# COUNTRYMARK REFINING AND LOGISTICS, LLC — Notice of Amendment

**Citation:** CPF 32025017NOA  
**Type / status:** enforcement / historical  
**Agency:** Pipeline and Hazardous Materials Safety Administration  
**Effective:** Not stated  
**Published:** 2025-07-02

CLOSED notice of amendment citing 195.402(a), 195.402(d)(4), 195.446(a), 195.446(b)(3), 195.446(c)(1), 195.446(d)(2), 195.446(e)(1), 195.446(e)(3).

## Document text

Notice of Amendment involving COUNTRYMARK REFINING AND LOGISTICS, LLC. PHMSA's enforcement data identifies the cited regulations as 195.402(a),  195.402(d)(4),  195.446(a),  195.446(b)(3),  195.446(c)(1),  195.446(d)(2),  195.446(e)(1),  195.446(e)(3). The case was opened on 2025-07-02 and is reported as closed as of 2025-09-17. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

32025017NOA_Closure Letter_09172025_(24-297198).pdf: https://primis.phmsa.dot.gov/enforcement-documents/32025017NOA/32025017NOA_Closure%20Letter_09172025_(24-297198).pdf

32025017NOA_Closure Letter_09172025_(24-297198)_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/32025017NOA/32025017NOA_Closure%20Letter_09172025_(24-297198)_text.pdf

32025017NOA_Notice of Amendment_07022025_(24-297198).pdf: https://primis.phmsa.dot.gov/enforcement-documents/32025017NOA/32025017NOA_Notice%20of%20Amendment_07022025_(24-297198).pdf

32025017NOA_Notice of Amendment_07022025_(24-297198)_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/32025017NOA/32025017NOA_Notice%20of%20Amendment_07022025_(24-297198)_text.pdf

32025017NOA_Operator Response to Notice_07252025_(24-297198).pdf: https://primis.phmsa.dot.gov/enforcement-documents/32025017NOA/32025017NOA_Operator%20Response%20to%20Notice_07252025_(24-297198).pdf

32025017NOA_Notice of Amendment_07022025_(24-297198)_text.pdf

NOTICE OF AMENDMENT
VIA ELECTRONIC MAIL TO: matt.smorch@countrymark.com, blair.currie@countrymark.com
July 2, 2025
Mr. Matt Smorch
President and CEO
CountryMark Refining and Logistics, LLC
225 S. East St, Suite 144
Indianapolis, IN 46202
CPF 3-2025-017-NOA
Dear Mr. Smorch:
From August 5 through September 24, 2024, a representative of the Pipeline and Hazardous
Materials Safety Administration (PHMSA), pursuant to Chapter 601 of 49 United States Code
(U.S.C.), inspected the plans and procedures for Control Room Management (CRM) of
CountryMark Refining and Logistics, LLC (CountryMark) in Mount Vernon, Indiana.
As a result of the inspection, PHMSA has identified the following apparent inadequacies within
CountryMark’s plans or procedures. The items inspected, alleged inadequacies, and proposed
revisions are described below:
1. § 195.402 Procedural manual for operations, maintenance, and emergencies.
(a) General. Each operator shall prepare and follow for each pipeline system a
manual of written procedures for conducting normal operations and maintenance
activities and handling abnormal operations and emergencies. This manual shall be
reviewed at intervals not exceeding 15 months, but at least once each calendar year,
and appropriate changes made as necessary to insure that the manual is effective.
This manual shall be prepared before initial operations of a pipeline system
commence, and appropriate parts shall be kept at locations where operations and
maintenance activities are conducted.
(b) . . . .



(d) Abnormal operation. The manual required by paragraph (a) of this section must
include procedures for the following to provide safety when operating design limits
have been exceeded:
(1) . . . .
(4) Notifying responsible operator personnel when notice of an abnormal operation is
received.
CountryMark’s CRM Program (rev. 14, effective July 2024) (CRM Plan), section 3.5.2, and its
Operation and Maintenance Plan, (rev. 5, effective August 25, 2020) (O&M Plan), Procedure
195.402(d), were not adequate to ensure notification of responsible operator personnel when notice
of an abnormal operation (AO) is received, per the requirements of § 195.402(d)(4). Specifically,
the CRM Plan and O&M Plan failed to require field personnel to call the control room when an
AO is discovered, and failed to define who is responsible for documenting AOs and the method of
documenting and recording them.
49 CFR § 195.402(d)(4) requires an operator to notify “responsible operator personnel when notice
of an abnormal operation is received” and § 195.446(f)(2) requires an operator’s field personnel
“to contact the control room when emergency conditions exist and when making field changes that
affect control room operations.” O&M Plan, Procedure 195.402(d), step 9 failed to include a step
for field personnel to call the control room when an AO is discovered. This step was a part of
CountryMark’s practice, but it was not included in their procedure.
O&M Plan, section 14, “Abnormal Operation Incident Report,” required reporting of an AO on a
form with no further reference. O&M Plan section 16, step 1, stated that the supervisor at the site
of the AO will complete Form “F-195.402(d)(5) Abnormal Operation: Procedure Review.”
However, the form itself stated the Manager of Pipeline Operations or the Pipeline Terminal
Manager reviews the form, assesses it, and documents “any revisions that should be made to
CountryMark procedures.” This is not included in the O&M Plan. Additionally, O&M Plan,
Procedure 195.402(d), step 2 listed additional personnel who were authorized to review the AO
response to determine its effectiveness.
The control room, however, uses a different process to document AOs. CRM Plan section 3.5.2.6
only required the controller to document and communicate the AO condition during shift
handover. CRM Plan, section 7.2, stated:
The Pipeline Controller will document by making a log entry in POEMS CRM
Software Suite when and under what circumstances the control room is contacted
by field personnel concerning changes that could affect control room operations.
These along with internal data such as near miss, [Abnormal Operating Condition]
documentation and incident data are reviewed by the Pipeline Control Center
Supervisor to confirm contact to the control room is being made as required.
During the inspection, the operator demonstrated that the application POEMS CRM Software Suite
was used for logging and documenting AOs. It is unclear, however, from the two procedures—
the O&M and CRM Plan—whether the two methods of reporting AOs are merged into one record
and reviewed, or if there are separate reviews.



Therefore, both the CRM Plan and O&M Plan require revision to meet the requirements of
§§ 195.446(b)(2), 195.402(d)(4), and 195.446(f)(2). These procedures must be amended to
include: a requirement for field personnel to contact the control room if they identify an abnormal
operation, the method for controllers to document the AO consistent with the current practice,
consistency between all O&M procedures for who is responsible for completing and reviewing the
Abnormal Operation Incident Report, and how the POEM CRM Software Suite will be
incorporated into these reviews.
2. § 195.446 Control room management.
(a) General. This section applies to each operator of a pipeline facility with a
controller working in a control room who monitors and controls all or part of a
pipeline facility through a SCADA system. Each operator must have and follow
written control room management procedures that implement the requirements of
this section. . . .
(b) Roles and responsibilities. Each operator must define the roles and responsibilities
of a controller during normal, abnormal, and emergency operating conditions. To
provide for a controller's prompt and appropriate response to operating conditions,
an operator must define each of the following:
(1) . . . .
(3) A controller's role during an emergency, even if the controller is not the first to
detect the emergency, including the controller's responsibility to take specific actions
and to communicate with others.
The CRM Plan, section 3.5.3, was not adequate to demonstrate compliance with § 195.446(b)(3)
because it did not define a controller’s role during an emergency. Specifically, it did not provide
a process for approval to restart the pipeline after a shut down. CRM Plan section 3.2, “Authority
and Responsibility,” stated, "the Pipeline Controller on duty has the authority and responsibility
to shut down any pipeline which they are operating if there are any possible indications of a
release." This section also provided that restart requires approval from the “Manager of Pipeline
Maintenance, Pipeline Operations Manager, Pipeline Control Center Supervisor, or the Director
of Midstream.” CRM Plan section 3.5.3 stated,
“the Pipeline Controller can start-up the line after
approval from the Manager of Pipeline Maintenance, Operations Supervisor, or the Manager of
Crude Gathering and Transportation.”
However, O&M Plan, Procedure 195.402(e), “Emergency Response,” section 10.3, stated,
“[t]he
responsibility for all actions in response to an emergency, rests with the Pipeline Superintendent.
He will determine shutdowns, isolation of line segments, repairs, tests, and restarts as required….”
This appears to conflict with the CRM Plan, especially since controllers are directed to follow
O&M Plan, Procedure 195.402(e), “Emergency Response,” in CRM Plan section 3.5.3.
CountryMark did not have a detailed process of defining how the decision to restart will be made,
how that decision will be documented, and how the decision will be communicated to the
controller. The practice in place was not consistent. CountryMark personnel indicated during the
inspection that sometimes the authorization was given verbally and sometimes written, through
email. The decision to restart after shutdown, especially after an indication of rupture or leak, is a



critical decision to avoid the potential for exacerbating the situation and contributing more to an
event, and therefore, it should be clearly detailed in the procedure.
Additionally, section 10.3 of O&M Plan, Procedure 195.402(e), “Emergency Response,” stated,
"[a]ll emergencies should be called into the dispatcher." This makes calling into the control room
(dispatcher) optional. Having the call, which reports the presence of an emergency, be optional
hinders a controller’s ability to execute their role during emergencies. Controllers must be notified
of emergencies for controllers to execute their roles and responsibilities during emergencies.
In addition, § 195.402(e)(10) requires an operator’s manual for operations, maintenance, and
emergencies to include procedures for actions to be taken by a controller during an emergency, in
accordance with the emergency plans required by § 195.446. Considering the inadequate
procedures described above which failed to meet the compliance requirements of § 195.446(b)(3),
the procedures were also inadequate to satisfy § 195.402(e)(10).
The procedures must be amended to provide clear and consistent processes defining who has the
authority for restart after a pipeline shut down for reasons other than normal operations.
Considerations for the determination of restart must be included. The procedure also must define
the method to document the authorization for restart and its communication to the control room.
3. § 195.446 Control room management.
(a) General. This section applies to each operator of a pipeline facility with a
controller working in a control room who monitors and controls all or part of a
pipeline facility through a SCADA system. Each operator must have and follow
written control room management procedures that implement the requirements of
this section.
(b) . . . .
(c) Provide adequate information. Each operator must provide its controllers with the
information, tools, processes and procedures necessary for the controllers to carry
out the roles and responsibilities the operator has defined by performing each of the
following:
(1) Implement API RP 1165 (incorporated by reference, see § 195.3) whenever a
SCADA system is added, expanded or replaced, unless the operator demonstrates
that certain provisions of API RP 1165 are not practical for the SCADA system used;
CountryMark’s CRM Plan, section 4.4, was not adequate to demonstrate compliance with
§ 195.446(c)(1) for providing controllers the information, tools, processes, and procedures to carry
out their responsibilities. Specifically, CountryMark did not provide definitions or examples of
“added, expanded or replaced” related to when to implement API RP 1165 in its SCADA system.
Absent definitions or examples, the CRM Plan does not provide sufficient guidance on when to
implement API RP 1165. Furthermore, CRM Plan, section 4.4, misstated the regulation. Section
4.4 used the language,
“modified, expanded, or replaced,” whereas the language of the regulation
is “added, expanded or replaced.” Additionally, Form F-195.446(c)(1) stated, “[t]his form should
be completed after a SCADA system change is added, expanded or repaired.” “Repaired” is an
inappropriate word and is not consistent with to the procedure or regulatory language.



The procedure must be amended to provide definitions for added, expanded, and replaced, as well
as examples that reflect the definitions. Also, the procedure and form must be amended to reflect
the regulatory language.
4. § 195.446 Control room management.
(a) General. This section applies to each operator of a pipeline facility with a
controller working in a control room who monitors and controls all or part of a
pipeline facility through a SCADA system. Each operator must have and follow
written control room management procedures that implement the requirements of
this section .
(b) . . . .
(d) Fatigue mitigation. Each operator must implement the following methods to
reduce the risk associated with controller fatigue that could inhibit a controller's
ability to carry out the roles and responsibilities the operator has defined:
(1) . . . .
(2) Educate controllers and supervisors in fatigue mitigation strategies and how off-
duty activities contribute to fatigue.
CountyMark’s CRM Plan, section 5.9, and related Form F-195.446(h), were not adequate to
demonstrate that controllers and supervisors were educated in fatigue mitigation strategies and
how off-duty activities contribute to fatigue, as required by § 195.446(d)(2). CRM Plan, section
5.9, listed criteria to consider when evaluating the effectiveness of the fatigue training program.
For example, criteria listed included “[i]ncrease in Pipeline Controller reports of potential fatigue”
and “[i]ncrease use of fatigue mitigation tactics.” However, the CRM Plan did not provide values
or measures to determine effectiveness of the training. Absent values or measures to determine
effectiveness, it cannot be determined that the education program had any effect.1 Additionally,
section 5.9 required test scoring; however, no corresponding test was included on Form F-
195.446(h). Form F-195.446(h) only considered training completion.
Country Mark used Form 195.446(h) as the form to document a review of the fatigue training
program. Form F-195.446(h) did not include all the criteria listed in CRM Plan section 5.9. CRM
Plan section 5.9 listed “Increase in Pipeline Controller reports of potential fatigue” but the form
provided for “Number of reports of fatigue or potential fatigue;” however, the form had no history
of data section to calculate a difference, year-on-year or greater. None of the other criteria listed
in CRM Plan, section 5.9, were included in the form.
The CRM Plan needs to be amended to provide measures to support the criteria for determining
training effectiveness. Form F-195.446(h) needs to be amended to require the documentation of
the criteria data, analysis, findings and document the review to determine if the fatigue education
and training program is effective once each calendar year not to exceed 15 months.
1 Per § 195.402(a) and (c)(13), respectively, the manual for operations, maintenance, and emergencies must be
reviewed at intervals not exceeding 15 months, but at least once each calendar year, and appropriate changes made
as necessary to insure that the manual is effective; and the manual must include procedures for periodically
reviewing the work done by operator personnel to determine the effectiveness of the procedures used in normal
operation and maintenance and taking corrective action where deficiencies are found.



5. § 195.446 Control room management.
(a) General. This section applies to each operator of a pipeline facility with a
controller working in a control room who monitors and controls all or part of a
pipeline facility through a SCADA system. Each operator must have and follow
written control room management procedures that implement the requirements of
this section.
(b) . . . .
(e) Alarm management. Each operator using a SCADA system must have a written
alarm management plan to provide for effective controller response to alarms. An
operator's plan must include provisions to:
(1) Review SCADA safety-related alarm operations using a process that ensures
alarms are accurate and support safe pipeline operations.
CountryMark’s Alarm Management Program (rev. 3, effective October 2012) (ALM Plan), section
1.7, “Roles and Responsibilities,” was not adequate to demonstrate compliance with having a
process that ensures alarms are accurate and support safe pipeline operations, as required by
§ 195.446(e)(1). Specifically, the ALM Plan required the controller to “[i]nitiate work requests to
repair malfunctioning field devices responsible for nuisance alarms.” CountryMark employed a
work order system named “The D365 System” (D365). Controllers could create and submit a
ticket to D365 that is reviewed by the supervisor or manager of the control room. The ticket then
was sent to field operations for further review. The field operations assigned the ticket to a group
or individual for follow-up. This process was not described or detailed in any process or training
content. There are various priority levels in D365 to assign to tickets which represent time
requirements for tickets to be completed. Examples include annual maintenance tasks, complete
in 30 days, etc. These priorities, or how to select the appropriate priority for a task, were not
identified in any procedure. As “[i]nitiate work requests” is specifically identified in a controller’s
roles and responsibilities, there should be a procedure and training content for D365, since it is
used to initiate SCADA safety-related alarm operations reviews.
While the D365 system is a powerful tool to create, assign, and document work, there was not a
process to track progress or completion of tickets to verify the priority requirements were being
met or to escalate tickets that were exceeding the priority established time limits. Exceeding
priority time limits would be considered a deficiency of CountryMark’s ALM Plan required by
§ 195.446(e)(6).
The ALM Plan must be amended to detail the conditions and steps to create a work ticket in the
D365 system. It must define the priorities and time limits to complete the ticket and define who
is responsible for the review and the frequency of the review of completed and outstanding work
tickets for control room generated tickets. The ALM Plan also needs to include a process for
escalation of review where there is a designated exceedance of the priority limits.
6. § 195.446 Control room management.
(a) General. This section applies to each operator of a pipeline facility with a
controller working in a control room who monitors and controls all or part of a



pipeline facility through a SCADA system. Each operator must have and follow
written control room management procedures that implement the requirements of
this section.
(b) . . . .
(e) Alarm management. Each operator using a SCADA system must have a written
alarm management plan to provide for effective controller response to alarms. An
operator's plan must include provisions to:
(1) . . . .
(3) Verify the correct safety-related alarm set-point values and alarm descriptions
when associated field instruments are calibrated or changed and at least once each
calendar year, but at intervals not to exceed 15 months.
CountryMark’s CRM Plan, section 6.6, was not adequate to demonstrate compliance with
§ 195.446(e)(3) because it simply restated the regulation and did not provide a process to identify
who is responsible for the review, how the review will be conducted, what information will be
used as the set point and description standard, how identified deficiencies will be documented, and
how the activity for the verification will be recorded.
The CRM Plan must be amended to provide details on who is responsible for the review, how the
review will be conducted, what information will be used as the set point and description standard,
how identified deficiencies will be documented, and how the activity for the verification will be
recorded. This must include considerations for when field instruments are calibrated or changed
as well as at least once each calendar year, but at intervals not to exceed 15 months.
Response to this Notice
This Notice is provided pursuant to 49 U.S.C. § 60108(a) and 49 CFR § 190.206. Enclosed as part
of this Notice is a document entitled Response Options for Pipeline Operators in Enforcement
Proceedings.
Please refer to this document and note the response options. Be advised that all material you
submit in response to this enforcement action is subject to being made publicly available. If you
believe that any portion of your responsive material qualifies for confidential treatment under
5 U.S.C. § 552(b), along with the complete original document you must provide a second copy of
the document with the portions you believe qualify for confidential treatment redacted and an
explanation of why you believe the redacted information qualifies for confidential treatment under
5 U.S.C. § 552(b).
Following the receipt of this Notice, you have 30 days to submit written comments, revised
procedures, or a request for a hearing under § 190.211. If you do not respond within 30 days of
receipt of this Notice, this constitutes a waiver of your right to contest the allegations in this Notice
and authorizes the Associate Administrator for Pipeline Safety to find facts as alleged in this Notice
without further notice to you and to issue an Order Directing Amendment. If your plans or
procedures are found inadequate as alleged in this Notice, you may be ordered to amend your plans
or procedures to correct the inadequacies (49 CFR § 190.206). If you are not contesting this



Notice, we propose that you submit your amended procedures to my office within 30 days of
receipt of this Notice. This period may be extended by written request for good cause. Once the
inadequacies identified herein have been addressed in your amended procedures, this enforcement
action will be closed.
It is requested (not mandated) that CountryMark Refining and Logistics, LLC maintain
documentation of the safety improvement costs associated with fulfilling this Notice of
Amendment (preparation/revision of plans, procedures) and submit the total to the Director,
Central Region, Pipeline and Hazardous Materials Safety Administration. In correspondence
concerning this matter, please refer to CPF 3-2025-017-NOA and, for each document you submit,
please provide a copy in electronic format whenever possible.
Sincerely,
David Barrett
Acting Director, Central Region, Office of Pipeline Safety
Pipeline and Hazardous Materials Safety Administration
cc: Blair Currie, Manager Pipeline Integrity, CountryMark, blair.currie@countrymark.com
Enclosure: Response Options for Pipeline Operators in Enforcement Proceedings

32025017NOA_Closure Letter_09172025_(24-297198)_text.pdf

U.S. Department
of Transportation
Pipeline and Hazardous
Materials Safety
901 Locust Street, Suite 480
Kansas City, MO 64106
VIA ELECTRONIC MAIL TO: matt.smorch@countrymark.com, blair.currie@countrymark.com
September 17, 2025
Mr. Matt Smorch
President and CEO
CountryMark Refining and Logistics, LLC
225 S. East St, Suite 144
Indianapolis, IN 46202
RE: CPF 3-2025-017-NOA
Dear Mr. Smorch:
From August 5 through September 24, 2024, a representative of the Pipeline and Hazardous
Materials Safety Administration (PHMSA), pursuant to Chapter 601 of 49 United States Code
(U.S.C.), inspected the plans and procedures for Control Room Management (CRM) of
CountryMark Refining and Logistics, LLC (CountryMark) in Mount Vernon, Indiana.
On July 2, 2025, pursuant to 49 CFR § 190.206, PHMSA issued a Notice of Amendment which
proposed amendment of CountryMark’s plans and procedures.
CountryMark submitted its amended procedures on September 17, 2025. PHMSA has reviewed
the amended procedures, and it appears that the inadequacies outlined in the Notice of Amendment
have been corrected.
This letter is to inform you that no further action is necessary, and this case is now closed. Thank
you for your cooperation.
Sincerely,
David Barrett
Acting Director, Central Region, Office of Pipeline Safety
Pipeline and Hazardous Materials Safety Administration
cc: Blair Currie, Manager Pipeline Integrity, CountryMark, blair.currie@countrymark.com

## Provenance

- Official: Yes
- Source: <https://primis.phmsa.dot.gov/enforcement-data/case/32025017NOA>
- Source ID: `phmsa-enforcement`
- SHA-256: `0229366d1d5305c06d0b2d50e15134418f3c0992e8129bc29fae2c454a999757`
- Retrieved: 2026-08-20T04:44:44.458Z
- Exported: 2026-08-22T13:20:58.887Z
- Document slug: `phmsa-enforcement-32025017noa`

### Source metadata

```json
{
  "cpf": "32025017NOA",
  "operator": "COUNTRYMARK REFINING AND LOGISTICS, LLC",
  "region": "Central",
  "pipelineType": "INTERSTATE LIQUID",
  "caseStatus": "CLOSED",
  "citedSections": [
    "195.402(a)",
    "195.402(d)(4)",
    "195.446(a)",
    "195.446(b)(3)",
    "195.446(c)(1)",
    "195.446(d)(2)",
    "195.446(e)(1)",
    "195.446(e)(3)"
  ],
  "dataAsOf": "08/04/2026 12PM",
  "caseDataAsOf": "2026-08-04",
  "attachmentCount": 5,
  "attachments": [
    {
      "name": "32025017NOA_Closure Letter_09172025_(24-297198).pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/32025017NOA/32025017NOA_Closure%20Letter_09172025_(24-297198).pdf",
      "bytes": 222391,
      "category": "agency_document"
    },
    {
      "name": "32025017NOA_Closure Letter_09172025_(24-297198)_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/32025017NOA/32025017NOA_Closure%20Letter_09172025_(24-297198)_text.pdf",
      "bytes": 153957,
      "category": "agency_document"
    },
    {
      "name": "32025017NOA_Notice of Amendment_07022025_(24-297198).pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/32025017NOA/32025017NOA_Notice%20of%20Amendment_07022025_(24-297198).pdf",
      "bytes": 379755,
      "category": "agency_document"
    },
    {
      "name": "32025017NOA_Notice of Amendment_07022025_(24-297198)_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/32025017NOA/32025017NOA_Notice%20of%20Amendment_07022025_(24-297198)_text.pdf",
      "bytes": 207293,
      "category": "agency_document"
    },
    {
      "name": "32025017NOA_Operator Response to Notice_07252025_(24-297198).pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/32025017NOA/32025017NOA_Operator%20Response%20to%20Notice_07252025_(24-297198).pdf",
      "bytes": 550570,
      "category": "party_submission"
    }
  ],
  "extractedAgencyDocumentCount": 2,
  "attachmentPolicy": "Official attachment links are retained. Agency-issued documents may also include a verified local PDF and page-level text representation.",
  "jurisdiction": "US",
  "operatorName": "COUNTRYMARK REFINING AND LOGISTICS, LLC"
}
```