# NAVAJO NATION OIL AND GAS COMPANY — Notice of Amendment

**Citation:** CPF 420055008M  
**Type / status:** enforcement / historical  
**Agency:** Pipeline and Hazardous Materials Safety Administration  
**Effective:** Not stated  
**Published:** 2005-01-07

CLOSED notice of amendment citing 195.452(f)(4), 195.452(f)(6), 195.452(i)(2), 195.452(i)(3), 195.452(j)(2), 195.452(j)(5).

## Document text

Notice of Amendment involving NAVAJO NATION OIL AND GAS COMPANY. PHMSA's enforcement data identifies the cited regulations as 195.452(f)(4),  195.452(f)(6),  195.452(i)(2),  195.452(i)(3),  195.452(j)(2),  195.452(j)(5). The case was opened on 2005-01-07 and is reported as closed as of 2007-05-11. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

420055008M_Order Directing Amendment_09062006.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420055008M/420055008M_Order%20Directing%20Amendment_09062006.pdf

CPF_NO_4-2005-5008M.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420055008M/CPF_NO_4-2005-5008M.pdf

420055008M_Order Directing Amendment_09062006.pdf

@
U.S. Deporlment
of Tronsporlotion
Pipeline ond Hozqrdous
Moteriols Sofety Administrqtion 400 Seventh Street, S.W
Washington, D.C.20590
$EP - 6 2006
Mr. Wilson Groen
President and General Manager
Navajo Nation Oil and Gas Company, Inc.
P.O. Box 4439
Window Rock, AZ 86515-4439
Re: CPF No. 4-2005-5008M
Dear Mr. Groen:
Enclosed is the Order Directing Amendment issued by the Associate Administrator for
Pipeline Safety in the above-referenced case. It makes a finding of inadequate procedures and
requires that you amend your written integrity management program. When the terms of the
Order are completed, as determined by the Director, Southwest Region, this enforcement action
will be closed. Your receipt of the Order Directing Amendment constitutes service of that
document under 49 C.F.R. $ 190.5.
Sincerely,
d="". {1--
James Reynolds
Pipeline Compliance Registry
Office of Pipeline Safety
Enclosure
CERTIFIED MAIL - RETURN RECEIPT REOUESTED



DEPARTMENT OF TRANSPORTATION
PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION
OFFICE OF PIPELINE SAFETY
WASHINGTON. DC 20590
In the Matter of
Navajo Nation Oil and Gas Company,Inc.,
Respondent
CPF No.4-20085-5008M
)
ORDER DIRECTING AMENDM4NT
On October 12-15,2004, pursuant to 49 U.S.C. $ 60117, representatives of the Pipeline and
Hazardous Materials Safety Administration's OfFrce of Pipeline Safety inspected Respondent's
written integrity management program (IMP) at its facility in Window Rock, Arizona. As a
'result of the inspection, the Director, Southwest Region, issued to Respondent, by letter dated
January 7, 2005, a Notice of Amendment (NOA). The NOA alleged inadequacies in
Respondent's IMP and proposed to require amendment of Respondent's procedures to comply
with the requirements at 49 C.F.R. g 195.452.
Respondent did not respond to the NOA within 30 days, but submitted a letter dated March 24,
2005. Respondent did not contest the allegations set forth in the NOA and described the actions
it is taking to address the inadequacies. Respondent did not request a hearing and has waived its
right to one. Respondent requested an extension of 90 days to submit documentation of its
compliance. By letter dated March 31,2005, the Director, Southwest Region, provided
Respondent an extension until May 20, 2005 to submit amended procedures for review.
Respondent failed to submit any documentation for review.
Accordingly, I find that Respondent's IMP is inadequate to ensure safe operation of its pipeline
system. Pursuant to 49 U.S.C. $ 60108(a) and 49 C.F.R. g 190.237, Respondent is ordered to
make the following changes to its IMP. Respondent must-
l. Amend the process for identifying which pipeline segments could affect a high
consequence area. The process must document the use of local knowledge, information
obtained from routine fie.ld activities (such as right-of-way surveillance and aerial
surveys), and other information sources to supplement data from the National Pipeline
Mapping System (NPMS) to accurately reflect current conditions in the vicinity of the
pipeline. Although Respondent's IMP refers to the use of "provisions to assure that local
knowledge . . . is used as required to supplement NPMS data," Respondent does not
actually provide details for that process. The IMP must provide a detailed process for



2
2.
a
J .
4.
supplementing NPMS data as described, including how, when and where the process is to
be performed, who is responsible, where the data flow goes, and why the process is
necessary.
Amend the process for review of integrity assessment results and information analysis by
someone qualified to evaluate the results and information. Respondent's IMP states that
after in-line inspection tool runs, Respondent may implement a process for excavating
anomalies to validate tool results using actual measured defect characteristics. The IMP
must include procedures to identifr and implement each activity that is required to
validate the in-line inspection data. If Respondent chooses not to validate and calibrate
tool results, the IMP must include documented justification to demonstrate that validation
and calibration activities are not necessary for Respondent's particular circumstances.
Respondent's IMP must also contain process documentation to provide guidance or
procedures for performing a detailed review of integrity assessment results, generating a
repair schedule, and integrating additional sources of risk factor data, such as cathodic
protection data and right-of-wa-y surveillance. The process must support the eval'riation
of pipeline condition and decision-making related to the repair or remediation of
conditions, to ensure that qualified persons are able to effectively implement the process.
Amend the process for the review of integrity assessment results and information analysis
by someone qualified to evaluate the results and information. The IMP must include
pioces documentation specifying how additional information should be integrated with
integrity assessment results to support decisions on excavation and repair of identified
conditions. Respondent's form titled "Pipeline Integrity Assessment Results Analysis"
provides a place for collected data to be recorded, but Respondent has no guidance for
using the form. Respondent must provide guidance for using the form in addition to
communication of results to ensure that the form is fully and consistently utilized.
Amend the process for analysis that integrates all available information about the
integrity of the entire pipeline and the consequences of a failure. The IMP must include a
documented justification or basis for the risk model numerical values and weights used
for variables and risk factors. Respondent must remove as much subjectivity from the
process as possible by assigning criteria to the 1, 3, and 5 weights or by providing
guidance for assigning subjective weights to assure consistent application and
repeatability. The IMP must integrate information about pipeline risks associated with all
modes of operation where hazardous liquids are present, including startup, shutdown, and
slack line operation. Respondent's discharge volumes are stated as worst case conditions,
but the analyses must consider lack of tankage isolation as a potential contributing factor
to spill volume. If the tankage is sufficiently isolated to prevent the tank inventory from
increasing the worst case spill volume, Respondent must provide a justified statement in
the IMP describing the supporting conditions.
Amend the element for identification of preventive and mitigative measures to protect
high consequence areas. The IMP must document the systematic decision-making
process that includes input from relevant parts of the organization such as management,
operations, and engineering. The process must consider the results of the risk analysis



J
6.
8.
along with other information in making decisions about which preventive and mitigative
actions to implement.
Amend the element for identification of preventive and mitigative measures to protect
high consequence areas. The IMP must document the process for evaluating the
capability of leak detection means and modify, as necessary, to protect high consequence
areas per S 195.452(i)(3). Respondent verbally refers to its Facility Response Procedure
manuals regarding leak detection evaluation, but Respondent must include a process in
the IMP for leak detection evaluation. The location of the nearest response personnel, as
addressed in the Facility Response Manuals, is one of the required factors for
consideration. Potential changes to leak detection capability as a response to operator
actions and reactions and lessons learned during drills must also be included in the
process. This manual, if used as part of Respondent's IMP must be referenced in the IMP
documentation.
Amend the Iiv{P to document the continual piocess of assessment and evaluation to
maintain a pipeline's integrity. The periodic evaluation must be conducted as frequently
as needed to assure pipeline integrity. Respondent must base the frequency of evaluation
on the risk factors specific to its pipeline including the factors specified in $ 195.452(e).
The evaluation must consider the results of the baseline and periodic integrity
assessments, information analysis ($ 195.452(9)), decisions about remediation, and
preventive and mitigative measures ($ 195.452(h) and (i)).
Amend the IMP to document the continual process of assessment and evaluation to
maintain a pipeline's integrity. The IMP must correlate assessment methods with
pipeline specific conditions and risk factors evaluated in accordance with $ 195.452CX5).
The correlation must be specific enough to ensure that Respondent chooses assessment
methods capable of detecting anomalies that could result from the specifrc risks to each
pipeline segment assessed. One of the purposes of the hazardous liquids pipeline
integrity management regulation is to promote rigorous, systematic management of
pipeline integrity through the implementation of management systems (processes). As
discussed during the inspection, as Respondent's IMP processes and management
systems are implemented and revised, there must be greater specificity in process
documentation, including inputs, steps performed, and expected outputs for evaluation to
ensure these processes can be consistently applied and repeated. Respondent's IMP is
largely comprised of language taken directly from PHMSA's Liquid IMP Inspection
Protocols. Although the Protocols are intended to be helpful guidance in the initial
deVelopment of an IMP, they do not constitute detailed process descriptions that meet
regulatory requirements. Respondent must develop sufficiently detailed processes and
procedural controls to assure consistent evaluation, quality, and communication of
integrity management processes. Where prescriptive terminology is used in the
regulation, such as deadlines, timelines or quantities, Respondent's IMP shall include that
language. Respondent must customize the required processes to its unique operating
environment. For example, Respondent must indicate how, when and where the
processes are to be performed, who is responsible, where the data flow goes, and why the
processes are necessary.



9. Complete each of the above items and submit documentation of completion within 30
days of receipt of this Order. Submit documentation to the Director, Southwest Region,
Pipeline and Hazardous Materials Safety Administration, 8701 South Gessner Drive,
Suite 1110, Houston, TX 77074-2949.
The Director, Southwest Region, may grant an extension of time to comply with any of the
required items upon a written request timely submitted by the Respondent demonstrating good
cause for an extension.
Failure to comply with this Order may result in administrative assessment of civil penalties up to
S100,000 per day for each violation and in referral to the Attorney General for appropriate relief
in a district court of the United States. The terms and conditions of this Order Directing
Amendment are effective upon receipt.
sEP - 6 20$$
Date Issued
for Pipeline Safety

## Provenance

- Official: Yes
- Source: <https://primis.phmsa.dot.gov/enforcement-data/case/420055008M>
- Source ID: `phmsa-enforcement`
- SHA-256: `b80e9b426f3e4077cf27e4986a6da14ca4a2ab8ee5d17b7e545eb0c2762fd991`
- Retrieved: 2026-08-20T04:44:44.458Z
- Exported: 2026-08-22T16:51:05.698Z
- Document slug: `phmsa-enforcement-420055008m`

### Source metadata

```json
{
  "cpf": "420055008M",
  "operator": "NAVAJO NATION OIL AND GAS COMPANY",
  "region": "Southwest",
  "pipelineType": "INTERSTATE LIQUID ONSHORE",
  "caseStatus": "CLOSED",
  "citedSections": [
    "195.452(f)(4)",
    "195.452(f)(6)",
    "195.452(i)(2)",
    "195.452(i)(3)",
    "195.452(j)(2)",
    "195.452(j)(5)"
  ],
  "dataAsOf": "08/04/2026 12PM",
  "caseDataAsOf": "2026-08-04",
  "attachmentCount": 2,
  "attachments": [
    {
      "name": "420055008M_Order Directing Amendment_09062006.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420055008M/420055008M_Order%20Directing%20Amendment_09062006.pdf",
      "bytes": 326337,
      "category": "agency_document"
    },
    {
      "name": "CPF_NO_4-2005-5008M.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420055008M/CPF_NO_4-2005-5008M.pdf",
      "bytes": 226939,
      "category": "case_document"
    }
  ],
  "extractedAgencyDocumentCount": 1,
  "attachmentPolicy": "Official attachment links are retained. Agency-issued documents may also include a verified local PDF and page-level text representation.",
  "jurisdiction": "US",
  "operatorName": "NAVAJO NATION OIL AND GAS COMPANY"
}
```
