# DIXIE PIPELINE COMPANY LLC — Safety Order

**Citation:** CPF 420115015S  
**Type / status:** enforcement / historical  
**Agency:** Pipeline and Hazardous Materials Safety Administration  
**Effective:** Not stated  
**Published:** 2011-09-29

CLOSED safety order.

## Document text

Safety Order involving DIXIE PIPELINE COMPANY LLC. The dataset does not identify a cited regulation for this case. The case was opened on 2011-09-29 and is reported as closed as of 2012-10-29. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

420115015S_ Consent Agreement_02292012.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420115015S/420115015S_%20Consent%20Agreement_02292012.pdf

420115015S_ Consent Agreement_02292012_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420115015S/420115015S_%20Consent%20Agreement_02292012_text.pdf

420115015S_ Consent Order_02292012.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420115015S/420115015S_%20Consent%20Order_02292012.pdf

420115015S_ Consent Order_02292012_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420115015S/420115015S_%20Consent%20Order_02292012_text.pdf

420115015S_Closure_10292012.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420115015S/420115015S_Closure_10292012.pdf

420115015S_Closure_10292012_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420115015S/420115015S_Closure_10292012_text.pdf

420115015S_NOPSO_09292011.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420115015S/420115015S_NOPSO_09292011.pdf

420115015S_NOPSO_09292011_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420115015S/420115015S_NOPSO_09292011_text.pdf

420115015S_ Consent Order_02292012_text.pdf

FEB 29 2012
Mr. Kevin Bodenhamer
Senior Vice President
Enterprise Products Operating, LLC
1100 Louisiana Street
Houston, TX 77002-5227
Re: CPF No. 4-2011-5015S
Dear Mr. Bodenhamer:
Enclosed please find a Consent Order incorporating the terms of the Consent Agreement
that you signed on February 17, 2012. Service of the Consent Order and Consent
Agreement by certified mail is deemed effective upon the date of mailing, or as otherwise
provided under 49 C.F.R. § 190.5.
Thank you for your cooperation in this matter.
Sincerely,
Jeffrey D. Wiese
Associate Administrator
for Pipeline Safety
Enclosure
cc: Mr. Rod Seeley, Director, Southwest Region, OPS
Mr. Alan Mayberry, Deputy Associate Administrator for Field Operations, OPS
CERTIFIED MAIL - RETURN RECEIPT REQUESTED [71791000164203292909]



U.S. DEPARTMENT OF TRANSPORTATION
PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION
OFFICE OF PIPELINE SAFETY
WASHINGTON, DC 20590
____________________________________
In the Matter of )
Enterprise Products Operating, LLC, ) CPF No. 4-2011-5015S
)
)
)
Respondent. )
____________________________________)
CONSENT ORDER
On February 17, 2012, Mr. Kevin Bodenhamer, Senior Vice President, Enterprise
Products Operating, LLC, signed a Consent Agreement in this case. I am signing the
Consent Agreement on this date and incorporating its terms into this Consent Order by
reference.
____________________________ __________________________
Jeffrey D. Wiese Date Issued
Associate Administrator
for Pipeline Safety

420115015S_ Consent Agreement_02292012_text.pdf

FEB 29 2012
U.S. DEPARTMENT OF TRANSPORTATION
PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION
OFFICE OF PIPELINE SAFETY
WASHINGTON, DC 20590
____________________________________
In the Matter of )
Enterprise Products Operating, LLC, ) CPF No. 4-2011-5015S
)
)
)
Respondent. )
____________________________________)
CONSENT AGREEMENT
On September 29, 2011, the Director, Southwest Region, Pipeline and Hazardous Materials
Safety Administration (PHMSA), Office of Pipeline Safety (OPS), issued a Notice of Proposed
Safety Order (Notice) to Enterprise Products Operating, LLC (Enterprise or Respondent). The
Notice alleged that it appeared a condition exists on a 28-mile portion of Respondent’s natural
gas liquids pipeline, known generally as the Dixie Pipeline, which poses a pipeline integrity risk
to public safety, property, or the environment. The Dixie Pipeline is primarily used to transport
liquid propane from Texas to customers in Georgia and South Carolina.
Specifically, the Notice referenced the 28-mile segment of the Dixie Pipeline, extending from the
Breaux Bridge Pump Station to the Maringouin Pump Station in South-Central Louisiana
(Affected Pipeline Segment). The Notice alleged that the Affected Pipeline Segment is located
in the Atchafalaya Basin, and that this environmentally sensitive wetlands area recently
experienced a prolonged period of unanticipated flooding. The Notice alleged that Enterprise
has been unable to perform a required integrity assessment of the Affected Pipeline Segment
under 49 C.F.R. § 195.452(j)(3) because of such flooding and that propane supply disruptions
could potentially result from any test failures or needed repairs. The Notice stated, however, that
Enterprise reduced the operating pressure of the Affected Pipeline Segment by 20 percent as a
temporary preventive and mitigative measure.
On October 10, 2011, Enterprise responded to the Notice and requested an informal conference.
Respondent and PHMSA (collectively, the Parties) met on November 16, 2011, and have since
engaged in good-faith settlement discussions. The Parties have concluded those discussions and
agree that the settlement set forth in this Consent Agreement will avoid further administrative
proceedings or litigation. The Parties further agree that the entry of this Consent Agreement is
the most appropriate means of resolving the Notice, without adjudication of any issue of fact or
law. Accordingly, the Parties agree as follows:



I. General Provisions
1. Enterprise acknowledges that as operator of the Dixie Pipeline, Respondent and the
subject pipeline are subject to the jurisdiction of the Federal pipeline safety laws, 49 U.S.C.
60101 et seq., and the regulations and administrative orders issued thereunder. For purposes of
this Consent Agreement, Respondent acknowledges that it received proper notice of PHMSA’s
action in this proceeding and that the Notice states claims upon which relief may be granted
pursuant to 49 U.S.C. 60101 et seq. and the regulations and orders issued thereunder.
2. Respondent neither admits nor denies any allegation or conclusion in the Notice but
agrees, for purposes of this proceeding, that the integrity risk identified in the Notice exists as
described in the Notice and agrees to address it by completing the corrective actions specified in
Section II of this Consent Agreement, including the actions set forth in any work plans and
schedules, each of which shall automatically be incorporated into this Consent Agreement upon
approval. Respondent’s participation in this Consent Agreement does not constitute an
admission of liability for any purpose except in a proceeding to enforce the provisions of this
Agreement.
3. After Respondent returns this signed Consent Agreement, PHMSA’s representative will
present it to the Associate Administrator for Pipeline Safety, PHMSA (Associate Administrator),
recommending that the Associate Administrator adopt the terms of this Agreement by issuing an
administrative order (Consent Order) incorporating the terms of this Consent Agreement. The
terms of this Consent Agreement constitute an offer of settlement until accepted by the Associate
Administrator. Upon the effective date of this Consent Agreement, any request for a hearing
submitted by Respondent shall be automatically withdrawn.
4. Respondent consents to the issuance of the Consent Order, and hereby waives any further
procedural requirements with respect to its issuance. Except as provided in Sections III and IV
of this Agreement, Respondent waives all rights to contest the adequacy of notice, or the validity
of the Consent Order or this Consent Agreement, including all rights to administrative or judicial
hearings or appeals.
5. This Consent Agreement shall apply to and be binding upon PHMSA, and upon
Respondent, its officers, directors, and employees, and its successors, assigns, or other entities or
persons otherwise bound by law. Respondent agrees to provide a copy of this Consent
Agreement and any incorporated work plans and schedules to all of Respondent’s officers,
employees, and agents whose duties might reasonably include compliance with this Agreement.
6. For all transfers of ownership or operating responsibility of the Dixie Pipeline,
Respondent shall provide a copy of this Consent Agreement to the prospective transferee at least
30 days prior to such transfer and simultaneously provide written notice of the prospective
transfer to the PHMSA Southwest Region Director (Director).
2



7. This Consent Agreement constitutes the final, complete and exclusive agreement and
understanding between the Parties with respect to the settlement embodied in this Agreement,
and the Parties acknowledge that there are no representations, agreements or understandings
relating to the settlement other than those expressly contained in this Agreement, except that the
terms of this Agreement may be construed by reference to the Notice.
8. Nothing in this Consent Agreement affects or relieves Respondent of its responsibility to
comply with all applicable requirements of the Federal pipeline safety laws, 49 U.S.C. § 60101
et seq., and the regulations and orders issued thereunder. Nothing in this Consent Agreement
alters PHMSA’s right of access, entry, inspection, and information gathering or PHMSA’s
authority to bring any enforcement action against Respondent pursuant to the Federal pipeline
safety laws, the regulations and orders issued thereunder, or any other provision of Federal or
State law.
9. This Consent Agreement does not waive or modify any Federal, State, or local laws or
regulations that are applicable to Respondent’s pipeline systems. This Consent Agreement is not
a permit, or a modification of any permit, under any Federal, State, or local laws or regulations.
Respondent remains responsible for achieving and maintaining compliance with all applicable
Federal, State, and local laws, regulations and permits.
10. This Consent Agreement does not create rights in, or grant any cause of action to, any
third party not party to this Agreement. The U.S. Department of Transportation is not liable for
any injuries or damages to persons or property arising from acts or omissions of Respondent or
its officers, employees, or agents carrying out the work required by this Consent Agreement.
Respondent agrees to indemnify and hold harmless the U.S. Department of Transportation, its
officers, employees, agents, and representatives from any and all causes of action arising from
any acts or omissions of Respondent or its contractors in carrying out the work required by this
Agreement.
II. Corrective Actions
11. Enterprise must maintain a twenty percent (20%) pressure reduction on the Affected
Pipeline Segment until the Director provides approval to return the pipeline to normal operating
conditions. Specifically, the pressure in this segment is not to exceed 1117 psig.
12. Enterprise will continue the weekly patrols on the Affected Pipeline Segment until the
corrective actions specified in this section are implemented and complete. At that point,
Enterprise will return to the normal routine patrol schedule as required by 49 CFR §195.412(a).
13. Within 60 days, Enterprise must develop a plan and schedule for completion of the
required integrity testing as soon as practicable. The work must be scheduled as soon as the
conditions delaying the testing have abated and the plan must include timeframes for making any
needed repairs based on the test results. Submit the plan and schedule, and any subsequent
3



revisions to that schedule, to the Director for approval. In the absence of good cause shown, the
actions required under this paragraph must be completed no later than September 31, 2012.
14. As soon as conditions permit, Enterprise must inspect each crossing under a navigable
waterway along the Affected Pipeline Segment to determine the condition of the crossing as
normally required by 195.412(b), report those findings to the Director, and submit a proposed
plan to take potential actions based on any adverse findings.
15. As soon as conditions permit, Enterprise must inspect for all required pipeline marker
signs as defined by § 195.434 and replace any damaged or missing signs as soon as practicable.
16. Submit quarterly reports to the Director that include available data and results of the
investigations and surveys required by this Consent Agreement. The first quarterly report is due
90 days after the Consent Order is issued.
17. The Director may grant an extension of time for compliance with any of the terms of this
Consent Agreement upon a written request timely submitted demonstrating good cause for an
extension.
18. Respondent may appeal any decision of the Director to the Associate Administrator.
Decisions of the Associate Administrator shall be final.
19. It is requested (not mandated) that Respondent maintain documentation of the safety
improvement costs associated with fulfilling this Consent Agreement and submit the total to the
Director. These safety improvement costs will be determined by Respondent to meet the
requirements of the Consent Agreement and may include, but not limited to, right-of-way
maintenance, additional patrolling, liaison with landowners, and development of the plan and
schedule described in paragraph 13.
III. Review and Approval Process
20. With respect to any submission under Section II of this Agreement that requires the
approval of the Director, the Director may: (a) approve, in whole or in part, the submission, (b)
approve the submission on specified conditions, (c) disapprove, in whole or in part, the
submission, or (d) any combination of the foregoing. In the event of approval, approval in part,
or approval upon conditions, Respondent will proceed to take all action required by the
submission as approved by the Director, subject to Respondent’s right to invoke the dispute
resolution procedures in Section IV with respect to any conditions identified by the Director. In
the event that the Director disapproves all or any portion of the submission, the Director will
provide Respondent with a written notice of the deficiencies. Respondent will correct all
deficiencies within the time specified by the Director and resubmit it for approval, subject to
Respondent’s right to invoke the dispute resolution procedures in Section IV with respect to any
conditions identified by the Director.
4



IV. Dispute Resolution
21. The Director and Respondent will informally attempt to resolve any disputes arising
under this Agreement. If Respondent and the Director are unable to informally resolve the
dispute within 15 days, Respondent may request in writing, within 10 days, a written
determination from the Associate Administrator resolving the dispute and provide all
information that Respondent believes is relevant to the dispute. If the request is submitted as
provided herein, the Associate Administrator will issue a written decision, which shall be final.
The existence of a dispute and PHMSA’s consideration of matters placed in dispute shall not
excuse, toll, or suspend any term or timeframe for completion of any work to be performed under
this Consent Agreement during the pendency of the dispute resolution process, except as agreed
by the Director or the Associate Administrator in writing.
V. Enforcement
22. This Consent Agreement, as adopted by the Consent Order, is subject to all enforcement
authorities available to PHMSA under 49 U.S.C. § 60101 et seq. and 49 C.F.R. Part 190,
including administrative civil penalties under § 60122, if PHMSA determines that Respondent is
not materially proceeding in accordance with terms of this Agreement, with determinations made
by the Director, or, if such determinations are appealed, with decisions of the Associate
Administrator. All work plans and associated schedules set forth or referenced in Section II shall
be automatically incorporated into this Agreement and are enforceable in the same manner.
VI. Record Keeping and Information Disclosure
23. Respondent agrees to maintain records demonstrating compliance with all requirements
of this Agreement for a period of at least five years following completion of all work to be
performed. For any reports, plans, or other deliverables required to be submitted to PHMSA
pursuant to this Agreement, Respondent may assert a claim of business confidentiality or other
protections applicable to the release of information by PHMSA, covering part or all of the
information required to be submitted to PHMSA pursuant to this Agreement in accordance with
49 C.F.R. Part 7. The claim of confidentiality shall be marked in writing on each page, and shall
include a statement specifying the grounds for each claim of confidentiality. PHMSA shall
determine release of any information submitted pursuant to this Consent Agreement in
accordance with 49 C.F.R. Part 7, the Freedom of Information Act, 5 U.S.C. § 552, DOT and/or
PHMSA policies, and other applicable regulations and Executive Orders.
VII. Effective Date
24. The Effective Date as used herein is the date on which this Consent Agreement has been
signed by both Respondent and PHMSA. Unless specified to the contrary, all deadlines for
actions required by this Agreement run from the date of issuance of the Consent Order adopting
this Agreement.
5



VIII. Modification
25. The terms of this Agreement may be modified by mutual agreement of the Parties. Such
modifications shall be in writing and shall be signed by both Parties.
IX. Termination
26. This Consent Agreement will terminate upon the completion of all terms set forth in
Section II. Respondent may request written confirmation from PHMSA when this Agreement is
terminated. To the extent ongoing monitoring is required, PHMSA may terminate this
Agreement with respect to all other requirements with the exception of such monitoring.
Nothing in this Agreement prevents Respondent from completing any of the obligations earlier
than the deadlines provided for herein.
X. Ratification
27. The Parties’ undersigned representatives certify that they are fully authorized to enter
into the terms and conditions of this Consent Agreement and to execute and legally bind such
party to this document.
28. The Parties hereby agree to all conditions and terms of this Consent Agreement:
For PHMSA: For Respondent:
_________________________ ____________________________
Mr. Rod M. Seeley Mr. Kevin Bodenhamer
Director, Southwest Region Sr. Vice President
Pipeline and Hazardous Materials Enterprise Products Operating, LLC
Safety Administration
_____________________ _____________________
Date Date
6

420115015S_Closure_10292012_text.pdf

CERTIFIED MAIL - RETURN RECEIPT REQUESTED
October 29, 2012
Mr. Kevin Bodenhamer
Senior Vice President
Enterprise Products Operating, LLC
1100 Louisiana Street
Houston, TX 77002-5227
CPF 4-2011-5015S
Dear Mr. Bodenhamer:
As a result of information Enterprise Products Operating, LLC (Enterprise) filed with this office
dated August 23, 2011 and subsequent inquiries by PHMSA staff a Notice of Proposed Safety
Order, CPF No. 4-2011-5015S was issued on September 29, 2011 and a Consent Agreement was
finalized on February 29, 2012.
Enterprise implemented all of the requirements of the Consent Agreement. This letter is to
inform you that no further action is necessary and this case is now closed. Thank you for your
cooperation.
Sincerely,
R. M. Seeley
Director, Southwest Region
Pipeline and Hazardous Materials Safety Administration

## Provenance

- Official: Yes
- Source: <https://primis.phmsa.dot.gov/enforcement-data/case/420115015S>
- Source ID: `phmsa-enforcement`
- SHA-256: `438fa868cce16e35f5dacb0ff0f3794394964f86ac06c162d572a0c245cd15dd`
- Retrieved: 2026-08-20T04:44:44.458Z
- Exported: 2026-08-22T16:44:29.050Z
- Document slug: `phmsa-enforcement-420115015s`

### Source metadata

```json
{
  "cpf": "420115015S",
  "operator": "DIXIE PIPELINE COMPANY LLC",
  "region": "Southwest",
  "pipelineType": "INTERSTATE LIQUID ONSHORE",
  "caseStatus": "CLOSED",
  "citedSections": [],
  "dataAsOf": "08/04/2026 12PM",
  "caseDataAsOf": "2026-08-04",
  "attachmentCount": 8,
  "attachments": [
    {
      "name": "420115015S_ Consent Agreement_02292012.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420115015S/420115015S_%20Consent%20Agreement_02292012.pdf",
      "bytes": 99777,
      "category": "agency_document"
    },
    {
      "name": "420115015S_ Consent Agreement_02292012_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420115015S/420115015S_%20Consent%20Agreement_02292012_text.pdf",
      "bytes": 32557,
      "category": "agency_document"
    },
    {
      "name": "420115015S_ Consent Order_02292012.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420115015S/420115015S_%20Consent%20Order_02292012.pdf",
      "bytes": 25901,
      "category": "agency_document"
    },
    {
      "name": "420115015S_ Consent Order_02292012_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420115015S/420115015S_%20Consent%20Order_02292012_text.pdf",
      "bytes": 11320,
      "category": "agency_document"
    },
    {
      "name": "420115015S_Closure_10292012.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420115015S/420115015S_Closure_10292012.pdf",
      "bytes": 17408,
      "category": "agency_document"
    },
    {
      "name": "420115015S_Closure_10292012_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420115015S/420115015S_Closure_10292012_text.pdf",
      "bytes": 4344,
      "category": "agency_document"
    },
    {
      "name": "420115015S_NOPSO_09292011.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420115015S/420115015S_NOPSO_09292011.pdf",
      "bytes": 2871992,
      "category": "case_document"
    },
    {
      "name": "420115015S_NOPSO_09292011_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420115015S/420115015S_NOPSO_09292011_text.pdf",
      "bytes": 38236,
      "category": "case_document"
    }
  ],
  "extractedAgencyDocumentCount": 3,
  "attachmentPolicy": "Official attachment links are retained. Agency-issued documents may also include a verified local PDF and page-level text representation.",
  "jurisdiction": "US",
  "operatorName": "DIXIE PIPELINE COMPANY LLC"
}
```