# MAGELLAN PIPELINE COMPANY, LP — Notice of Probable Violation

**Citation:** CPF 420125010  
**Type / status:** enforcement / historical  
**Agency:** Pipeline and Hazardous Materials Safety Administration  
**Effective:** Not stated  
**Published:** 2012-03-23

CLOSED notice of probable violation citing 195.402(a), 195.406(a), 195.406(b), 195.410, 195.430, 195.432, 195.567(b), 195.571, 195.573(c), 195.573(d), 195.575(a).

## Document text

Notice of Probable Violation involving MAGELLAN PIPELINE COMPANY, LP. PHMSA's enforcement data identifies the cited regulations as 195.402(a),  195.406(a),  195.406(b),  195.410,  195.430,  195.432,  195.567(b),  195.571,  195.573(c),  195.573(d),  195.575(a). The case was opened on 2012-03-23 and is reported as closed as of 2016-03-04. Proposed civil penalty: $149,800. Assessed civil penalty: $149,800. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

420125010_Closure Letter_03042016.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420125010/420125010_Closure%20Letter_03042016.pdf

420125010_Closure Letter_03042016_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420125010/420125010_Closure%20Letter_03042016_text.pdf

420125010_Final Order_09022014.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420125010/420125010_Final%20Order_09022014.pdf

420125010_Final Order_09022014_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420125010/420125010_Final%20Order_09022014_text.pdf

420125010_NOPV PCP PCO_03232012.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420125010/420125010_NOPV%20PCP%20PCO_03232012.pdf

420125010_NOPV PCP PCO_03232012_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420125010/420125010_NOPV%20PCP%20PCO_03232012_text.pdf

420125010_Operator_Response_and_Request_for_Hearing_04272012.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420125010/420125010_Operator_Response_and_Request_for_Hearing_04272012.pdf

420125010_NOPV PCP PCO_03232012_text.pdf

NOTICE OF PROBABLE VIOLATION
PROPOSED CIVIL PENALTY
and
PROPOSED COMPLIANCE ORDER
CERTIFIED MAIL - RETURN RECEIPT REQUESTED
March 23, 2012
Mr. Larry Davied
Vice President, Technical Services
Magellan Pipeline Company
One Williams Center
Tulsa, OK 74172
CPF 4-2012-5010
Dear Mr. Davied:
Between March 22, 2010 and April 22, 2011, representatives of the Pipeline and Hazardous
Materials Safety Administration (PHMSA) pursuant to Chapter 601 of 49 United States Code
were on site and inspected your operations and maintenance procedures and ten pipeline
inspection units in Oklahoma and Texas.
As a result of the inspection, it appears that you have committed probable violations of the
Pipeline Safety Regulations, Title 49, Code of Federal Regulations. The items inspected and the
probable violation(s) are:
1. 195.575 Which facilities must I electrically isolate and what inspections, tests, and
safeguards are required?
(a) You must electrically isolate each buried or submerged pipeline from other
metallic structures, unless you electrically interconnect and cathodically protect the
pipeline and the other structures as a single unit. (b) You must install one or more
insulating devices where electrical isolation of a portion of a pipeline is necessary to
facilitate the application of corrosion control. (c) You must inspect and electrically



test each electrical isolation to assure the isolation is adequate. (d) If you install an
insulating device in an area where a combustible atmosphere is reasonable to
foresee, you must take precautions to prevent arcing. (e) If a pipeline is in close
proximity to electrical transmission tower footings, ground cables, or counterpoise,
or in other areas where it is reasonable to foresee fault currents or an unusual risk
of lightning, you must protect the pipeline against damage from fault currents or
lightning and take protective measures at insulating devices.
Magellan (the Operator) failed to isolate each buried pipeline from other metallic structures as
required by §195.575 and confirmed in the written procedures required under §195.402. As
discussed below, the Operator has both metallically and electrolytically shorted casings in the
units inspected (including Longhorn, Duncan to Ft. Smith, Cimarron Pipeline, Orion West,
Oklahoma City, and Tulsa) and has not consistently taken measures to achieve electrical
isolation between the casings and carrier pipes.
Metallically shorted casings are addressed by Magellan Corrosion Control Program procedures,
7.04-ADM-001, Section 2.9.4, which states that metallically shorted casings require actions
when the casing potential is within 100 millivolts of the carrier pipe. Magellan’s annual surveys
of pipe-to-soil and casing-to-soil readings show some casing-to-soil readings taken at the same
test station or a nearby test station to be within 100 mV of the pipe-to-soil readings. According
to Magellan records, testing performed by the Operator has confirmed that some of these casings
are metallically shorted but actions have not been taken to achieve the electrical isolation
required to comply with the requirements of 195.575. In addition, the Operator has not followed
its procedures to clear the short or fill the casing annulus with dielectric material for each
metallically shorted casing.
A sample of the Magellan annual cathodic protection survey records, included as evidence, show
the inspection date, the name of the pipeline segment, the milepost, a description of the location,
the pipe-to-soil and casing-to-soil readings in volts and the casing status. Some examples in the
Magellan records with casing-to-soil reading within 100 mV of the pipe-to-soil reading,
indicating the potential for the casing to be metallically shorted, include the following:
Segment Name MP/Station Year(s) Comments
Ponca City to Barnsdall 22+24 2005, 2006, 2007, 2008, 2009 (2009) P/S -2.175V, C/S -2.181V
Enid to Oklahoma City 74+06 2005, 2006, 2007, 2008, 2009 (2009) P/S -1.612V, C/S -1.602V
Allen to Drumright 16+27 20072, 20082, 20091 (2009) P/S -0.926V, C/S -0.844V
Tulsa Jct. to Kansas St. Line 119.223 20053,20064,20074,20084,20094 (2009) P/S -1.620V, C/S -1.617V
Barnsdall to Kansas City #3-8 1+06 20052, 20072, 20084, 20092 (2008) P/S -1.205V, C/S -1.109V
West Tulsa to Glenpool 4.38 20054,20064,20074,20084,20091 (2009) P/S -0.901V, C/S -0.900V
West Tulsa to Glenpool 4.58 20054,20064,20074,20084,20091 (2009) P/S -0.943V, C/S -0.930V
Clyde to DeLeon 156.302 2010 P/S -1.127V, C/S -1.124V
1 Casing-to-soil within 100 mV of pipe-to-soil but shown in Magellan records to be clear.
2 >100 mV difference and shown in Magellan records as electrolytically shorted.
3 Casing-to-soil within 100 mV of pipe-to-soil and shown in Magellan records to be metallically shorted.
4 Casing-to-soil within 100 mV of pipe-to-soil and shown in Magellan records to be electrolytically shorted.
The Magellan records show casing status test designations using “C” for clear (not shorted), “E”
for electrolytically shorted, “S” for metallically shorted, and “I” for inhibited (the annulus of the
casing has been filled with a dielectric material). These designations have sometimes changed2



from year to year between metallically shorted, electrolytically shorted, and clear. For example,
the shorted casing at station 22+24 on the Ponca City to Barnsdall segment was designated to be
metallically shorted (S) as early as 2005, was changed to electrolytically shorted (E) in 2006,
then back to metallically shorted (S) in 2007, 2008, and 2009. The operator does not explain
these inconsistencies.
Research on corrosion of cased pipes supports the need to achieve electrical isolation between
the carrier pipe and casing and a discussion is provided in the associated Violation Report.
Magellan does not have a procedure specifically addressing the issue of electrolytically shorted
casings, but the records indicate that the Operator has recognized the issue given the many
casings in their records designated to be electrolytically shorted. The records, however, do not
indicate the operator has taken consistent actions to address these electrolytic shorts and achieve
electrical isolation as required by 195.575. Out of the many shorted casings (electrolytically) on
the Magellan system where the casing-to-soil readings are not within 100 mV of the pipe-to-soil
readings some specific examples are as follows:
Segment Name MP/Station Year(s) Comments
Ponca City to Barnsdall 0+04,44+22,52+08 20051,20061,2007,2008,2009 (00+04,2009) P/S -1.395V,C/S -1.102V
Enid to Oklahoma City 69+14,80+26 20062,20072,2008,2009 (69+14,2009) P/S -1.271V,C/S -1.062V
Allen to Drumright 68+25,69+16,75+15 2007,2008,2009 (68+25,2009) P/S-1.692V, C/S -1.466V
Tulsa Jct. to Kansas St. Line 110.878,151.557 20053,2006,2007,2008,20091 (110.87,2009) P/S-1.519V,C/S -0.992V
Barnsdall to Kansas City (#3-8) 29+44 2006,2007,2008,2009 (2009) P/S -1.791V, C/S -0.953V
Cushing to Drumright 8+15 2006,2007,2008,2009,2010 (2010) P/S -1.457V, C/S -1.177V
Drumright to Tulsa 0+24, 28+40, 32+29 20055,20061,20074,20084,2009 (2009,0+24) P/S -1.349V, C/S -0.896V
Concord to East Houston 170.6 2006,2007,2008,2009,2010 (2010) P/S -1.171V, C/S -1171V
Clyde to DeLeon 187.200 2010 P/S -1.201V, C/S -0.972V
1 Casing(s) designated as clear even though casing-to-soil reading is significantly more electronegative than native steel in soil.
2 Casing at 80+26 designated as clear.
3 Casing at 110.878 designated as metallically shorted.
4 Casing at 32+29 designated as clear.
5 Casings at 0+24 designated as clear even though casing-to-soil reading is significantly more electronegative than native steel in soil.
None of the casings were intentionally bonded to the carrier pipe or connected to the cathodic
protection system to cathodically protect the casings. Therefore, it was not the intent of the
Operator to protect the pipe and casing as a unit. In addition, no records were presented
documenting the installation of galvanic anodes to cathodically protect the casings which could
result in elevated casing-to-soil readings.
2. 195.410 Line Markers.
(1) Markers must be located at each public road crossing, at each railroad crossing,
and in sufficient number along the remainder of each buried line so that its location
is accurately known. (c) Each operator shall provide line marking at locations
where the line is above ground in areas that are accessible to the public.
The Operator did not meet the requirements of §195.410 by placing a sufficient number of
markers along the buried pipeline so that its location is accurately known. Magellan also did not
follow its “Pipeline Marking Procedure, 7.05-ADM-002, pages 1-5 of 5” dated January 1, 2010
3



regarding its criteria to “Effectively delineate the pipeline corridor.” This procedure also states
that “Markers must be placed and maintained over each buried pipeline at the following
locations: 3.3.4 in sufficient numbers along the remainder of each buried line so that its location
is accurately known.”
During the field inspection there were locations on the Magellan pipeline system where there
were an inadequate number of pipeline markers in order to accurately know the location of the
pipeline, even when turning 360 degrees. At each of the sites listed below and by walking in
various directions from each of the specific known pipeline locations identified by the operator,
it was impossible to ascertain with any certainty the ongoing pipeline path through the further
observation of pipeline markers that would accurately show the location of the pipeline.
Locations where there were inadequate pipeline markers include segments in the Barnsdall,
Tulsa, Oklahoma City, Odessa to El Paso, and Cimarron inspection units. Some examples are
included in the following table:
Date Unit Pipeline Segment Approximate Location Comments
08/10/2010 Tulsa Tulsa to State Line Oologah, OK near Road E0390 Pipeline near house, apt. bldg.
09/24/2010 Oklahoma City Allen to Drumright County Road 3261 near 81+05 Pipeline near corral, residence
09/28/2010 Oklahoma City Wynnewood to OKC County road crossing near MP 11 Pipeline near residence
09/21/2010 Oklahoma City Tulsa to Drumright 56th Street near 26+48
08/10/2010 Tulsa Tulsa to State Line ROW near MP 138 Near Oologah Lake block valve
08/10/2010 Tulsa Tulsa to State Line ROW near MP 148
08/10/2010 Tulsa Tulsa to State Line ROW near MP 144 Near old Alluwe Station site
05/11/2010 Duncan-Ft. Smith Duncan to Ft. Smith ROW near 94+07 Near east end of Sander Road
05/11/2010 Duncan-Ft. Smith Duncan to Ft. Smith ROW near 128+96 Near county road crossing
05/11/2010 Duncan-Ft. Smith Duncan to Ft. Smith ROW near 142+31 Near Massey Point gate valve
05/11/2010 Duncan-Ft. Smith Duncan to Ft. Smith ROW near 199+32 Near Havener gate valve
05/11/2010 Duncan-Ft. Smith Duncan to Ft. Smith ROW near MP 201 Near Spiro rectifier
05/14/2010 Duncan-Ft. Smith Duncan to Ft. Smith ROW near 213+21 Near RR x-ing
06/09/2010 Orion West Frost to Odessa ROW near MP 310 Near Frost Station
06/09/2010 Orion West Frost to Odessa ROW near MP 202 Near Highway 8 crossing
06/09/2010 Orion West Frost to Odessa ROW near MP 174
06/09/2010 Orion West Frost to Odessa ROW near MP 163 Near county road 483
06/09/2010 Orion West Frost to Odessa ROW near MP 162 Near state highway 283
06/09/2010 Orion West Frost to Odessa ROW near MP 73 Near Colorado River crossing
06/10/2010 Orion West Frost to Odessa ROW near MP 72 Near Colorado River crossing
07/27/2010 Odessa-El Paso Odessa to El Paso ROW near MP 44
07/27/2010 Odessa-El Paso Odessa to El Paso ROW near MP 46 Damaged marker
07/27/2010 Odessa-El Paso Odessa to El Paso ROW near MP 61 Damaged marker
07/27/2010 Odessa-El Paso Odessa to El Paso ROW near rectifier E-8 Near 355+00
07/29/2010 Odessa-El Paso Odessa to El Paso ROW near rectifier E-40 Near 11208+95
08/10/2010 Tulsa Tulsa to State Line ROW near MP 168 Near Highway 10 crossing
08/10/2010 Tulsa Tulsa to State Line ROW near MP 158 Near county road crossing
08/10/2010 Tulsa Tulsa to State Line ROW near MP 147
08/10/2010 Tulsa Tulsa to State Line ROW near MP 139
08/10/2010 Tulsa Tulsa to State Line ROW near MP 130
08/10/2010 Tulsa Tulsa to State Line ROW near MP 118 Pipeline near residence
08/10/2010 Tulsa Tulsa to State Line ROW near 49th Street North
08/10/2010 Tulsa Tulsa to State Line ROW near MP 105 Near Million Dollar Casino
08/10/2010 Tulsa Glenpool to W. Tulsa ROW near MP 10
08/11/2010 Tulsa Glenpool to W. Tulsa ROW near MP 2 Old Koch tie-in
09/21/2010 Tulsa Tulsa to Drumright 56th Street area
09/21/2010 Tulsa Tulsa to Drumright MP 19 area
09/23/2010 Oklahoma City OKC to Wynnewood MP 34 area
09/23/2010 Oklahoma City OKC to Wynnewood Wynnewood tank farm area
09/23/2010 Oklahoma City Allen to Drumright ROW near 1+42
09/24/2010 Oklahoma City Allen to Drumright MP 74 area
4



09/24/2010 Oklahoma City Allen to Drumright MP 40 area County road 108
09/24/2010 Oklahoma City Allen to Drumright MP 29 area
10/05/2010 Cimarron Crude Glenpool to Tulsa MP 3 area
10/05/2010 Cimarron Crude Glenpool to Tulsa South I-44 and railroad tracks
3. 195.567 Which pipelines must have test leads and what must I do to install and
maintain the leads?
(b) Installation. You must install test leads as follows: (1) Locate the leads at
intervals frequent enough to obtain electrical measurements indicating the
adequacy of cathodic protection.
(c) Maintenance. You must maintain the test lead wires in a condition that enables
you to obtain electrical measurements to determine whether cathodic protection
complies with §195.571.
Magellan failed to maintain its test lead wires in a condition that enabled Magellan to obtain
electrical measurements to determine whether cathodic protection complies with §195.571.
During the field inspection, Magellan was observed to have cathodic protection test stations
listed in their records as annual test points that were damaged but had not yet been repaired so
that electrical measurements to determine the adequacy of cathodic protection could be made.
For example:
• The test station on the Wynnewood to Allen segment of the Duncan to Ft. Smith
12-inch and 10-inch pipeline located on Racetrack Road north of County Road
357 was destroyed and had not been repaired at the time of the inspection.
• The test station at 7705+00 on the Black river to Hueco segment of the Odessa to
El Paso pipeline had been destroyed and not repaired at the time of the inspection.
• The test station on the Cimarron pipeline near County Road 4804 read -707mV at
the time of the inspection and the analysis performed by the corrosion technician
indicated that the test leads may not have been solidly connected to the pipe.
These actions also show that the Operator failed to follow its procedure for installing and
maintaining test leads as required in their procedure titled “Corrosion Control Program, 7.04-
ADM-001, pages 1-21 of 21, dated January 1, 2010, section 2.10 Test Leads 195.567, 192.460,
and 192.471.”
4. 195.406 Maximum operating pressure.
(a) Except for surge pressures and other variations from normal operations, no
operator may operate a pipeline at a pressure that exceeds any of the following: (1)
The internal design pressure of the pipe determined in accordance with §195.106.
However, for steel pipe in pipelines being converted under §195.5, if one or more
factors of the design formula (§195.106) are unknown, one of the following pressures
5



is to be used as design pressure: (i) Eighty percent of the first test pressure that
produces yield under section N5.0 of Appendix N of ASME B31.8, reduced by the
appropriate factors in §§195.106(a) and (e); or (ii) If the pipe is 323.8 mm (12¾ in)
or less outside diameter and is not tested to yield under this paragraph, 1379 kPa
(200 psig). (2) The design pressure of any other component of the pipeline. (3)
Eighty percent of the test pressure for any part of the pipeline which has been
pressure tested under Subpart E of this part. (4) Eighty percent of the factory test
pressure or of the prototype test pressure for any individually installed component
which is excepted from testing under §195.305. (5) For pipelines under
§§195.302(b)(1) and (b)(2)(i), that have not been pressure tested under Subpart E of
this part, 80 percent of the test pressure or highest operating pressure to which the
pipeline was subjected for 4 or more continuous hours that can be demonstrated by
recording charts or logs made at the time the test or operations were conducted.
(b) No operator may permit the pressure in a pipeline during surges or other
variations from normal operations to exceed 110 percent of the operating pressure
limit established under paragraph (a) of this section. Each operator must provide
adequate controls and protective equipment to control the pressure within this limit.
Magellan has allowed pipeline pressures to exceed the maximum operating pressure in violation
of the requirements in §195.406. Specifically, according to records submitted by the Operator in
response to the PHMSA March 3, 2011, Request for Specific Information, Magellan has allowed
their pipeline system to exceed the Maximum Operating Pressure (MOP) for ten (10) minutes, or
longer, seventeen (17) times since 2007. Magellan states that it is standard practice per their
System Integrity Plan procedure 13.01-ADM-008, Abnormal Operating Conditions List, to alarm
as an abnormal operating condition when exceeding MOP on a ten minute basis. However,
allowing the pressure to remain over the MOP for ten minutes is not consistent with a reasonable
definition of surge pressure.
Another issue involving an overpressure situation occurred when the Magellan control center
received an alarm indicating that the MOP +110% had been exceeded at the Ponca City facility.
The Operator determined that a pressure relief valve had been incorrectly set at 1,440 psig for a
pipeline with a MOP of 480 psig. A Magellan technician also found during an inspection at the
Sooner Road facility that the numbered tags identifying the pressure relief devices did not match
the numbers on the Pipeline and Instrumentation Drawing (P&ID). In addition to showing the
configuration of the piping, valves, and relief devices, the P&ID ties the MOP of the pipeline
segment to the relief valve so that the correct settings can be established. Incorrect tagging may
result in incorrect setpoints for the pressure relief devices.
Magellan records also show that at the Drumright facility the overpressure devices were set to
activate at pressures higher than the designated pressure on the inspection form (07-FORM-
0741). For example, the inspection form indicates that device MLMF-0033 on the East Pig
Bypass should be set to activate at a pressure of 1,050 psig. However, on September 24, 2009,
the pressure was set at 1,448 psig. Another example is device UNT2-0012 was set to activate at
6



809 psig but the maximum pressure indicated on the form is 800 psig. The inspection form for
the Oklahoma City Reno facility shows that device PSV-1221 was found to be set to relieve at
500 psig but the maximum pressure is 305 psig. Improperly setting the relief device pressures
may allow an overpressure condition and could result in a failure of the pipeline facilities.
5. 195.402(a) Procedural manual for operations, maintenance, and emergencies.
(a) General. Each operator shall prepare and follow for each pipeline system a
manual of written procedures for conducting normal operations and maintenance
activities and handling abnormal operations and emergencies. This manual shall be
reviewed at intervals not exceeding 15 months, but at least once each calendar year,
and appropriate changes made as necessary to insure that the manual is effective.
This manual shall be prepared before initial operations of a pipeline commence, and
appropriate parts shall be kept at locations where operations and maintenance
activities are conducted.
Magellan failed to follow its Inspection of Right-of-way Procedure, 7.05-ADM-006, which
requires the Operator to identify activity along the right-of-way that could, if not corrected, pose
a hazard or compromise the safety, integrity or operation of pipelines and right-of-way.
Specifically, several encroachments were observed during the field inspection with large
quantities of junk on the right-of-way (abandoned trucks and cars, and oil storage tanks) in West
Tulsa and near Drumright, OK. While barn construction predates the Magellan acquisition of the
pipeline, there are other indications of encroachment and overgrowth indicating Magellan is not
following its Inspection of Right-of-way Procedure for identifying conditions on the pipeline
right-of-way that could pose a hazard or compromise safety.
Specific locations where problems were found related to encroachment activities found on or adjacent to the pipeline
ROW include:
1. Sandler Road, tank on the ROW
2. Race Track Road, encroachment of equipment on the ROW
3. County Road 145, barn on the ROW
4. Commercial business wareyard on the ROW
5. Cushing 8”, truck and storage facilities encroaching on the ROW
6. Cushing 8”, oil field debris on the ROW
7. Wynnewood 12”, metal debris on the ROW
8. Cushing to Glenpool, abandoned vehicles on the ROW
9. West Tulsa Area, miscellaneous materials in yard over ROW
10. Tulsa to Drumright 8”, facility encroachment on the ROW
Major overgrowth which obscured the ROW was found at the following locations identified as follows:
1. 39th street
2. Caney River
3. 49th street
4. Glenpool to PSO
5. Glenpool to West Tulsa
7



6. South Ok City
7. Allen to Drumright 8”, MP68
6. 195.402(a) Procedural manual for operations, maintenance, and emergencies.
(a) General. Each operator shall prepare and follow for each pipeline system a
manual of written procedures for conducting normal operations and maintenance
activities and handling abnormal operations and emergencies. This manual shall be
reviewed at intervals not exceeding 15 months, but at least once each calendar year,
and appropriate changes made as necessary to insure that the manual is effective.
This manual shall be prepared before initial operations of a pipeline commence, and
appropriate parts shall be kept at locations where operations and maintenance
activities are conducted.
Magellan did not install pipeline markers where the pipe is to remain exposed as specified by its
procedures, Corrosion Control Program, 7.04-ADM-001, 2.11.4. The Magellan procedures state
that if the pipe is to remain exposed, proper pipeline markers shall be installed. During the field
inspection exposures were observed without pipeline markers and without stated plans for
reburial. The Operator was found to have unmarked exposures on the Glenpool to West Tulsa,
Tulsa to Drumright, Drumright to Cushing, Cushing to Glenpool, Barnsdall to El Dorado, and
Odessa to El Paso pipelines.
7. 195.571 What criteria must I use to determine the adequacy of cathodic protection?
Cathodic protection required by this subpart must comply with one or more of the
applicable criteria and other considerations for cathodic protection contained in
paragraphs 6.2 and 6.3 of NACE Standard RP 0169 (incorporated by reference, see
§195.3).
Magellan did not meet one of the applicable cathodic protection criteria required by §195.571 for
portions of its pipeline system. With regard to §195.571, the Operator was unable to adequately
show how IR drop is considered in the pipe-to-soil readings as required by the referenced
standard (NACE RP 0169). Magellan also did not follow its Corrosion Control Program
procedure, 7.04-ADM-001, Sections 2.3 and 2.4. During the field portion of the inspection,
some pipe-to-soil readings were not meeting the criterion chosen by the Operator for determining
the adequacy of the cathodic protection. Examples of inadequate readings were found on the
Cimarron 8-inch pipeline at MP 53 (-683mV), MP 54 (-768mV), MP 61 (-696mV), MP 71 (-
707mv), the Odessa to El Paso pipeline at 9899+72 (-700mV), 9700+19 (-771mV), 9747+19 (-
500mV), 10123+95 (-500mV), 10264+00 (-654mV), the Cushing to Oklahoma City pipeline at
MP 30.5 (-781mV), MP 0.7 (-817mV), the Glenpool to PSO pipeline at MP 16.7 (-822mV), the
Tulsa to State Line pipeline at MP 110.5 (-500mV), MP 128.4 (-746mV).
8. 195.573 What must I do to monitor external corrosion control?
8



(d) Breakout tanks. You must inspect each cathodic protection system used to
control corrosion on the bottom of an aboveground breakout tank to ensure that
operation and maintenance of the system are in accordance with API Recommended
Practice 651. However, this inspection is not required if you note in the corrosion
control procedures established under §195.402(c)(3) why compliance with all or
certain operation and maintenance provisions of API Recommended Practice 651 is
not necessary for the safety of the tank.
Magellan did not meet one of the applicable cathodic protection criteria required by §195.573 for
some breakout tanks. For the breakout tanks not meeting the cathodic protection requirements,
the operator has not demonstrated why compliance with API 651 is unnecessary as required by
§195.573. Magellan also did not follow its Corrosion Control Program procedure, 7.04-ADM-
001, Sections 2.3 and 2.4. During the field portion of the inspection, some tank-to-soil readings
were not meeting the criterion chosen by the Operator for determining the adequacy of the
cathodic protection. With regard to §195.573, structure-to-soil readings for breakout tanks 533,
535, and 868 in Oklahoma City were found to not meet the criterion chosen by the operator.
9. 195.573 What must I do to monitor atmospheric corrosion control?
(c) If you find atmospheric corrosion during an inspection, you must provide
protection against the corrosion as required by Sec. 195.581.
Magellan failed to provide protection against atmospheric corrosion as required by §195.581.
The operator also did not follow its Corrosion Control Program procedure, 7.04-ADM-001,
Section 3.0. There were areas of oxidation observed on the chime area of some breakout tanks,
above ground valves and piping, flange bolts, pipe/soil interfaces, and spans at various locations
on the Magellan Pipeline System. Evidence includes photographs taken during the field inspection.
These photographs indicate ongoing atmospheric corrosion at the following locations:
1. Allen Station Breakout Tank (BOT) 880
2. Barnsdale BOT 1214
3. Barnsdale BOT 416
4. Barnsdale BOT 729
5. Barnsdale BOT 730
6. Enid BOT 1231
7. Enid BOT 1232
8. Enid BOT 1238
9. Odessa BOT 574
10. Odessa piping
11. Odessa BOT 586
12. Odessa BOT 225
13. Odessa BOT 228
14. Odessa BOT 229
15. Line #1, 8” MP 21
16. P/S Interface on Old Tulsa line
9



17. Orion West Unit
18. Orion West MP 312
19. Pipeline span near Black River Station
20. Glenpool to West Tulsa
21. MLV @ MP 21
22. Pipeline Span @ MP 46
10. 195.430 Firefighting equipment.
Each operator shall maintain adequate firefighting equipment at each pump station
and breakout tank area. The equipment must be-
(a) In proper operating condition at all times;
(b) Plainly marked so that its identity as firefighting equipment is clear; and,
(c) Located so that it is easily accessible during a fire.
Magellan does not maintain adequate firefighting equipment at each pump station and breakout
tank area. The Operator has only fire extinguishers at most pump stations and breakout tank
areas as required under its Portable Fire Extinguishers Administrative Procedure, 5.05-ADM-
076, which states that “equipment shall be adequate to extinguish fires that are in the early stages
of development and in no case shall be expected to fight a fully engulfed fire.” The Operator
relies on public firefighting agencies or firefighting cooperatives to respond to fires at their
breakout facilities. However, liaison documentation is not adequate to show that Magellan has
confirmed that these agencies have adequate training, equipment, and supplies to respond to fires
at their pump stations and breakout tank areas.
11. 195.432 Inspection of in-service breakout tanks.
(a) Except for breakout tanks inspected under paragraphs (b) and (c) of this section,
each operator shall, at intervals not exceeding 15 months, but at least once each
calendar year, inspect each in-service breakout tank.
(b) Each operator must inspect the physical integrity of in-service atmospheric and
low-pressure steel aboveground breakout tanks according to API Standard 653
(incorporated by reference, see §195.3). However, if structural conditions prevent
access to the tank bottom, the bottom integrity may be assessed according to a plan
included in the operations and maintenance manual under §195.402(c)(3).
The Magellan breakout tank inspection program and methodology to establish in-service and
out-of-service inspections does not meet the requirements for a risk-based inspection process
defined by API 653, incorporated into Part 195 by reference. Specifically, the Magellan Tank
Integrity Risk Based Inspection Procedure, 7.10-ADM-013, does not adequately incorporate
some of the factors in the referenced version of API 653, including the materials of construction,
the as-built standard, the accuracy and completeness of determining bottom plate thickness, the
methods used to determine the product side and soil side corrosion rates and accuracy of the
10



methods, the availability, accuracy and need for leak detection, the effectiveness of corrosion
mitigation measures, and the quality of maintenance including previous repairs. Magellan
personnel administering the risk-based program do not have formal training in risk-based
inspection methodology and no records showing initial and subsequent assessments of the
program by an authorized inspector and tank engineer were presented. Also, the Magellan
routine breakout tank inspections failed to identify issues that should be addressed by the
Operator’s breakout tank maintenance program such as plugged telltale holes, corrosion near the
floor to shell weld, corrosion of the extension, soil or gravel covering the extension, corrosion
around the perimeter of the reinforcing plates, cracked foundations supporting equipment and
piping connected to the tanks, incomplete records of construction and repairs, and documentation
that API 653 inspection recommended repairs were evaluated and completed or determined by
the operator to not be needed.
Proposed Civil Penalty
Under 49 United States Code, § 60122, you are subject to a civil penalty not to exceed $100,000
for each violation for each day the violation persists up to a maximum of $1,000,000 for any
related series of violations. The Compliance Officer has reviewed the circumstances and
supporting documentation involved in the above probable violation(s) and has recommended that
you be preliminarily assessed a civil penalty of $149,800 as follows:
Item number PENALTY
2 $ 61,500
4 $ 55,400
5 $ 32,900
Warning Items
With respect to item(s) 3, and 6 through 11 we have reviewed the circumstances and supporting
documents involved in this case and have decided not to conduct additional enforcement action
or penalty assessment proceedings at this time. We advise you to promptly correct these item(s).
Be advised that failure to do so may result in Magellan Pipeline Company being subject to
additional enforcement action.
Proposed Compliance Order
With respect to item(s) 1, 2, 4, and 5, pursuant to 49 United States Code § 60118, the Pipeline
and Hazardous Materials Safety Administration proposes to issue a Compliance Order to
Magellan Pipeline Company. Please refer to the Proposed Compliance Order, which is enclosed
and made a part of this Notice.
Response to this Notice
Enclosed as part of this Notice is a document entitled Response Options for Pipeline Operators
in Compliance Proceedings. Please refer to this document and note the response options. Be
advised that all material you submit in response to this enforcement action is subject to being
made publicly available. If you believe that any portion of your responsive material qualifies for
confidential treatment under 5 U.S.C. 552(b), along with the complete original document you11



must provide a second copy of the document with the portions you believe qualify for
confidential treatment redacted and an explanation of why you believe the redacted information
qualifies for confidential treatment under 5 U.S.C. 552(b). If you do not respond within 30 days
of receipt of this Notice, this constitutes a waiver of your right to contest the allegations in this
Notice and authorizes the Associate Administrator for Pipeline Safety to find facts as alleged in
this Notice without further notice to you and to issue a Final Order.
In your correspondence on this matter, please refer to CPF 4-2012-5010 and for each document
you submit, please provide a copy in electronic format whenever possible.
Sincerely,
R. M. Seeley
Director, Southwest Region
Pipeline and Hazardous Materials Safety Administration
Enclosures: Proposed Compliance Order
Response Options for Pipeline Operators in Compliance Proceedings
12



PROPOSED COMPLIANCE ORDER
Pursuant to 49 United States Code § 60118, the Pipeline and Hazardous Materials Safety
Administration (PHMSA) proposes to issue to Magellan Pipeline Company a Compliance Order
incorporating the following remedial requirements to ensure the compliance of Magellan
Pipeline Company with the pipeline safety regulations:
1. In regard to Item Number 1 of the Notice pertaining to electrical isolation where Magellan failed
to address metallically and electrolytically shorted casings, the Operator must perform tests to
determine if each casing is metallically or electrolytically shorted. If a casing is determined to be
metallically or electrolytically shorted, the Operator must evaluate any existing ILI data to
determine if there are metal loss indications and make any required repairs to the carrier pipe. If
no ILI data is available from studies made within the past five years, Magellan must perform
studies using ILI or an alternative technology to determine for each casing if there is metal loss
requiring repairs. The Operator must also clear the shorts, purge the casings of electrolyte, and
replace the end seals as described in NACE SP0200. The Operator must also develop a
procedure that specifically addresses the issue of electrolytically shorted casings.
2. In regard to Item Number 2 of the Notice pertaining to line markers where Magellan failed to
adequately mark its pipeline, the Operator must install additional line markers in the Barnsdall,
Tulsa, Oklahoma City, Odessa to El Paso, and Cimarron inspection units so that the location of
the pipeline is accurately known as required by 195.410.
3. In regard to Item Number 4 of the Notice pertaining to maximum operating pressure where
Magellan allowed the pipeline pressure to exceed the MOP for durations longer than indicated by
a surge event, the Operator must review the design of its overpressure protection and make
changes necessary to prevent recurrence. Magellan must also perform a review of the MOP’s for
each pipeline segment, check the setpoints of each overpressure device, ensure each overpressure
device is correctly tagged, and check each inspection form to ensure the tag numbers, maximum
pressures, and setpoints are all correct.
4. In regard to Item Number 5 of the Notice pertaining to patrolling the rights-of-way where
Magellan failed to identify activity along the right-of-way that could, if not corrected, pose a
hazard or compromise the safety, integrity or operation of pipelines and right-of-way specified
by its inspection of right-of-way procedure. The Operator also failed to remedy overgrowth that
prevents the inspection of the surface condition on or adjacent to the pipeline right-of-way, also
as specified by its right-of-way procedure. Magellan must make modifications to its patrolling
practices to ensure that its procedures are followed. The Operator must also remedy existing
encroachments that impair observation of the right-of-way and safety of the pipeline system.
The operator must also perform maintenance on areas of the right-of-way that are obscured by
vegetation.
5. Magellan must complete all items within 180 days following receipt of the Final Order.
13



6. It is requested (not mandated) that Magellan Pipeline Company maintain documentation of the
safety improvement costs associated with fulfilling this Compliance Order and submit the total to
R. M. Seeley, Director, Southwest Region, Pipeline and Hazardous Materials Safety
Administration. It is requested that these costs be reported in two categories: 1) total cost
associated with preparation/revision of plans, procedures, studies and analyses, and 2) total cost
associated with replacements, additions and other changes to pipeline infrastructure.
14

420125010_Final Order_09022014_text.pdf

SEPTEMBER 2, 2014
Mr. Michael N. Mears
President and Chief Executive Officer
Magellan Midstream Partners, LP
Magellan Pipeline Company, LP
One Williams Center
Tulsa, OK 74172
Re: CPF No. 4-2012-5010
Dear Mr. Mears:
Enclosed please find the Final Order issued in the above-referenced case. It makes findings of
violation, assesses a civil penalty of $149,800, and specifies corrective action that must be
completed. The penalty payment terms are set forth in the Final Order. When the civil penalty
has been paid and the terms of the compliance order completed, as determined by the Director,
Southwest Region, this enforcement action will be closed. Service of the Final Order is made
pursuant to 49 C.F.R. § 190.5.
Thank you for your cooperation in this matter.
Sincerely,
Jeffrey D. Wiese
Associate Administrator
for Pipeline Safety
Enclosure
cc: Mr. R.M. Seeley, Director, Southwest Region, OPS
Ms. Bizunesh Scott, Steptoe & Johnson LLP
1330 Connecticut Ave. NW, Washington, D.C. 20036
CERTIFIED MAIL – RETURN RECEIPT REQUESTED



U.S. DEPARTMENT OF TRANSPORTATION
PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION
OFFICE OF PIPELINE SAFETY
WASHINGTON, D.C. 20590
___________________________________
In the Matter of )
Magellan Pipeline Company, LP, ) CPF No. 4-2012-5010
)
)
)
Respondent. )
___________________________________ )
FINAL ORDER
Between March 22, 2010, and April 22, 2011, pursuant to 49 U.S.C. § 60117, representatives of
the Pipeline and Hazardous Materials Safety Administration (PHMSA), Office of Pipeline Safety
(OPS), conducted an inspection of the pipeline facilities and records of Magellan Pipeline
Company, LP (Magellan or Respondent) in Oklahoma and Texas.
1
As a result of the inspection, the Director, Southwest Region, OPS, issued a Notice of Probable
Violation, Proposed Civil Penalty, and Proposed Compliance Order on March 23, 2012 (Notice).
In accordance with 49 C.F.R. § 190.207, the Notice alleged Magellan committed four violations
of the hazardous liquid pipeline safety regulations, proposed a civil penalty of $149,800, and
proposed corrective action to be taken. The Notice also included seven warning items.
Magellan responded by requesting a hearing on April 27, 2012, and then submitted a
supplemental response dated August 17, 2012 (Supp. Response). In accordance with 49 C.F.R.
§ 190.211, a hearing was held on August 28, 2012, in Houston, Texas, before the Presiding
Official from the Office of Chief Counsel, PHMSA. After the hearing, Magellan submitted a
post-hearing brief dated October 29, 2012 (Brief).
FINDINGS OF VIOLATION
The Notice alleged that Respondent committed four violations of the pipeline safety standards in
49 C.F.R. Part 195, as follows:
Item 1: The Notice alleged that Respondent violated 49 C.F.R. § 195.575(a), which states:
1 Magellan is a subsidiary of Magellan Midstream Partners, LP, and operates approximately 10,000 miles of
pipeline primarily transporting refined petroleum products in Kansas, Texas, Oklahoma, and other west-central
states, as reported for the 2013 calendar year pursuant to § 195.49.



2
§ 195.575 Which facilities must I electrically isolate and what
inspections, tests, and safeguards are required?
(a) You must electrically isolate each buried or submerged pipeline
from other metallic structures, unless you electrically interconnect and
cathodically protect the pipeline and the other structures as a single unit.
The Notice alleged that Respondent violated § 195.575(a) by failing to electrically isolate buried
pipelines from metallic casings. Specifically, the Notice alleged that Respondent failed to
remedy “shorted casings” at various units over a number of years, including units at Longhorn,
Duncan to Ft. Smith, Cimarron Pipeline, Orion West, Oklahoma City, and Tulsa. In addition, the
Notice alleged that Respondent did not follow its written procedures to address metallically
shorted casings, and did not have procedures to address electrolytically shorted casings.
In its written submissions and at the hearing, Magellan responded that the alleged violation
should be withdrawn because § 195.575(a) does not require operators to remedy or “clear”
shorted casings. Respondent also argued that the evidence does not support the allegation that
Magellan failed to follow its procedures, or that there is even a requirement to have procedures
for clearing shorted casings.
PHMSA first considers Respondent’s argument that § 195.575(a) does not require operators to
electrically isolate their pipelines from metallic casings. If the standard does require electrical
isolation from casings, as alleged in the Notice, then PHMSA must determine whether
Respondent complied with that standard.
A. Safety Standards
In matters of regulatory application, PHMSA begins by examining the plain language of the rule.
The text of a regulation is controlling, but the Agency may consider other administrative material
to ensure consistent application of its rules. Administrative material may include prior
enforcement cases, guidance documents, regulatory history, and other material, if relevant.
(1) Regulatory language
Section 195.575(a) requires operators with cathodic protection systems to electrically isolate
each buried pipeline from other metallic structures, unless the operator interconnects and
cathodically protects the pipeline and other structure as a single unit.
Cathodic protection systems are used by pipeline operators to protect steel pipelines from
external corrosion.2 A cathodic protection system with an impressed current prevents external
corrosion by applying a direct electric current to the metal of the pipeline in an amount sufficient
to prevent metal loss to the surrounding environment.3 Operators must maintain a minimum
2 § 195.563.
3 Kinder Morgan Energy Partners, L.P., CPF 4-2006-5023, Item 4, 2010 WL 6531634 (Aug. 31, 2010). Final
orders can be viewed on PHMSA’s website at http://www.phmsa.dot.gov/pipeline/enforcement (follow link for
enforcement since 2002 and then for final orders issued by year).



3
level of cathodic protection to protect their pipelines.
4 Any deficiency identified in the corrosion
control must be corrected.5 Deficiencies in corrosion control may arise when cathodically
protected pipelines are adjacent to other metallic structures. The deficiency results when current
from the cathodic protection system gets diverted from the pipeline to the foreign structure.
A pipeline casing is typically a larger diameter steel pipe that surrounds the pipeline transporting
hazardous liquid. A casing can be used to protect a pipeline from stresses imposed on the pipe,
such as when the line is buried beneath a highway or railroad. The inside of the casing is
generally lined with spacing material so the pipeline does not touch the casing, and the ends of
the casing are sealed to prevent water from entering. A steel casing that surrounds a pipeline
with cathodic protection may become “shorted,” which means the casing is no longer electrically
isolated from the pipeline and current is leaving the pipe for the casing.6 There are generally two
types of shorted casings. A metallically shorted casing is caused by physical contact between the
casing and the carrier pipe, which may be caused by movement of the pipe inside the casing or
failure of spacing material. An electrolytically shorted casing is caused by ionic contact between
the casing and carrier pipe via some electrolyte, such as water that has entered the casing.
By definition, a steel casing is a metallic structure. Section 195.575(a) requires operators to
ensure their buried pipelines are electrically isolated from “other metallic structures.” The
regulation does not explicitly exclude casings or any other type of metallic structure from this
requirement.
Accordingly, PHMSA finds that a plain reading of the regulation requires operators to
electrically isolate buried pipelines from other metallic structures, including metallic casings,
unless the pipeline and casing are electrically interconnected and cathodically protected as a
single unit. PHMSA also reviews the applicable administrative material, including material cited
by Respondent, to ensure this plain reading is consistent with other applications of the rule.
(2) Enforcement history
In prior enforcement cases that involved shorted casings under § 195.575, PHMSA determined
that shorted casings are not in compliance with the regulation. In July 2012, PHMSA issued a
final order finding a violation of § 195.575 where cathodic protection tests demonstrated the
operator had a metallic short.7 In that case, PHMSA found the shorted casing proved the
operator had failed to electrically isolate its pipeline, among other violations of § 195.575.
Likewise, in May 2005, PHMSA issued a final order finding a violation of § 195.575(a) based on
evidence from cathodic protection tests demonstrating a shorted casing was present.8 Both the
4 § 195.571.
5 § 195.573(e). See also § 195.401(b) (requiring operators to correct any discovered condition that could adversely
affect the safe operation of a pipeline system).
6 Alyeska Pipeline Serv. Co., CPF 5-2005-5023, Items 10(a) and 10(b), 2009 WL 7810542 (July 28, 2009)
(“Electrically shorted casings may interfere with cathodic protection and result in inadequate protection.”).
7 Buckeye Partners, L.P., CPF 1-2011-5013, Item 2, 2012 WL 4025918 (Jul. 27, 2012).
8 Alyeska Pipeline Serv. Co., CPF 5-2003-5002, Item 5(b), 2005 WL 5010121 (May 19, 2005).



4
casing vent and settlement rod readings indicated a pipe-to-soil potential of -1.25 volts,
suggesting the casing or casing test lead was in electrical contact with the carrier pipe. PHMSA
determined the operator had violated § 195.575(a) by failing to electrically isolate the buried
pipeline from other metallic structures.
Magellan cited an enforcement case that it believed supported the contrary view that § 195.575
does not require operators to remedy shorted casings.9 In the case cited by Magellan, PHMSA
issued a warning to an operator for failing to inspect shorted casing vents every six months as
required by the company’s written procedures. In that case, PHMSA warned that a failure to
follow written procedures was a probable violation of § 195.402(a). Magellan argued this
demonstrates PHMSA has allowed an alternative to clearing shorted casings.
PHMSA finds the case cited by Respondent has limited applicability because the case concerned
compliance with a different regulation than is at issue in the present matter. The issue in that
case was whether the operator followed its own written procedures as required by § 195.402(a).
The case did not address compliance with § 195.575; nor did it find any conduct to be
permissible or prohibited under § 195.575.
In prior cases that explicitly addressed shorted casings under § 195.575, PHMSA determined that
shorted casings do not comply with the regulation. Accordingly, having reviewed prior
applications of § 195.575, PHMSA finds a plain reading of the regulation is consistent with the
prior enforcement history.
(3) Administrative guidance
Magellan argued further that administrative “guidance developed at the time this regulation
became effective and in effect during the inspections in this case” demonstrates that § 195.575
does not require operators to remedy shorted casings.10 Respondent contended that under that
guidance, PHMSA considers pipelines to be protected if an electrolytic short is present.
Respondent also contended that the guidance established various methods to comply with the
regulation besides merely clearing the short.
PHMSA has developed inspection and enforcement guidance for § 195.575 that discusses,
among other things, the cathodic protection of pipelines inside metallic casings.
11 It is not clear
if Respondent was referring to this guidance or some other document, because Respondent did
not cite the guidance by name, publication date, or location where it could be accessed, and did
not submit a copy as evidence.
12
9 Supp. Response at 14, citing Texas Eastern Products Pipeline Co., CPF 4-2009-5010, Item 2, 2010 WL 5761110
(Dec. 30, 2010).
10 Supp. Response at 10.
11 Part 195 Corrosion Enforcement Guidance. PHMSA staff manuals and instructions are available on its website
at http://www.phmsa.dot.gov/foia/e-reading-room.
12 See, e.g., Supp. Response at 10.



5
The inspection and enforcement guidance issued by PHMSA for § 195.575 notes that casings are
electrically isolated because otherwise they can drain current away from the carrier pipe. The
guidance also states that once a shorted casing is identified, “the operator should determine a
course of action to correct or negate the adverse effects . . . within six months.” It also states that
shorts “should be removed since they could reduce the effectiveness of [cathodic protection] to
not only the carrier pipe in the casing but to the line pipe on either side of the casing.”13
Although this guidance is informational and may not constitute the basis for a violation by itself,
the guidance is consistent with the conclusion that § 195.575(a) requires operators to correct
shorted casings or negate the adverse effects by cathodically protecting the pipeline and structure
as a single unit. In fact, the guidance states that a violation of § 195.575(a) likely occurs if an
operator fails to timely initiate corrective action upon discovery of a shorted casing.14
Having reviewed the relevant administrative guidance material, PHMSA finds it is consistent
with the reading of § 195.575(a).15
(4) Regulatory history
Magellan cited the regulatory history of § 195.575 in support of its position that shorted casings
are not required to be remediated. Respondent argued that rulemaking documents show PHMSA
intentionally omitted any “measures to remedy shorted casings.”16
In December 2000, PHMSA issued a notice of proposed rulemaking to revise the corrosion
control standards for hazardous liquid pipelines. In the notice, PHMSA explained that the
proposed standards were “identical to present corrosion control requirements in Part 195 [for
hazardous liquid pipelines] and standards that are substantially like present requirements in Part
192 [for gas pipelines].”17
The version of § 195.575(a) proposed by PHMSA was based on a comparable provision in
§ 192.467(a), which requires gas pipeline operators to electrically isolate their pipelines from
other metallic structures.18 Section 192.467(c) of the gas regulations, which PHMSA did not
propose to include in § 195.575, requires that “each pipeline be electrically isolated from
metallic casings.” PHMSA stated that it was not including a provision like § 192.467(c) in the
proposal because the safety need to clear shorted casings was not apparent. Magellan argued “it
13 Corrosion Enforcement Guidance at 52.
14 Corrosion Enforcement Guidance at 53.
15 OPS also included as evidence another guidance document, Guidelines for Integrity Assessment of Cased Pipe for
Gas Transmission Pipelines in HCAs. Violation Report, Exhibit 1-15, available at http://primis.phmsa.dot.gov/
gasimp/techreports.htm. This guidance concerns different requirements for gas pipelines, but does refer to shorted
casings as “immediate” and “scheduled” priorities.
16 Supp. Response at 12, quoting Controlling Corrosion on Hazardous Liquid and Carbon Dioxide Pipelines, 65
Fed. Reg. 76968, 76977 (proposed Dec. 8, 2000). Reference to “PHMSA” includes predecessor agencies.
17 Controlling Corrosion, 65 Fed. Reg. at 76975.
18 Controlling Corrosion, 65 Fed. Reg. at 76977.



6
is reasonable to infer that the absence of a similar provision in § 195.575 means that there is not
a regulatory requirement to isolate casing[s] under § 195.575.”19
PHMSA has considered the preamble to the notice of proposed rulemaking and agrees the
proposed rule did not indicate an intent to include a provision identical to § 192.467(c). The
final rule, however, adopted regulatory language for hazardous liquid pipelines that covers all
metallic structures without exception. The final rule did not differentiate between casings and
any other type of metallic structure that must be electrically isolated from pipelines.20 In the
event of any perceived inconsistency between the text of the final rule and a statement in the
preamble of the proposed rule, the text of the final rule must control. Moreover, after adoption
of the final rule, PHMSA has issued at least two enforcement cases that concluded § 195.575(a)
requires operators to electrically isolate hazardous liquid pipelines from metallic casings.
Therefore, PHMSA rejects Respondent’s argument that the regulatory history requires a different
application of the regulation.
(5) Other research materials
Finally, the Notice alleged that “[r]esearch on corrosion of cased pipes supports the need to
achieve electrical isolation between the carrier pipe and casing.”21 As support for this assertion,
OPS produced two research documents prepared by third-parties.
Magellan responded that it was not taking a position on the research, but noted that none of the
reference materials suggested operators must take specific actions to address shorted casings.
22
The first report, Statistical Analysis of External Corrosion Anomaly Data of Cased Pipe
Segments, studied the significance of corrosion damage on cased pipelines.23 One of the
conclusions after evaluating thousands of casings was that “shorted casings are significantly
more susceptible to corrosion than non-shorted casings.”24 Particularly with metallically shorted
casings, the study noted that “a metallic short does increase the chances of external pipe
corrosion and thus, shorted casings should be considered to receive prioritization for integrity
assessment.”25
19 Supp. Response at 12.
20 Controlling Corrosion on Hazardous Liquid and Carbon Dioxide Pipelines, 66 FR 66994, 67000 (Dec. 27, 2001).
21 Notice at 3.
22 Supp. Response at 13-14.
23 Violation Report, Exhibit 1-14. The report was prepared for INGAA Foundation, Inc. by Southwest Research
Institute (Dec. 2007).
24 Statistical Analysis at 33.
25 Statistical Analysis at 16.



7
The second document, Research Efforts for Addressing Cased Pipeline Integrity Management,
echoed the findings of the Statistical Analysis study.26 It also referred to metallic shorts as
“severe” and electrolytic shorts as “moderate” issues requiring action.27
While these reference materials do not control the application of § 195.575, they are informative
about the risks to pipeline safety posed by shorted casings and the need to address them to
prevent pipeline failures caused by corrosion.
In conclusion, on the issue of whether shorted casings must be addressed under § 195.575(a),
PHMSA finds the plain reading of the regulation requires operators to electrically isolate each
buried pipeline from other metallic structures, including metallic casings, unless the pipeline and
casing are electrically interconnected and cathodically protected as a single unit. The relevant
enforcement history and administrative guidance material that have been issued since the final
regulation was adopted are consistent with this reading.
B. Analysis and Findings
The Notice alleged that Respondent violated § 195.575(a) by failing to electrically isolate buried
pipelines from metallic casings, and they were not electrically interconnected and cathodically
protected as a single unit.
It was not disputed at the hearing or in the written submissions that Respondent’s pipeline
system had multiple metallically and electrolytically shorted casings over a number of years.28
By definition, shorted casings are not electrically isolated from the pipeline because the short
involves current being diverted or shielded from the pipeline. Therefore, the pipelines in
question were not electrically isolated.
As to whether the pipelines and casings were electrically interconnected and cathodically
protected as a single unit, the Notice alleged that none of the casings were intentionally bonded
to a carrier pipe or connected to the cathodic protection system in a manner that cathodically
protected the pipe and casing as a single unit. The Notice further alleged Respondent never
intended to protect the pipes and casings together as a unit.
In its written submissions and at the hearing, Respondent argued that an electrolytically shorted
casing is essentially electrically interconnected and cathodically protected.29 Respondent
explained that Magellan does not intentionally short casings, but an electrolytically shorted
casing can be considered the same as being electrically interconnected.30 (Respondent did not
26 Violation Report, Exhibit 1-17. The document was prepared by Pipeline Research Council International, Inc. for
a PHMSA workshop (Jul. 14, 2008).
27 Research Efforts at 7.
28 See Violation Report, Exhibits 1-4 through 1-13 (containing annual cathodic protection survey data for
Respondent’s pipeline facilities primarily for years 2005 through 2009).
29 Supp. Response at 10.
30 Respondent did not contend that it intentionally bonded pipe and casings as a single unit.



8
contend that a metallically shorted casing was electrically interconnected and cathodically
protected.)
At the hearing, OPS argued that allowing a previously isolated casing to lapse into a shorted
condition is not an electrical interconnection under the regulation. OPS explained that
intentionally protecting the structures as a single unit would be accomplished using a wire for the
electrical connection. OPS agreed with Respondent that if a short is caused by water entering the
annulus of the casing, current will travel through the electrolyte. But if the electrolyte does not
surround the entire pipe, some areas of the pipe may not get any protection. Also, OPS stated the
presence of water constitutes a more corrosive environment, resulting in a higher risk of
corrosion especially when there is reduced protection from the short.
Having considered the information presented by both parties, PHMSA concludes that a shorted
casing is not equivalent to a pipeline and casing being electrically interconnected and
cathodically protected as a single unit under § 195.575(a). An electrolytically shorted casing
caused by the presence of water in the annulus may result in limited areas of electrical
connection, which is different than a system purposefully designed and controlled to ensure the
pipe receives the intended level of protection over its entire surface. Therefore, PHMSA rejects
Respondent’s argument that an electrolytically shorted casing complies with § 195.575(a).
Respondent’s annual cathodic protection survey records demonstrate the shorted casings were
not electrically isolated. The evidence also shows Respondent did not electrically interconnect
and cathodically protect them as a single unit. Accordingly, PHMSA finds Respondent violated
§ 195.575(a) by failing to electrically isolate each buried pipeline from other metallic
31
structures.
Item 2: The Notice alleged that Respondent violated 49 C.F.R. § 195.410, which states in part:
§ 195.410 Line markers.
(a) Except as provided in paragraph (b) of this section, each operator
shall place and maintain line markers over each buried pipeline in
accordance with the following:
(1) Markers must be located at each public road crossing, at each
railroad crossing, and in sufficient number along the remainder of each
buried line so that its location is accurately known.
The Notice alleged that Respondent violated § 195.410 by failing to place line markers over each
buried pipeline at public road crossings, railroad crossings, and in sufficient number along the
remainder of the pipeline so that its location is accurately known. The Notice also alleged that
Respondent did not follow its written procedures to effectively delineate the pipeline corridor.
The Notice listed 45 locations, including road and railroad crossings and other areas where there
were allegedly inadequate pipeline markers to ascertain the location of the pipeline. OPS alleged
that at each of those locations, inspectors walked in various directions at the pipeline right-of-
31 The Notice also alleged that Respondent did not follow its procedures. It is not necessary to reach a conclusion
on this issue because Respondent’s cathodic protection records prove a violation of § 195.575(a).



9
way but could not identify the path of the pipeline through observation of pipeline markers even
when turning to look 360 degrees. OPS included photographs of the rights-of-way taken during
the inspection.
In its written submissions and at the hearing, Respondent argued that § 195.410 does not require
pipeline markers to be placed in sufficient number so they can be viewed by looking 360
degrees. Respondent argued that such a “360-degree test” is not mandated by the regulation and
is also indistinguishable from the “line of sight test” rejected by PHMSA in prior enforcement
cases. Respondent also argued that evidence in this case was not presented to Magellan in a
manner that allowed for meaningful rebuttal.
A. Safety Standards
Section 195.410 requires operators to have above-ground line markers in the area of their
pipelines. The markers must include the words “Warning,” “Caution,” or “Danger” followed by
“Petroleum (or the name of the hazardous liquid transported) Pipeline,” the name of the operator,
and a telephone number where the operator can be reached at all times. With some exceptions,
line markers must be placed and maintained at each public road crossing, at each railroad
crossing, and “in sufficient number along the remainder of each buried line so that its location is
accurately known.”
This regulation contains both prescriptive and performance-based requirements. The
prescriptive requirements tell operators exactly where certain line markers must be placed: at
each public road crossing and at each railroad crossing. The performance-based requirement
tells operators that markers must also be placed in “sufficient” number along the remainder of
each buried line so that its location is “accurately known.”32 The regulation does not establish a
minimum number of markers or maximum distance between markers along the pipeline. Rather
than establish a uniform distance for markers, the rule provides flexibility for operators to mark
their pipelines in a manner appropriate for their system as long as the location of the pipeline is
“accurately known” from the markers.
In previous enforcement cases involving § 195.410, PHMSA took a cautious approach to
gauging compliance with the performance-based requirement. In 2008, PHMSA began
reexamining the “line-of-sight” test used by some inspectors to check if markers were sufficient
in number. The line-of-sight test had been used primarily at cultivated agricultural fields and
valve sites. An inspector would stand at a valve site or at one end of a cultivated field and
observe whether the operator’s next line marker could be seen when looking in both directions.
Between 2008 and 2011, PHMSA withdrew a number of alleged violations of § 195.410 where
line-of-sight was the basis for the alleged violation.33
32 See, e.g., Tennessee Gas Pipeline Co., CPF 4-2012-1020, Item 1, 2013 WL 8284480 (Dec. 26, 2013) (discussing
performance-based regulations in the context of a requirement to have “sufficient” test stations to determine the
adequacy of cathodic protection).
33 See, e.g., Citgo Pipeline Co., CPF 4-2007-5010, Item 3, 2011 WL 2040231 (Apr. 14, 2011); Kinder Morgan CO2
Co., CPF 4-2006-5003, Item 1, 2010 WL 6539184 (Oct. 12, 2010); Kinder Morgan Energy Partners, L.P., CPF 4-
2006-5023, Item 2, 2010 WL 6531634 (Aug. 31, 2010); BP Pipelines (North America), Inc., CPF 4-2007-5003, Item
1, 2010 WL 6518288 (Jul. 19, 2010); Enterprise Products Operating, LLC, CPF 4-2007-5015, Item 2, 2009 WL



10
Magellan argued that PHMSA has explicitly rejected the line-of-sight test and therefore any
“360-degree test” must also be rejected as they are indistinguishable.34
PHMSA disagrees that line-of-sight was explicitly rejected. PHMSA did withdraw a number of
alleged violations that were based on line-of-sight, but PHMSA made clear the withdrawals were
due to a reexamination of the test and that “no decision” had been made “whether or how [line-
of-sight] should be applied.”35 PHMSA also clarified that the “withdrawal neither constitutes an
interpretation of § 195.410(a)(1) nor prejudices future potential enforcement action.”36 During
the same time period PHMSA continued to find violations of § 195.410 in other cases that did
not explicitly implicate line-of-sight.
37 The manner in which line-of-sight was addressed in prior
enforcement actions does not preclude enforcement of § 195.410 in this case, regardless of the
manner in which OPS inspectors observed Magellan’s pipeline.
Respondent also argued that § 195.410 does not require pipeline markers to be placed in
sufficient number so that they can be viewed by looking 360 degrees and that a “360-degree test”
is not mandated by the regulation.
At the hearing, OPS contended that its inspectors did not employ a “360-degree test,” but rather
used the terminology “even when turning 360 degrees” in the Notice to describe how the
inspectors examined the right-of-way. In other words, the inspectors walked in different
directions but did not see markers to decipher the location of the pipeline when looking in all
directions.
Having considered the positions of the parties, PHMSA concludes that the inspectors
appropriately used normal senses of visual perception to observe whether markers were placed in
the area of Respondent’s pipeline. Since § 195.410 requires markers to be placed “in sufficient
number along the [pipeline] so that its location is accurately known,” inspectors must be able to
use normal methods of observation to see if markers are present and to discern the location of the
pipeline. In this case, inspectors were walking around and looking in all directions to see where
pipeline markers were located. There is nothing inappropriate about this method of evaluating
compliance with § 195.410.
5538652 (Dec. 2, 2009); and NuStar Logistics, L.P., CPF 4-2005-5048, Item 2, 2009 WL 1211363 (Mar. 11, 2009).
PHMSA also held a public workshop on February 20-21, 2008, in Houston, Texas, to discuss, among other issues,
placement of line markers. See also, Pipeline Safety: Workshop on Public Awareness Programs for Pipeline
Operators and Location of Line Markers, 73 Fed. Reg 223 (Jan. 2, 2008).
34 Brief at 13.
35 E.g., Enterprise Products, CPF 4-2007-5015, Item 2.
36 E.g., Enterprise Products, CPF 4-2007-5015, Item 2.
37 See, e.g., Buckeye Partners, LP, CPF 1-2013-5003, Item 1, 2013 WL 4406977 (Jun. 10, 2013); ExxonMobil
Pipeline Co., CPF 5-2011-500, Item 1, 2011 WL 7006608 (Nov. 2, 2011); Marathon Pipe Line LLC, CPF 5-2010-
5013, Item 2, 2011 WL 1303343 (Feb. 18, 2011); Sunoco Pipeline, L.P., CPF 4-2007-5040, Item 4, 2010 WL
5761108 (Dec. 16, 2010); Kinder Morgan Energy Partners, L.P., CPF 4-2006-5023, Item 2, 2010 WL 6531634
(Aug. 31, 2010); and Magellan Pipeline Co., CPF 4-2007-5050, Item 1, 2009 WL 5538658 (Dec. 28, 2009).



11
B. Analysis and Findings
PHMSA evaluates whether Respondent complied with § 195.410 by reviewing the evidence to
determine if Respondent had line markers over each buried pipeline at public road and railroad
crossings and in sufficient number along the remainder of each buried line so that its location is
accurately known.
As with any performance standard, it is inherent that operators evaluate their own conduct under
the rule to determine whether they have satisfied the minimum standard.38 It is also inherent that
operators be able to demonstrate their conduct complies with the minimum standard. At the
hearing, Respondent argued that it could not demonstrate compliance without knowing what
standard PHMSA uses to evaluate compliance.
PHMSA notes that the text of the regulation provides the minimum standard: operators must
ensure the location of their pipeline can be accurately known from the markers placed along the
line. If the location of the pipeline cannot be accurately known from the markers, the operator is
not likely to be in compliance with the minimum standard.
Evidence in the record demonstrates there were locations on Respondent’s pipeline system that
did not have enough markers to accurately know the location of the pipeline. Approximately 60
photographs from the OPS inspection show areas where there are no visible line markers to
indicate the path of the pipeline. The inspector explained at the hearing that he actively tried to
locate markers by walking around and looking for them, but the location of the pipeline could
not be determined by observing markers in these areas.
Respondent argued that the photographic evidence taken at the time of the inspection was not
presented to Magellan in a manner that allowed for meaningful rebuttal. Specifically,
Respondent contended the photographs were taken in 2010, but were not provided to Magellan
until June 1, 2012, preventing the Company from challenging whether the alleged conditions
actually existed in 2010. In addition, Respondent argued that OPS never articulated the camera
settings used to take the photographs.
At the hearing, the inspector explained that several Magellan personnel accompanied him on the
inspection when the pictures were taken. They also participated in pre-inspection and post-
inspection review meetings during which line marker issues were discussed. Testimony at the
hearing confirmed that the photographs were taken with standard camera settings.
Having reviewed the record, PHMSA finds no basis for Respondent’s contention that it was not
able to provide meaningful rebuttal to the allegations. The Notice identified each of the 45
locations where adequate markers were allegedly not present. Respondent was free to present
evidence at the hearing that those locations had sufficient markers to accurately know the
location of the pipeline.
38 Tennessee Gas Pipeline Co., CPF 4-2012-1020, Item 1.



12
Accordingly, PHMSA finds Respondent violated § 195.410 by failing to place line markers over
each buried pipeline at public road crossings, railroad crossings, and in sufficient number along
the remainder of the pipeline so that its location is accurately known.
39
Item 4: The Notice alleged that Respondent violated 49 C.F.R. § 195.406(a) and (b), which
states in part:
§ 195.406 Maximum operating pressure.
(a) Except for surge pressures and other variations from normal
operations, no operator may operate a pipeline at a pressure that exceeds
any of the following:
(1) The internal design pressure of the pipe determined in accordance
with § 195.106 . . . .
(2) The design pressure of any other component of the pipeline.
(3) Eighty percent of the test pressure for any part of the pipeline
which has been pressure tested under subpart E of this part.
(4) Eighty percent of the factory test pressure . . . for any individually
installed component which is excepted from testing under § 195.305.
(5) For pipelines under §§ 195.302(b)(1) and (b)(2)(i) that have not
been pressure tested under subpart E of this part, 80 percent of the test
pressure or highest operating pressure to which the pipeline was subjected
for 4 or more continuous hours . . . .
(b) No operator may permit the pressure in a pipeline during surges or
other variations from normal operations to exceed 110 percent of the
operating pressure limit established under paragraph (a) of this section.
Each operator must provide adequate controls and protective equipment to
control the pressure within this limit.
The Notice alleged that Respondent violated § 195.406(a) by operating pipelines at a pressure
exceeding their maximum operating pressure (MOP). Specifically, the Notice alleged that
company records from 2007 through 2011 show Magellan allowed its pipeline system to operate
above MOP for durations in excess of ten minutes on at least 17 occasions. In addition, the
Notice alleged that Respondent violated § 195.406(b) at the Ponca City facility where pressure
exceeded 110% of MOP due to an incorrect setting on a pressure relief valve.
With regard to the alleged violation of § 195.406(b), Respondent did not contest that pressure
exceeded 110% of MOP on that occasion. Respondent explained the event was a result of
thermal pressure increasing on a shutdown pipeline. Pressure reached 135% of MOP because
the relief pressure was incorrectly set at a value much higher than it should have been.
Respondent contested the alleged violation of § 195.406(a), and argued that exceeding MOP was
permitted under the regulation as “variations from normal operations.” Respondent explained
that it does not allow pressure above MOP for any amount of time; rather, it takes immediate
39 The Notice also alleged Respondent did not follow procedures to delineate the pipeline corridor. It is not
necessary to reach a conclusion on this issue because the photographs and testimony prove a violation of § 195.410.



13
action to reduce pressure. Respondent stated a pressure excursion above MOP triggers an alarm
and requires the controller to take immediate action to reduce pressure, which may include
shutting down units. If the corrective measures do not result in pressure being brought under
MOP after ten minutes, an additional alarm is triggered and Respondent logs the event as an
abnormal operating condition for further analysis to prevent reoccurrence. The second alarm
does not change the controller’s actions that are already underway to reduce pressure. The ten
minute interval, Respondent explained, is based on how long it typically takes pressure to settle
after start up.
With regard to the 17 specific events in question, Respondent contended that thirteen were
attributed to thermal pressure increase in idle lines, two were related to the malfunction of a
component that failed to control pressure as designed, one event was attributed to personnel error
where a block valve was misaligned, and the final event occurred during startup. Respondent
argued that none of the events were caused by intentionally exceeding MOP.
At the hearing, OPS contended that the durations of the excursions were not the type of
temporary pressure spikes permitted by the regulation for surges and other variations from
normal operations. OPS also contended that the multiple events of pressure exceeding MOP for
more than 10 minutes demonstrate Respondent’s system is not designed with adequate pressure
control and relief to ensure pressure can be kept within MOP.
A. Safety Standards
The pipeline safety regulations at 49 C.F.R. § 195.406 establish the maximum safe operating
pressure for pipelines. Pursuant to § 195.406(a), an operator is prohibited from operating any
pipeline at a pressure that exceeds the established MOP of the line, with limited exceptions.
The exceptions to the maximum operating limit in § 195.406(a) are for “surge pressures and
other variations from normal operations.” A “surge pressure” is defined in § 195.2 as the
pressure produced by a change in velocity of the moving stream that results from shutting down
a pump station or pumping unit, closure of a valve, or any other blockage of the moving stream.
Due to the low compressibility of hazardous liquid and near instantaneous adjustment in pressure
for the transient condition, surges should be brief in duration depending on the length of the
affected segment. For example, PHMSA has found that a pressure excursion lasting less than
one minute that occurred during a shutdown was a surge pressure under § 195.406.40
“[O]ther variations from normal operations” is not separately defined in the regulation. The
regulatory history of the rule and subsequent publications do not suggest any distinguishing
characteristics between surge pressures and other variations from normal operations, as those
terms are used in § 195.406.41 Whereas a surge may be caused by a shutdown or blockage of the
40 BP Pipelines (North America), Inc., CPF 3-2009-5002, Item 1, 2012 WL 1901291 (Apr. 3, 2012).
41 See, e.g., Transportation of Hazardous Materials by Pipeline, 33 Fed. Reg. 10213 (proposed Jul. 17, 1968); and
Testing Requirements and Operating Pressure Limitations, 35 Fed. Reg. 17183 (Nov. 7, 1970). Both rulemaking
documents primarily refer to surges, but occasionally refer to “surges or other pressure variations from normal
operation” without distinguishing the terminology.



14
moving stream, a variation from normal operation could have a different cause. Regardless of
the cause of the variation, the excursion is not permitted to exceed MOP for an indefinite amount
of time. In order to comply with the operating pressure restriction in § 195.406(a), an operator’s
pipeline system must be capable of achieving timely pressure reduction in the event of a surge or
other type of variation from normal operation.
B. Analysis and Findings
In the present case, Respondent’s system experienced multiple pressure excursions above MOP
for periods longer than ten minutes. Respondent took action to reduce pressure at the first sign
of exceeding MOP, but Respondent was not able to bring pressure back to within MOP in a
timely manner. Pressure excursions lasting more than ten minutes on multiple occasions over
the course of several years, even if unintentional, are not merely “variations from normal
operations” permitted under the regulation. Such long-lasting and regular excursions suggest
that relief equipment, operating procedures, or both were not adequate to ensure operations in
accordance with § 195.406.
Accordingly, PHMSA finds Respondent violated § 195.406(a) by operating its pipeline above
MOP for durations exceeding 10 minutes on 17 occasions. PHMSA also finds Respondent
violated § 195.406(b) by failing to prevent pressure from exceeding 110% of MOP.
Item 5: The Notice alleged that Respondent violated 49 C.F.R. § 195.402(a), which states:
§ 195.402 Procedural manual for operations, maintenance, and
emergencies.
(a) General. Each operator shall prepare and follow for each pipeline
system a manual of written procedures for conducting normal operations
and maintenance activities and handling abnormal operations and
emergencies . . . .
The Notice alleged that Respondent violated § 195.402(a) by failing to follow its written
procedures that required Respondent to identify activity along the right-of-way that could pose a
hazard or compromise the safety, integrity or operation of the pipeline and right-of-way. The
Notice alleged there were encroachments in Respondent’s right-of-way, such as large quantities
of junk, abandoned cars, and oil storage tanks.
In its written submissions and at the hearing, Respondent did not contest the alleged violation,
but did request modification of the proposed compliance order, which is discussed below.
Having considered the evidence, PHMSA finds Respondent violated § 195.402(a) by failing to
follow its written procedures for inspecting pipeline rights-of-way.
These findings of violation will be considered prior offenses in any subsequent enforcement
action taken against Respondent.



15
ASSESSMENT OF PENALTY
Under 49 U.S.C. § 60122 (2011), Respondent is subject to an administrative civil penalty not to
exceed $100,000 per violation for each day of the violation, up to a maximum of $1,000,000 for
any related series of violations.42 The Notice proposed a total civil penalty of $149,800 for the
violations in Items 2, 4, and 5. The Notice did not proposed a civil penalty for Item 1.
In determining the amount of a civil penalty under 49 U.S.C. § 60122 and 49 C.F.R. § 190.225,
PHMSA must consider the following criteria: the nature, circumstances and gravity of the
violation, including adverse impact on the environment; the degree of Respondent’s culpability;
the history of Respondent’s prior offenses; the good faith of Respondent in attempting to comply
with the pipeline safety regulations; and the effect on Respondent’s ability to continue in
business. In addition, PHMSA may consider the economic benefit gained from violation without
any reduction because of subsequent damages, and such other matters as justice may require.
Item 2: The Notice proposed a civil penalty of $61,500 for Respondent’s violation of 49 C.F.R.
§ 195.410. Respondent failed to place line markers in sufficient number over each buried
pipeline so that its location is accurately known.
With regard to the nature, circumstances, and gravity of the violation, PHMSA finds that
pipeline integrity or safe operation was potentially compromised at road or railroad crossings and
other areas where third party damage is a risk of releasing hazardous liquid affecting the public,
property, and environment.
Respondent was cognizant of the regulatory requirement and took some steps to address the issue
by having line markings in some locations, but Respondent did not achieve compliance on every
pipeline segment.
PHMSA finds the proposed penalty is supported by the record and there is not sufficient reason
to adjust the penalty for culpability, good faith, effect on ability to continue in business, or
history of prior offenses. Accordingly, having reviewed the record and considered the
assessment criteria, PHMSA assesses Respondent a civil penalty of $61,500 for the violation of
§ 195.410.
Item 4: The Notice proposed a civil penalty of $55,400 for Respondent’s violation of § 195.406.
Respondent violated § 195.406(a) by failing to reduce pressure excursions to within MOP for
durations exceeding 10 minutes. In addition, Respondent violated § 195.406(b) by failing to
prevent pressure from exceeding 110% of MOP.
With regard to the nature, circumstances, and gravity of the violations, PHMSA finds pipeline
integrity or safe operation was potentially compromised resulting in an elevated risk of an
overpressure condition and pipeline release affecting the safety of the public, property, and
environment.
42 Subsequent to the actions that gave rise to this case, the Pipeline Safety, Regulatory Certainty, and Job Creation
Act of 2011, Pub. L. No. 112-90, § 2(a), 125 Stat. 1905 (Jan. 3, 2012), increased the maximum civil penalty for a
pipeline safety violation to $200,000 per violation for each day up to a maximum of $2,000,000 for a related series.



16
Respondent was cognizant of the regulatory requirement and took some steps to address the
problem by discovering issues with its overpressure monitoring system, but Respondent did not
achieve compliance by preventing reoccurrence.
PHMSA finds the proposed penalty is supported by the record and there is not sufficient reason
to adjust the penalty for culpability, good faith, effect on ability to continue in business, or
history of prior offenses. Accordingly, having reviewed the record and considered the
assessment criteria, PHMSA assesses Respondent a civil penalty of $55,400 for the violation of
§ 195.406.
Item 5: The Notice proposed a civil penalty of $32,900 for Respondent’s violation of
§ 195.402(a). Magellan failed to follow its written procedures for identifying activity along the
pipeline right-of-way that could pose a hazard or compromise the safety, integrity or operation of
the pipeline or right-of-way. Respondent did not contest the proposed penalty for this violation.
Accordingly, having reviewed the record and considered the assessment criteria, PHMSA
assesses Respondent a civil penalty of $32,900 for violation of § 195.402(a).
In summary, having reviewed the record and considered the assessment criteria for each of the
Items cited above, PHMSA assesses Respondent a total civil penalty of $149,800.
Payment of the civil penalty must be made within 20 days of service. Federal regulations (49
C.F.R. § 89.21(b)(3)) require such payment to be made by wire transfer through the Federal
Reserve Communications System (Fedwire), to the account of the U.S. Treasury. Detailed
instructions are contained in the enclosure. Questions concerning wire transfers should be
directed to: Financial Operations Division (AMK-325), Federal Aviation Administration, Mike
Monroney Aeronautical Center, P.O. Box 269039, Oklahoma City, Oklahoma 73125-4915. The
Financial Operations Division telephone number is (405) 954-8845.
Failure to pay the $149,800 civil penalty will result in accrual of interest at the current annual
rate in accordance with 31 U.S.C. § 3717, 31 C.F.R. § 901.9 and 49 C.F.R. § 89.23. Pursuant to
those same authorities, a late penalty charge of six percent (6%) per annum will be charged if
payment is not made within 110 days of service. Furthermore, failure to pay the civil penalty
may result in referral of the matter to the Attorney General for appropriate action in a district
court of the United States.
COMPLIANCE ORDER
The Notice proposed a compliance order with respect to each of the violations cited above.
Under 49 U.S.C. § 60118(a), each person who engages in the transportation of hazardous liquids
by pipeline or who owns or operates a pipeline facility is required to comply with the applicable
safety standards established under chapter 601.



17
With regard to the violation of § 195.575 (Item 1), Respondent argued that it would be
inappropriate to include the proposed requirement to clear shorted casings because that is not the
only method to comply with § 195.575.43
PHMSA agrees that the terminology of the compliance order should be changed to recognize the
regulation permits operators to address shorted casings either by electrical isolation or by
electrically interconnecting and cathodically protecting the pipeline and casing a single unit.
With regard to the violation of § 195.402(a) (Item 5), Respondent argued the proposed
compliance order should be revised to reflect Magellan’s written maintenance program, which
requires at a minimum, aerial surveillance once a year and an integrity assessment to identify
areas that may require maintenance.
44 Respondent also argued that it should be allowed to use
other methods of patrolling if a right-of-way cannot be inspected aerially due to obstructions.45
PHMSA concludes that Respondent must achieve compliance with § 195.402(a) by having and
following written procedures that implement the right-of-way inspection and maintenance
requirements.46 Respondent must ensure proper patrolling practices are followed and must
remedy existing encroachments and vegetation that could adversely affect pipeline safety, or that
could impair observation of the right-of-way during inspection. PHMSA does not find the
compliance order warrants modification to the degree suggested by Respondent.
Notwithstanding, PHMSA agrees the compliance order should recognize that Respondent may
use methods of inspection like walking or driving if a right-of-way is not capable of being
aerially inspected.
Pursuant to the authority of 49 U.S.C. § 60118(b) and 49 C.F.R. § 190.217, Respondent is
ordered to take the following actions to ensure compliance with the pipeline safety regulations
applicable to its operations:
1. With respect to the violation of § 195.575 (Item 1), Respondent must perform tests to
determine if casings are metallically or electrolytically shorted. If as a result of those
tests, a casing is determined to be metallically or electrolytically shorted, Respondent
must evaluate inline inspection (ILI) data of that location for indications of corrosion
or metal loss and make any required repairs to the carrier pipe. If ILI data from the
past five years is not available for that location, Respondent must perform studies
using ILI or an alternative technology to determine if there is corrosion or metal loss
requiring repairs. Respondent must also address the shorted casings either by
electrically isolating the buried or submerged pipeline from other metallic structures,
or by electrically interconnecting and cathodically protecting the pipeline and
structure as a single unit. Respondent must submit a plan to perform the actions
43 Brief at 11.
44 Supp. Response at 2.
45 Brief at 3.
46 See §§ 195.401 and 195.412.



18
2. 3. 4. 5. 6. required in this paragraph within 30 day of receipt along with its written procedures
for addressing both metallically and electrolytically shorted casings.
With respect to the violation of § 195.410 (Item 2), Respondent must install
additional line markers at the identified locations in the Barnsdall, Tulsa, Oklahoma
City, Odessa to El Paso, and Cimarron inspection units so that the location of the
pipeline is accurately known.
With respect to the violation of § 195.406 (Item 4), Respondent must review the
design of its overpressure protection systems and make changes necessary to prevent
instances of exceeding MOP for longer than a surge event. Respondent must also
perform a review of the establish MOP for each pipeline segment, check the set
points of each overpressure device, ensure each overpressure device is correctly
tagged, and check each inspection form to ensure the tag numbers, maximum
pressures, and set points are all correct.
With respect to the violation of § 195.402(a) (Item 5), Respondent must make
appropriate changes to its written operations and maintenance procedures for
inspecting rights-of-way to ensure such procedures are followed. Respondent must
also remedy any encroachments and vegetation that could adversely affect pipeline
safety or that could impair observation of the right-of-way during inspection. The
procedures must include provisions for each method of inspection used, including
walking or driving if Respondent uses those methods to inspect rights-of-way that are
not capable of being aerially inspected.
Submit documentation demonstrating compliance with this Compliance Order within
180 days of receipt of this Order. Documentation must be submitted to the Director,
Southwest Region, Pipeline and Hazardous Materials Safety Administration, 8701
South Gessner, Suite 1110, Houston, TX 77074.
It is requested that Respondent maintain documentation of the safety improvement
costs associated with fulfilling this Compliance Order and submit the total to the
Director. It is requested that these costs be reported in two categories: (1) total cost
associated with preparation/revision of plans, procedures, studies and analyses, and
(2) total cost associated with replacements, additions and other changes to pipeline
infrastructure.
The Director, Southwest Region, OPS may grant an extension of time to comply with any of the
required items upon a written request timely submitted by the Respondent and demonstrating
good cause for an extension.
Failure to comply with this Order may result in the administrative assessment of civil penalties
not to exceed $200,000 for each violation for each day the violation continues or in referral to the
Attorney General for appropriate relief in a district court of the United States.



19
WARNING ITEMS
With respect to Items 3, 6, 7, 8, 9, 10 and 11, the Notice alleged probable violations of Part 195,
but considered them to be warning items.
A warning item issued pursuant to 49 C.F.R. § 190.205 constitutes an allegation that OPS has
identified a potential issue, which if found in a future inspection, may subject the operator to an
enforcement action. Unlike other alleged violations, PHMSA does not make a finding as to
whether an allegation contained in a warning was proven by evidence in the record. An operator
may respond to a warning. In this case, Respondent responded to Items 3, 8, 9 and 10.
The warnings in the Notice were for:
49 C.F.R. § 195.567 (Item 3) – Respondent’s alleged failure to maintain test lead wires
in a condition to enable obtaining electrical measurements and to determine whether
cathodic protection complies with applicable criteria. In its response, Respondent did not
dispute that test leads were damaged or destroyed, but contended that no violation was
proven because Respondent had a reasonable amount of time to correct the conditions
under § 195.401.47
49 C.F.R. § 195.402(a) (Item 6) – Respondent’s alleged failure to follow its written
procedures for marking exposed pipe.
49 C.F.R. § 195.571 (Item 7) – Respondent’s alleged failure to ensure that cathodic
protection on pipelines met applicable criteria.
49 C.F.R. § 195.573(d) (Item 8) – Respondent’s alleged failure to ensure that cathodic
protection on the bottom of breakout tanks met applicable criteria. In its response,
Respondent did not dispute that cathodic protection failed to meet applicable criteria, but
contended that no violation was proven because evidence in the record did not relate to
Respondent’s inspection intervals.48
49 C.F.R. § 195.583(c)49 (Item 9) – Respondent’s alleged failure to provide protection
against atmospheric corrosion at certain locations. Respondent did not dispute that
atmospheric corrosion was observed at 22 locations on its pipeline facility, but contended
that no violation was proven because evidence did not relate to Respondent’s inspection
intervals or show that the corrosion would affect safe operations.50
49 C.F.R. § 195.430 (Item 10) – Respondent’s alleged failure to maintain adequate
firefighting equipment at each pump station and breakout tank area. Respondent did not
47 Supp. Response at 19-22.
48 Supp. Response at 22-23.
49 The Notice erroneously cited this regulation as § 195.573(c).
50 Supp. Response at 23-25.



20
dispute that it only had fire extinguishers at most pump stations and breakout tank areas,
and that it relied on public firefighting agencies and cooperatives. Respondent
contended, however, there is no obligation under the regulation for operators to confirm
whether local firefighting organizations have adequate firefighting equipment.51
49 C.F.R. § 195.432(b) (Item 11) – Respondent’s alleged failure to have an inspection
program and methodology that meets the requirements for inspecting the physical
integrity of in-service breakout tanks according to API Standard 653 (incorporated by
reference, see § 195.3).
Respondent is warned that if a probable violation of these provisions is identified in the future,
Respondent may be subject to additional enforcement.
Under 49 C.F.R. § 190.243, Respondent may submit a petition for reconsideration of this Final
Order to the Associate Administrator for Pipeline Safety, PHMSA, 1200 New Jersey Avenue SE,
East Building, 2nd Floor, Washington, D.C. 20590, no later than 20 days after receipt of the
Final Order by Respondent. Any petition submitted must contain a statement of the issue(s) and
meet all other requirements of 49 C.F.R. § 190.215. The filing of a petition automatically stays
the payment of any civil penalty assessed. All other terms of the order, including the corrective
action, remain in effect unless the Associate Administrator, upon request, grants a stay. The
terms and conditions of this Final Order are effective upon service in accordance with 49 C.F.R.
§ 190.5.
________________________________ __________________
Jeffrey D. Wiese Date Issued
Associate Administrator
for Pipeline Safety
51 Supp. Response at 16-19.

420125010_Closure Letter_03042016_text.pdf

CERTIFIED MAIL - RETURN RECEIPT REQUESTED
March 4, 2016
Mr. Michael Pearson
Senior Vice President, Technical Services
Magellan Pipeline Company, L.P.
P.O. Box 22186
Tulsa, OK 74172
CPF 4-2012-5010
Dear Mr. Pearson:
On various dates in 2010 and 2011, representatives of the Pipeline and Hazardous Materials Safety
Administration (PHMSA), Office of Pipeline Safety (OPS), pursuant to Chapter 601 of 49 United States
Code conducted inspections of the Magellan Pipeline, L.P., (Magellan, the Operator) Duncan to Ft. Smith,
Tulsa, Barnsdall, Oklahoma City, Cimarron & Osage, Orion East, Orion West, Odessa to El Paso,
Longhorn East, and Longhorn West pipeline units, the Tulsa, OK control center and O&M procedures.
As a result of the inspections, on March 23, 2012 a Notice of Probable Violation with Proposed Civil
Penalties and Proposed Compliance Order was issued to Magellan Pipeline, L.P. (Magellan, the Operator)
CPF 4-2012-5010. Magellan responded by letter on April 27, 2012, by requesting a hearing. Magellan also
submitted a supplemental response on August 17, 2012 prior to the hearing. The hearing was held on
August 28, 2012 at the PHMSA Southwest Region offices. Magellan submitted a Post-Hearing Brief dated
October 29, 2012.
On September 2, 2014, PHMSA issued a Final Order that included a civil penalty of $149,800 and a
Compliance Order. Magellan responded to the Final Order with submissions on October 8, 2014 and
March 6, 2015. PHMSA also performed field verifications of the Final Order in March 2015.
This letter is to inform you no further action is necessary and this case is now closed. Thank you for your
cooperation.
Sincerely,
R. M. Seeley
Director, Southwest Region
Pipeline and Hazardous Materials Safety Administration

## Provenance

- Official: Yes
- Source: <https://primis.phmsa.dot.gov/enforcement-data/case/420125010>
- Source ID: `phmsa-enforcement`
- SHA-256: `de81caa4bc444111fad62035546549cff9c56d23e43a4988220bd5d8041fc54b`
- Retrieved: 2026-08-20T04:44:44.458Z
- Exported: 2026-08-23T20:07:39.834Z
- Document slug: `phmsa-enforcement-420125010`

### Source metadata

```json
{
  "cpf": "420125010",
  "operator": "MAGELLAN PIPELINE COMPANY, LP",
  "region": "Southwest",
  "pipelineType": "INTERSTATE LIQUID ONSHORE",
  "caseStatus": "CLOSED",
  "citedSections": [
    "195.402(a)",
    "195.406(a)",
    "195.406(b)",
    "195.410",
    "195.430",
    "195.432",
    "195.567(b)",
    "195.571",
    "195.573(c)",
    "195.573(d)",
    "195.575(a)"
  ],
  "dataAsOf": "08/04/2026 12PM",
  "caseDataAsOf": "2026-08-04",
  "attachmentCount": 7,
  "attachments": [
    {
      "name": "420125010_Closure Letter_03042016.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420125010/420125010_Closure%20Letter_03042016.pdf",
      "bytes": 416991,
      "category": "agency_document"
    },
    {
      "name": "420125010_Closure Letter_03042016_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420125010/420125010_Closure%20Letter_03042016_text.pdf",
      "bytes": 7027,
      "category": "agency_document"
    },
    {
      "name": "420125010_Final Order_09022014.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420125010/420125010_Final%20Order_09022014.pdf",
      "bytes": 1389452,
      "category": "agency_document"
    },
    {
      "name": "420125010_Final Order_09022014_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420125010/420125010_Final%20Order_09022014_text.pdf",
      "bytes": 95034,
      "category": "agency_document"
    },
    {
      "name": "420125010_NOPV PCP PCO_03232012.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420125010/420125010_NOPV%20PCP%20PCO_03232012.pdf",
      "bytes": 1047169,
      "category": "agency_document"
    },
    {
      "name": "420125010_NOPV PCP PCO_03232012_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420125010/420125010_NOPV%20PCP%20PCO_03232012_text.pdf",
      "bytes": 109818,
      "category": "agency_document"
    },
    {
      "name": "420125010_Operator_Response_and_Request_for_Hearing_04272012.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420125010/420125010_Operator_Response_and_Request_for_Hearing_04272012.pdf",
      "bytes": 228707,
      "category": "party_submission"
    }
  ],
  "extractedAgencyDocumentCount": 3,
  "attachmentPolicy": "Official attachment links are retained. Agency-issued documents may also include a verified local PDF and page-level text representation.",
  "jurisdiction": "US",
  "operatorName": "MAGELLAN PIPELINE COMPANY, LP"
}
```
