# USG WHEATLAND PIPELINE, LLC — Notice of Amendment

**Citation:** CPF 320206003M  
**Type / status:** enforcement / historical  
**Agency:** Pipeline and Hazardous Materials Safety Administration  
**Effective:** Not stated  
**Published:** 2020-11-12

CLOSED notice of amendment citing 195.230, 195.402(c)(3), 195.402(d)(3), 195.563(c), 195.573(d), 195.573(e), 195.585, 195.587.

## Document text

Notice of Amendment involving USG WHEATLAND PIPELINE, LLC. PHMSA's enforcement data identifies the cited regulations as 195.230,  195.402(c)(3),  195.402(d)(3),  195.563(c),  195.573(d),  195.573(e),  195.585,  195.587. The case was opened on 2020-11-12 and is reported as closed as of 2021-10-07. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

320206003M_Closure Letter_10072021_(18-163067S).pdf: https://primis.phmsa.dot.gov/enforcement-documents/320206003M/320206003M_Closure%20Letter_10072021_(18-163067S).pdf

320206003M_Closure Letter_10072021_(18-163067S)_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/320206003M/320206003M_Closure%20Letter_10072021_(18-163067S)_text.pdf

320206003M_Notice of Amendment_11122020.pdf: https://primis.phmsa.dot.gov/enforcement-documents/320206003M/320206003M_Notice%20of%20Amendment_11122020.pdf

320206003M_Notice of Amendment_11122020_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/320206003M/320206003M_Notice%20of%20Amendment_11122020_text.pdf

320206003M_Operator Response to Notice_12082020_(18-163067S).pdf: https://primis.phmsa.dot.gov/enforcement-documents/320206003M/320206003M_Operator%20Response%20to%20Notice_12082020_(18-163067S).pdf

320206003M_Notice of Amendment_11122020_text.pdf

NOTICE OF AMENDMENT
VIA ELECTRONIC MAIL TO: TJ.Tuscai@nexteraenergy.com
Larry.Wall@nexteraenergy.com and William.Meyer@nexteraenergy.com
November 12, 2020
TJ Tuscai
President, Gas Infrastructure
USG Wheatland Pipeline, LLC
601 Travis Street,
Houston, TX 77002
CPF 3-2020-6003M
Dear Mr. Tuscai:
From June 10 through July 12, 2019, a representative of the Pipeline and Hazardous Materials
Safety Administration (PHMSA), pursuant to Chapter 601 of 49 United States Code, inspected
(Wheatland) procedures for construction, operations and maintenance, operator qualification,
public awareness, damage prevention, facilities and storage, time dependent threats, and
emergency response in Williston, North Dakota.
On the basis of the inspection, PHMSA has identified the apparent inadequacies found within
Wheatland’s plans or procedures, as described below:
1. §195.230 Welds: Repair or removal of defects.
(a) Each weld that is unacceptable under §195.228 must be removed or repaired.
Except for welds on an offshore pipeline being installed from a pipe lay vessel, a weld
must be removed if it has a crack that is more than 8 percent of the weld length.



(b) Each weld that is repaired must have the defect removed down to sound metal
and the segment to be repaired must be preheated if conditions exist which would
adversely affect the quality of the weld repair. After repair, the segment of the weld
that was repaired must be inspected to ensure its acceptability.
(c) Repair of a crack, or of any defect in a previously repaired area must be in
accordance with written weld repair procedures that have been qualified under
§195.214. Repair procedures must provide that the minimum mechanical properties
specified for the welding procedure used to make the original weld are met upon
completion of the final weld repair.
Wheatland’s operation and maintenance (O&M) manual was inadequate because it did not have a
procedure specifying repair or removal of weld defects as part of its construction procedures.
Following the inspection, Wheatland developed and submitted procedure O&M Section 5.3.2.10
on September 5, 2019 that satisfactorily addressed this item. No further action is required.
2. §195.402 Procedural manual for operations, maintenance, and emergencies.
(d) Abnormal operation. The manual required by paragraph (a) of this section must
include procedures for the following to provide safety when operating design limits
have been exceeded:
(3) Correcting variations from normal operation of pressure and flow equipment and
controls.
Wheatland’s O&M manual was inadequate because it did not have a procedure for correcting
variations from normal operations of pressure flow equipment and controls. Wheatland must
amend its O&M plan to include such a procedure as required by §195.402(d)(3).
3. §195.402(c)(3) Procedural manual for operations, maintenance, and emergencies.
(c) Maintenance and normal operations. The manual required by paragraph (a) of
this section must include procedures for the following to provide safety during
maintenance and normal operations:
(3) Operating, maintaining, and repairing the pipeline system in accordance with
each of the requirements of this subpart and subpart H of this part.
§195.563 Which pipelines must have cathodic protection?
(c) All other buried or submerged pipelines that have an effective external coating
must have cathodic protection. (see Note below) Except as provided by paragraph (d)
of this section, this requirement does not apply to breakout tanks and does not apply
2



to buried piping in breakout tank areas and pumping stations until December 29,
2003
Wheatland’s O&M manual was inadequate because it incorrectly required operator personnel to
follow §195.565 and incorporated API 651 to determine whether cathodic protection is needed on
breakout tanks instead of §195.563. Section 195.563 requires cathodic protection on all breakout
tanks built after December 29, 2003. Wheatland must amend its O&M manual to include a
procedure for determining whether cathodic protection is needed on breakout tanks in accordance
with §195.563.
4. §195.402(c)(3) Procedural manual for operations, maintenance, and emergencies.
(c) Maintenance and normal operations. The manual required by paragraph (a) of
this section must include procedures for the following to provide safety during
maintenance and normal operations:
(3) Operating, maintaining, and repairing the pipeline system in accordance with
each of the requirements of this subpart and subpart H of this part.
§195.573 What must I do to monitor external corrosion control?
(d) Breakout tanks. You must inspect each cathodic protection system used to control
corrosion on the bottom of an aboveground breakout tank to ensure that operation
and maintenance of the system are in accordance with API RP 651 (incorporated by
reference, see § 195.3). However, this inspection is not required if you note in the
corrosion control procedures established under §195.402(c)(3) why complying with
all or certain operation and maintenance provisions of API RP 651 is not necessary
for the safety of the tank.
Wheatland’s O&M manual was inadequate because it did not have a procedure for inspecting
corrosion control on breakout tanks in accordance with §195.573. Wheatland must amend its
O&M manual to include a procedure that addresses the requirements of §195.573.
5. §195.402(c)(3) Procedural manual for operations, maintenance, and emergencies.
(c) Maintenance and normal operations. The manual required by paragraph (a) of
this section must include procedures for the following to provide safety during
maintenance and normal operations:
(3) Operating, maintaining, and repairing the pipeline system in accordance with
each of the requirements of this subpart and subpart H of this part.
§195.573 What must I do to monitor external corrosion control?
3



(e) Corrective action. You must correct any identified deficiency in corrosion control
as required by § 195.401(b). However, if the deficiency involves a pipeline in an
integrity management program under § 195.452, you must correct the deficiency as
required by § 195.452(h).
Wheatland’s O&M manual was inadequate because it did not have a procedure specifying repair
timing of corrosion control deficiencies. Following the inspection, Wheatland developed and
submitted procedure O&M Section 5.3.1 on July 18, 2019, that satisfactorily addressed this item.
No further action is required.
6. §195.402(c)(3) Procedural manual for operations, maintenance, and emergencies.
(c) Maintenance and normal operations. The manual required by paragraph (a) of
this section must include procedures for the following to provide safety during
maintenance and normal operations:
(3) Operating, maintaining, and repairing the pipeline system in accordance with
each of the requirements of this subpart and subpart H of this part.
§195.585 What must I do to correct corroded pipe?
(a) General corrosion. If you find pipe so generally corroded that the remaining wall
thickness is less than that required for the maximum operating pressure of the
pipeline, you must replace the pipe. However, you need not replace the pipe if you--
(1) Reduce the maximum operating pressure commensurate with the strength of the
pipe needed for serviceability based on actual remaining wall thickness; or
(2) Repair the pipe by a method that reliable engineering tests and analyses show can
permanently restore the serviceability of the pipe.
(b) Localized corrosion pitting. If you find pipe that has localized corrosion pitting to
a degree that leakage might result, you must replace or repair the pipe, unless you
reduce the maximum operating pressure commensurate with the strength of the pipe
based on actual remaining wall thickness in the pits.
Wheatland’s O&M manual was inadequate because it did not have a procedure for repairing or
replacing corroded pipe. Following the inspection, Wheatland developed and submitted procedure
O&M Section 5.3.2.10 on September 5, 2019, that satisfactorily addressed this item. No further
action is required.
4



7. §195.402(c)(3) Procedural manual for operations, maintenance, and emergencies.
(c) Maintenance and normal operations. The manual required by paragraph (a) of
this section must include procedures for the following to provide safety during
maintenance and normal operations:
(3) Operating, maintaining, and repairing the pipeline system in accordance with
each of the requirements of this subpart and subpart H of this part.
§195.587 What methods are available to determine the strength of corroded pipe?
Under §195.585, you may use the procedure in ASME/ANSI B31G (incorporated by
reference, see §195.3) or in PRCI PR-3-805 (R-STRENG) (incorporated by reference,
see §195.3) to determine the strength of corroded pipe based on actual remaining wall
thickness. These procedures apply to corroded regions that do not penetrate the pipe
wall, subject to the limitations set out in the respective procedures.
Wheatland’s O&M manual was inadequate because it did not have a procedure for determining
the strength of corroded pipe in accordance with §195.587. Wheatland developed and submitted
procedure O&M Section 5.3.2.2 on September 5, 2019 that satisfactorily addressed this item. No
further action is required.
Response to this Notice
This Notice is provided pursuant to 49 U.S.C. § 60108(a) and 49 C.F.R. § 190.206. Enclosed as
part of this Notice is a document entitled Response Options for Pipeline Operators in Enforcement
Proceedings. Please refer to this document and note the response options. Be advised that all
material you submit in response to this enforcement action is subject to being made publicly
available. If you believe that any portion of your responsive material qualifies for confidential
treatment under 5 U.S.C. 552(b), along with the complete original document you must provide a
second copy of the document with the portions you believe qualify for confidential treatment
redacted and an explanation of why you believe the redacted information qualifies for confidential
treatment under 5 U.S.C. 552(b).
Following the receipt of this Notice, you have 30 days to submit written comments, revised
procedures, or a request for a hearing under §190.211. If you do not respond within 30 days of
receipt of this Notice, this constitutes a waiver of your right to contest the allegations in this Notice
and authorizes the Associate Administrator for Pipeline Safety to find facts as alleged in this Notice
without further notice to you and to issue an Order Directing Amendment. If your plans or
procedures are found inadequate as alleged in this Notice, you may be ordered to amend your plans
or procedures to correct the inadequacies (49 C.F.R. § 190.206). If you are not contesting this
Notice, we propose that you submit your amended procedures to my office within 60 days of
receipt of this Notice. This period may be extended by written request for good cause. Once the
inadequacies identified herein have been addressed in your amended procedures, this enforcement
action will be closed.
5



It is requested (not mandated) that USG Wheatland Pipeline, LLC maintain documentation of the
safety improvement costs associated with fulfilling this Notice of Amendment
(preparation/revision of plans, procedures) and submit the total to Greg Ochs, Director, Central
Region, Pipeline and Hazardous Materials Safety Administration. In correspondence concerning
this matter, please refer to CPF 3-2020-6003M and, for each document you submit, please provide
a copy in electronic format whenever possible.
Sincerely,
Gregory A. Ochs
Director, Central Region, OPS
Pipeline and Hazardous Materials Safety Administration
Enclosure: Response Options for Pipeline Operators in Enforcement Proceedings
Cc: Larry Wall, Chief Commercial Officer, USG Wheatland Pipeline, LLC, 601 Travis Street,
Houston, TX 77002, Larry.Wall@nexteraenergy.com
William (Bill) Meyer, Director, Asset Integrity and Regulatory Affair, NextEra™ Energy Pipeline
Services, 601 Travis, Suite 1900, Houston, TX 77002,
William.Meyer@nexteraenergy.com
6

320206003M_Closure Letter_10072021_(18-163067S)_text.pdf

VIA ELECTRONIC MAIL TO: TJ.Tuscai@nexteraenergy.com
Larry.Wall@nexteraenergy.com and William.Meyer@nexteraenergy.com
October 7, 2021
TJ Tuscai, President, Gas Infrastructure
USG Wheatland Pipeline, LLC
601 Travis Street,
Houston, TX 77002
Re: CPF 3-2020-6003M
Dear Mr. Tuscai:
From June 10 through July 12, 2019, a representative from the Pipeline and Hazardous Materials
Safety Administration (PHMSA), pursuant to chapter 601 of 49 United States Code, conducted an
on-site pipeline safety inspection of USG Wheatland Pipeline, LLC procedures in Williston, North
Dakota. As a result of the inspection, USG Wheatland Pipeline, LLC was issued a Notice of
Amendment on November 12, 2020, which proposed amendments of your procedures.
USG Wheatland Pipeline, LLC submitted its amended procedures on October 6, 2021. My staff
reviewed the amended procedures and it appears that the inadequacies outlined in this Notice of
Amendment have been corrected.
This letter is to inform you no further action is necessary and this case is now closed. Thank you
for your cooperation.
Sincerely,
Gregory A. Ochs
Director, Central Region, OPS
Pipeline and Hazardous Materials Safety Administration
cc: Larry Wall, Chief Commercial Officer, USG Wheatland Pipeline, LLC, 601 Travis Street,
Houston, TX 77002, Larry.Wall@nexteraenergy.com
William (Bill) Meyer, Director, Asset Integrity and Regulatory Affair, NextEra™ Energy Pipeline
Services, 601 Travis, Suite 1900, Houston, TX 77002, William.Meyer@nexteraenergy.com

## Provenance

- Official: Yes
- Source: <https://primis.phmsa.dot.gov/enforcement-data/case/320206003M>
- Source ID: `phmsa-enforcement`
- SHA-256: `d1c8afcff32f3b5099fe93bb25ce6ae2b20c30274a6212897bd3f7e1d375b68b`
- Retrieved: 2026-08-20T04:44:44.458Z
- Exported: 2026-08-22T11:16:55.785Z
- Document slug: `phmsa-enforcement-320206003m`

### Source metadata

```json
{
  "cpf": "320206003M",
  "operator": "USG WHEATLAND PIPELINE, LLC",
  "region": "Central",
  "pipelineType": "INTRASTATE LIQUID ONSHORE",
  "caseStatus": "CLOSED",
  "citedSections": [
    "195.230",
    "195.402(c)(3)",
    "195.402(d)(3)",
    "195.563(c)",
    "195.573(d)",
    "195.573(e)",
    "195.585",
    "195.587"
  ],
  "dataAsOf": "08/04/2026 12PM",
  "caseDataAsOf": "2026-08-04",
  "attachmentCount": 5,
  "attachments": [
    {
      "name": "320206003M_Closure Letter_10072021_(18-163067S).pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/320206003M/320206003M_Closure%20Letter_10072021_(18-163067S).pdf",
      "bytes": 256159,
      "category": "agency_document"
    },
    {
      "name": "320206003M_Closure Letter_10072021_(18-163067S)_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/320206003M/320206003M_Closure%20Letter_10072021_(18-163067S)_text.pdf",
      "bytes": 83510,
      "category": "agency_document"
    },
    {
      "name": "320206003M_Notice of Amendment_11122020.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/320206003M/320206003M_Notice%20of%20Amendment_11122020.pdf",
      "bytes": 296647,
      "category": "agency_document"
    },
    {
      "name": "320206003M_Notice of Amendment_11122020_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/320206003M/320206003M_Notice%20of%20Amendment_11122020_text.pdf",
      "bytes": 130406,
      "category": "agency_document"
    },
    {
      "name": "320206003M_Operator Response to Notice_12082020_(18-163067S).pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/320206003M/320206003M_Operator%20Response%20to%20Notice_12082020_(18-163067S).pdf",
      "bytes": 109766,
      "category": "party_submission"
    }
  ],
  "extractedAgencyDocumentCount": 2,
  "attachmentPolicy": "Official attachment links are retained. Agency-issued documents may also include a verified local PDF and page-level text representation.",
  "jurisdiction": "US",
  "operatorName": "USG WHEATLAND PIPELINE, LLC"
}
```
