# NORTHERN NATURAL GAS CO — Corrective Action Order

**Citation:** CPF 32026002CAO  
**Type / status:** enforcement / current  
**Agency:** Pipeline and Hazardous Materials Safety Administration  
**Effective:** Not stated  
**Published:** 2026-01-17

OPEN corrective action order.

## Document text

Corrective Action Order involving NORTHERN NATURAL GAS CO. The dataset does not identify a cited regulation for this case. The case was opened on 2026-01-17 and is reported as open. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

32026002CAO_Corrective Action Order_01172026_(26-362536).pdf: https://primis.phmsa.dot.gov/enforcement-documents/32026002CAO/32026002CAO_Corrective%20Action%20Order_01172026_(26-362536).pdf

32026002CAO_Corrective Action Order_01172026_(26-362536)_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/32026002CAO/32026002CAO_Corrective%20Action%20Order_01172026_(26-362536)_text.pdf

32026002CAO_Corrective Action Order_01172026_(26-362536)_text.pdf

U.S. Department
of Transportation
Pipeline and Hazardous
Materials Safety
Administration
1200 New Jersey Avenue, SE
Washington, DC 20590
January 17, 2026
VIA ELECTRONIC MAIL TO: brian.mundt@nngco.com
Brian Mundt
President/CEO
Northern Natural Gas Company
1111 South 103rd Street
Omaha, Nebraska 68124
Re: CPF No. 3-2026-002-CAO
Dear Mr. Mundt,
Enclosed please find a Corrective Action Order (CAO or Order) issued by the Pipeline and
Hazardous Materials Safety Administration (PHMSA), Office of Pipeline Safety (OPS). The CAO
requires Northern Natural Gas Company (NNG) to take certain corrective actions with respect to
the pipeline failure that occurred on January 16, 2026, on the 20-inch M440B pipeline
approximately two miles west of Willow River, Minnesota.
Service of the CAO by electronic mail is effective upon the date of transmission and
acknowledgment of receipt as provided under 49 CFR § 190.5. The terms and conditions of this
Order are effective upon completion of service.
Sincerely,
Linda Daugherty
Acting Associate Administrator
for Pipeline Safety
Enclosure: CAO
cc: Mr. David Barrett, Acting Director, Central Region, OPS, PHMSA
CONFIRMATION OF RECEIPT REQUESTED



U.S. DEPARTMENT OF TRANSPORTATION
PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION
OFFICE OF PIPELINE SAFETY
WASHINGTON, D.C. 20590
____________________________________
)
In the Matter of )
)
Northern Natural Gas Company, ) CPF No. 3-2026-002-CAO
)
Respondent. )
)
____________________________________)
CORRECTIVE ACTION ORDER
Purpose and Background
The Pipeline and Hazardous Materials Safety Administration (PHMSA), Office of Pipeline
Safety (OPS), is issuing this Corrective Action Order (CAO or Order) pursuant to the authority
provided in 49 U.S.C. § 60112. The CAO requires Northern Natural Gas Company (NNG or
Respondent), a subsidiary of Berkshire Hathaway Energy,
1 to take certain necessary corrective
actions to protect the public, property, and the environment from the potential hazards associated
with the continued operation of the M440B pipeline. The M440B pipeline is an 86-mile, 20-inch
diameter interstate natural gas pipeline system that extends from the North Branch Compressor
Station to the Carlton Compressor Station in Minnesota.
On January 16, 2026, at approximately 2:00 pm CDT, the M440B pipeline ruptured at a location
approximately two miles west of Willow River, Minnesota (Failure). The Failure resulted in the
release of approximately 63 MMcf of natural gas in a rural area. The released natural gas caught
fire in two locations approximately 1,000 feet apart. NNG responded by shutting down the
pipeline and closing valves necessary to isolate the site of the Failure. Three nearby towns lost
natural gas service following the Failure with approximately 830 customers being affected.
Pursuant to 49 U.S.C. § 60117, PHMSA has initiated an investigation of the Failure. The
preliminary findings of PHMSA’s ongoing investigation are as follows:
Preliminary Findings
January 16, 2026 Incident
1 NNG operates the largest interstate natural gas pipeline system in the United States, with 14,300 miles of pipe
extending from the Permian Basin in Texas to the Upper Peninsula of Michigan. NNG accesses supply from every
major Mid-Continent basin, as well as the Permian, Rocky Mountain and Western Canadian basins. This supply is
ultimately delivered to end-use customers in Minnesota, Iowa, Nebraska, South Dakota, Wisconsin, Illinois, and the
Upper Peninsula of Michigan. NNG also operates three underground natural gas storage (UNGS) facilities and two
liquefied natural gas (LNG) peaking units.



• On January 16, 2026, at approximately 2:00 pm CDT, the M440B pipeline ruptured
approximately 2 miles west of Willow River, MN. The released natural gas caught fire in
two locations approximately 1,000 feet apart at each end of the failed pipe.
• The Respondent initiated efforts to contain the release by closing valves to isolate the
Failure.
• The Failure occurred in a rural area and did not result in any fatalities, or injuries. Three
homes were evacuated, and the residents were allowed to return home later in the day.
• NNG notified the National Response Center (NRC) of the Failure on January 16, 2026, at
approximately 3:30 pm (NRC Incident Report # 1452887).
• PHMSA and the Minnesota Office of Pipeline Safety (MNOPS) launched an onsite
investigation and investigators arrived at the site of the Failure on January 16, 2026.
• PHMSA and MNOPS investigators at the site saw the ruptured pipeline and observed that
approximately 1,000 feet of pipe had self-excavated during the rupture.
• The pipe at the Failure location is 20-inch diameter pipe manufactured in 1959 with API
5L X52 low frequency electric resistance welded (LF-ERW) longitudinal seam
manufactured by Youngstown. LF-ERW pipe of this vintage is known to be susceptible
to integrity issues.
• In 2021, NNG ran inline inspection (ILI) tools through the M440B pipeline at the
location of the Failure, including magnetic flux leakage (MFL), circumferential MFL,
mapping tool, and a pipe grade tool.
• The maximum allowable operating pressure (MAOP) of the pipe at the Failure site is
1,050 pounds per square inch gauge (psig). The operating pressure at the time of the
Failure was approximately 1,016 psig.
• NNG indicated to PHMSA and MNOPS investigators that the Failure resulted in the
estimated release of approximately 63 MMcf of natural gas.
• Three nearby towns lost natural gas service following the Failure with approximately 830
customers being affected
Determination of Necessity for Corrective Action Order and Right to Hearing
Section 60112 of title 49, United States Code, authorizes PHMSA to determine that a pipeline
facility is or would be hazardous to life, property, or the environment and if there is a likelihood
of serious harm, to expeditiously order the operator of the facility to take necessary corrective
action, including suspended or restricted use of the facility, physical inspection, testing, repair,



replacement, or other appropriate action. An order issued expeditiously must provide an
opportunity for a hearing as soon as practicable after the order is issued.
In deciding whether to issue an order, PHMSA must consider the following, if relevant: (1) the
characteristics of the pipe and other equipment used in the pipeline facility, including the age,
manufacture, physical properties, and method of manufacturing, constructing, or assembling the
equipment; (2) the nature of the material the pipeline facility transports, the corrosive and
deteriorative qualities of the material, the sequence in which the material is transported, and the
pressure required for transporting the material; (3) the aspects of the area in which the pipeline
facility is located, including climatic and geologic conditions and soil characteristics; (4) the
proximity of the area in which the facility is located to environmentally sensitive areas; (5) the
population density and population and growth patterns of the area in which the pipeline facility is
located; (6) any recommendation of the National Transportation Safety Board made under
another law; and (7) any other factors PHMSA may consider as appropriate.
After evaluating the foregoing preliminary findings of fact, and having considered the
characteristics of the pipeline, the nature of the failure; the hazardous nature of the material
transported; the existing and potential additional impacts to property, the environment, and
wildlife; it is hereby determined that continued operation of the Affected Segment of the NNG
M440B pipeline, as defined below, without corrective measures is or would be hazardous to life,
property, or the environment, and that failure to issue this Order expeditiously would result in the
likelihood of serious harm.
Accordingly, this Order mandating immediate corrective action is issued expeditiously without
prior notice and opportunity for a hearing. The terms and conditions of this Order are effective
upon completion of service.
Within 10 days of receipt of this Order, Respondent may request a hearing, to be held as soon as
practicable, by notifying the Associate Administrator for Pipeline Safety in writing, with a copy
to the Director, PHMSA, OPS Central Region. If a hearing is requested, it will be held in
accordance with 49 CFR § 190.211.
After receiving and analyzing additional data in the course of this investigation, PHMSA may
identify other corrective measures that need to be taken. Respondent will be notified of any
additional measures required and, if appropriate, PHMSA will consider a further amended order.
To the extent consistent with safety, Respondent will be afforded notice and an opportunity for a
hearing prior to the imposition of any additional corrective measures.
Definitions
Affected Segment – The “Affected Segment” means the 20-inch diameter, M440B pipeline from
the North Branch Compressor Station (M.P. 0) to Carlton Compressor Station (MP 85.67).
Isolated Segment – The “Isolated Segment” means the 20-inch diameter M440B pipeline from
MP 43 to MP 57.
Failure Segment – The Failure Segment means the approximately 1,000 feet of pipe (MP 53.88
to 54.6) that ruptured on January 16, 2026.



Director – The “Director” means the Director, PHMSA, OPS Central Region.
1. Restart Plan. Prior to resuming operation of the Isolated Segment, NNG must develop and
submit a written Restart Plan to the Director for prior approval. The Restart Plan may be
submitted in incremental stages.
a. The Restart Plan must include a Repair Plan for the Director’s approval. The Repair
Plan may include short-term provisions to operate portions of the Isolated Segment at
reduced pressure outside the limits of the Failure Segment to provide natural gas
service to local communities supplied within the Isolated Segment while completing
repairs within the Failure Segment. Any short-term operating provisions within the
Repair Plan must specify pressure limits within the Isolated Segment while completing
repairs.
b. The Director may approve the Restart Plan incrementally, including the Repair Plan,
without approving the entire plan.
c. Once approved by the Director, the Restart Plan will be incorporated by reference into
this Order.
d. The Restart Plan must provide for adequate patrolling and sufficient surveillance of
the Isolated Segment during the restart process to ensure that no leaks are present
when operation of the line resumes.
e. The Restart Plan must specify a day-light restart and include advance communications
with local emergency response officials.
2. Operating Pressure Restriction. NNG must reduce and maintain a twenty percent (20%)
pressure reduction in the actual operating pressure along the entire length of the Affected
Segment, such that the operating pressure along the Affected Segment will not exceed
eighty percent (80%) of the actual operating pressure in effect immediately prior to the
failure on January 16, 2026.
a. This pressure restriction must remain in effect until written approval to increase the
pressure or return the pipeline to its pre-failure operating pressure is obtained from the
Director.
b. Within 10 days of issuance of the Order, NNG must provide the Director the actual
operating pressures of each compressor station and each main line pressure regulating
station on the Affected Segment at the time of failure and the reduced pressure
restriction set-points at these same locations.
c. This pressure restriction requires any relevant remote or local alarm limits, software
programming set-points or control points, and mechanical over-pressure devices to be
adjusted accordingly.
d. When determining the pressure restriction set-points, NNG must take into account any
in-line inspection (ILI) features or anomalies present in the Affected Segment to
provide for continued safe operation while further corrective actions are completed.
e. NNG must review the pressure restriction monthly by analyzing the operating pressure
data. NNG must take into account any ILI features or anomalies present in the
Affected Segment and immediately reduce the operating pressure to maintain the safe
operations of the Affected Segment, if warranted by the monthly review. NNG must
submit the results of the monthly review to the Director. The results must include, at a
minimum, the current discharge set-points (including any additional pressure
reductions), and any pressure exceedance at discharge set-points.



f. NNG may request approval from the Director to increase the operating pressure on
individual segments on the Affected Pipeline based on an engineering analysis or other
justification that the segment does not pose a safety risk.
3. Mechanical and Metallurgical Testing. Within 45 days of receipt of this Order, NNG
must complete mechanical and metallurgical testing and failure analysis of the failed pipe,
including an analysis of soil samples and any foreign materials. Complete the testing and
analysis as follows:
a. Document the chain-of-custody when handling and transporting the failed pipe section
and other evidence from the failure site.
b. Within 10 days of receipt of this Order, develop and submit the testing protocol and
the proposed testing laboratory to the Director for prior approval.
c. Prior to beginning the mechanical and metallurgical testing, provide the Director with
the scheduled date, time, and location of the testing to allow for an OPS representative
to witness the testing.
d. Ensure the testing laboratory distributes all reports (whether draft or final) in their
entirety to the Director at the same time they are made available to NNG.
4. Root Cause Failure Analysis. Within 90 days following receipt of this Order, NNG must
complete a root cause failure analysis (RCFA) and submit a final report of this RCFA to
the Director. The RCFA must be supplemented/facilitated by an independent third-party
acceptable to the Director and must document the decision making process and all factors
contributing to the failure. The final report must include findings, and any lessons learned
and whether the findings and any lessons learned are applicable to other locations within
NNG’s pipeline system. The independent third-party must distribute all RCFA reports
(whether draft or final) in their entirety to the Director at the same time they are made
available to NNG provide all versions of the RCFA
5. Remedial Work Plan (RWP).
a. Within 120 days following receipt of this Order, NNG must submit a Remedial Work
Plan (RWP) to the Director for approval.
b. The Director may approve the RWP incrementally without approving the entire RWP.
c. Once approved by the Director, the RWP will be incorporated by reference into this
Order.
d. The RWP must specify the tests, inspections, assessments, evaluations, and remedial
measures NNG will use to verify the integrity of the Affected Segment. It must
address all known or suspected factors and causes of the January 16, 2026 failure.
NNG must consider both the risk of another failure and the consequence of another
failure to develop a prioritized schedule for RWP related work along the Affected
Segment.
e. The RWP must include a procedure or process to:
i. Identify pipe in the Affected Segment with characteristics similar to the contributing
factors identified for the January 16, 2026 failure.
ii. Gather all data necessary to review the failure history (in service and pressure test
failures) of the Affected Segment and to prepare a written report containing all the
available information such as the locations, dates, and causes of leaks and failures.
iii. Integrate the results of the metallurgical testing, RCFA, and other corrective actions
required by this Order with all relevant pre-existing operational and assessment data
for the Affected Segment. Pre-existing operational data includes, but is not limited



to, construction, operations, maintenance, testing, repairs, prior metallurgical
analyses, and any third party consultation information. Pre-existing assessment data
includes, but is not limited to, ILI tool runs, hydrostatic pressure testing, direct
assessments, close interval surveys, and DCVG/ACVG surveys.
iv. Determine if conditions similar to those contributing to the failure on January 16,
2026, are likely to exist elsewhere on the Affected Segment.
v. Conduct additional field tests, inspections, assessments, and/or evaluations to
determine whether, and to what extent, the conditions associated with the failure on
January 16, 2026, and other failures from the failure history (see [(e)(ii)] above) or
any other integrity threats are present elsewhere on the Affected Segment. At a
minimum, this process must consider all failure causes and specify the use of one or
more of the following:
1) ILI tools that are technically appropriate for assessing the pipeline system based
on the cause of failure on January 16, 2026, and that can reliably detect and identify
anomalies,
2) Hydrostatic pressure testing,
3) Close-interval surveys,
4) Cathodic protection surveys, to include interference surveys in coordination with
other utilities (e.g. underground utilities, overhead power lines, etc.) in the area,
5) Coating surveys,
6) Stress corrosion cracking surveys,
7) Selective seam corrosion surveys; and,
8) Other tests, inspections, assessments, and evaluations appropriate for the failure
causes.
Note: NNG may use the results of previous tests, inspections, assessments, and
evaluations if approved by the Director, provided the results of the tests, inspections,
assessments, and evaluations are analyzed with regard to the factors known or
suspected to have caused the January 16, 2026 failure.
vi. Describe the inspection and repair criteria NNG will use to prioritize, excavate,
evaluate, and repair anomalies, imperfections, and other identified integrity threats.
Include a description of how any defects will be graded and a schedule for repairs or
replacement.
vii. Describe the methods NNG will use to repair, replace, or take other corrective
measures to remediate the conditions associated with the pipeline failure on January
16, 2026, and to address other known integrity threats along the Affected Segment.
The repair, replacement, or other corrective measures must meet the criteria
specified in [1(d)(vi)] above.
viii. Implement continuing long-term periodic testing and integrity verification measures
to ensure the ongoing safe operation of the Affected Segment considering the results
of the analyses, inspections, evaluations, and corrective measures undertaken
pursuant to the Order.
f. Include a proposed schedule for completion of the RWP.
g. NNG must revise the RWP as necessary to incorporate new information obtained
during the failure investigation and remedial activities, to incorporate the results of
actions undertaken pursuant to this Order, and/or to incorporate modifications required
by the Director.
i. Submit any plan revisions to the Director for prior approval.
ii. The Director may approve plan revisions incrementally.



iii. Any and all revisions to the RWP after it has been approved and incorporated by
reference into this Order will be fully described and documented in the CAO
Documentation Report (CDR).
h. Implement the RWP as it is approved by the Director, including any revisions to the
plan.
6. CAO Documentation Report (CDR). NNG must create and revise, as necessary, a CAO
Documentation Report (CDR). When NNG has concluded all the items in this Order it will
submit the final CDR in its entirety to the Director. This will allow the Director to complete
a thorough review of all actions taken by NNG with regards to this Order prior to
approving the closure of this Order. The intent is for the CDR to summarize all activities
and documentation associated with this Order in one document.
a. The Director may approve the CDR incrementally without approving the entire CDR.
b. Once approved by the Director, the CDR will be incorporated by reference into this
Order.
c. The CDR must include but not be limited to:
i. Table of Contents;
ii. Summary of the pipeline failure of January 16, 2026, and the response activities;
iii. Summary of pipe data/properties and all prior assessments of the Affected Segment;
iv. Summary of all tests, inspections, assessments, evaluations, and analysis required by
the Order;
v. Summary of the Mechanical and Metallurgical Testing as required by the Order;
vi. Summary of the RCFA with all root causes as required by the Order;
vii. Documentation of all actions taken by NNG to implement the RWP, the results of
those actions, and the inspection and repair criteria used;
viii. Documentation of any revisions to the RWP including those necessary to incorporate
the results of actions undertaken pursuant to this Order and whenever necessary to
incorporate new information obtained during the failure investigation and remedial
activities;
ix. Lessons learned while completing this Order;
x. A path forward describing specific actions NNG will take on its entire pipeline
system as a result of the lessons learned from work on this Order; and
xi. Appendices (if required).
Other Requirements:
7. Approvals. With respect to each submission under this Order that requires the approval of
the Director, the Director may: (a) approve, in whole or part, the submission; (b) approve
the submission on specified conditions; (c) modify the submission to cure any
deficiencies; (d) disapprove in whole or in part, the submission, directing that Respondent
modify the submission, or (e) any combination of the above. In the event of approval,
approval upon conditions, or modification by the Director, Respondent shall proceed to
take all action required by the submission as approved or modified by the Director. If the
Director disapproves all or any portion of the submission, Respondent must correct all
deficiencies within the time specified by the Director and resubmit it for approval.
8. Extensions of Time. The Director may grant an extension of time for compliance with any
of the terms of this Order upon a written request timely submitted demonstrating good
cause for an extension.



9. Reporting. Submit quarterly reports to the Director that: (1) include all available data and
results of the testing and evaluations required by this Order; and (2) describe the progress
of the repairs or other remedial actions being undertaken. The first quarterly report is due
on April 30, 2026, covering the period through March 31, 2026. The Director may change
the interval for the submission of these reports.
10. Documentation of the Costs. It is requested that Respondent maintain documentation of
the costs associated with implementation of this CAO. Include in each monthly report
submitted, the to-date total costs associated with: (1) preparation and revision of
procedures, studies, and analyses; (2) physical changes to pipeline infrastructure, including
repairs, replacements, and other modifications; and (3) environmental remediation, if
applicable.
Be advised that all material submitted in response to this enforcement action is subject to being
made publicly available. If you believe that any portion of your responsive material qualifies
for confidential treatment under 5 U.S.C. § 552(b), along with the complete original document
you must provide a second copy of the document with the portions you believe qualify for
confidential treatment redacted and an explanation of why you believe the redacted information
qualifies for confidential treatment under 5 U.S.C. § 552(b).
In your correspondence on this matter, please refer to “CPF No. 3-2026-002-CAO” and for
each document you submit, please provide a copy in electronic format whenever possible. The
actions required by this Order are in addition to and do not waive any requirements that apply
to Respondent’s pipeline system under 49 CFR Parts 190 through 199, under any other order
issued to Respondent under authority of 49 U.S.C. Chapter 601, or under any other provision of
federal or state law.
Respondent may appeal any decision of the Director to the Associate Administrator for
Pipeline Safety. Decisions of the Associate Administrator shall be final.
Failure to comply with this Order may result in the assessment of civil penalties and in referral
to the Attorney General for appropriate relief in United States District Court pursuant to 49
U.S.C. § 60120.
The terms and conditions of this Order are effective upon service in accordance with
49 CFR § 190.5.
January 17, 2026
_____________________________ __________________________
Linda Daugherty Date Issued
Acting Associate Administrator
for Pipeline Safety

## Provenance

- Official: Yes
- Source: <https://primis.phmsa.dot.gov/enforcement-data/case/32026002CAO>
- Source ID: `phmsa-enforcement`
- SHA-256: `05740c3958efd0a82d60f5281051abab5479a97c46cdedd7d2346664999fe6a9`
- Retrieved: 2026-08-20T04:44:44.458Z
- Exported: 2026-08-25T14:32:09.015Z
- Document slug: `phmsa-enforcement-32026002cao`

### Source metadata

```json
{
  "cpf": "32026002CAO",
  "operator": "NORTHERN NATURAL GAS CO",
  "region": "Central",
  "pipelineType": "INTERSTATE GAS TRANSMISSION",
  "caseStatus": "OPEN",
  "citedSections": [],
  "dataAsOf": "08/04/2026 12PM",
  "caseDataAsOf": "2026-08-04",
  "attachmentCount": 2,
  "attachments": [
    {
      "name": "32026002CAO_Corrective Action Order_01172026_(26-362536).pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/32026002CAO/32026002CAO_Corrective%20Action%20Order_01172026_(26-362536).pdf",
      "bytes": 273249,
      "category": "agency_document"
    },
    {
      "name": "32026002CAO_Corrective Action Order_01172026_(26-362536)_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/32026002CAO/32026002CAO_Corrective%20Action%20Order_01172026_(26-362536)_text.pdf",
      "bytes": 293868,
      "category": "agency_document"
    }
  ],
  "extractedAgencyDocumentCount": 1,
  "attachmentPolicy": "Official attachment links are retained. Agency-issued documents may also include a verified local PDF and page-level text representation.",
  "jurisdiction": "US",
  "operatorName": "NORTHERN NATURAL GAS CO"
}
```