# TC OIL PIPELINE OPERATIONS INC — Warning Letter

**Citation:** CPF 420165012W  
**Type / status:** enforcement / historical  
**Agency:** Pipeline and Hazardous Materials Safety Administration  
**Effective:** Not stated  
**Published:** 2016-04-27

CLOSED warning letter citing 195.402(e)(9), 195.420(c), 195.446(f)(1), 195.565.

## Document text

Warning Letter involving TC OIL PIPELINE OPERATIONS INC. PHMSA's enforcement data identifies the cited regulations as 195.402(e)(9),  195.420(c),  195.446(f)(1),  195.565. The case was opened on 2016-04-27 and is reported as closed as of 2016-04-27. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

420165012W_Warning Letter_04272016.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420165012W/420165012W_Warning%20Letter_04272016.pdf

420165012W_Warning Letter_04272016_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420165012W/420165012W_Warning%20Letter_04272016_text.pdf

420165012W_Warning Letter_04272016_text.pdf

WARNING LETTER
CERTIFIED MAIL - RETURN RECEIPT REQUESTED
April 27, 2016
Mr. Paul Miller
Executive-Vice President/President, Liquids Pipelines
TC Oil Pipeline Operations Inc.
450-1 Street SW
Calgary, Alberta, Canada
T2P 5H1
CPF 4-2016-5012W
Dear Mr. Miller:
On March 3, 2015 – May 14, 2015, a representative of the Pipeline and Hazardous Materials Safety
Administration (PHMSA) pursuant to Chapter 601 of 49 United States Code inspected your
procedures, records, and pipeline facilities for the Keystone XL – Gulf Coast Pipeline.
As a result of the inspection, it appears that you have committed § 195.420(c) of the Pipeline Safety
Regulations, Title 49, Code of Federal Regulations. The items inspected and the probable
violation(s) are:
1. § 195.402 Procedural manual for operations, maintenance, and emergencies.
(e) Emergencies. The manual required by paragraph (a) of this section must include
procedures for the following to provide safety when an emergency condition occurs:
(9) Providing for a post-accident review of employee activities to determine whether
the procedures were effective in each emergency and taking corrective action where
deficiencies are found.
TransCanada did not perform a timely post-accident review of its procedures to determine their
effectiveness in each emergency. During the review of TransCanada’s Incident Investigation



Report, issued on 8/29/14, an incident occurred on 7/29/14 at the Bryan Pump Station when oil
backed up on the sump drain piping and released 20 gallons of oil onto the surrounding area. Post-
accident, TransCanada completed a review of its procedures on 8/26/14, and those procedures
were modified and recommended for approval on 9/3/14. The revised procedures were
implemented almost three months after accident on 11/14/14. TransCanada needs to evaluate its
corrective action process when deficiencies are found in order to expedite the time for
implementing recommended procedural changes.
2. § 195.420 Valve maintenance.
(c) Each operator shall provide protection for each valve from unauthorized
operation and from vandalism.
TransCanada did not adequately secure each valve from unauthorized operation. TransCanada’s
pipeline facilities had a fence with locked gates to prevent entry, and main line valves were chained
with locks at the time of the inspection. Valve controls that disable the remote operation of the
valve and valve operation that were not locked at the time of the inspection are as follows: Bryan
1A, Bryan 1B, Delta 4A, WNSBR 2A, LIBRT 4A, LUFKN 2A and LKTLR 2A. PHMSA brought
this to the attention of the company representative on site, and they agreed to lock all control boxes.
3. § 195.446 Control room management.
(f) Change management. Each operator must assure that changes that could affect
control room operations are coordinated with the control room personnel by
performing each of the following:
(1) Implement section 7 of API RP 1168 (incorporated by reference, see § 195.3) for
control room management change and require coordination between control room
representatives, operator's management, and associated field personnel when
planning and implementing physical changes to pipeline equipment or configuration;
and…
TransCanada did not perform an adequate review of a control room management change that could
affect control room operations. Based on TransCanada’s “Record of Change Review by Oil
Control Centre” document, the controller Douglas Robertson reviewed and approved a CRM
change on the same date and time. The record indicates that the change was reviewed on 5/28/14
at 08:11:13, and approved on 5/28/14 at 08:11:13. This indicates the controller did not review the
change before approving or the system utilized to document the process did not accurately record



the time between reviewing and approving the change. TransCanada must ensure proper review
of any changes that could affect control room operations.
4. § 195.565 How do I install cathodic protection on breakout tanks?
After October 2, 2000, when you install cathodic protection under § 195.563(a) to
protect the bottom of an aboveground breakout tank of more than 500 barrels
(79.5m3 ) capacity built to API Specification 12F, API Standard 620, or API Standard
650 (or its predecessor Standard 12C), you must install the system in accordance with
API Recommended Practice 651. However, installation of the system need not comply
with API Recommended Practice 651 on any tank for which you note in the corrosion
control procedures established under § 195.402(c)(3) why compliance with all or
certain provisions of API Recommended Practice 651 is not necessary for the safety
of the tank.
TransCanada did not adequately design its cathodic protection system for newly constructed
breakout tanks on the Keystone Gulf Coast Pipeline North system. During the inspection of the
cathodic protection potentials for Tanks #5 and #7, there were issues identified with the cp readings
varying between the 850 mV and 100 mV polarization criteria. Once the operator has established
cp criteria as specified by API 651, he cannot arbitrarily switch from one criteria (850 mV) to
another (100 mV polarization) during a survey cycle. Furthermore, the 2015 native surveys
document cp potentials between 237 mV to 669 mV for both tanks which would be considered
considerably low for a new tank bottom.
Based on these findings TransCanada needs to evaluate the tank bottoms of these tanks for
corrosion; determine if there is possible stray current near the tank facility; determine if grounding
for the electrical equipment has been installed correctly at the site; and re-evaluate the design of
the cathodic protection system for the breakout tanks.
Under 49 United States Code, § 60122, you are subject to a civil penalty not to exceed $200,000
per violation per day the violation persists up to a maximum of $2,000,000 for a related series of
violations. For violations occurring prior to January 4, 2012, the maximum penalty may not exceed
$100,000 per violation per day, with a maximum penalty not to exceed $1,000,000 for a related
series of violations. We have reviewed the circumstances and supporting documents involved in
this case, and have decided not to conduct additional enforcement action or penalty assessment
proceedings at this time. We advise you to correct the item(s) identified in this letter. Failure to
do so will result in TC Oil Pipeline Operations Inc. being subject to additional enforcement action.



No reply to this letter is required. If you choose to reply, in your correspondence please refer to
CPF 4-2016-5012W. Be advised that all material you submit in response to this enforcement
action is subject to being made publicly available. If you believe that any portion of your
responsive material qualifies for confidential treatment under 5 U.S.C. 552(b), along with the
complete original document you must provide a second copy of the document with the portions
you believe qualify for confidential treatment redacted and an explanation of why you believe the
redacted information qualifies for confidential treatment under 5 U.S.C. 552(b).
Sincerely,
R. M. Seeley
Director, Southwest Region
Pipeline and Hazardous Materials Safety Administration

## Provenance

- Official: Yes
- Source: <https://primis.phmsa.dot.gov/enforcement-data/case/420165012W>
- Source ID: `phmsa-enforcement`
- SHA-256: `95f33951d64fe3e06319bc24a5c8fbf2840af5b074a7f6bc2cf859bebcb950e1`
- Retrieved: 2026-08-20T04:44:44.458Z
- Exported: 2026-08-24T15:59:01.832Z
- Document slug: `phmsa-enforcement-420165012w`

### Source metadata

```json
{
  "cpf": "420165012W",
  "operator": "TC OIL PIPELINE OPERATIONS INC",
  "region": "Southwest",
  "pipelineType": "INTERSTATE LIQUID ONSHORE",
  "caseStatus": "CLOSED",
  "citedSections": [
    "195.402(e)(9)",
    "195.420(c)",
    "195.446(f)(1)",
    "195.565"
  ],
  "dataAsOf": "08/04/2026 12PM",
  "caseDataAsOf": "2026-08-04",
  "attachmentCount": 2,
  "attachments": [
    {
      "name": "420165012W_Warning Letter_04272016.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420165012W/420165012W_Warning%20Letter_04272016.pdf",
      "bytes": 73951,
      "category": "agency_document"
    },
    {
      "name": "420165012W_Warning Letter_04272016_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420165012W/420165012W_Warning%20Letter_04272016_text.pdf",
      "bytes": 16283,
      "category": "agency_document"
    }
  ],
  "extractedAgencyDocumentCount": 1,
  "attachmentPolicy": "Official attachment links are retained. Agency-issued documents may also include a verified local PDF and page-level text representation.",
  "jurisdiction": "US",
  "operatorName": "TC OIL PIPELINE OPERATIONS INC"
}
```
