# TENNESSEE GAS PIPELINE COMPANY — Corrective Action Order

**Citation:** CPF 420151009H  
**Type / status:** enforcement / historical  
**Agency:** Pipeline and Hazardous Materials Safety Administration  
**Effective:** Not stated  
**Published:** 2015-08-06

CLOSED corrective action order.

## Document text

Corrective Action Order involving TENNESSEE GAS PIPELINE COMPANY. The dataset does not identify a cited regulation for this case. The case was opened on 2015-08-06 and is reported as closed as of 2016-08-11. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

420151009H_Closure Letter_08112016.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420151009H/420151009H_Closure%20Letter_08112016.pdf

420151009H_Closure Letter_08112016_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420151009H/420151009H_Closure%20Letter_08112016_text.pdf

420151009H_Corrective Action Order_08062015.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420151009H/420151009H_Corrective%20Action%20Order_08062015.pdf

420151009H_Corrective Action Order_08062015_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420151009H/420151009H_Corrective%20Action%20Order_08062015_text.pdf

420151009H_Corrective Action Order_08062015_text.pdf

August 6, 2015
VIA CERTIFIED MAIL AND FAX TO: (832) 397-4536
Mr. Gary Buchler
Vice President, Operations and Engineering
Tennessee Gas Pipeline Company, LLC
1001 Louisiana Street
Houston, TX, 77002
Re: CPF No. 4-2015-1009H
Dear Mr. Buchler:
Enclosed is a Corrective Action Order issued in the above-referenced case. It requires Tennessee
Gas Pipeline Company, LLC, to take certain corrective actions with respect to the San Salvador
Line 400-1 natural gas pipeline, which failed on August 3, 2015, in Brooks County, Texas.
Service is being made by certified mail and facsimile. Service by electronic transmission is
deemed complete upon transmission and acknowledgement of receipt, or as otherwise provided
under 49 C.F.R. § 190.5. The terms and conditions of this Order are effective upon completion
of service.
Thank you for your cooperation in this matter.
Sincerely,
Jeffrey D. Wiese
Associate Administrator
for Pipeline Safety
Enclosure
cc: Ms. Linda Daugherty, Deputy Associate Administrator for Field Operations, OPS
Mr. R. M. Seeley, Director, Southwest Region, OPS
Mr. Reji George, Director, Compliance Codes and Standards, Natural Gas Pipeline
Company of America, LLC
Mr. Steven J. Kean, President and Chief Operating Officer, Kinder Morgan, Inc.



U.S. DEPARTMENT OF TRANSPORTATION
PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION
OFFICE OF PIPELINE SAFETY
WASHINGTON, D.C. 20590
____________________________________
In the Matter of )
Tennessee Gas Pipeline ) CPF No. 4-2015-1009H
Company, LLC, )
)
)
)
Respondent. )
___________________________________ )
CORRECTIVE ACTION ORDER
Purpose and Background:
This Corrective Action Order (Order) is being issued under the authority of 49 U.S.C. § 60112 to
require Tennessee Gas Pipeline Company, LLC (TGP or Respondent), to take the necessary
corrective actions to protect the public, property, and the environment from potential hazards
associated with the recent failure on Respondent’s San Salvador Line 400-1 natural gas
pipeline.1
A reportable accident occurred on the San Salvador Line 400-1 pipeline in Brooks County,
Texas, on August 3, 2015, resulting in the release of an estimated 11 million cubic feet (mmcf)
of natural gas into the atmosphere. Pursuant to 49 U.S.C. § 60117, the Pipeline and Hazardous
Materials Safety Administration (PHMSA), Office of Pipeline Safety (OPS), initiated an
investigation of the accident. The preliminary findings of the ongoing investigation are as
follows.
Preliminary Findings:
• On August 3, 2015, at approximately 8:30 p.m. Central Standard Time (CST), a failure
occurred on Respondent’s 16-inch diameter Line 400-1 pipeline approximately 1.5 miles
southwest of the town of Falfurrias, Texas. The accident was reported to the National
Response Center (NRC Report # 1124690) on August 3, 2015, at approximately
9:49 p.m. CST.
1 Tennessee Gas Pipeline Company, LLC operates an approximately 11,900-mile pipeline system that transports
natural gas from Louisiana, the Gulf of Mexico and south Texas to the northeastern U.S. and is a subsidiary of
Kinder Morgan, Inc. See http://www kindermorgan.com/pages/business/gas_pipelines/east/TGP/default.aspx (last
accessed August 5, 2015).



CPF No. 4-2015-1009H
Page 2
• The Line 400-1 pipeline extends approximately 98.79 miles from Agua Dulce Station to
Edinburg Station and is part of a system of several parallel pipelines. The segment on
which the failure occurred extends approximately 11.16 miles from VS 403-1 to
VS 404-1. The pipeline crosses public roads and traverses areas near residences.
Portions of the pipeline are located in Class 2 populated areas.
• As a result of the failure, an estimated 11 mmcf of natural gas was released. The blow
out resulted in an approximate 70- by 30-foot crater.
• The failure site is located at Station 517+92.2 and is approximately 350 feet away from a
residence. Local emergency responders evacuated an area within a five-mile radius of
the failure site.
• In response, TGP depressurized the pipeline and isolated the 11.16-mile section by
closing valves VS 403-1 and VS 404-1.
• The pipeline remains shut down. The cause of the failure has not yet been confirmed, but
a longitudinal split in the pipe approximately 55 feet long could be observed. TGP
intends to transport the failed pipe section to a metallurgist for testing and failure
analysis.
• The Line 400-1 pipeline was originally constructed in 1947. It consists of Grade X-42
16-inch diameter electric resistance weld (ERW) seam pipe manufactured by
Youngstown Steel and has a nominal wall thickness of 0.250 inches, with a coal tar
enamel coating and an impressed current cathodic protection system.
• The maximum allowable operating pressure (MAOP) of the pipeline is 903 psig. The
pipeline was hydrostatically tested in 1997. The operating pressure at the time of the
failure was approximately 827 psig.
• PHMSA issued Alert Notice ALN-88-01 in January 1988, advising owners and operators
of natural gas and hazardous liquids pipelines to consider the threat from ERW pipe
manufactured prior to 1970. The operators were to determine whether their pipelines
were susceptible to ERW seam failures and address the potential impact on pipeline
integrity.
Determination of Necessity for Corrective Action Order and Right to Hearing:
Section 60112 of Title 49, United States Code, provides for the issuance of a Corrective Action
Order, after reasonable notice and the opportunity for a hearing, requiring corrective action,
which may include the suspended or restricted use of a pipeline facility, physical inspection,
testing, repair, replacement, or other action, as appropriate. The basis for making the
determination that a pipeline facility is or would be hazardous, requiring corrective action, is set
forth both in the above-referenced statute and 49 C.F.R. § 190.233, a copy of which is enclosed.
Section 60112 and the regulations promulgated thereunder provide for the issuance of a
Corrective Action Order, without prior notice and opportunity for hearing, upon a finding that



CPF No. 4-2015-1009H
Page 3
failure to issue the Order expeditiously would result in the likelihood of serious harm to life,
property, or the environment. In such cases, an opportunity for a hearing and expedited review
will be provided as soon as practicable after the issuance of the Order.
After evaluating the foregoing preliminary findings of fact, I find that continued operation of the
pipeline without corrective measures is or would be hazardous to life, property, or the
environment. Additionally, having considered the nature of the failure; the proximity of the
pipeline to public road crossings and residences; the age and manufacture of the pipeline; the
hazardous nature of the product the pipeline transports; the pressure required for transporting the
material; the uncertainties as to the cause of the failure; the potential for ERW seam issues not
previously identified; and the ongoing investigation to determine the cause of the failure, I find
that a failure to issue this Order expeditiously to require immediate corrective action would result
in the likelihood of serious harm to life, property, or the environment.
Accordingly, this Corrective Action Order mandating immediate corrective action is issued
without prior notice and opportunity for a hearing. The terms and conditions of this Order are
effective upon receipt.
Within 10 days of receipt of this Order, Respondent may contest its issuance obtain expedited
review either by answering in writing or requesting a hearing under 49 C.F.R. § 190.211, to be
held as soon as practicable under the terms of such regulation, by notifying the Associate
Administrator for Pipeline Safety in writing, with a copy to the Director, Southwest Region,
PHMSA (Director). If Respondent requests a hearing, it will be held telephonically or in-person
in Southwest Region Office or Washington, D.C.
After receiving and analyzing additional data in the course of this investigation, PHMSA may
identify other corrective measures that need to be taken. In that event, PHMSA will notify
Respondent of any additional measures that are required and an amended Order issued, if
necessary. To the extent consistent with safety, Respondent will be afforded notice and an
opportunity for a hearing prior to the imposition of any additional corrective measures.
Required Corrective Actions:
Pursuant to 49 U.S.C. § 60112, I hereby order TGP to immediately take the following corrective
actions on the San Salvador Line 400-1 pipeline:
Definitions:
“Affected Segment” - The “Affected Segment” means TGP's San Salvador Line 400-1
pipeline extending 98.79 miles from Agua Dulce Station 1 to Edinburg Station 409.
"Isolated Segment" - The "Isolated Segment" means the 11.16-mile segment of Line 400-1
extending from VS 403-1 to VS 404-1.
"Director"
- The "Director" means the Director, Pipeline and Hazardous Materials Safety
Administration (PHMSA), Office of Pipeline Safety, Southwest Region. The Director’s
address is 8701 S. Gessner, Suite 1110, Houston, Texas 77074.
Operating Restriction. TGP must not operate the Isolated Segment until authorized to do so
by the Director.
1.



CPF No. 4-2015-1009H
Page 4
2. Pressure Restriction. TGP must reduce and maintain a twenty percent (20%) pressure
reduction in the actual operating pressure along the entire length of the Affected Segment
such that the operating pressure along the Affected Segment will not exceed eighty percent
(80%) of the actual operating pressure in effect immediately prior to the failure on August 3,
2015.
a. This pressure restriction is to remain in effect until written approval to increase the
pressure or return the pipeline to its pre-failure operating pressure is obtained from the
Director.
b. This pressure restriction requires any relevant remote or local alarm limits, software
programming set-points or control points, and mechanical over-pressure devices to be
adjusted accordingly.
3. Restart Plan. Prior to resuming operation of the Isolated Segment develop and submit a
written Restart Plan to the Director for prior approval.
a. The Director may approve the Restart Plan incrementally without approving the entire
plan, but the Isolated Segment cannot resume operation until the Restart Plan is approved
in its entirety.
b. Once approved by the Director, the Restart Plan will be incorporated by reference into
this Order.
c. The Restart Plan must provide for adequate patrolling of the Isolated Segment during the
restart process and must include incremental pressure increases during start-up, with each
increment to be held for at least 2 hours.
d. The Restart Plan must include sufficient surveillance of the pipeline during each pressure
increment to ensure that no leaks are present when operation of the line resumes.
e. The Restart Plan must specify a day-light restart and include advance communications
with local emergency response officials.
f. The Restart Plan must provide for a review of the Isolated Segment for conditions similar
to those of the failure, including a review of construction, operating and maintenance
(O&M) and integrity management records such as in-line inspection (ILI) results,
hydrostatic tests, root cause failure analysis of prior failures, aerial and ground patrols,
corrosion, cathodic protection, excavations and pipe replacements. TGP must address
any findings that require remedial measures to be implemented prior to restart.
g. The Restart Plan must also include documentation of the completion of all required
actions, and a management of change plan to ensure that all procedural modifications are
incorporated into TGP’s operations and maintenance procedures manual.
4. Return to Service. After the Director approves the Restart Plan, TGP may return the
Isolated Segment to service but the operating pressure must not exceed eighty percent (80%)
of the actual operating pressure in effect immediately prior to the failure on August 3, 2015,
in accordance with Item 2 above.
5. Removal of Pressure Restriction.
a. The Director may allow the removal or modification of the pressure restriction upon a
written request from TGP demonstrating that restoring the pipeline to its pre-failure
operating pressure is justified based on a reliable engineering analysis showing that the



CPF No. 4-2015-1009H
Page 5
pressure increase is safe considering all known defects, anomalies, and operating
parameters of the pipeline.
b. The Director may allow the temporary removal or modification of the pressure
restrictions upon a written request from TGP demonstrating that temporary mitigative
and preventive measures are implemented prior to and during the temporary removal or
modification of the pressure restriction. The Director's determination will be based on the
failure cause and provision of evidence that preventative and mitigative actions taken by
the operator provide for the safe operation of the Affected Segment during the temporary
removal or modification of the pressure restriction. Appeals to determinations of the
Director in this regard will be decided by the Associate Administrator for Pipeline Safety.
6. Mechanical and Metallurgical Testing. Within 45 days of receipt of this Order, complete
independent third-party mechanical and metallurgical testing and failure analysis of the failed
pipe, including an analysis of soil samples and any foreign materials. Complete the testing
and analysis as follows:
a. Document the chain-of-custody when handling and transporting the failed pipe section
and other evidence from the failure site and transport the pipe in accordance with
applicable protocols to ensure the fracture surface is not damaged.
b. Within 10 days of receipt of this Order, develop and submit the testing protocol and the
proposed testing laboratory to the Director for prior approval.
c. Prior to beginning the mechanical and metallurgical testing, provide the Director with the
scheduled date, time, and location of the testing to allow for an OPS representative to
witness the testing.
d. Ensure the testing laboratory distributes all reports whether draft or final in their entirety
to the Director at the same time they are made available to TGP.
7. Root Cause Failure Analysis. Within 90 days following receipt of this Order, complete a
root cause failure analysis (RCFA) and submit a final report of this RCFA to the Director.
The RCFA must be supplemented/facilitated by an independent third party acceptable to the
Director and must document the decision making process and all factors contributing to the
failure. The RCFA should include a review of TGP’s approach to monitoring its system for
potential longitudinal seam issues. The final report must include findings and any lessons
learned and whether the findings and any lessons learned are applicable to other locations
within TGP’s pipeline system.
8. Remedial Work Plan (RWP).
a. Within 90 days following receipt of this Order, TGP must submit a Remedial Work Plan
(RWP) to the Director for approval.
b. The Director may approve the RWP incrementally without approving the entire RWP.
c. Once approved by the Director, the RWP will be incorporated by reference into this
Order.
d. The RWP must specify the tests, inspections, assessments, evaluations, and remedial
measures TGP will use to verify the integrity of the Affected Segment. It must address all
known or suspected factors and causes of the August 3, 2015 failure. TGP should
consider both the risk of another failure and the consequence of another failure to develop



CPF No. 4-2015-1009H
Page 6
e. a prioritized schedule for RWP-related work along the Affected Segment.
The RWP must include a procedure or process to:
i. Identify pipe in the Affected Segment with characteristics similar to the contributing
factors identified for the August 3, 2015 failure.
ii. Gather all data necessary to review the failure history (in service and pressure test
failures) of the Affected Segment and to prepare a written report containing all the
available information such as the locations, dates, and causes of leaks and failures.
iii. Integrate the results of the metallurgical testing, root cause failure analysis, and other
corrective actions required by this Order with all relevant pre-existing operational and
assessment data for the Affected Segment. Pre-existing operational data includes, but
is not limited to, construction, operations, maintenance, testing, repairs, prior
metallurgical analyses, and any third-party consultation information. Pre-existing
assessment data includes, but is not limited to, ILI tool runs, hydrostatic pressure
testing, direct assessments, close interval surveys, and DCVG/ACVG surveys.
iv. Determine if conditions similar to those contributing to the failure on August 3, 2015
are likely to exist elsewhere within the TGP pipeline systems.
v. Conduct additional field tests, inspections, assessments, and/or evaluations to
determine whether, and to what extent, the conditions associated with the failure on
August 3, 2015, and other failures from the failure history or any other integrity
threats are present elsewhere on the Affected Segment. At a minimum, this process
must consider all failure causes and specify the use of one or more of the following:
1) ILI tools that are technically appropriate for assessing the pipeline system, based
on the cause of failure and that can reliably detect and identify anomalies;
2) Hydrostatic pressure testing;
3) Close-interval surveys;
4) Cathodic protection surveys, to include interference surveys in coordination with
other utilities (e.g. underground utilities, overhead power lines, etc.) in the area;
5) Coating surveys;
6) Stress corrosion cracking surveys;
7) Selective seam corrosion surveys; and
8) Other tests, inspections, assessments, and evaluations appropriate for the failure
causes.
Note: TGP may use the results of previous tests, inspections, assessments, and
evaluations if approved by the Director, provided the results of the tests, inspections,
assessments, and evaluations are analyzed with regard to the factors known or
suspected to have caused the failure.
vi. Describe the inspection and repair criteria TGP will use to prioritize, excavate,
evaluate, and repair anomalies, imperfections, and other identified integrity threats.
Include a description of how any defects will be graded and a schedule for repairs or
replacement.
vii. Based on the known history and condition of the Affected Segment, describe the
methods TGP will use to repair, replace, or take other corrective measures to



CPF No. 4-2015-1009H
Page 7
f. g. h. remediate the conditions associated with the pipeline failure and to address other
known integrity threats along the Affected Segment.
viii. Implement continuing long-term periodic testing and integrity verification measures
to ensure the ongoing safe operation of the Affected Segment, considering the results
of the analyses, inspections, evaluations, and corrective measures undertaken
pursuant to the Order.
Include a proposed schedule for completion of the RWP.
TGP must revise the RWP as necessary to incorporate new information obtained during
the failure investigation and remedial activities, to incorporate the results of actions
undertaken pursuant to this Order, and/or to incorporate modifications required by the
Director.
i. ii. iii. Submit any plan revisions to the Director for prior approval.
The Director may approve plan revisions incrementally.
Any and all revisions to the RWP after it has been approved and incorporated by
reference into this Order will be fully described and documented.
Implement the RWP as it is approved by the Director, including any revisions to the plan
and maintain records of all actions taken pursuant to this Corrective Action Order for a
period of not less than 10 years.
Other Requirements:
1. Reporting. Submit quarterly reports to the Director that: (1) include all available data and
results of the testing and evaluations required by this Order; (2) document any approved
revisions to the RWP and their implementation; and (3) describe the progress of the
repairs or other remedial actions being undertaken. The first quarterly report is due on
November 1, 2015. The Director may change the interval for the submission of these
reports.
2. Documentation of Costs. It is requested but not required that Respondent maintain
documentation of the costs associated with implementation of this Order. Include in each
monthly report the to-date total costs associated with: (1) preparation and revision of
procedures, studies and analyses; and (2) physical changes to pipeline facilities, including
repairs, replacements and other modifications.
3. Approvals. With respect to each submission requiring the approval of the Director, the
Director may: (a) approve the submission in whole or in part; (b) approve the submission
on specified conditions; (c) modify the submission to cure any deficiencies;(d)
disapprove the submission in whole or in part and direct Respondent to modify the
submission; or (e) any combination of the above. In the event of approval, approval upon
conditions, or modification by the Director, Respondent shall proceed to take all action
required by the submission, as approved or modified by the Director. If the Director
disapproves all or any portion of a submission, Respondent must correct all deficiencies
within the time specified by the Director and resubmit it for approval.



CPF No. 4-2015-1009H
Page 8
4. Extensions of Time. The Director may grant an extension of time for compliance with
any of the terms of this Order upon a written request timely submitted and demonstrating
good cause for an extension.
The actions required by this Corrective Action Order are in addition to and do not waive any
requirements that apply to Respondent’s pipeline system under 49 C.F.R. Parts 190-199, under
any other order issued to Respondent under authority of 49 U.S.C. § 60101, et seq., or under any
other provision of Federal or State law.
Respondent may appeal any decision of the Director to the Associate Administrator for Pipeline
Safety. Decisions of the Associate Administrator shall be final.
Be advised that all material you submit in response to this enforcement action is subject to being
made publicly available. If you believe that any portion of your responsive material qualifies for
confidential treatment under 5 U.S.C. 552(b), along with the complete original document you
must provide a second copy of the document with the portions you believe qualify for
confidential treatment redacted and an explanation of why you believe the redacted information
qualifies for confidential treatment under 5 U.S.C. 552(b).
Failure to comply with this Order may result in the assessment of civil penalties and in referral to
the Attorney General for appropriate relief in United States District Court pursuant to 49 U.S.C.
§ 60120.
In your correspondence on this matter, please refer to CPF No. 4-2015-1009H and for each
document you submit, please provide a copy in electronic format whenever possible.
The terms and conditions of this Corrective Action Order are effective upon receipt.
__________________________________ __________________
Jeffrey D. Wiese Date Issued
Associate Administrator
for Pipeline Safety

420151009H_Closure Letter_08112016_text.pdf

CERTIFIED MAIL - RETURN RECEIPT REQUESTED
August 11, 2016
Mr. Gary Buchler
Vice President, Operations and Engineering
Tennessee Gas Pipeline Company, LLC
1001 Louisiana Street
Houston, TX 77002
CPF 4-2015-1009H
Dear Mr. Buchler:
On August 3, 2015, a failure occurred on TGP’s Line 400-1 approximately 1.5 miles from the
City of Falfurrias, Texas. The incident was reported to the National Response Center (NRC
Report # 1124690) on August 3, 2015 at approximately 9:49 p.m. CST.
PHMSA issued the Corrective Action Order (CAO) 4-2015-1009H to Tennessee Gas Pipeline
Company (TGP) on August 6, 2015 requiring a pressure restriction on the affected segment,
development of a remedial work plan and mitigative actions necessary for the continued safe
operation of the pipeline.
Based on our review of the documentation you provided, it has been determined that you have
complied with the terms of this Order.
Accordingly, this case is now closed and no further action is contemplated with respect to the
matters involved in this case. Thank you for your cooperation in this matter.
Sincerely,
R. M. Seeley
Director, Southwest Region
Pipeline and Hazardous Materials Safety Administration

## Provenance

- Official: Yes
- Source: <https://primis.phmsa.dot.gov/enforcement-data/case/420151009H>
- Source ID: `phmsa-enforcement`
- SHA-256: `ac94a35fb9a9cf1032bce368b6c523f37fc5c4330969d2def758ce9253a73e19`
- Retrieved: 2026-08-20T04:44:44.458Z
- Exported: 2026-08-22T05:09:39.797Z
- Document slug: `phmsa-enforcement-420151009h`

### Source metadata

```json
{
  "cpf": "420151009H",
  "operator": "TENNESSEE GAS PIPELINE COMPANY",
  "region": "Southwest",
  "pipelineType": "GAS INTERSTATE ONSHORE",
  "caseStatus": "CLOSED",
  "citedSections": [],
  "dataAsOf": "08/04/2026 12PM",
  "caseDataAsOf": "2026-08-04",
  "attachmentCount": 4,
  "attachments": [
    {
      "name": "420151009H_Closure Letter_08112016.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420151009H/420151009H_Closure%20Letter_08112016.pdf",
      "bytes": 291074,
      "category": "agency_document"
    },
    {
      "name": "420151009H_Closure Letter_08112016_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420151009H/420151009H_Closure%20Letter_08112016_text.pdf",
      "bytes": 66781,
      "category": "agency_document"
    },
    {
      "name": "420151009H_Corrective Action Order_08062015.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420151009H/420151009H_Corrective%20Action%20Order_08062015.pdf",
      "bytes": 583273,
      "category": "agency_document"
    },
    {
      "name": "420151009H_Corrective Action Order_08062015_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420151009H/420151009H_Corrective%20Action%20Order_08062015_text.pdf",
      "bytes": 48438,
      "category": "agency_document"
    }
  ],
  "extractedAgencyDocumentCount": 2,
  "attachmentPolicy": "Official attachment links are retained. Agency-issued documents may also include a verified local PDF and page-level text representation.",
  "jurisdiction": "US",
  "operatorName": "TENNESSEE GAS PIPELINE COMPANY"
}
```
