# SHELL PIPELINE CO., L.P. — Notice of Probable Violation

**Citation:** CPF 420165023  
**Type / status:** enforcement / historical  
**Agency:** Pipeline and Hazardous Materials Safety Administration  
**Effective:** Not stated  
**Published:** 2016-07-07

CLOSED notice of probable violation citing 195.64(c)(1).

## Document text

Notice of Probable Violation involving SHELL PIPELINE CO., L.P.. PHMSA's enforcement data identifies the cited regulation as 195.64(c)(1). The case was opened on 2016-07-07 and is reported as closed as of 2018-02-28. Proposed civil penalty: $25,900. Assessed civil penalty: $25,900. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

420165023_Final Order_01182018.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420165023/420165023_Final%20Order_01182018.pdf

420165023_Final Order_01182018_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420165023/420165023_Final%20Order_01182018_text.pdf

420165023_NOPV PCP_07072016.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420165023/420165023_NOPV%20PCP_07072016.pdf

420165023_NOPV PCP_07072016_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420165023/420165023_NOPV%20PCP_07072016_text.pdf

420165023_Operator Reponse to Notice_08082016.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420165023/420165023_Operator%20Reponse%20to%20Notice_08082016.pdf

420165023_Operator Reponse to Notice_08082016.pdf

CERTIFIED MAIL - RETURN RECEIPT REQUESTED
Shell Pipeline Company LP
One Shell Plaza
August 8, 2016
910 Louisiana Street
42nd Floor
Mr. R.M. Seeley
Houston, Texas 77002-5316
Pipeline and Hazardous Materials Safety Administration
Director, Southwest Region
8701 South Gessner, Suite 1110
Houston, TX 77074
SUBJECT: NOPV-PCP-PCO, CPF 4-2016-5023
Dear Mr. Seeley:
Shell Pipeline Company LP (SPLC) acknowledges the receipt of CPF 4-2016-5023 Notice of
Probable Violation (NOPV) and Proposed Civil Penalty (PCP) from the Pipeline and Hazardous
Materials Safety Administration (PHMSA) on July 18, 2016. SPLC is committed to operational
excellence and full compliance with federal, state and local regulations. SPLC is also committed to
striving to meet PHMSA expectations above the requitements of 49 CFR 195; however the
requirements of 49 CFR 195 alone are what should be used in determining probable violations.
Response to Notice of Proposed Violation
On August 12, 2015, SPLC submitted a notification of proposed construction for the construction
of 30 miles of pipeline in the Gulf of Mexico. SPLC reported the expected date for start of
construction to be September 1, 2015. This would have been only 19 days prior to construction
instead of the 60 days required by the regulation but not the 233 days late as alleged by PHMSA.
And in fact, field construction activities were delayed and did not begin until work on the crossing
preparation started on December 17, 2015.
PHMSA alleges that "construction" began on February 20, 2015. This date is based on the dates
that some of the purchase orders for the pipe were issued. While Advisory Bulletin ADB 2014-03
does encourage operators to make notification based on pipe purchase, ROW purchase and other
activities that occut prior to field "construction" the ADB itself acknowledges that this is guidance
and not a requirement. Specifically it states, "While the notification prior to the fust occurring construction-
related activity is strongly encouraged and will benefit both PHMSA and the operator, tbese activities may not
necessarily represent the commencement of construction for purposes of triggering the minimum 60- day notice period in
the regulations subject to enforcement by PHMSA." Thereforc, the date of purchase of the pipe does not
necessarily constitute "construction" and this definition presented through an advisory bulletin
should not be used in an enforcement action.
Furthermore, SPLC disagrees with the assertion in the Pipeline Safety Violation Report "Section E6
- Circumstances" that the violation was discovered by PHMSA. SPLC believes in being open and
fully cooperating with our regulators, and we believe that the record bears that out in this instance.



There was no intent to hide a violation and by submitting the notification, SPLC went on record
that the construction was planned to start less than 60 days from the submittal. As was the case
with CPF 4-2016-5010, it is unclear to SPLC what other notification could have been provided to
PHMSA in this instance. SPLC would like to know what the expectation is to self repott this type
of instance in the future if a deadline for a report is missed.
Response to Proposed Civil Penalty
In accotdance with the Response Options for Pipeline Operators in Compliance Proceedings, SPLC
believes that the proposed penalty should be reviewed in light of the contested allegations presented
above.
Thank you for yout consideration. We look forward to hearing your response. If you have any
questions regarding this response or need any additional information, please contact Deborah Price
at (713) 241-2035.
Sincerely,
Sal Dir
Deborah Price
Integrity & Regulatory Services Manager
Shell Pipeline Company LP

420165023_Final Order_01182018_text.pdf

January 18, 2018
Mr. Greg Smith
President
Shell Pipeline Company, LP
Two Shell Plaza
777 Walker Street
Houston, TX 77022
Re: CPF No. 4-2016-5023
Dear Mr. Smith:
Enclosed please find the Final Order issued in the above-referenced case. It makes one finding
of violation and assesses a civil penalty of $25,900. The penalty payment terms are set forth in
the Final Order. This enforcement action closes automatically upon receipt of payment. Service
of the Final Order by certified mail is effective upon the date of mailing as provided under
49 C.F.R. § 190.5.
Thank you for your cooperation in this matter.
Sincerely,
Alan K. Mayberry
Associate Administrator
for Pipeline Safety
Enclosure
cc: Director, Southwest Region, Office of Pipeline Safety, PHMSA
Ms. Deborah Price, Integrity & Regulatory Services Manager, Shell Pipeline Company
LP, One Shell Plaza, 910 Louisiana Street, 42nd Floor, Houston, TX, 77022
CERTIFIED MAIL - RETURN RECEIPT REQUESTED



U.S. DEPARTMENT OF TRANSPORTATION
PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION
OFFICE OF PIPELINE SAFETY
WASHINGTON, D.C. 20590
____________________________________
In the Matter of )
Shell Pipeline Company, LP, ) CPF No. 4-2016-5023
)
)
)
Respondent. )
____________________________________)
FINAL ORDER
From April 14 through June 28, 2016, pursuant to 49 U.S.C. § 60117, a representative of the
Pipeline and Hazardous Materials Safety Administration (PHMSA), Office of Pipeline Safety
(OPS), conducted an inspection of the records of Shell Pipeline Company, LP (SPLC or
Respondent), in Houston, Texas. SPLC owns and operates seven tank farms across the United
States, and transports more than 1.5 billion barrels of crude oil and refined products annually
through 3,800 pipeline miles across the Gulf of Mexico and five states.1
As a result of the inspection, the Director, Southwest Region, OPS (Director), issued to
Respondent, by letter dated July 7, 2016, a Notice of Probable Violation and Proposed Civil
Penalty (Notice). In accordance with 49 C.F.R. § 190.207, the Notice proposed finding that
SPLC had violated 49 C.F.R. § 195.64(c) and proposed assessing a civil penalty of $25,900 for
the alleged violation.
SPLC responded to the Notice by letter dated August 8, 2016 (Response). The company
contested the allegation, offered additional information in response to the Notice, and requested
that the proposed civil penalty be reviewed in light of the additional information presented.
Respondent did not request a hearing and therefore has waived its right to one.
FINDING OF VIOLATION
Item 1: The Notice alleged that Respondent violated 49 C.F.R. § 195.64(c)(1), which states:
§ 195.64 National Registry of Pipeline and LNG Operators.
(a) …
(c) Changes. Each operator must notify PHMSA electronically through
1 Shell Pipeline Company, LP website, available at http://www.shell.us/business-customers/shell-pipeline/about-
shell-pipeline.html (last accessed August 16, 2017).



CPF No. 4-2016-5023
Page 2
the National Registry of Pipeline and LNG Operators at
http://opsweb.phmsa.dot.gov, of certain events.
(1) An operator must notify PHMSA of any of the following events not
later than 60 days before the event occurs:
(i) Construction or any planned rehabilitation, replacement, modifica-
tion, upgrade, uprate, or update of a facility, other than a section of line pipe,
that costs $10 million or more. If 60 day notice is not feasible because of an
emergency, an operator must notify PHMSA as soon as practicable;
(ii) Construction of 10 or more miles of a new hazardous liquid
pipeline;.…2
The Notice alleged that Respondent violated 49 C.F.R. § 195.64(c)(1) by failing to notify
PHMSA of the construction of 10 or more miles of new hazardous liquid pipeline at least 60
days before such event occurred. Specifically, the Notice alleged that SPLC failed to provide
PHMSA with proper notification of SPLC’s “Amberjack Debottleneck” construction project,
which consisted of more than 30 miles of pipeline in the Gulf of Mexico. According to the
Notice, on August 12, 2015, SPLC submitted a notification for construction of 10 or more miles
of new or replacement hazardous liquid pipeline, with an anticipated start date for construction
activities of September 1, 2015.3 However, based on information provided by SPLC following
submittal of the notification, OPS alleged that the Amberjack Debottleneck construction project
had actually started construction on February 20, 2015, approximately six months before the
notification date. Consequently, PHMSA alleged that “the notification should have been
submitted no later than December 22, 2014 in order to provide PHMSA the required 60 day
notice prior to construction.”
In its Response, SPLC admitted that it had submitted its construction notification only 19 days
prior to its anticipated construction start date of September 1, 2015.4 However, Respondent
challenged the February 20, 2015 date that PHMSA stated should have been used by Shell as the
start of construction activities. SPLC noted that this date was “based on the dates that some of
the purchase orders for the pipe were issued.”5 Referring to PHMSA’s Advisory
Bulletin PHMSA-2014-0017 (Advisory Bulletin), SPLC argued that the date of purchasing pipe
does not necessarily constitute a construction-related activity that would trigger a notification to
2 The Notice mistakenly included subparagraph (iii) of § 195.64(c)(1): “Construction of a new hazardous liquid
pipeline facility.” This subparagraph was not a provision of 49 C.F.R. § 195.64(c)(1) in effect at the time SPLC
submitted its notification on August 12, 2015, or when PHMSA either conducted its inspection from April to June
2016, or issued the Notice on July 7, 2016. Since this subparagraph is not at issue in this Item, any error is harmless.
3 Operator Registry Notification G-20150812-8307.
4 Although SPLC stated that field construction activities were delayed and did not begin until December 17, 2015,
the notification submitted by SPLC on August 12, 2015, noted that the anticipated start date for field construction
activities was September 1, 2015. See Pipeline Safety Violation Report (Violation Report), (July 7, 2016) (on file
with PHMSA), at 20-23.
5 Response, at 1. See also Violation Report, Exhibit A.



CPF No. 4-2016-5023
Page 3
PHMSA.6 required:
According to SPLC, the following language from the Advisory Bulletin confirmed
that the list of construction-related activities cited in the bulletin was only suggestive and not
While the notification prior to the first occurring construction-related
activity is strongly encouraged and will benefit both PHMSA and the
operator, these activities may not necessarily represent the commencement
of construction for purposes of triggering the minimum 60-day notice
period in the regulations subject to enforcement by PHMSA.
According to Shell, the date that it purchased the pipe did not necessarily constitute the
commencement of construction in this case and that a “definition presented through an advisory
bulletin should not be used in an enforcement action.”7
Shell is correct that the Advisory Bulletin is merely guidance, used by PHMSA as an opportunity
to inform the industry and the public of the benefits of early construction notifications and to
“strongly encourage” operators to use certain milestones, such as the purchasing and
manufacturing of line pipe, to alert PHMSA of a company’s construction plans. While I find
nothing in the record of this case that would justify the conclusion that “construction” began
when Shell ordered line pipe in February 2015, the company, by its own admission, did file the
60-day notification only 19 days in advance of the company’s own reported start date of
September 1, 2015.8
Therefore, on this basis alone, there is sufficient evidence to find that Respondent failed to
provide at least 60 days’ notice of the company’s own reported construction start date.
Accordingly, after considering the evidence and the legal issues presented, I find that
Respondent violated 49 C.F.R. § 195.64(c)(1) by failing to notify PHMSA of the construction of
10 or more miles of new hazardous liquid pipeline at least 60 days before the event occurred.
This finding of violation will be considered a prior offense in any subsequent enforcement action
taken against Respondent.
6 See Advisory Bulletin, Pipeline Safety: Construction Notification, 79 FR 54777 (September 9, 2014). In that notice,
PHMSA provided guidance to operators on the agency’s need for advance notice of certain construction-related
activities so that it could schedule its own inspections and reviews and so operators could avoid costly modifications
or repairs in order to achieve compliance. The advisory notice states:
Accordingly, PHMSA strongly encourages operators to provide the required
construction-related notification(s) not later than 60 days prior to whichever of the
following events occurs first: Material purchasing and manufacturing; right-of-way
acquisition; construction equipment move-in activities; onsite or offsite fabrications; or
right-of-way clearing, grading and ditching” (emphasis added)
7 Response, at 1.
8 Id.



CPF No. 4-2016-5023
Page 4
ASSESSMENT OF PENALTY
Under 49 U.S.C. § 60122, Respondent is subject to an administrative civil penalty not to exceed
$200,000 per violation for each day of the violation, up to a maximum of $2,000,000 for any
related series of violations.9 In determining the amount of a civil penalty under 49 U.S.C.
§ 60122 and 49 C.F.R. § 190.225, I must consider the following criteria: the nature,
circumstances, and gravity of the violation, including adverse impact on the environment; the
degree of Respondent’s culpability; the history of Respondent’s prior offenses; and any effect
that the penalty may have on its ability to continue doing business; and the good faith of
Respondent in attempting to comply with the pipeline safety regulations. In addition, I may
consider the economic benefit gained from the violation without any reduction because of
subsequent damages, and such other matters as justice may require. The Notice proposed a total
civil penalty of $25,900 for the violation cited above.
Item 1: The Notice proposed a civil penalty of $25,900 for Respondent’s violation of 49 C.F.R.
§ 195.64(c)(1), for failing to notify PHMSA of the construction of 10 or more miles of hazardous
liquid pipeline at least 60 days before such event occurred. As previously mentioned, the Notice
alleged that SPLC failed to inform PHMSA of the Amberjack Debottleneck construction project
at least 60 days prior to the anticipated construction start date.
In its Response, SPLC disputed that the alleged violation was discovered by PHMSA, as stated
in Section E6 of the Violation Report.10 Specifically, SPLC argued that by submitting the
notification, it “went on record that the construction was planned to start less than 60 days from
the submittal.”11
I disagree. While SPLC argued that it self-reported the violation when it went “on record” with
its submission of an untimely notification, such a filing is not the same as self-reporting. There
is no evidence that SPLC proactively informed PHMSA that it had failed to comply with the 60-
day notice requirement, but, rather, the record shows that SPLC filed a routine construction
notice without mentioning that it constituted a violation or affirmatively bringing the violation to
the agency’s attention. As discussed above, PHMSA discovered Respondent’s violation of the
60-day notice requirement during an inspection of SPLC’s construction records. Accordingly, I
find that a penalty reduction is not warranted because SPLC did not self-report the violation to
PHMSA. Furthermore, I have reviewed the record and can find no evidence to suggest that Shell
discovered its non-compliance and took documented action to address the cause of the violation
before PHMSA learned of it. If it had, then it is possible a penalty reduction might be in order.
In conclusion, having reviewed the record and considered the assessment criteria, I assess
Respondent a civil penalty of $25,900 for violation of 49 C.F.R. § 195.64(c)(1).
Payment of the civil penalty must be made within 20 days of service. Federal regulations
9 These amounts are adjusted annually for inflation. See, e.g., Pipeline Safety: Inflation Adjustment of Maximum
Civil Penalties, 82 Fed. Reg. 19325 (April 27, 2017).
10 Violation Report, at 7.
11 Response, at 2.



CPF No. 4-2016-5023
Page 5
(49 C.F.R. § 89.21(b)(3)) require such payment to be made by wire transfer through the Federal
Reserve Communications System (Fedwire), to the account of the U.S. Treasury. Detailed
instructions are contained in the enclosure. Questions concerning wire transfers should be
directed to: Financial Operations Division (AMK-325), Federal Aviation Administration, Mike
Monroney Aeronautical Center, 6500 S MacArthur Blvd, Oklahoma City, Oklahoma 79169.
The Financial Operations Division telephone number is (405) 954-8845.
Failure to pay the $25,900 civil penalty will result in accrual of interest at the current annual rate
in accordance with 31 U.S.C. § 3717, 31 C.F.R. § 901.9 and 49 C.F.R. § 89.23. Pursuant to
those same authorities, a late penalty charge of six percent (6%) per annum will be charged if
payment is not made within 110 days of service. Furthermore, failure to pay the civil penalty
may result in referral of the matter to the Attorney General for appropriate action in a district
court of the United States.
Under 49 C.F.R. § 190.243, Respondent may submit a Petition for Reconsideration of this Final
Order to the Associate Administrator, Office of Pipeline Safety, PHMSA, 1200 New Jersey
Avenue, SE, East Building, 2nd Floor, Washington, DC 20590, with a copy sent to the Office of
Chief Counsel, PHMSA, at the same address, no later than 20 days after receipt of service of the
Final Order by Respondent. Any petition submitted must contain a brief statement of the issue(s)
and meet all other requirements of 49 C.F.R. § 190.243. The filing of a petition automatically
stays the payment of any civil penalty assessed. The other terms of the order, including any
corrective action, remain in effect unless the Associate Administrator, upon request, grants a
stay. If Respondent submits payment of the civil penalty, the Final Order becomes the final
administrative decision and the right to petition for reconsideration is waived. The terms and
conditions of this Final Order are effective upon service in accordance with 49 C.F.R. § 190.5.
January 18, 2018
___________________________________ __________________________
Alan K. Mayberry Date Issued
Associate Administrator
for Pipeline Safety

## Provenance

- Official: Yes
- Source: <https://primis.phmsa.dot.gov/enforcement-data/case/420165023>
- Source ID: `phmsa-enforcement`
- SHA-256: `6333b437a92f8435491d2e89839941d805b222fb583ffa980dcc2aa08ea7f485`
- Retrieved: 2026-08-20T04:44:44.458Z
- Exported: 2026-08-22T11:49:01.220Z
- Document slug: `phmsa-enforcement-420165023`

### Source metadata

```json
{
  "cpf": "420165023",
  "operator": "SHELL PIPELINE CO., L.P.",
  "region": "Southwest",
  "pipelineType": "INTERSTATE LIQUID ONSHORE",
  "caseStatus": "CLOSED",
  "citedSections": [
    "195.64(c)(1)"
  ],
  "dataAsOf": "08/04/2026 12PM",
  "caseDataAsOf": "2026-08-04",
  "attachmentCount": 5,
  "attachments": [
    {
      "name": "420165023_Final Order_01182018.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420165023/420165023_Final%20Order_01182018.pdf",
      "bytes": 1548727,
      "category": "agency_document"
    },
    {
      "name": "420165023_Final Order_01182018_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420165023/420165023_Final%20Order_01182018_text.pdf",
      "bytes": 131252,
      "category": "agency_document"
    },
    {
      "name": "420165023_NOPV PCP_07072016.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420165023/420165023_NOPV%20PCP_07072016.pdf",
      "bytes": 42201,
      "category": "case_document"
    },
    {
      "name": "420165023_NOPV PCP_07072016_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420165023/420165023_NOPV%20PCP_07072016_text.pdf",
      "bytes": 105008,
      "category": "case_document"
    },
    {
      "name": "420165023_Operator Reponse to Notice_08082016.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420165023/420165023_Operator%20Reponse%20to%20Notice_08082016.pdf",
      "bytes": 98409,
      "category": "agency_document"
    }
  ],
  "extractedAgencyDocumentCount": 2,
  "attachmentPolicy": "Official attachment links are retained. Agency-issued documents may also include a verified local PDF and page-level text representation.",
  "jurisdiction": "US",
  "operatorName": "SHELL PIPELINE CO., L.P."
}
```
