# CENTURION PIPELINE L.P. — Notice of Probable Violation

**Citation:** CPF 420185013  
**Type / status:** enforcement / historical  
**Agency:** Pipeline and Hazardous Materials Safety Administration  
**Effective:** Not stated  
**Published:** 2018-07-23

CLOSED notice of probable violation citing 195.452(l)(1)(ii), 195.505(a), 195.563(a), 195.563(d), 195.583(a), 195.61.

## Document text

Notice of Probable Violation involving CENTURION PIPELINE L.P.. PHMSA's enforcement data identifies the cited regulations as 195.452(l)(1)(ii),  195.505(a),  195.563(a),  195.563(d),  195.583(a),  195.61. The case was opened on 2018-07-23 and is reported as closed as of 2020-09-09. Proposed civil penalty: $40,300. Assessed civil penalty: $40,300. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

420185013_Closure Letter_09092020.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420185013/420185013_Closure%20Letter_09092020.pdf

420185013_Closure Letter_09092020_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420185013/420185013_Closure%20Letter_09092020_text.pdf

420185013_Final Order_08082019.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420185013/420185013_Final%20Order_08082019.pdf

420185013_Final Order_08082019_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420185013/420185013_Final%20Order_08082019_text.pdf

420185013_NOPV PCP PCO_07232018.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420185013/420185013_NOPV%20PCP%20PCO_07232018.pdf

420185013_NOPV PCP PCO_07232018_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420185013/420185013_NOPV%20PCP%20PCO_07232018_text.pdf

420185013_Operator Response to the Notice_09242018.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420185013/420185013_Operator%20Response%20to%20the%20Notice_09242018.pdf

420185013_Closure Letter_09092020_text.pdf

ELECTRONIC MAIL - RETURN RECEIPT REQUESTED
September 9, 2020
Mike Prince
Chief Executive Officer
Lotus Midstream, LLC
2150 Town Square Place
Suite 395
Sugarland, Texas 77479
CPF 4-2018-5013
Dear Mr. Prince:
On August 8, 2019, the Pipeline and Hazardous Materials Safety Administration (PHMSA) issued
to Centurion Pipeline LP (Lotus Midstream, LLC), a Final Order in the above-referenced case that
included a civil penalty and Compliance Order. PHMSA has received the payment of penalty and
has reviewed the records submitted in response to the Order. The Southwest region has determined
the installation of Cathodic Protection on Tank 6689 and Tank 1878 satisfies the terms of the
Compliance Order.
Accordingly, this case is now closed and no further action is contemplated with respect to the
matters involved in this case. Thank you for your cooperation.
Sincerely,
Mary. L. McDaniel, P.E.
Director, Southwest Region
Pipeline and Hazardous Materials Safety Administration

420185013_Final Order_08082019_text.pdf

August 8, 2019
Mr. Mike Prince
Chief Executive Officer
Lotus Midstream, LLC
2150 Town Square Place
Suite 395
Sugar Land, Texas 77479
Re: CPF No. 4-2018-5013
Dear Ms. Hollub:
Enclosed please find the Final Order issued in the above-referenced case to your subsidiary,
Centurion Pipeline, LP. It makes findings of violation, assesses a civil penalty of $40,300, and
specifies actions that need to be taken to comply with the pipeline safety regulations. The
penalty payment terms are set forth in the Final Order. When the civil penalty has been paid and
the terms of the compliance order completed, as determined by the Director, Southwest Region,
this enforcement action will be closed. Service of the Final Order by certified mail is effective
upon the date of mailing, as provided under 49 C.F.R. § 190.5.
Thank you for your cooperation in this matter.
Sincerely,
Alan K. Mayberry
Associate Administrator
for Pipeline Safety
Enclosure
cc: Ms. Mary L. McDaniel, Director, Southwest Region, Office of Pipeline Safety, PHMSA
Mr. Michael Morgan, GM Operations, Centurion Pipeline, LP
CERTIFIED MAIL - RETURN RECEIPT REQUESTED



U.S. DEPARTMENT OF TRANSPORTATION
PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION
OFFICE OF PIPELINE SAFETY
WASHINGTON, D.C. 20590
__________________________________________
In the Matter of )
Centurion Pipeline, LP, ) CPF No. 4-2018-5013
a subsidiary of Lotus Midstream, LLC, )
)
)
)
Respondent. )
__________________________________________)
FINAL ORDER
From May 1, 2017, through February 23, 2018, pursuant to 49 U.S.C. § 60117, a representative
of the Pipeline and Hazardous Materials Safety Administration (PHMSA), Office of Pipeline
Safety (OPS), conducted an on-site pipeline safety inspection of the facilities and records of
Centurion Pipeline, LP (Centurion or Respondent), in Houston and Midland, Texas. Centurion
operates approximately 2,900 miles of pipeline extending from southeast New Mexico across the
Permian Basin of west Texas to Cushing, Oklahoma.1 At the time of our pipeline safety
inspection, Centurion was a wholly-owned subsidiary of Occidental Petroleum Corporation2 but
is now a subsidiary of Lotus Midstream, LLC.
As a result of the inspection, the Director, Southwest Region, OPS (Director), issued to
Respondent, by letter dated July 23 , 2018, a Notice of Probable Violation, Proposed Civil
Penalty, and Proposed Compliance Order (Notice), which also included a warning pursuant to 49
C.F.R. § 190.205. In accordance with 49 C.F.R. § 190.207, the Notice proposed finding that
Centurion had committed three violations of 49 C.F.R. Part 195 and proposed assessing a civil
penalty of $40,300 for one of the alleged violations. The Notice also proposed ordering
Respondent to take certain measures to correct the alleged violations. The warning items
required no further action but warned Centurion to correct the probable violations or face
possible future enforcement action.
After requesting and receiving an extension of time to respond, Centurion responded to the
Notice by letter dated September 24, 2018 (Response). The company contested several of the
allegations of violation, provided an explanation of its actions, and requested that the proposed
civil penalty be eliminated. The Southwest Region subsequently held an in-person meeting with
Centurion on September 26, 2018, after which Respondent submitted a Supplemental Response
1 Centurion Pipeline, LP website, available at http://www.centurionpipeline.com/about/about-centurion-
pipeline.aspx (last accessed March 7, 2019).
2 Pipeline Safety Violation Report (Violation Report) (July 23, 2018) (on file with PHMSA), at 1.



CPF No. 4-2018-5013
Page 2
dated December 6, 2018, that corrected certain information contained in the initial Response and
made additional arguments regarding the proposed compliance order. Respondent did not
request a hearing and therefore has waived its right to one.
FINDINGS OF VIOLATION
The Notice alleged that Respondent violated 49 C.F.R. Part 195, as follows:
Item 1: The Notice alleged that Respondent violated 49 C.F.R. § 195.583(a), which states:
§ 195.583 What must I do to monitor atmospheric corrosion control?
(a) You must inspect each pipeline or portion of pipeline that is exposed
to the atmosphere for evidence of atmospheric corrosion, as follows:
If the pipeline is located: Then the frequency of
inspection is:
Onshore ……….......................... At least once every 3 calendar
years, but with intervals not
exceeding 39 months.
Offshore …….............................. At least once each calendar year,
but with intervals not exceeding
15 months.
The Notice alleged that Respondent violated 49 C.F.R. § 195.583(a) by failing to inspect each
onshore pipeline or portion of pipeline that is exposed to the atmosphere for evidence of
atmospheric corrosion at least once every 3 calendar years, but at intervals not exceeding 39
months. Specifically, the Notice alleged that Centurion failed, within the required timeframe, to
inspect exposed portions of its pipeline between Bretch and El Reno, Oklahoma, for evidence of
atmospheric corrosion. Centurion inspected this pipeline segment for atmospheric corrosion on
April 1, 2013, but did not inspect it again until October 2017, exceeding the July 1, 2016
maximum interval date.
Respondent did not contest this allegation of violation. Accordingly, based upon a review of all
of the evidence, I find that Respondent violated 49 C.F.R. § 195.583(a) by failing to inspect each
onshore pipeline or portion of pipeline that is exposed to the atmosphere for evidence of
atmospheric corrosion at least once every 3 calendar years, but at intervals not exceeding 39
months.
Item 3: The Notice alleged that Respondent violated 49 C.F.R. § 195.452(l)(1)(ii), which states:
§ 195.452 Pipeline integrity management in high consequence areas.
(a) . . . .
(l) What records must an operator keep to demonstrate compliance?
(1) An operator must maintain, for the useful life of the pipeline, records
that demonstrate compliance with the requirements of this subpart. At a



CPF No. 4-2018-5013
Page 3
minimum, an operator must maintain the following records for review
during an inspection:
(i) . . .
(ii) Documents to support the decisions and analyses, including any
modifications, justifications, deviations and determinations made,
variances, and actions taken, to implement and evaluate each element of the
integrity management program listed in paragraph (f) of this section.
The Notice alleged that Respondent violated 49 C.F.R. § 195.452(l)(1)(ii) by failing to maintain,
for the useful life of the pipeline, records demonstrating compliance with the requirements of
§ 195.452(f) and (g), Compliance would include, at a minimum, the maintenance of documents
supporting the decisions and analyses, including any modifications, justifications, deviations and
determinations made, variances, and actions taken, to implement and evaluate each element of an
operator’s integrity management program, as listed in 49 C.F.R. § 195.452(f). Specifically, the
Notice alleged that during the PHMSA inspection, Centurion was unable to produce records
documenting that it had conducted the information analysis required by subparagraph (3) of
§ 195.452(f)3 and paragraph (g) to support the company’s pipeline integrity-evaluation
decisions.4
Respondent contested this allegation of violation, arguing that § 195.452(l)(1)(ii) requires an
operator to maintain “documents to support the decisions and analyses” made as part of its
integrity-management program, but not records “documenting the information analysis” it had
conducted under § 195.452(g). The company stated: “Although Centurion believes that its
records satisfy both standards, Centurion believes that the plain regulatory language differs from
the NOPV’s characterization of the requirement. The regulatory language requires records of
supporting documentation, while the NOPV contemplates written documentation summarizing
the analysis.” The company pointed to the various records5 it had provided during the PHMSA
inspection that supported its decisions and analyses made under § 195.452(g) and argued that
3 Subparagraph (3) of § 195.452(f) states that operators must include “[a]n analysis that integrates all available
information about the integrity of the entire pipeline and the consequences of a failure (see paragraph (g) of this
section)…”
4 Paragraph 195.452(g) states:
“(g) What is an information analysis? In periodically evaluating the integrity of each pipeline segment
(paragraph (j) of this section), an operator must analyze all available information about the integrity of the entire
pipeline and the consequences of a failure. This information includes:
(1) Information critical to determining the potential for, and preventing, damage due to excavation, including
current and planned damage prevention activities, and development or planned development along the pipeline
segment;
(2) Data gathered through the integrity assessment required under this section;
(3) Data gathered in conjunction with other inspections, tests, surveillance and patrols required by this Part,
including, corrosion control monitoring and cathodic protection surveys; and
(4) Information about how a failure would affect the high consequence area, such as location of the water
intake.”
5 Centurion stated that it had provided to PHMSA the following records: “(1) In-line inspection (“ILI”) results; (2)
Threat analysis documents; (3) Select tool process to inspect threats on pipeline; (4) Process to review ILI results;
(5) Calculate corrosion growth rate; (6) Documents showing categorization of needed repairs; (7) Repair plan; and
(8) Work journal for the project.”



CPF No. 4-2018-5013
Page 4
these documents satisfied the record-keeping requirement under § 195.452(l)(1)(ii).6
I disagree. Subpart F of Part 195 requires all operators to develop and implement a
comprehensive integrity-management program that provides an extra measure of safety and
environmental protection for “High Consequence Areas” (HCAs)7 and neighboring “could-
affect” areas along the routes of their hazardous liquid pipelines. This program includes the
general record-keeping requirement in § 195.452(l), under which operators must keep records
specifically documenting how it made all “decisions and analyses, including any modifications,
justifications, deviations and determinations made, variances, and actions taken, to implement
and evaluate each element” of their integrity management program.
One of the most important elements of an integrity-management program is the “information
analysis” required under § 195.452(g), which involves an engineering analysis that periodically
evaluates the integrity of each pipeline segment and analyzes “all available information about the
integrity of the entire pipeline and the consequences of a failure.” Such an analysis must include
at least four sets of risk data, including the prevention of damage from excavation, ILI data,
information gathered through other inspections, tests, surveillance, corrosion control and
corrosion-control surveys, and information related to the potential consequences of a pipeline
failure on the operator’s HCAs. This analysis then forms the basis for addressing anomalies on
the pipeline and developing preventive and mitigative measures to reduce the likelihood and
consequences of potential releases. In many ways, this “information analysis” lies at the heart of
integrity management because it not merely compiles various risk data, but actually analyzes and
integrates all available information to identify and address the unique risks affecting the integrity
of each pipeline segment.
In this case, Respondent could not produce records showing that this sort of integrative
information analysis had actually taken place. For example, Respondent had in-inline inspection
results, threat-analysis documents, corrosion-rate calculations, and other data, but there was no
record explaining and summarizing how Centurion had actually taken this data to reach certain
conclusions about risk and how the company had gone about implementing an effective
integrity-management strategy.
Accordingly, based upon a review of all of the evidence, I find that Respondent violated 49
C.F.R. § 195.452(l)(1)(ii) by failing to maintain, for the useful life of the pipeline, records that
demonstrate compliance with the requirements of § 195.452(f) and (g).
Item 4: The Notice alleged that Respondent violated 49 C.F.R. § 195.563, which states, in
relevant part:
§ 195.563 Which pipelines must have cathodic protection?
(a) Each buried or submerged pipeline that is constructed, relocated,
replaced, or otherwise changed after the applicable date in § 195.401(c)
must have cathodic protection. The cathodic protection must be in
6 Response, at 1-2.
7 See 49 C.F.R. § 194.450 for the definition of “High Consequence Area.”



CPF No. 4-2018-5013
Page 5
operation no later than 1 year after the pipeline is constructed, relocated,
replaced, or otherwise changed, as applicable.
(b) . . . .
(d) Bare pipelines, breakout tank areas, and buried pumping station
piping must have cathodic protection in places where regulations in effect
before January 28, 2002 required cathodic protection as a result of electrical
inspections. . . .
The Notice alleged that Respondent violated 49 C.F.R. § 195.563 by failing to have cathodic
protection (CP) on five of its breakout tanks. Specifically, the Notice alleged that Centurion
installed vapor corrosion inhibitors (VCIs) with electric resistance (ER) probes for monitoring
the corrosion rate between the floors of five breakout tanks (Tank Nos. 6689, 7264, 7265, 6719,
and 1878). The Notice alleged that while Centurion had CP on the old tank floors, the use of
VCI with ER probes could not serve as a substitute for CP on the new tank floors.
In its Response, Centurion contested the allegation of violation only with respect to one of its
tanks, No. 6719. The company argued that this particular tank was a single-bottom tank that
already had CP in place. Subsequently, during a September 26, 2018 in-person meeting with the
Region, Centurion demonstrated that Tank Nos. 7264 and 7265 were reconstructed as single-
bottom tanks with CP already in place. Respondent did not contest the allegation of violation
with respect to Tank Nos. 6689 and 1878, but “[sought] to clarify the proposed compliance
order” as discussed below.8
Accordingly, based upon a review of all of the evidence, I find that Respondent violated 49
C.F.R. § 195.563 by failing to have CP on two breakout tanks (Tank Nos. 6689 and 1878), but
withdraw the allegation of violation with regard to the remaining three tanks (Tank Nos. 6719,
7264, and 7265).
The above findings of violation will be considered prior offenses in any subsequent enforcement
action taken against Respondent.
ASSESSMENT OF PENALTY
Under 49 U.S.C. § 60122, Respondent is subject to an administrative civil penalty not to exceed
$200,000 per violation for each day of the violation, up to a maximum of $2,000,000 for any
related series of violations.9 In determining the amount of a civil penalty under 49 U.S.C.
§ 60122 and 49 C.F.R. § 190.225, I must consider the following criteria: the nature,
circumstances, and gravity of the violation, including adverse impact on the environment; the
degree of Respondent’s culpability; the history of Respondent’s prior offenses; any effect that
the penalty may have on its ability to continue doing business; and the good faith of Respondent
8 Response, at 2.
9 These amounts are adjusted annually for inflation. See 49 C.F.R. § 190.223; Revisions to Civil Penalty Amounts,
83 Fed. Reg. 60732, 60744 (Nov. 27, 2018).



CPF No. 4-2018-5013
Page 6
in attempting to comply with the pipeline safety regulations. In addition, I may consider the
economic benefit gained from the violation without any reduction because of subsequent
damages, and such other matters as justice may require. The Notice proposed a total civil
penalty of $40,300 for the violation cited in Item 1 above.10
Item 1: The Notice proposed a civil penalty of $40,300 for Respondent’s violation of 49 C.F.R.
§ 195.583(a), for failing to inspect each onshore pipeline or portion of pipeline that is exposed to
the atmosphere for evidence of atmospheric corrosion at least once every 3 calendar years, but
with intervals not exceeding 39 months. In its Response, Centurion noted it had entered annual
atmospheric corrosion inspections into its Maximo electronic work-scheduling system that goes
beyond the regulatory requirement. In consideration of this corrective action, Centurion
requested full mitigation of the proposed penalty. I find that elimination of the penalty for this
item is not appropriate because Respondent failed to comply with the regulatory requirement as
of the date of the PHMSA inspection and did not come into compliance until after PHMSA had
discovered the violation. Accordingly, having reviewed the record and considered the
assessment criteria, I assess Respondent a civil penalty of $40,300 for violation of 49 C.F.R.
§ 195.583(a).
Payment of the civil penalty must be made within 20 days of service. Federal regulations (49
C.F.R. § 89.21(b)(3)) require such payment to be made by wire transfer through the Federal
Reserve Communications System (Fedwire), to the account of the U.S. Treasury. Detailed
instructions are contained in the enclosure. Questions concerning wire transfers should be
directed to: Financial Operations Division (AMK-325), Federal Aviation Administration, Mike
Monroney Aeronautical Center, 6500 S MacArthur Blvd, Oklahoma City, Oklahoma 79169.
The Financial Operations Division telephone number is (405) 954-8845.
Failure to pay the $40,300 civil penalty will result in accrual of interest at the current annual rate
in accordance with 31 U.S.C. § 3717, 31 C.F.R. § 901.9 and 49 C.F.R. § 89.23. Pursuant to
those same authorities, a late penalty charge of six percent (6%) per annum will be charged if
payment is not made within 110 days of service. Furthermore, failure to pay the civil penalty
may result in referral of the matter to the Attorney General for appropriate action in a district
court of the United States.
COMPLIANCE ORDER
The Notice proposed a compliance order with respect to Items 3 and 4 in the Notice for
violations of 49 C.F.R. §§ 195.452(l)(1)(ii) and 195.563, respectively. Under 49 U.S.C.
§ 60118(a), each person who engages in the transportation of hazardous liquids or who owns or
operates a pipeline facility is required to comply with the applicable safety standards established
under chapter 601.
With regard to the violation of § 195.452(l)(1)(ii) (Item 3), the Director has indicated that
10 Although the Notice inadvertently failed to specify that the proposed civil penalty applied to the alleged violation
of § 195.583(a) (Item 1) and no other, the Violation Report shows that the penalty was applicable solely to Item 1.
(Violation Report, at 6).



CPF No. 4-2018-5013
Page 7
Respondent has taken action to satisfy the terms of the proposed compliance order. Therefore, it
is unnecessary to include the terms of the proposed compliance order associated with this Item in
this Order.
With regard to the violation of § 195.563 (Item 4), Respondent argued that the compliance terms
should be withdrawn with respect to Tank Nos. 6719, 7264, and 7265 because they are single-
bottom tanks with cathodic protection in place. For the reasons stated above, I withdraw the
compliance terms associated with these three tanks.
Additionally, Respondent argued that the remaining compliance terms should be modified to
allow Centurion to take periodic CP readings directly around Tank Nos. 6689 and 1878 and not
to apply CP directly to the bottom of the tanks. Respondent noted that although many of the CP
readings taken on the tanks are below the standard -0.850 volt criteria, they are at least 100 mv
more negative than the native reading, demonstrating the safety of the tanks. Respondent also
stated that additional CP for these two tanks is unnecessary for the safety of the tanks because of
the presence of a vapor corrosion inhibitor (VCI) on the second bottom of the tanks and the deep
well anodes in the area of the tanks.
Having considered Respondent’s proposal, I find that it must be rejected. These two tanks have
double bottoms, with the old bottom forming a shield that prevents CP from reaching the new
bottom to protect against corrosion. CP measurements taken around the tanks, as proposed by
Respondent, would measure the CP on the old tank bottoms. However, the new tank bottoms are
not protected using CP and the presence of the VCI system does not substitute for a sacrificial
anode as it is unassociated with the CP system, which is absent on the new bottoms.
Pursuant to the authority of 49 U.S.C. § 60118(b) and 49 C.F.R. § 190.217, Respondent is
ordered to take the following actions to ensure compliance with the pipeline safety regulations
applicable to its operations:
1. With respect to the violation of § 195.563 (Item 4), Respondent must submit a
plan to bring Tank Nos. 6689 and 1878 into compliance within 30 days of receipt of
the Final Order; and
2. With respect to the violation of § 195.563 (Item 4), Respondent must submit to
the Director, Southwest Region, records demonstrating compliance with § 195.563 no
later than six months from the issuance of the Final Order.
The Director may grant an extension of time to comply with any of the required items upon a
written request timely submitted by the Respondent and demonstrating good cause for an
extension.
It is requested (not mandated) that Centurion maintain documentation of the safety improvement
costs associated with fulfilling this Compliance Order and submit the total to the Director. It is
requested that these costs be reported in two categories: (1) total cost associated with
preparation/revision of plans, procedures, studies and analyses; and (2) total cost associated with
replacements, additions and other changes to pipeline infrastructure.



CPF No. 4-2018-5013
Page 8
Failure to comply with this Order may result in the administrative assessment of civil penalties
not to exceed $200,000, as adjusted for inflation (49 C.F.R. § 190.223), for each violation for
each day the violation continues or in referral to the Attorney General for appropriate relief in a
district court of the United States.
WARNING ITEMS
With respect to Items 2 and 5, the Notice alleged probable violations of Part 195 but did not
propose a civil penalty or compliance order for these items. Therefore, these are considered to
be warning items. The warnings were for:
49 C.F.R. § 195.61 (Item 2) ─ Respondent’s alleged failure to submit geospatial
data to PHMSA for the 2015 and 2016 calendar years, on or before June 15,
representing assets as of December 31, of the previous year; and
49 C.F.R. § 195.505 (Item 5) ─ Respondent’s alleged failure to follow its own
written operator-qualification program.
Centurion presented information in its Response showing that it had taken certain actions to
address the cited items. If OPS finds a violation of any of these items in a subsequent inspection,
Respondent may be subject to future enforcement action.
Under 49 C.F.R. § 190.243, Respondent may submit a Petition for Reconsideration of this Final
Order to the Associate Administrator, Office of Pipeline Safety, PHMSA, 1200 New Jersey
Avenue, SE, East Building, 2nd Floor, Washington, DC 20590, with a copy sent to the Office of
Chief Counsel, PHMSA, at the same address, no later than 20 days after receipt of service of this
Final Order by Respondent. Any petition submitted must contain a statement of the issue(s) and
meet all other requirements of 49 C.F.R. § 190.243. The filing of a petition automatically stays
the payment of any civil penalty assessed. The other terms of the order, including corrective
action, remain in effect unless the Associate Administrator, upon request, grants a stay.
The terms and conditions of this Final Order are effective upon service in accordance with 49
C.F.R. § 190.5.
August 8, 2019
___________________________________ __________________________
Alan K. Mayberry Date Issued
Associate Administrator
for Pipeline Safety

420185013_NOPV PCP PCO_07232018_text.pdf

NOTICE OF PROBABLE VIOLATION
PROPOSED CIVIL PENALTY
and
PROPOSED COMPLIANCE ORDER
CERTIFIED MAIL - RETURN RECEIPT REQUESTED
July 23, 2018
Michael Morgan
GM Operations
Centurion Pipeline L.P.
5 Greenway Plaza, Suite 110
Houston, TX, 77046
CPF 4-2018-5013
Dear Mr. Morgan:
On May 1, 2017 through February 23, 2018, a representative of the Pipeline and Hazardous
Materials Safety Administration (PHMSA), Office of Pipeline Safety (OPS), pursuant to Chapter
601 of 49 United States Code (U.S.C.) inspected your procedures for operations and maintenance
in Houston and Midland Texas.
As a result of the inspection, it is alleged that you have committed probable violations of the
Pipeline Safety Regulations, Title 49, Code of Federal Regulations (CFR). The items inspected
and the probable violation(s) are:
1. §195.583 – What must I do to monitor atmospheric corrosion control?
(a) You must inspect each pipeline or portion of pipeline that is exposed to the
atmosphere for evidence of atmospheric corrosion, as follows:



If the pipeline is
located:
Onshore Offshore 2. 3. Then the frequency of inspection is:
At least once every 3 calendar years, but with intervals not
exceeding 39 months
At least once each calendar year, but with intervals not exceeding
15 months
Centurion Pipeline failed to inspect the exposed portions of its pipeline between Bretch
and El Reno, Oklahoma for evidence of atmospheric corrosion as required by 49 CFR
§195.583. Atmospheric corrosion inspections are required at least once every 3 calendar
years not to exceed 39 months, and the last atmospheric corrosion inspection on the Bretch
to El Reno portion of the pipeline was performed in April 1, 2013. Based on the last
inspection date, the maximum interval for the next inspection would have been July 1,
2016.
The atmospheric inspection was not performed until October 2017 following the PHMSA
inspection of the pipeline system.
§195.61 – National Pipeline Mapping system
(a) Each operator of a hazardous liquid pipeline facility must provide the following
geospatial data to PHMSA for that facility.
(b) This information must be submitted each year, on or before June 15, representing
assets as of December 31, of the previous year. If no changes have occurred since
the previous year’s submission, the operator must refer to the information
provided in the NPMS Operator Standards manual available at
www.npms.phmsa.dot.gov or contact the PHMSA Geographic Information
Systems Manager at (202)366-4595.
Centurion failed to submit NPMS data on or before June 15th for both the 2015 and 2016
calendar year data submittals. Letters acknowledging receipt of the NPMS data submitted
by Centurion’s personnel to PHMSA in 2016 and 2017 indicates that the submission dates
were June 21, 2016 for CY2015 and June 30, 2017 for CY2016.
§195.452(l)(1)(ii) –What records must an operator keep to demonstrate compliance?
(1) An operator must maintain, for the useful life of the pipeline, records that
demonstrate compliance with the requirements of this subpart. At a minimum, an
operator must maintain the following records for review during an inspection:
2



4. (ii) Documents to support the decisions and analyses, including any modifications,
justifications, deviations and determinations made, variances, and actions taken, to
implement and evaluate each element of the integrity management program
listed in paragraph (f) of this section.
Centurion Pipeline failed to maintain records documenting the information analysis
required by 49 CFR §195.452(g). While the data required under 195.452(g) for the
analysis was gathered and entered into the mapping system, there is no record to document
an analysis carried out by the Subject Matter Expert (SME.)
Centurion was unable to provide records for review during the inspection of the
information analysis carried out to support the pipeline integrity evaluation decisions.
§195.563 – Which pipelines must have cathodic protection?
(a) Each buried or submerged pipeline that is constructed, relocated, replaced, or
otherwise changed after the applicable date in §195.401(c) must have cathodic
protection. The cathodic protection must be in operation no later than 1 year after
the pipeline is constructed, relocated, replaced, or otherwise changed, as
applicable.
(d) Bare pipelines, breakout tank areas, and buried pumping station piping must
have cathodic protection in places where regulations in effect before January 28,
2002 required cathodic protection as a result of electrical inspections.
Centurion Pipeline failed to provide cathodic protection to protect 5 breakout tanks in
accordance with §195.563 where new tank bottoms were installed. The tanks include:
Tank # 6689 Slaughter Station
Tanks #7264 and 7265 Artesia Station
Tank #6719 Wasson Station
Tank #1878 Seminole Station.
Centurion installed vapor corrosion inhibitors (VCI) with electric resistance (ER) probes
for monitoring the corrosion rates between the tank floors. The use of VCI with ER probes
for corrosion control and monitoring is a not considered cathodic protection as required by
§195.563(d) and 195.565(section 7.2.4.3 of ANSI/API RP 651).
§195.563 and §195.565 require cathodic protection and its installation and does not permit
the use of VCI as a substitute for cathodic proection. In each of these tanks, Centurion has
cathodic protection on the old tank floor but does not have cathodic protection on the new
tank floors.
3



5. §195.505 – Qualification Program
Each operator shall have and follow a written qualification program. The program
shall include provisions:
(a) Identify covered tasks
Centurion Pipeline, L.P failed to follow section 2.2 of their written operator qualification
plan that prescribes the four-part test components as described in §195.501. Centurion
failed to determine if personnel performing tasks needed to be evaluated and if the task
should have been classified as a covered task. Conditions 1,2,3 and 4 in section 2.2 of the
OQ plan required that any construction type activities to be carried out on a facility used
in the transportation of hazardous liquids needs to be classified as a covered task and the
individuals carrying out this task need to be evaluated prior to performing the task.
Centurion did not identify the installation, inspection and maintenance of the Vapor
Corrosion Inhibitor systems on 5 of it’s regulated breakout tanks prior to the installation
and monitoring of the VCI systems on the breakout tanks.
Proposed Civil Penalty
Under 49 U.S.C. § 60122 and 49 CFR § 190.223, you are subject to a civil penalty not to exceed
$209,002 per violation per day the violation persists, up to a maximum of $2,090,022 for a related
series of violations. For violations occurring prior to November 2, 2015, the maximum penalty
may not exceed $200,000 per violation per day, with a maximum penalty not to exceed $2,000,000
for a related series of violations. The Compliance Officer has reviewed the circumstances and
supporting documentation involved in the above probable violation(s) and has recommended that
you be preliminarily assessed a civil penalty of $40,300.
Warning Items
With respect to items 2 and 5 we have reviewed the circumstances and supporting documents
involved in this case and have decided not to conduct additional enforcement action or penalty
assessment proceedings at this time. We advise you to promptly correct this item. Failure to do
so may result in additional enforcement action.
Proposed Compliance Order
With respect to items 3 and 4 pursuant to 49 U.S.C. § 60118, the Pipeline and Hazardous Materials
Safety Administration proposes to issue a Compliance Order to Centurion Pipeline L.P. Please
refer to the Proposed Compliance Order, which is enclosed and made a part of this Notice.
4



Response to this Notice
Enclosed as part of this Notice is a document entitled Response Options for Pipeline Operators in
Compliance Proceedings. Please refer to this document and note the response options. All
material you submit in response to this enforcement action may be made publicly available. If you
believe that any portion of your responsive material qualifies for confidential treatment under 5
U.S.C. 552(b), along with the complete original document you must provide a second copy of the
document with the portions you believe qualify for confidential treatment redacted and an
explanation of why you believe the redacted information qualifies for confidential treatment under
5 U.S.C. 552(b).
Following the receipt of this Notice, you have 30 days to submit written comments, or request a
hearing under 49 CFR § 190.211. If you do not respond within 30 days of receipt of this Notice,
this constitutes a waiver of your right to contest the allegations in this Notice and authorizes the
Associate Administrator for Pipeline Safety to find facts as alleged in this Notice without further
notice to you and to issue a Final Order. If you are responding to this Notice, we propose that you
submit your correspondence to my office within 30 days from receipt of this Notice. This period
may be extended by written request for good cause.
In your correspondence on this matter, please refer to CPF 4-2018-5013 and, for each document
you submit, please provide a copy in electronic format whenever possible.
Sincerely,
Mary L. McDaniel, P.E
Director, Southwest Region
Pipeline and Hazardous Materials Safety Administration
Enclosures: Proposed Compliance Order
Response Options for Pipeline Operators in Compliance Proceedings
5



PROPOSED COMPLIANCE ORDER
Pursuant to 49 United States Code § 60118, the Pipeline and Hazardous Materials Safety
Administration (PHMSA) proposes to issue to Centurion Pipeline, L.P a Compliance Order
incorporating the following remedial requirements to ensure the compliance of Centurion Pipeline,
L.P with the pipeline safety regulations:
1. 2. 3. 4. In regard to Item Number 3 of the Notice pertaining to maintenance of records for
each analysis carried out during the information analysis activity as required under
the regulation cited, Centurion Pipeline, L.P shall ensure that records of all analysis
carried out as part of the information analysis under the integrity management
program are maintained and made available for review during the next scheduled
PHMSA inspection.
In regard to item number 4 of the notice pertaining to providing cathodic protection
to the new floors of the breakout tanks for corrosion control. Centurion Pipeline,
L.P shall submit a plan to bring the affected tanks into compliance within 30 days
from the receipt of the final order.
Records showing compliance with Item 4 shall be submitted to PHMSA no later
than 6 months from the issuance of the Final Order in this case.
It is requested (not mandated) that Centurion Pipeline, L.P. maintain documentation
of the safety improvement costs associated with fulfilling this Compliance Order
and submit the total to Mary McDaniel, Director, Southwest Region, Pipeline and
Hazardous Materials Safety Administration. It is requested that these costs be
reported in two categories: 1) total cost associated with preparation/revision of
plans, procedures, studies and analyses, and 2) total cost associated with
replacements, additions and other changes to pipeline infrastructure.
6

## Provenance

- Official: Yes
- Source: <https://primis.phmsa.dot.gov/enforcement-data/case/420185013>
- Source ID: `phmsa-enforcement`
- SHA-256: `b0763f4162b5bc05e221d55c7fd0f9189e0ee6eea2588a65ff1ef6553849b253`
- Retrieved: 2026-08-20T04:44:44.458Z
- Exported: 2026-08-22T18:26:10.634Z
- Document slug: `phmsa-enforcement-420185013`

### Source metadata

```json
{
  "cpf": "420185013",
  "operator": "CENTURION PIPELINE L.P.",
  "region": "Southwest",
  "pipelineType": "INTERSTATE LIQUID ONSHORE",
  "caseStatus": "CLOSED",
  "citedSections": [
    "195.452(l)(1)(ii)",
    "195.505(a)",
    "195.563(a)",
    "195.563(d)",
    "195.583(a)",
    "195.61"
  ],
  "dataAsOf": "08/04/2026 12PM",
  "caseDataAsOf": "2026-08-04",
  "attachmentCount": 7,
  "attachments": [
    {
      "name": "420185013_Closure Letter_09092020.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420185013/420185013_Closure%20Letter_09092020.pdf",
      "bytes": 225040,
      "category": "agency_document"
    },
    {
      "name": "420185013_Closure Letter_09092020_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420185013/420185013_Closure%20Letter_09092020_text.pdf",
      "bytes": 77345,
      "category": "agency_document"
    },
    {
      "name": "420185013_Final Order_08082019.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420185013/420185013_Final%20Order_08082019.pdf",
      "bytes": 2546763,
      "category": "agency_document"
    },
    {
      "name": "420185013_Final Order_08082019_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420185013/420185013_Final%20Order_08082019_text.pdf",
      "bytes": 173851,
      "category": "agency_document"
    },
    {
      "name": "420185013_NOPV PCP PCO_07232018.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420185013/420185013_NOPV%20PCP%20PCO_07232018.pdf",
      "bytes": 123184,
      "category": "agency_document"
    },
    {
      "name": "420185013_NOPV PCP PCO_07232018_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420185013/420185013_NOPV%20PCP%20PCO_07232018_text.pdf",
      "bytes": 136595,
      "category": "agency_document"
    },
    {
      "name": "420185013_Operator Response to the Notice_09242018.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420185013/420185013_Operator%20Response%20to%20the%20Notice_09242018.pdf",
      "bytes": 123561,
      "category": "party_submission"
    }
  ],
  "extractedAgencyDocumentCount": 3,
  "attachmentPolicy": "Official attachment links are retained. Agency-issued documents may also include a verified local PDF and page-level text representation.",
  "jurisdiction": "US",
  "operatorName": "CENTURION PIPELINE L.P."
}
```
