# EXXONMOBIL PIPELINE CO — Notice of Probable Violation

**Citation:** CPF 420175027  
**Type / status:** enforcement / historical  
**Agency:** Pipeline and Hazardous Materials Safety Administration  
**Effective:** Not stated  
**Published:** 2017-08-11

CLOSED notice of probable violation citing 195.452(j)(2), 195.505, 195.571, 195.573(c).

## Document text

Notice of Probable Violation involving EXXONMOBIL PIPELINE CO. PHMSA's enforcement data identifies the cited regulations as 195.452(j)(2),  195.505,  195.571,  195.573(c). The case was opened on 2017-08-11 and is reported as closed as of 2019-04-19. Proposed civil penalty: $203,400. Assessed civil penalty: $0. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

420175027_Final Order_04032019.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420175027/420175027_Final%20Order_04032019.pdf

420175027_Final Order_04032019_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420175027/420175027_Final%20Order_04032019_text.pdf

420175027_NOPV PCP_08112017.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420175027/420175027_NOPV%20PCP_08112017.pdf

420175027_NOPV PCP_08112017_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420175027/420175027_NOPV%20PCP_08112017_text.pdf

420175027_Operator Post Hearing Submission_Second Amended and Restated Statement of Isssues_06142018.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420175027/420175027_Operator%20Post%20Hearing%20Submission_Second%20Amended%20and%20Restated%20Statement%20of%20Isssues_06142018.pdf

420175027_Operator Post-Hearing Brief_06142018.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420175027/420175027_Operator%20Post-Hearing%20Brief_06142018.pdf

420175027_Operator Response to Notice and Request For Hearing_10192017.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420175027/420175027_Operator%20Response%20to%20Notice%20and%20Request%20For%20Hearing_10192017.pdf

420175027_Operator_Pre-Hearing_Submissions_05042018.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420175027/420175027_Operator_Pre-Hearing_Submissions_05042018.pdf

420175027_PHC Hearing Rescheduled_03302018.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420175027/420175027_PHC%20Hearing%20Rescheduled_03302018.pdf

420175027_PHC Hearing Rescheduled_03302018_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420175027/420175027_PHC%20Hearing%20Rescheduled_03302018_text.pdf

420175027_PHC Hearing Scheduled_02132018.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420175027/420175027_PHC%20Hearing%20Scheduled_02132018.pdf

420175027_PHC Hearing Scheduled_02132018_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420175027/420175027_PHC%20Hearing%20Scheduled_02132018_text.pdf

420175027_Final Order_04032019_text.pdf

April 3, 2019
Mr. Richard Byrne
General Counsel
ExxonMobil Pipeline Company
22777 Springwoods Village Parkway
Energy 3 5A.491
Spring, TX 77389-2170
Re: CPF No. 4-2017-5027
Dear Mr. Byrne:
Enclosed please find the Final Order issued in the above-referenced case. It withdraws the
allegations of violation. Service of the Final Order by certified mail is effective upon the date of
mailing as provided under 49 C.F.R. § 190.5.
Thank you for your cooperation in this matter.
Sincerely,
Alan K. Mayberry
Associate Administrator
for Pipeline Safety
Enclosure
cc: Director, Southwest Region, Office of Pipeline Safety, PHMSA
Mr. Johnnie R. Randolph, Jr., Counsel, Exxon Mobil Corporation
Mr. Vince Murchison, Murchison Law Firm, PLLC, 325 North St. Paul Street, Suite
2700, Dallas, TX 75201
CERTIFIED MAIL - RETURN RECEIPT REQUESTED



U.S. DEPARTMENT OF TRANSPORTATION
PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION
OFFICE OF PIPELINE SAFETY
WASHINGTON, D.C. 20590
____________________________________
In the Matter of )
ExxonMobil Pipeline Company, ) CPF No. 4-2017-5027
)
)
)
Respondent. )
____________________________________)
FINAL ORDER
From March 2013 through February 2016, pursuant to 49 U.S.C. § 60117, representatives of the
Pipeline and Hazardous Materials Safety Administration (PHMSA), Office of Pipeline Safety
(OPS), conducted on-site pipeline safety inspections of the facilities and records of ExxonMobil
Pipeline Company (Exxon or Respondent), in Woodlands, Texas. Exxon and its affiliates
transport 2.8 million barrels of crude oil, refined petroleum products, liquefied petroleum gases,
natural gas liquids, and chemical feedstocks through approximately 8,000 miles of pipeline in 10
states and the Gulf of Mexico,1
As a result of the inspection, the Director, Southwest Region, OPS (Director), issued to
Respondent, by letter dated August 11, 2017, a Notice of Probable Violation and Proposed Civil
Penalty (Notice). In accordance with 49 C.F.R. § 190.207, the Notice proposed finding that
Exxon committed a number of violations of 49 C.F.R. Part 195 and proposed assessing a civil
penalty of $203,400 for the alleged violations.
Exxon responded to the Notice by letter dated October 19, 2017 (Response). Respondent
contested the allegations and requested a hearing. A hearing was subsequently held on May 14,
2018, in Houston, TX, before a Presiding Official from the Office of Chief Counsel, PHMSA. At
the hearing, Respondent was represented by counsel. After the hearing, Respondent provided a
post-hearing statement for the record, by letter dated June 14, 2018 (Closing). In addition, the
Respondent also submitted a response to the Region Recommendation for the record, by letter
dated July 6, 2018 (Response to the Region Recommendation).
1 https://corporate.exxonmobil.com/en/company/worldwide-operations/locations/united-states/pipeline-
operations/overview (last accessed November 29, 2018).



CPF No. 4-2017-5027
Page 2
FINDINGS OF VIOLATION
The Notice alleged that Respondent violated 49 C.F.R. Part 195, as follows:
Item 1: The Notice alleged that Respondent violated 49 C.F.R. § 195.505, which states in
relevant part:
§ 195.505 Qualification program.
Each operator shall have and follow a written qualification program.
The program shall include provisions to:
(a) Identify covered tasks;
(b) Ensure through evaluation that individuals performing covered tasks
are qualified;
(c) Allow individuals that are not qualified pursuant to this subpart to
perform a covered task if directed and observed by an individual that
is qualified;
(d) Evaluate an individual if the operator has reason to believe that the
individual's performance of a covered task contributed to an accident as
defined in Part 195;
(e) Evaluate an individual if the operator has reason to believe that the
individual is no longer qualified to perform a covered task;
(f) Communicate changes that affect covered tasks to individuals
performing those covered tasks;
(g) Identify those covered tasks and the intervals at which evaluation of the
individual's qualifications is needed;
(i) After December 16, 2004, notify the Administrator or a state agency
participating under 49 U.S.C. Chapter 601 if the operator significantly
modifies the program after the administrator or state agency has verified that
it complies with this section. Notifications to PHMSA may be submitted by
electronic mail to InformationResourcesManager@dot.gov, or by mail to
ATTN: Information Resources Manager DOT/PHMSA/OPS, East Building,
2nd Floor, E22-321, New Jersey Avenue SE., Washington, DC 20590.
The Notice alleged that Respondent violated 49 C.F.R. § 195.505 by failing to follow their
written qualification program. Specifically, the Notice alleged that Exxon failed to follow its
own qualification program that required requalification of a Cathodic Protection technician (CP
technician) following a July 2012 failure to properly install a cathodic protection rectifier. The
procedure, Qualification of Pipeline Personnel (October 2012) (the procedure),2 states, in
relevant part:
4.3.3 Re-qualification
EMPCo’s Written Program identifies the circumstances in which individuals need to be
re-qualified. Personnel will be re-evaluated and re-qualified prior to performing the
covered task when any of the following circumstances occur (49 CFR 195.505 or
192.805):
2 Pipeline Safety Violation Report (Violation Report)), (August 11, 2017) (on file with PHMSA), at Exhibit A.



CPF No. 4-2017-5027
Page 3
3) Reason to believe an employee is no longer able to perform or displays
unsatisfactory performance: If an individual’s performance is identified to be
unsatisfactory, regardless of whether it has resulted in an incident, the individual must be
re-qualified prior to further performance of the covered task. An individual’s
performance may be determined to be unsatisfactory during an incident investigation,
observations by Supervisors, or other qualified individuals, or a near-miss occurrence.
Before attempting to re-qualify an employee, the Supervisor should consider and
document any of the following that are completed:
 Reviewing the applicable policy and procedure(s) with the individual
 Assigning a qualified individual to work with the individual
 Identifying applicable training for the individual
At the hearing, Exxon argued that OPS failed to prove that it violated the procedure. First, the
Respondent argued that it abided by the language in the procedure and was not required to
requalify the CP technician given that requalification is only required prior to further
performance of the covered task.
Alternatively, Exxon contended that, even if it was required to requalify the CP technician per
the procedure, the CP technician was requalified on October 16, 2012, after the display of
unsatisfactory performance in July 2012 and prior to identification of the error in January 2013.
Therefore, the terms of the procedural requirement were met as of October 16, 2012.
The Region contended that Exxon could only requalify the CP technician following discovery of
the mistake in January 2013 (emphasis added). According to OPS, Exxon could not requalify
the CP technician prior to identifying the error. Therefore, the October 16, 2012 qualification
did not count as a requalification, even though the practical result of a further qualification (or
requalification) would have resulted in the CP technician repeating the same testing module.
OPS pointed out that Exxon chose to requalify the CP technician in May 2013 following the
inspection, after investigators pointed out the failure to requalify. During the hearing, OPS
argued that this fact establishes that, as of January 2013, Exxon also believed it was required to
requalify. 3
3 Informal Hearing Transcript Excerpt:
“Mr. Murchison (Exxon): Well, is there anything in the case file that shows us that unsatisfactory performance was
determined?
Ms. McDaniel (OPS): To me, yes. Hooking it up incorrectly would be unsatisfactory performance. And when it
was brought to ExxonMobil’s attention in May of 2013, he was immediately requalified. So, ExxonMobil must
have felt the same thing; otherwise, why would he be requalified if he was on a three-year requalification – or five-
year requalification time period. I mean, to me that sort of falls in line to where, based off of my comment, which is
sort of what they said here; after being questioned by PHMSA staff during the inspection, EMPCo was requalified.
So, based off that.
Mr. Randolph (Exxon): Okay. So—but that pursuant to the procedure, when its determined that his performance
was unsatisfactory is when the requirement kicks in.
Ms. McDaniel (OPS): Right. So, January of 2013….
Mr. Randolph (Exxon): So a violation of this element could not start until January of 2013, once unsatisfactory
performance was determined?
Mr. Matthews (OPS): Yes, I think we’d be willing to concede that, yes.”
(Informal Hearing Tr. 107-108, May 14, 2018).



CPF No. 4-2017-5027
Page 4
Analysis
The October qualification cannot count as a requalification because the procedure also requires
that “(b)efore attempting to re-qualify an employee the supervisor consider and document that”
they reviewed the policy with the individual, assigned a qualified individual to work with the
individual, or identified applicable training for the individual. There is no evidence that Exxon
did this prior to the October 16, 2012 qualification. Therefore, this cannot credibly be
considered a requalification following a display of unsatisfactory performance.
However, I agree with the Respondent that, in order to prove that it violated the procedure, OPS
must establish that the CP technician performed the task again prior to requalification. The
procedure states that “individuals need to be re-qualified … prior to performing the covered task
when any of the following circumstances occur (49 CFR 195.505 or 192.805): . . . if an
individual’s performance is identified to be unsatisfactory . . .the individual must be re-
requalified prior to further performance of the covered task.”
Critically, the procedure only requires requalification “prior to further performance of the
covered task.” There is nothing in the Violation Report to suggest that OPS inquired or collected
evidence establishing that the CP technician continued to perform the covered task. OPS
conceded this point.4 Both parties acknowledged that CP technicians perform duties that do not
include this covered task. It is OPS’ burden to prove that the CP technician continued to perform
this task – not the Respondent’s burden to prove that he did not. Therefore, OPS has not
established that Exxon failed to follow the procedure.
Accordingly, after considering all the evidence, I find that OPS did not present evidence proving
that the operator failed to follow the procedure. Based upon the foregoing, I hereby order that
Item 1 be withdrawn.
Item 2: The Notice alleged that Respondent violated 49 C.F.R. § 195.573(c), which states:
§ 195.573 What must I do to monitor external corrosion control?
(c) Rectifiers and other devices. You must electrically check for proper
performance each device in the first column at the frequency stated in the
second column.
4 Mr. Murchison (Exxon): Where in the case file, the NOPV, the violation report, the exhibits to the violation
report is … the evidence that the gentleman, Kevin Hollingsworth covered this particular task --… prior to being
requalified?
Ms. McDaniel (OPS): I’m not saying performed. I don’t have evidence to show he performed the covered task.
But he was not removed from his position as a CP technician doing this stuff … I do not have evidence in here that
shows that he installed another rectifier at that time.
(Informal Hearing Tr. 111-112, May 14, 2018).Mr. Phillips (OPS): No, I’m asking if the employee did the covered
task.
Mr. Murchison (Exxon Counsel): The burden is yours, sir. Do you have any evidence?
Mr. Phillips (OPS): And I’m asking. And if you don’t have it, that’s fine.
(Informal Hearing Tr. 134, May 14, 2018).



CPF No. 4-2017-5027
Page 5
Device Check frequency
Rectifier
At least six times each calendar
year, but with intervals not
exceeding 2 ½ months.
Reverse current switch
Diode
Interface bond whose failure would
jeopardize structural protection
Other interface bond
At least once each calendar year but
with intervals not exceeding 15
months
The Notice alleged that Respondent violated 49 C.F.R. § 195.573 by failing to electrically check
the performance of a newly installed rectifier at the required frequencies. Specifically, the
Notice alleged that Exxon failed to perform electric checks for six months after the improper
installation of a rectifier.
At the hearing, the Region acknowledged that the NOPV was based on a misunderstanding of the
facts in evidence and withdrew the allegation of violation.
Based upon the foregoing, I hereby order that the item be withdrawn.
Item 3: The Notice alleged that Respondent violated 49 C.F.R. § 195.571, which states:
§ 195.571 What criteria must I use to determine the adequacy of cathodic
protection?
Cathodic protection required by this subpart must comply with one or more
of the applicable criteria and other considerations for cathodic protection
contained paragraphs 6.2.2, 6.2.3, 6.2.4, 6.2.5 and 6.3 in NACE SP 0169
(incorporated by reference, see §195.3).
The Notice alleged that Respondent violated 49 C.F.R. § 195.571 by failing to maintain the
cathodic protection required by NACE SP 0169. Specifically, the Notice alleged that the
Respondent could not have met one of the required cathodic protection criterion required by the
regulation given that there was a reverse rectifier connection in place.
At the hearing, Exxon argued that the Region failed to establish that it failed to comply with any
of the applicable criteria for cathodic protection in NACE SP 0169. The Respondent introduced
an expert in cathodic protection, Mr. Kevin Garrity, P.E. At the hearing, both sides debated
whether § 195.571 requires adequate cathodic protection and, if not, whether OPS produced
sufficient evidence to establish a violation of this regulation. Mr. Garrity testified that § 195.571
requires only that the cathodic protection meet the requirement of SP 0169, which includes three
measurement criteria. For each criteria, Mr. Garrity stated that there was no evidence in the
record to demonstrate that the reverse connection on the rectifier changed the polarity of the



CPF No. 4-2017-5027
Page 6
cathodic protection measurement under those three criteria. In fact, the expert testified that the
only evidence in the record5 demonstrated that there were no significant external metal loss
anomalies in the area of the reversed rectifier. While the metal loss report found approximately
one-hundred anomalies over the entire 49 mile ILI run, the two most significant anomalies (63
percent deep) were found 30-miles away from the reversed rectifier – squarely outside of the
rectifier’s area of influence. Given the lack of external metal loss in the area, in Mr. Garrity’s
expert opinion, the reversed rectifier did not compromise adequate cathodic protection on the
pipeline.
OPS acknowledged that there was no evidence in the record that the incorrectly installed rectifier
resulted in a charge on the pipeline. However, OPS argued that the evidence in the record,
namely the ILI tool run, was not the correct tool to adequately evaluate corrosion.6
Analysis
There is no evidence in the record that this pipeline did not have adequate cathodic protection.
While the reversed rectifier connection could have put current onto the pipeline that negated the
area of influence of the other rectifiers, neither the ILI data nor the pipe-to-soil readings support
that supposition. The ILI data and the pipe-to-soil readings are the only evidence of the current
on the pipeline.
Experts for OPS and Exxon proffered conflicting testimony. The Regional Director testified that
“it would be almost impossible to have adequate cathodic protection in that area.”7 Exxon’s
expert testified that he had personally observed situations where a single rectifier wired in
reverse polarity was compensated for by other rectifiers. In its post-hearing recommendation,
OPS stated “basic cathodic protection and engineering principles would clearly call into question
the adequacy of cathodic protection for an area of pipe that was influenced by an incorrectly
installed rectifier.”8 I agree that OPS called into question the adequacy of the cathodic protection
at or near the reversed rectifier, but it has no supporting evidence. Contrary to the Regional
Recommendation, the Respondent is not required to “rule[d] out as being possible that the area
5 Exxon ran an in-line inspection tool through the pipeline. In the opinion of Mr. Garrity, if the cathodic protection
was inadequate, “coincident metal loss anomalies” would have been observed (Page 196).
(Informal Hearing Tr. 196, May 14, 2018).
6 Informal Hearing Excerpt:
Ms. McDaniel (OPS): And I think maybe it I’m hearing you right, your conclusion is based off the lack of evidence
to say that there was inadequate cathodic protection supported by your looking at the tool run; is that correct?...
Mr. Garrity: It’s a combination of that and also the fact that there was a rectifier half a mile away discharging
almost twice as much of the current of the Lake Washington rectifier.”
Ms. McDaniel (OPS): But it’s sort of in the same situation when I was asked the question; it’s supposition. We
don’t know. And I would think the same thing from you, wouldn’t we? Without any evidence, we don’t’ know.
Mr. Garrity (Exxon): Well, in my opinion, the tool data is very persuasive and it’s very conclusive. And I don’t
want to sound curt, but if we have a lack of evidence, in the absence of evidence, how is a speculation the basis for a
violation? Or the allegation of a violation?” (Informal Hearing Tr. 198-199, May 14, 2018).
7 (Informal Hearing Tr. 151, May 14, 2018).
8 Post Hearing Regional Recommendation, at 3.



CPF No. 4-2017-5027
Page 7
influenced by the rectifier did not meet the required criteria of -850mv.”9 The burden of proof is
on OPS to establish there was not adequate cathodic protection.
Accordingly, after considering all of the evidence I find that OPS has not met its burden of proof
in establishing that there was not adequate cathodic protection on this pipeline. Based upon the
foregoing, I hereby order that the Item be withdrawn.
WARNING ITEM
With respect to Item 4, the Notice alleged probable violations of Part 195 but did not propose a
civil penalty or compliance order for this item. Therefore, this is considered as a warning
item. The warning was for:
49 C.F.R. § 195.452 (Item 4) ─ Respondent’s alleged failure to continue to assess
the line pipe at specified intervals and periodically evaluate the integrity of each
pipeline segment that could affect a high consequence area.
Exxon requested withdrawal of Item 4, because OPS lacked data to substantiate the allegation
that cathodic protection adequacy was compromised. Under § 190.205, PHMSA does not
adjudicate warning items to determine whether a probable violation occurred. If OPS finds a
violation of this provision in a subsequent inspection, Respondent may be subject to future
enforcement action.
ASSESSMENT OF PENALTY
Under 49 U.S.C. § 60122, Respondent is subject to an administrative civil penalty not to exceed
$200,000 per violation for each day of the violation, up to a maximum of $2,000,000 for any
related series of violations.10 In determining the amount of a civil penalty under 49 U.S.C.
§ 60122 and 49 C.F.R. § 190.225, I must consider the following criteria: the nature,
circumstances, and gravity of the violation, including adverse impact on the environment; the
degree of Respondent’s culpability; the history of Respondent’s prior offenses; and any effect
that the penalty may have on its ability to continue doing business; and the good faith of
Respondent in attempting to comply with the pipeline safety regulations. In addition, I may
consider the economic benefit gained from the violation without any reduction because of
subsequent damages, and such other matters as justice may require. The Notice proposed a total
civil penalty of $203,400 for the violations cited above.
Item 1: The Notice proposed a civil penalty of $63,900 for Respondent’s violation of 49 C.F.R.
§ 195.505, for failing to follow their written qualification program. For the reasons discussed
above, I find that the Respondent did not violate this regulation. Based upon the foregoing, I
withdraw the proposed penalty for violation of 49 C.F.R. § 195.505.
9 Post Hearing Regional Recommendation, at 3.
10 These amounts are adjusted annually for inflation. See, e.g., Pipeline Safety: Inflation Adjustment of Maximum
Civil Penalties, 82 Fed. Reg. 19325 (April 27, 2017).



CPF No. 4-2017-5027
Page 8
Item 2: The Notice proposed a civil penalty of $75,600 for Respondent’s violation of 49 C.F.R.
§ 195.573, for failing to electrically check the performance of a newly installed rectifier at the
required frequencies. For the reasons discussed above, I find that the Respondent did not violate
this regulation. Based upon the foregoing, I withdraw the proposed penalty for violation of 49
C.F.R. § 195.573.
Item 3: The Notice proposed a civil penalty of $63,900 for Respondent’s violation of 49 C.F.R.
§ 195.571, for failing to maintain the cathodic protection required by NACE SP 0169. For the
reasons discussed above, I find that the Respondent did not violate this regulation. Based upon
the foregoing, I withdraw the proposed penalty for violation of 49 C.F.R. § 195.571.
Under 49 C.F.R. § 190.243, Respondent may submit a Petition for Reconsideration of this Final
Order to the Associate Administrator, Office of Pipeline Safety, PHMSA, 1200 New Jersey
Avenue, SE, East Building, 2nd Floor, Washington, DC 20590, with a copy sent to the Office of
Chief Counsel, PHMSA, at the same address, no later than 20 days after receipt of service of the
Final Order by Respondent. Any petition submitted must contain a brief statement of the issue(s)
and meet all other requirements of 49 C.F.R. § 190.243. The filing of a petition automatically
stays the payment of any civil penalty assessed. The other terms of the order, including any
corrective action, remain in effect unless the Associate Administrator, upon request, grants a
stay. If Respondent submits payment of the civil penalty, the Final Order becomes the final
administrative decision and the right to petition for reconsideration is waived.
The terms and conditions of this Final Order are effective upon service in accordance with 49
C.F.R. § 190.5.
April 3, 2019
___________________________________ __________________________
Alan K. Mayberry Date Issued
Associate Administrator
for Pipeline Safety

420175027_PHC Hearing Scheduled_02132018_text.pdf

February 13, 2018
VIA CERTIFIED MAIL AND EMAIL TO: Richard.E.Byrne@exxonmobil.com and
Mary.McDaniel@dot.gov
Mr. Richard E. Byrne
General Counsel
ExxonMobil Pipeline Company
22777 Springwoods Village Pkwy
Spring, TX 77389
Ms. Mary McDaniel
Director, Southwest Region
Pipeline and Hazardous Materials Safety Administration
8701 South Gessner, Suite 630
Houston, TX 77074
Re: Notice of Hearing, ExxonMobil Pipeline Company
CPF No. 4-2017-5027
Dear Mr. Byrne and Ms. McDaniel:
In accordance with 49 C.F.R. § 190.211, an informal hearing will be held regarding the Notice of
Probable Violation and Proposed Civil Penalty issued by the Office of Pipeline Safety in the above-
referenced case. The hearing has been rescheduled and will take place on April 4, 2018, beginning
at 9:00 a.m. Central Time.
The hearing will be at the PHMSA Southwest Region office, 8701 South Gessner, Suite 630,
Houston, TX 77074. Upon arrival at the building, attendees will be required to present photo
identification to security personnel. A contact phone number for the day of the hearing is
(713) 272-2859.
Both parties must submit and exchange any additional written materials they intend to present at
least 10 calendar days prior to the hearing (March 25, 2018), along with a list of attendees, and the
names of any witnesses who may testify. You may provide this information electronically. If you
have any questions, please contact me at (202) 366-6139 or at kristin.baldwin@dot.gov.



CPF No. 4-2017-5027
Page 2
If you have any questions, please do not hesitate to contact me.
Sincerely,
Kristin Baldwin
Presiding Official
cc (email): Mr. Adam Phillips, Counsel, Southwest Region, OPS

420175027_PHC Hearing Rescheduled_03302018_text.pdf

March 30, 2018
VIA CERTIFIED MAIL AND EMAIL TO: Johnnie.R.Randolph@exxonmobil.com and
Mary.McDaniel@dot.gov
Mr. Johnnie Randolph
General Counsel
ExxonMobil Pipeline Company
22777 Springwoods Village Pkwy
Spring, TX 77389
Ms. Mary McDaniel
Director, Southwest Region
Pipeline and Hazardous Materials Safety Administration
8701 South Gessner, Suite 630
Houston, TX 77074
Re: Notice of Hearing, ExxonMobil Pipeline Company
CPF No. 4-2017-5027
Dear Mr. Randolph and Ms. McDaniel:
In accordance with 49 C.F.R. § 190.211, an informal hearing will be held regarding the Notice of
Probable Violation and Proposed Civil Penalty issued by the Office of Pipeline Safety in the above-
referenced case. The hearing has been rescheduled and will take place on May 14, 2018, beginning
at 9:00 a.m. Central Time.
The hearing will be at the PHMSA Southwest Region office, 8701 South Gessner, Suite 630,
Houston, TX 77074. Upon arrival at the building, attendees will be required to present photo
identification to security personnel. A contact phone number for the day of the hearing is
(713) 272-2859.
Both parties must submit and exchange any additional written materials they intend to present at
least 10 calendar days prior to the hearing (March 25, 2018), along with a list of attendees, and the
names of any witnesses who may testify. You may provide this information electronically. If you
have any questions, please contact me at (202) 366-6139 or at kristin.baldwin@dot.gov.



CPF No. 4-2017-5027
Page 2
If you have any questions, please do not hesitate to contact me.
Sincerely,
Kristin Baldwin
Presiding Official
cc (email): Mr. Adam Phillips, Counsel, Southwest Region, OPS

## Provenance

- Official: Yes
- Source: <https://primis.phmsa.dot.gov/enforcement-data/case/420175027>
- Source ID: `phmsa-enforcement`
- SHA-256: `89a313cb4868b7087f58cead509ef0e32b972a7d0294d94a6d2939c153f38f14`
- Retrieved: 2026-08-20T04:44:44.458Z
- Exported: 2026-08-22T13:16:03.989Z
- Document slug: `phmsa-enforcement-420175027`

### Source metadata

```json
{
  "cpf": "420175027",
  "operator": "EXXONMOBIL PIPELINE CO",
  "region": "Southwest",
  "pipelineType": "INTERSTATE LIQUID ONSHORE",
  "caseStatus": "CLOSED",
  "citedSections": [
    "195.452(j)(2)",
    "195.505",
    "195.571",
    "195.573(c)"
  ],
  "dataAsOf": "08/04/2026 12PM",
  "caseDataAsOf": "2026-08-04",
  "attachmentCount": 12,
  "attachments": [
    {
      "name": "420175027_Final Order_04032019.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420175027/420175027_Final%20Order_04032019.pdf",
      "bytes": 2410008,
      "category": "agency_document"
    },
    {
      "name": "420175027_Final Order_04032019_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420175027/420175027_Final%20Order_04032019_text.pdf",
      "bytes": 183605,
      "category": "agency_document"
    },
    {
      "name": "420175027_NOPV PCP_08112017.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420175027/420175027_NOPV%20PCP_08112017.pdf",
      "bytes": 84119,
      "category": "case_document"
    },
    {
      "name": "420175027_NOPV PCP_08112017_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420175027/420175027_NOPV%20PCP_08112017_text.pdf",
      "bytes": 120565,
      "category": "case_document"
    },
    {
      "name": "420175027_Operator Post Hearing Submission_Second Amended and Restated Statement of Isssues_06142018.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420175027/420175027_Operator%20Post%20Hearing%20Submission_Second%20Amended%20and%20Restated%20Statement%20of%20Isssues_06142018.pdf",
      "bytes": 1080704,
      "category": "case_document"
    },
    {
      "name": "420175027_Operator Post-Hearing Brief_06142018.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420175027/420175027_Operator%20Post-Hearing%20Brief_06142018.pdf",
      "bytes": 2918854,
      "category": "party_submission"
    },
    {
      "name": "420175027_Operator Response to Notice and Request For Hearing_10192017.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420175027/420175027_Operator%20Response%20to%20Notice%20and%20Request%20For%20Hearing_10192017.pdf",
      "bytes": 167217,
      "category": "party_submission"
    },
    {
      "name": "420175027_Operator_Pre-Hearing_Submissions_05042018.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420175027/420175027_Operator_Pre-Hearing_Submissions_05042018.pdf",
      "bytes": 684930,
      "category": "case_document"
    },
    {
      "name": "420175027_PHC Hearing Rescheduled_03302018.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420175027/420175027_PHC%20Hearing%20Rescheduled_03302018.pdf",
      "bytes": 323497,
      "category": "agency_document"
    },
    {
      "name": "420175027_PHC Hearing Rescheduled_03302018_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420175027/420175027_PHC%20Hearing%20Rescheduled_03302018_text.pdf",
      "bytes": 85826,
      "category": "agency_document"
    },
    {
      "name": "420175027_PHC Hearing Scheduled_02132018.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420175027/420175027_PHC%20Hearing%20Scheduled_02132018.pdf",
      "bytes": 268008,
      "category": "agency_document"
    },
    {
      "name": "420175027_PHC Hearing Scheduled_02132018_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420175027/420175027_PHC%20Hearing%20Scheduled_02132018_text.pdf",
      "bytes": 85772,
      "category": "agency_document"
    }
  ],
  "extractedAgencyDocumentCount": 3,
  "attachmentPolicy": "Official attachment links are retained. Agency-issued documents may also include a verified local PDF and page-level text representation.",
  "jurisdiction": "US",
  "operatorName": "EXXONMOBIL PIPELINE CO"
}
```
