year. Specifically, these 80 valves, which PEPL recorded as
being DOT regulated, which means requiring to be inspected per §192.745 because they
might be required during an emergency, were not inspected during calendar year 2017.
Additionally, PHMSA inspectors identified that 35 similar valves in the
Liberal(DCP)/Satanta (Unit 82882) were not inspected within the 15-month inspection
interval from 2016 to 2018. PEPL was the owner of these pipelines from 2016 to 2018,
with DCP providing operations and maintenances activities in which 115 transmission
valves failed to meet the regulatory requirements.
§192.905 How does an operator identify a high consequence area?
(a) . . .
(c) Newly identified areas. When an operator has information that the area around
a pipeline segment not previously identified as a high consequence area could
satisfy any of the definitions in § 192.903, the operator must complete the
evaluation using method (1) or (2). If the segment is determined to meet the
definition as a high consequence area, it must be incorporated into the
operator’s baseline assessment plan as a high consequence area within one year
from the date the area is identified.
PEPL failed to complete an evaluation to identify a high consequence area (HCA) using
method (1) or (2) from the definition of “High Consequence Area” contained in §192.903
when PEPL had information that the area around a pipeline segment not previously
identified as an HCA could satisfy any of the definitions in § 192.903. Specifically,
PEPL did not act upon new information in an area that was not previously identified as a
HCA. On July 13, 2007, PEPL personnel investigated a fireworks store that was built
230 feet from its pipeline, adjacent to the right-of-way, and found the store to have an
occupancy of 3 people, 6 days a week, for 52 weeks per year. Since the initial
assessment in 2007, the business expanded three times. The store expanded parallel to the
pipeline in 2011 and again in 2014. In 2017, the store expanded from the back of the
business toward the pipeline. Aerial imagery shows the expansions. However, during the
inspection, PEPL was unable to produce any records confirming it performed an
evaluation to determine if the segment met the definition of HCA.
4



In October 2019, after PHMSA inspectors inquired about PEPL’s knowledge of this
business’ expansion, and whether PEPL completed an evaluation under §192.905(c),
PEPL personnel contacted the store and received new information. The store was found
to have at least 21 people, 7 days a week for approximately 8.5 weeks per year, with less
than 10 people per day for the rest of the year. Although this new information did not
meet the definition of an HCA, PEPL failed to follow-up on information received from
patrolling and other notifications to perform the required evaluation under §192.905(c).
6. §192.937 What is a continual process of evaluation and assessment to maintain a
pipeline's integrity?
(a) . . .
(b) Evaluation. An operator must conduct a periodic evaluation as frequently as
needed to assure the integrity of each covered segment. The periodic evaluation
must be based on a data integration and risk assessment of the entire pipeline as
specified in §192.917. For plastic transmission pipelines, the periodic evaluation
is based on the threat analysis specified in §192.917(d) For all other transmission
pipelines, the evaluation must consider the past and present integrity assessment
results, data integration and risk assessment information (§192.917), and
decisions about remediation (§ 192.933)and additional preventive and mitigative
actions (§ 192.935).An operator must use the results from this evaluation to
identify the threats specific to each covered segment and the risk represented by
these threats.
PEPL failed to follow its integrity management plan for performing a continual process
of evaluation and assessment to maintain its pipeline integrity. As part of its periodic
evaluation, PEPL’s Integrity Management Plan Section 5.1 states: “Risk Assessment is
run annually on each HCA-managed segment to capture year -to-year changes in
operation, maintenance, and integrity-related activities.” PEPL failed to run its risk
model yearly in 2017 and 2018. The last record of risk model results was for 2016.
Proposed Civil Penalty
Under 49 U.S.C. § 60122 and 49 CFR § 190.223, you are subject to a civil penalty not to exceed
$218,647 per violation per day the violation persists, up to a maximum of $2,186,465 for a
related series of violations. For violations occurring on or after November 27, 2018 and before
July 31, 2019, the maximum penalty may not exceed $213,268 per violation per day, with a
maximum penalty not to exceed $2,132,679. For violations occurring on or after November 2,
2015 and before November 27, 2018, the maximum penalty may not exceed $209,002 per
violation per day, with a maximum penalty not to exceed $2,090,022. For violations occurring
prior to November 2, 2015, the maximum penalty may not exceed $200,000 per violation per
5



day, with a maximum penalty not to exceed $2,000,000 for a related series of violations. We
have reviewed the circumstances and supporting documentation involved for the above probable
violations and recommend that you be preliminarily assessed a civil penalty of $226,500 as
follows:
Item number
PENALTY
Item 3
Item 4
Item 6
$ 20,400
$145,000
$ 61,100
Warning Items
With respect to items 2 and 5, we have reviewed the circumstances and supporting documents
involved in this case and have decided not to conduct additional enforcement action or penalty
assessment proceedings at this time. We advise you to promptly correct these items. Failure to
do so may result in additional enforcement action.
Proposed Compliance Order
With respect to items 1 and 6, pursuant to 49 U.S.C. § 60118, the Pipeline and Hazardous
Materials Safety Administration proposes to issue a Compliance Order to Panhandle Eastern
Pipeline Company. Please refer to the Proposed Compliance Order, which is enclosed and made
a part of this Notice.
Response to this Notice
Enclosed as part of this Notice is a document entitled Response Options for Pipeline Operators
in Enforcement Proceedings. Please refer to this document and note the response options. All
material you submit in response to this enforcement action may be made publicly available. If
you believe that any portion of your responsive material qualifies for confidential treatment
under 5 U.S.C. 552(b), along with the complete original document you must provide a second
copy of the document with the portions you believe qualify for confidential treatment redacted
and an explanation of why you believe the redacted information qualifies for confidential
treatment under 5 U.S.C. 552(b).
Following the receipt of this Notice, you have 30 days to submit written comments, or request a
hearing under 49 CFR § 190.211. If you do not respond within 30 days of receipt of this Notice,
this constitutes a waiver of your right to contest the allegations in this Notice and authorizes the
Associate Administrator for Pipeline Safety to find facts as alleged in this Notice without further
notice to you and to issue a Final Order. If you are responding to this Notice, we propose that
you submit your correspondence to my office within 30 days from receipt of this Notice. This
period may be extended by written request for good cause.
In your correspondence on this matter, please refer to CPF 3-2020-1005 and, for each document
you submit, please provide a copy in electronic format whenever possible.
6



Sincerely,
William I. Rush
Acting Director, Central Region, OPS
Pipeline and Hazardous Materials Safety Administration
Enclosures: Proposed Compliance Order
Response Options for Pipeline Operators in Enforcement Proceedings
cc: Mr. Ryan Coffey, Executive Vice President, Operations,Energy Transfer, dba Panhandle
Eastern Pipeline Company, 800 E. Sonterra Blvd. #400, San Antonio, TX 78258
ryan.coffey@energytransfer.com
Mr. Eric Amundsen, Senior Vice President, Energy Transfer, dba Panhandle Eastern
Pipeline Company, 1300 Main Street, Houston, TX 77002,
Eric.Amundsen@energytransfer.com
7



PROPOSED COMPLIANCE ORDER
Pursuant to 49 United States Code § 60118, the Pipeline and Hazardous Materials Safety
Administration (PHMSA) proposes to issue to Panhandle Eastern Pipe Line Company (PEPL) a
Compliance Order incorporating the following remedial requirements to ensure the compliance
of PEPL with the pipeline safety regulations:
1. 2. 3. 4. In regard to Item 1 of the Notice pertaining to the location of emergency
shutdowns at the Olpe compressor station, PEPL must install or otherwise make
provisions for an exit gate near ESD #3 that meets the requirements in
§192.163(d).
In regard to Item 6 of the Notice pertaining to PEPL’s failure to run its risk model
yearly as required by its procedures, PEPL must run its risk model and integrate
the results so it can track its year to year changes.
PEPL must complete the requirements of Items 1 and 2 of the Complianc Order
within 90 days of receipt of a final order and provide documentation to Director,
Central Region, OPS Pipeline and Hazardous Materials Safety Administration.
It is requested (not mandated) that PEPL maintain documentation of the safety
improvement costs associated with fulfilling this Compliance Order and submit
the total to Director, Central Region, Pipeline and Hazardous Materials Safety
Administration. It is requested that these costs be reported in two categories: 1)
total cost associated with preparation/revision of plans, procedures, studies and
analyses, and 2) total cost associated with replacements, additions and other
changes to pipeline infrastructure.
8

## Provenance

- Official: Yes
- Source: <https://primis.phmsa.dot.gov/enforcement-data/case/320201005>
- Source ID: `phmsa-enforcement`
- SHA-256: `2614a1e62328cb506a574e54a781bf5bccf07214506502ef390b3bd81643ed3c`
- Retrieved: 2026-08-20T04:44:44.458Z
- Exported: 2026-08-23T23:04:37.362Z
- Document slug: `phmsa-enforcement-320201005`

### Source metadata

```json
{
  "cpf": "320201005",
  "operator": "PANHANDLE EASTERN PIPELINE CO",
  "region": "Central",
  "pipelineType": "GAS INTERSTATE ONSHORE",
  "caseStatus": "CLOSED",
  "citedSections": [
    "192.167(a)(4)(ii)",
    "192.605(b)(3)",
    "192.709(c)",
    "192.745(a)",
    "192.905(c)",
    "192.937(b)"
  ],
  "dataAsOf": "08/04/2026 12PM",
  "caseDataAsOf": "2026-08-04",
  "attachmentCount": 7,
  "attachments": [
    {
      "name": "320201005_Closure Letter_12102020.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/320201005/320201005_Closure%20Letter_12102020.pdf",
      "bytes": 246917,
      "category": "agency_document"
    },
    {
      "name": "320201005_Closure Letter_12102020_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/320201005/320201005_Closure%20Letter_12102020_text.pdf",
      "bytes": 80564,
      "category": "agency_document"
    },
    {
      "name": "320201005_Final Order_12042020.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/320201005/320201005_Final%20Order_12042020.pdf",
      "bytes": 394374,
      "category": "agency_document"
    },
    {
      "name": "320201005_Final Order_12042020_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/320201005/320201005_Final%20Order_12042020_text.pdf",
      "bytes": 111365,
      "category": "agency_document"
    },
    {
      "name": "320201005_NOPV PCP PCO_09092020.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/320201005/320201005_NOPV%20PCP%20PCO_09092020.pdf",
      "bytes": 325441,
      "category": "agency_document"
    },
    {
      "name": "320201005_NOPV PCP PCO_09092020_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/320201005/320201005_NOPV%20PCP%20PCO_09092020_text.pdf",
      "bytes": 163857,
      "category": "agency_document"
    },
    {
      "name": "320201005_Operator Response to Notice_10262020.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/320201005/320201005_Operator%20Response%20to%20Notice_10262020.pdf",
      "bytes": 205538,
      "category": "party_submission"
    }
  ],
  "extractedAgencyDocumentCount": 3,
  "attachmentPolicy": "Official attachment links are retained. Agency-issued documents may also include a verified local PDF and page-level text representation.",
  "jurisdiction": "US",
  "operatorName": "PANHANDLE EASTERN PIPELINE CO"
}
```