# HARVEST MIDSTREAM COMPANY — Notice of Probable Violation

**Citation:** CPF 420185016  
**Type / status:** enforcement / historical  
**Agency:** Pipeline and Hazardous Materials Safety Administration  
**Effective:** Not stated  
**Published:** 2018-08-31

CLOSED notice of probable violation citing 194.107(c)(1)(ix), 194.121(a), 195.402(c)(13), 195.402(c)(5), 195.402(d)(5), 195.403(b), 195.403(c).

## Document text

Notice of Probable Violation involving HARVEST MIDSTREAM COMPANY. PHMSA's enforcement data identifies the cited regulations as 194.107(c)(1)(ix),  194.121(a),  195.402(c)(13),  195.402(c)(5),  195.402(d)(5),  195.403(b),  195.403(c). The case was opened on 2018-08-31 and is reported as closed as of 2020-02-04. Proposed civil penalty: $88,300. Assessed civil penalty: $88,300. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

420185016_Closure Letter_02042020.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420185016/420185016_Closure%20Letter_02042020.pdf

420185016_Closure Letter_02042020_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420185016/420185016_Closure%20Letter_02042020_text.pdf

420185016_Final Order_09122019.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420185016/420185016_Final%20Order_09122019.pdf

420185016_Final Order_09122019_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420185016/420185016_Final%20Order_09122019_text.pdf

420185016_NOPV PCP PCO_08312018.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420185016/420185016_NOPV%20PCP%20PCO_08312018.pdf

420185016_NOPV PCP PCO_08312018_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420185016/420185016_NOPV%20PCP%20PCO_08312018_text.pdf

420185016_Operator Response to Notice_12182018.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420185016/420185016_Operator%20Response%20to%20Notice_12182018.pdf

420185016_NOPV PCP PCO_08312018_text.pdf

NOTICE OF PROBABLE VIOLATION
PROPOSED CIVIL PENALTY
and
PROPOSED COMPLIANCE ORDER
CERTIFIED MAIL - RETURN RECEIPT REQUESTED
August 31, 2018
Steve Jacobs
President
Harvest Pipeline Company
1111 Travis Street
Houston, TX 77002
CPF 4-2018-5016
Dear Mr. Jacobs:
Between November 3, 2016 and January 27, 2017, representatives of the Pipeline and Hazardous
Materials Safety Administration (PHMSA), Office of Pipeline Safety (OPS), pursuant to Chapter
601 of 49 United States Code inspected your Eugene Island Facility in New Iberia, LA and the
Southwest Pass 24 Oil Terminal Facility in Venice, LA and the Harvest Pipeline Company records
in Houston, TX.
As a result of the inspection, it is alleged that you have committed probable violations of the
Pipeline Safety Regulations, Title 49, Code of Federal Regulations. The items inspected and the
probable violations are:
1. §194.107 General response plan requirements
(c) Each response plan must include:
(1) A core plan consisting of-
(ix) Drill program-an operator will satisfy the requirement for a drill
program by following the National Preparedness for Response Exercise
Program (PREP) guidelines. An operator choosing not to follow PREP



guidelines must have a drill program that is equivalent to PREP. The
operator must describe the drill program in the response plan and OPS
will determine if the program is equivalent to PREP.
Harvest Pipeline Company failed to follow their Facility Response Plan Section 1 Introduction and
Section 4 Evaluation. Harvest Pipeline’s drill program references the PREP Guidelines; however,
their records demonstrate that they did not follow the Guidelines when they conducted their drills.
Records provided by Harvest did not consistently document core components exercised, lessons
learned, or signatures of authorized representatives.
2. §194.121 Response plan review and update procedures
(a) Each operator shall update its response plan to address new or different operating
conditions or information. In addition, each operator shall review its response plan
in full at least every 5 years from the date of the last submission or the last approval
as follows:
(1) For substantial harm plans, an operator shall resubmit its response plan
to OPS every 5 years from the last submission date.
(2) For significant and substantial harm plans, an operator shall resubmit
every 5 years from the last approval date.
Harvest Pipeline failed to resubmit its response plan to PHMSA within 5 years from the date of
the last submission or the last approval. The previous response plan was submitted and approved
in 2010, and the current response plan should have been submitted/approved at the 5-year mark in
2015, but was not submitted until September 2016.
3. §195.402 Procedural manual for operations, maintenance, and emergencies
(c) Maintenance and normal operations. The manual required by paragraph (a) of
this section must include procedures for the following to provide safety during
maintenance and normal operations:
(5) Analyzing pipeline accidents to determine their causes.
Harvest Pipeline failed to follow their procedure, Liquid O&M Manual, P-195.402c5: Accident
and Incident Investigation for conducting investigations to determine the probable cause of an
accident. The procedures state “The investigation process is the same regardless of the level of
investigation to be used. What is different is the investigation method or methods that will be used
to identify cause and implement safeguards and corrective actions.” Harvest Pipeline failed to
perform an analysis and document their findings for two reported accidents (PHMSA Form
F7000.1 ID’s 20160310 and 20150070.)
2



4. §195.402 Procedural manual for operations, maintenance, and emergencies
(c) Maintenance and normal operations. The manual required by paragraph (a) of
this section must include procedures for the following to provide safety during
maintenance and normal operations:
(13) Periodically reviewing the work done by operator personnel to determine
the effectiveness of the procedures used in normal operation and maintenance
and taking corrective action where deficiencies are found.
Harvest Pipeline failed to follow their procedure, Liquid O&M Manual, P-195.402c13: Review of
Work done by Operator. The procedure states “Each supervisor will review the work performed
by the operations personnel reporting to him to ensure that the procedures in use are adequate and
any deficiencies or recommendations are reported. This review should be documented on form F-
195.402(c)(13) Review of Work Done by Operator.” Harvest Pipeline could not provide any
completed copies of the form or confirmation that the review had been completed.
5. §195.402 Procedural manual for operations, maintenance, and emergencies
(d) Abnormal operation. The manual required by paragraph (a) of this section must
include procedures for the following to provide safety when operating design limits
have been exceeded;
(5) Periodically reviewing the response of operator personnel to determine the
effectiveness of the procedures controlling abnormal operation and taking
corrective action where deficiencies are found.
Harvest Pipeline failed to follow their procedure, Liquid Operations & Maintenance Manual P-
195.402d: Abnormal Operations to document the periodic review required by §195.402(d)(5). The
procedure states “Periodically, or as needed (after a condition has occurred), members of the
Harvest Control Center Management Team and or Lead Controllers designated shall review the
response of control center personnel to ensure the effectiveness of the procedures controlling an
abnormal condition.” Harvest Pipeline could not provide the required documentation to show that
this procedure was followed. In Table 3: Necessary Compliance Records, it shows that Review of
Personnel Response to Abnormal Operations records will be kept for 3 years. Harvest did not
produce any records at the time of the inspection, but stated that the Controller Supervisor conducts
verbal reviews.
6. §195.403 Emergency Response Training
(b) At the intervals not exceeding 15 months, but at least once each calendar year,
each operator shall:
(1) Review with personnel their performance in meeting the objectives of the
emergency response training program set forth in paragraph (a) of this
section; and
(2) Make appropriate changes to the emergency response training program as
3



necessary to ensure that it is effective.
Harvest Pipeline failed to document and retain records when following their procedure, Liquid
Operations & Maintenance Manual P-195.403: Training. The procedure states “At the intervals
not exceeding 15 months, but at least once each calendar year, each operator shall: 1. Review with
personnel their performance in meeting the objectives of the emergency response training program
and review employee activities to determine whether the procedure was effectively followed in
each emergency.”
7. §195.403 Emergency Response Training
(c) Each operator shall require and verify that its supervisors maintain a thorough
knowledge of that portion of the emergency response procedures established under
195.402 for which they are responsible to ensure compliance.
Harvest Pipeline failed to document their verification of supervisors’ knowledge of emergency
response procedures in accordance with their procedure, Liquid Operations & Maintenance
Manual P-195.403: Training. The procedure states that “A verification of supervisor knowledge
is required, which should be documented on form (F-195.403c).” Harvest Pipeline has not been
consistently documenting their verification of supervisor knowledge. The Operator had one form,
dated 12/1/16 (The HQ inspection was conducted Nov 28th
– Dec 2nd 2016). The form was not
completely filled out and did not include what topics were reviewed. There were no additional
records.
Proposed Civil Penalty
Under 49 U.S.C. § 60122 and 49 CFR § 190.223, you are subject to a civil penalty not to exceed
$209,002 per violation per day the violation persists up to a maximum of $2,090,022 for a related
series of violations. For violations occurring prior to November 2, 2015, the maximum penalty
may not exceed $200,000 per violation per day, with a maximum penalty not to exceed $2,000,000
for a related series of violations. The Compliance Officer has reviewed the circumstances and
supporting documentation involved in the above probable violations and has recommended that
you be preliminarily assessed a civil penalty of $88,300 as follows:
Item number PENALTY
3 $19,300
4 $19,000
5 $15,500
6 $19,000
7 $15,500
4



Warning Items
With respect to item 2, PHMSA reviewed the circumstances and supporting documents involved
in this case and have decided not to conduct additional enforcement action or penalty assessment
proceedings at this time. We advise you to promptly correct this item. Failure to do so may result
in additional enforcement action.
Proposed Compliance Order
With respect to items 1, 3, 4, 5, and 6, pursuant to 49 United States Code § 60118, the Pipeline
and Hazardous Materials Safety Administration proposes to issue a Compliance Order to Harvest
Pipeline Company. Please refer to the Proposed Compliance Order, which is enclosed and made
a part of this Notice.
Response to this Notice
Enclosed as part of this Notice is a document entitled Response Options for Pipeline Operators in
Compliance Proceedings. Please refer to this document and note the response options. All
material you submit in response to this enforcement action may be made publicly available. If you
believe that any portion of your responsive material qualifies for confidential treatment under 5
U.S.C. 552(b), along with the complete original document you must provide a second copy of the
document with the portions you believe qualify for confidential treatment redacted and an
explanation of why you believe the redacted information qualifies for confidential treatment under
5 U.S.C. 552(b). If you do not respond within 30 days of receipt of this Notice, this constitutes a
waiver of your right to contest the allegations in this Notice and authorizes the Associate
Administrator for Pipeline Safety to find facts as alleged in this Notice without further notice to
you and to issue a Final Order.
In your correspondence on this matter, please refer to CPF 4-2018-5016 and for each document
you submit, please provide a copy in electronic format whenever possible.
Sincerely,
Mary L. McDaniel, P.E.
Director, Southwest Region
Pipeline and Hazardous Materials Safety Administration
Enclosures: Proposed Compliance Order
Response Options for Pipeline Operators in Compliance Proceedings
5



PROPOSED COMPLIANCE ORDER
Pursuant to 49 United States Code § 60118, the Pipeline and Hazardous Materials Safety
Administration (PHMSA) proposes to issue to Harvest Pipeline Company a Compliance Order
incorporating the following remedial requirements to ensure the compliance of Harvest Pipeline
Company with the pipeline safety regulations:
1. 2. 3. 4. 5. 6. In regard to Item Number 1 of the Notice pertaining to satisfying the requirements
for a drill program by following the National Preparedness for Response Exercise
Program (PREP) Guidelines, Harvest Pipeline Company must, upon completion of
their emergency response drills, perform an objective evaluation of personnel,
procedures, drill scenarios, and other factors, where lessons learned are used in
response plan revisions. This must be done in accordance with their Facility
Response Plan Guidelines- Section 7.3.2: Certification to include a signature of an
authorized representative.
In regard to Item Number 3 of the Notice pertaining to the failure to analyze
pipeline accidents to determine their causes, Harvest Pipeline Company must
amend their procedure to include analysis techniques or methods to analyze
pipeline accidents to determine their causes. Section B: Conduct the Investigation,
does not provide detail of how to actually conduct an accident investigation other
than to refer to a diagram that identifies the organization flow of conducting an
investigation, yet there is no diagram.
In regard to Item Number 4 of the Notice pertaining to review of work done by
operator personnel to determine the effectiveness of the procedures used in normal
operation and maintenance and taking corrective action where deficiencies are
found. Harvest Pipeline must begin to conduct reviews of operations personnel and
document those reviews on Harvest Pipeline Form F-195.402(c)(13) titled Review
of Work Done by Operator. This must be done in accordance with their Liquid
O&M Manual P-195.402c13: Review of Work Done by Operator.
In regard to Item Number 5 of the Notice pertaining to review of response of
operator personnel to determine the effectiveness of the procedures controlling
abnormal operation and taking corrective action where deficiencies are found.
Harvest Pipeline failed to provide documentation of reviews of the response of
control center personnel to ensure the effectiveness of procedures controlling
abnormal conditions. Harvest must begin documenting their verbal reviews of
responses of control center personnel for abnormal conditions. This must be done
in accordance with their Liquid O&M Manual P-195.402d: Abnormal Operations.
In regard to Item Number 6 of the Notice pertaining to review of emergency
personnel performance in meeting the objectives of the emergency response
training program. Harvest Pipeline failed to provide documentation of reviews of
emergency personnel performance. Harvest must conduct reviews of emergency
personnel performance and document these reviews at the required interval. This
must be done in accordance with their Liquid O&M Manual P-195.403: Training.
Aforementioned to be accomplished within 30 days following receipt of the Final
Order.
6



7. It is requested (not mandated) that Harvest Pipeline Company maintain
documentation of the safety improvement costs associated with fulfilling this
Compliance Order and submit the total to Mary L. McDaniel, Director, Southwest
Region, Pipeline and Hazardous Materials Safety Administration. It is requested
that these costs be reported in two categories: 1) total cost associated with
preparation/revision of plans, procedures, studies and analyses, and 2) total cost
associated with replacements, additions and other changes to pipeline
infrastructure.
7

420185016_Closure Letter_02042020_text.pdf

CERTIFIED MAIL - RETURN RECEIPT REQUESTED
February 4, 2020
Jason Rebrook
Chief Executive Officer
Harvest Midstream Company
1111 Travis Street
Houston, Texas 77002
CPF 4-2018-5016
Dear Mr. Rebrook:
On September 12, 2019, the Pipeline and Hazardous Materials Safety Administration (PHMSA)
issued to Harvest Midstream Company a Final Order in the above-referenced case. This Order
included a Compliance Order and Civil Penalty assessment. Based on our review of the
documentation you provided and confirmation of payment of the civil penalty, it has been
determined that you have complied with the terms of this Order.
Accordingly, this case is now closed and no further action is contemplated with respect to the
matters involved in this case. Thank you for your cooperation in this matter.
Sincerely,
Mary L. McDaniel, P.E.
Director, Southwest Region
Pipeline and Hazardous Materials Safety Administration

420185016_Final Order_09122019_text.pdf

September 12, 2019
Mr. Jason Rebrook
Chief Executive Officer
Harvest Midstream Company
1111 Travis Street
Houston, Texas 77002
Re: CPF No. 4-2018-5016
Dear Mr. Rebrook:
Enclosed please find the Final Order issued in the above-referenced case. It makes findings of
violation, assesses a civil penalty of $88,300 and specifies actions that need to be taken by
Harvest Midstream Company to comply with the pipeline safety regulations. The penalty
payment terms are set forth in the Final Order. When the civil penalty has been paid and the
terms of the compliance order completed, as determined by the Director, Southwest Region, this
enforcement action will be closed. Service of the Final Order by certified mail is effective upon
the date of mailing, as provided under 49 C.F.R. § 190.5.
Thank you for your cooperation in this matter.
Sincerely,
Alan K. Mayberry
Associate Administrator
for Pipeline Safety
Enclosure
cc: Ms. Mary McDaniel, Director, Southwest Region, Office of Pipeline Safety, PHMSA
Mr. Troy Brown, Sr., Regulatory Compliance Specialist, Harvest Midstream Company,
1111 Travis Street, Houston, Texas 77002
Mr. Craig Murski, Integrity Manager, Harvest Midstream Company, 1111 Travis Street,
Houston, Texas 77002
CERTIFIED MAIL - RETURN RECEIPT REQUESTED



U.S. DEPARTMENT OF TRANSPORTATION
PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION
OFFICE OF PIPELINE SAFETY
WASHINGTON, D.C. 20590
____________________________________
In the Matter of )
Harvest Midstream Company, ) CPF No. 4-2018-5016
)
)
)
Respondent. )
____________________________________)
FINAL ORDER
From November 3, 2016 through January 27, 2017, pursuant to 49 U.S.C. § 60117,
representatives of the Pipeline and Hazardous Materials Safety Administration (PHMSA), Office
of Pipeline Safety (OPS), conducted an on-site pipeline safety inspection of the facilities and
records of Harvest Midstream Company (Harvest or Respondent). Specifically, PHMSA
inspected the Eugene Island Facility in New Iberia, Louisiana, the Southwest Pass 24 Oil
Terminal Facility in Venice, Louisiana, and records of the company in Houston, Texas. Harvest
transports and processes oil, natural gas and natural gas liquids across the United States, with
assets in Alaska, Louisiana, New Mexico, Ohio, Pennsylvania and Texas.1
As a result of the inspection, the Director, Southwest Region, OPS (Director), issued to
Respondent, by letter dated August 31, 2018, a Notice of Probable Violation, Proposed Civil
Penalty, and Proposed Compliance Order (Notice), which also included a warning pursuant to 49
C.F.R. § 190.205. In accordance with 49 C.F.R. § 190.207, the Notice proposed finding that
Harvest had committed seven violations of 49 C.F.R. Parts 194 and 195, and proposed assessing
a civil penalty of $88,300 for the alleged violations. The Notice also proposed ordering
Respondent to take certain measures to correct the alleged violations. The warning item required
no further action, but warned the operator to correct the probable violation or face possible future
enforcement action.
After requesting and receiving an extension of time to respond, Harvest responded to the Notice
by letter dated December 18, 2018 (Response). The company did not contest the allegations of
violation but provided information concerning the corrective actions it had taken and would take
in the future. Respondent did not request a hearing and therefore has waived its right to one.
1 Harvest website, available at http://www.harvestmidstream.com/ (last accessed June 24, 2019).



CPF No. 4-2018-5016
Page 2
FINDINGS OF VIOLATION
The Notice alleged that Respondent violated 49 C.F.R. Parts 194 and 195, as follows:
Item 1: The Notice alleged that Respondent violated 49 C.F.R. § 194.107(c)(1)(ix), which states:
§ 194.107 General response plan requirements.
(a) ….
(c) Each response plan must include:
(1) A core plan consisting of -
(i) ….
(ix) Drill program - an operator will satisfy the requirement for a
drill program by following the National Preparedness for Response
Exercise Program (PREP) guidelines. An operator choosing not to follow
PREP guidelines must have a drill program that is equivalent to PREP. The
operator must describe the drill program in the response plan and OPS will
determine if the program is equivalent to PREP.
The Notice alleged that Respondent violated 49 C.F.R. § 194.107(c)(1)(ix) by failing to follow
the PREP guidelines in its response plan. Specifically, the Notice alleged that Harvest did not
follow PREP guidelines when conducting drills, nor did the company consistently document core
components exercised, lessons learned, or signatures of authorized representatives.
Respondent did not contest this allegation of violation. Accordingly, based upon a review of all
of the evidence, I find that Respondent violated 49 C.F.R. § 194.107(c)(1)(ix) by failing to
follow PREP guidelines in its response plan.
Item 2: The Notice alleged that Respondent violated 49 C.F.R. § 194.121(a), which states:
§ 194.121 Response plan review and update procedures.
(a) Each operator shall update its response plan to address new or
different operating conditions or information. In addition, each operator
shall review its response plan in full at least every 5 years from the date of
the last submission or the last approval as follows:
(1) For substantial harm plans, an operator shall resubmit its response
plan to OPS every 5 years from the last submission date.
(2) For significant and substantial harm plans, an operator shall
resubmit every 5 years from the last approval date.
The Notice alleged that Respondent violated 49 C.F.R. § 194.121(a) by failing to timely resubmit
its response plan to OPS. Specifically, the Notice alleged that Harvest failed to resubmit its
response plan to OPS 5 years after the last plan was submitted and approved in 2010. Instead, of
submitting it in 2015, Harvest’s response plan was submitted in September 2016.
Respondent did not contest this allegation of violation. Accordingly, based upon a review of all
of the evidence, I find that Respondent violated 49 C.F.R. § 194.121(a) by failing to timely



CPF No. 4-2018-5016
Page 3
resubmit its response plan to OPS.
Item 3: The Notice alleged that Respondent violated 49 C.F.R. § 195.402(c)(5) which states:
§ 195.402 Procedural manual for operations, maintenance, and
emergencies.
(a) ….
(c) Maintenance and normal operations. The manual required by
paragraph (a) of this section must include procedures for the following to
provide safety during maintenance and normal operations:
(1) ….
(5) Analyzing pipeline accidents to determine their causes.
The Notice alleged that Respondent violated 49 C.F.R. § 195.402(c)(5) by failing to prepare and
follow procedures for analyzing pipeline accidents to determine their causes. Specifically, the
Notice alleged that Harvest’s Liquid Operations and Maintenance (O&M) Manual had
insufficient procedures regarding accident investigations. Further, the Notice alleged that
Harvest failed to perform a root cause analysis and document its findings on two reported
accidents (PHMSA Form 7000.1 ID 20160310 and 20150070).
Respondent did not contest this allegation of violation. Accordingly, based upon a review of all
of the evidence, I find that Respondent violated 49 C.F.R. § 195.402(c)(5) by failing to have
procedures for analyzing pipeline accidents to determine their causes.
Item 4: The Notice alleged that Respondent violated 49 C.F.R. § 195.402(c)(13), which states:
§ 195.402 Procedural manual for operations, maintenance, and
emergencies.
(a) ….
(c) Maintenance and normal operations. The manual required by
paragraph (a) of this section must include procedures for the following to
provide safety during maintenance and normal operations:
(1) ....
(13) Periodically reviewing the work done by operator personnel to
determine the effectiveness of the procedures used in normal operation and
maintenance and taking corrective action where deficiencies are found.
The Notice alleged that Respondent violated 49 C.F.R. § 195.402(c)(13) by failing to prepare
and follow procedures regarding periodically reviewing work done by operator personnel to
determine the effectiveness of the procedures and taking corrective action when deficiencies are
found. Specifically, the Notice alleged that Harvest failed to provide any records evidencing that
this review had been completed.
Respondent did not contest this allegation of violation. Accordingly, based upon a review of all
of the evidence, I find that Respondent violated 49 C.F.R. § 195.402(c)(13) by failing to prepare
and follow procedures on periodically reviewing work done by operator personnel to determine



CPF No. 4-2018-5016
Page 4
the effectiveness of the procedures used in normal operation and maintenance and taking
corrective action when deficiencies are found.
Item 5: The Notice alleged that Respondent violated 49 C.F.R. § 195.402(d)(5) which states:
§ 195.402 Procedural manual for operations, maintenance, and
emergencies.
(a) ….
(d) Abnormal operation. The manual required by paragraph (a) of this
section must include procedures for the following to provide safety when
operating design limits have been exceeded:
(1) ….
(5) Periodically reviewing the response by operator personnel to
determine the effectiveness of the procedures controlling abnormal
operation and taking corrective action where deficiencies are found.
The Notice alleged that Respondent violated 49 C.F.R. § 195.402(d)(5) by failing to prepare and
follow procedures regarding periodically reviewing the response of operator personnel to
determine the effectiveness of the procedures controlling abnormal operation and taking
corrective action where deficiencies are found. Specifically, the Notice alleged that Harvest
failed to provide any records evidencing that this review had been completed, despite the
requirement in its O&M Manual, Table 3: Necessary Compliance Records requiring this
documentation be kept for three years.
Respondent did not contest this allegation of violation. Accordingly, based upon a review of all
of the evidence, I find that Respondent violated 49 C.F.R. § 195.402(d)(5) by failing to prepare
and follow procedures regarding periodically reviewing the response of operator personnel to
determine the effectiveness of the procedures controlling abnormal operation and taking
corrective action where deficiencies are found.
Item 6: The Notice alleged that Respondent violated 49 C.F.R. § 195.403(b) which states:
§ 195.403 Emergency response training.
(a) ….
(b) At intervals not exceeding 15 months, but at least once each calendar
year, each operator shall:
(1) Review with personnel their performance in meeting the objectives
of the emergency response training program set forth in paragraph (a) of
this section; and
(2) Make appropriate changes to the emergency response training
program as necessary to ensure that it is effective.
The Notice alleged that Respondent violated 49 C.F.R. § 195.403(b) by failing to document and
retain records of reviewing with personnel their performance in meeting the objectives of the
emergency response training program and making appropriate changes as necessary to ensure
that it is effective. Specifically, the Notice alleged that Harvest failed to provide any records



CPF No. 4-2018-5016
Page 5
evidencing that this review had been completed, despite the requirement in its O&M Manual, P-
195.403: Training requiring this review at intervals not exceeding 15 months but at least once
each calendar year.
Respondent did not contest this allegation of violation. Accordingly, based upon a review of all
of the evidence, I find that Respondent violated 49 C.F.R. § 195.403(b) by failing to establish
and conduct a training program that required review with personnel of their performance in
meeting the objectives of the emergency response training program and making appropriate
changes as necessary to ensure that it is effective.
Item 7: The Notice alleged that Respondent violated 49 C.F.R. § 195.403(c), which states:
§ 195.403 Emergency response training.
(a) ….
(c) Each operator shall require and verify that its supervisors maintain
a thorough knowledge of that portion of the emergency response procedures
established under 195.402 for which they are responsible to ensure
compliance.
The Notice alleged that Respondent violated 49 C.F.R. § 195.403(c) by failing to require and
verify that its supervisors maintain a thorough knowledge of that portion of the emergency
response procedures established under § 195.402 for which they are responsible to ensure
compliance. Specifically, the Notice alleged that Harvest failed to provide any records
evidencing verification of supervisor knowledge for emergency response procedures they are
responsible for ensuring compliance, despite the requirement in its O&M P-195.403: Training
that requires verification of supervisor knowledge be documented on form F195.403c. During
the inspection, Harvest only provided one form, dated 12/1/2016, which was not completely
filled out.
Respondent did not contest this allegation of violation. Accordingly, based upon a review of all
of the evidence, I find that Respondent violated 49 C.F.R. § 195.403(c) by failing to require and
verify that its supervisors maintain a thorough knowledge of that portion of the emergency
response procedures established under § 195.402 for which they are responsible to ensure
compliance.
These findings of violation will be considered prior offenses in any subsequent enforcement
action taken against Respondent.
ASSESSMENT OF PENALTY
Under 49 U.S.C. § 60122, Respondent is subject to an administrative civil penalty not to exceed
$200,000 per violation for each day of the violation, up to a maximum of $2,000,000 for any



CPF No. 4-2018-5016
Page 6
related series of violations.2 In determining the amount of a civil penalty under 49 U.S.C.
§ 60122 and 49 C.F.R. § 190.225, I must consider the following criteria: the nature,
circumstances, and gravity of the violation, including adverse impact on the environment; the
degree of Respondent’s culpability; the history of Respondent’s prior offenses; any effect that
the penalty may have on its ability to continue doing business; and the good faith of Respondent
in attempting to comply with the pipeline safety regulations. In addition, I may consider the
economic benefit gained from the violation without any reduction because of subsequent
damages, and such other matters as justice may require. The Notice proposed a total civil
penalty of $88,300 for the violations cited above.
Item 3: The Notice proposed a civil penalty of $19,300 for Respondent’s violation of 49 C.F.R.
§ 195.402(c)(5) for failing to prepare and follow procedures for analyzing pipeline accidents to
determine their causes. In its Response, Harvest stated that it was performing accident
investigations as evidenced by completed F7000.1 forms, but recognized that it could improve
the detail, methods, and documentation it uses in this process. Since the Notice, Harvest has
made changes to its Accident and Incident Investigation procedure. Harvest neither contested
the allegation nor presented any evidence or argument justifying a reduction in or elimination of
the proposed penalty. As a result, Harvest failed to comply with a requirement that was clearly
applicable. Accordingly, having reviewed the record and considered the assessment criteria, I
assess Respondent a civil penalty of $19,300 for violation of 49 C.F.R. § 195.402(c)(5).
Item 4: The Notice proposed a civil penalty of $19,000 for Respondent’s violation of 49 C.F.R.
§ 195.402(c)(13) for failing to prepare and follow procedures regarding periodically reviewing
work done by operator personnel to determine the effectiveness of the procedures and taking
corrective action when deficiencies are found. Harvest neither contested the allegation nor
presented any evidence or argument justifying a reduction in or elimination of the proposed
penalty. As a result, Harvest failed to comply with a regulation that was clearly applicable.
Accordingly, having reviewed the record and considered the assessment criteria, I assess
Respondent a civil penalty of $19,000 for violation of 49 C.F.R. § 195.402(c)(13).
Item 5: The Notice proposed a civil penalty of $15,500 for Respondent’s violation of 49 C.F.R.
§ 195.402(d)(5) for failing to prepare and follow procedures regarding periodically reviewing the
response of operator personnel to determine the effectiveness of the procedures controlling
abnormal operation and taking corrective action where deficiencies are found. In its Response,
Harvest stated that it transitioned to operational control of the Louisiana assets at issue on June
28, 2016 and was currently evaluating how it can update its procedures. Recent acquisition of
assets, however, does not absolve an operator of its regulatory duties. Harvest failed to comply
with a regulation that was clearly applicable. Based upon the foregoing, I assess Respondent a
civil penalty of $15,500 for violation of 49 C.F.R. § 195.402(d)(5).
Item 6: The Notice proposed a civil penalty of $19,000 for Respondent’s violation of 49 C.F.R.
§ 195.403(b) for failing to document and retain records of reviewing with personnel their
performance in meeting the objectives of the emergency response training program and making
2 These amounts are adjusted annually for inflation. See 49 C.F.R. § 190.223; Revisions to Civil Penalty Amounts,
83 Fed. Reg. 60732, 60744 (Nov. 27, 2018).



CPF No. 4-2018-5016
Page 7
appropriate changes as necessary to ensure that it is effective. Harvest neither contested the
allegation nor presented any evidence or argument justifying a reduction in or elimination of the
proposed penalty. As a result, Harvest failed to comply with a regulation that was clearly
applicable. Accordingly, having reviewed the record and considered the assessment criteria, I
assess Respondent a civil penalty of $19,000 for violation of 49 C.F.R. § 195.403(b).
Item 7: The Notice proposed a civil penalty of $15,500 for Respondent’s violation of 49 C.F.R.
§ 195.403(c) for failing to require and verify that its supervisors maintain a thorough knowledge
of that portion of the emergency response procedures established under § 195.402 for which they
are responsible to ensure compliance. Harvest neither contested the allegation nor presented any
evidence or argument justifying a reduction in or elimination of the proposed penalty. As a
result, Harvest failed to comply with a regulation that was clearly applicable. Accordingly,
having reviewed the record and considered the assessment criteria, I assess Respondent a civil
penalty of $15,500 for violation of 49 C.F.R. § 195.403(c).
In summary, having reviewed the record and considered the assessment criteria for each of the
Items cited above, I assess Respondent a total civil penalty of $88,300.
Payment of the civil penalty must be made within 20 days of service. Federal regulations (49
C.F.R. § 89.21(b)(3)) require such payment to be made by wire transfer through the Federal
Reserve Communications System (Fedwire), to the account of the U.S. Treasury. Detailed
instructions are contained in the enclosure. Questions concerning wire transfers should be
directed to: Financial Operations Division (AMK-325), Federal Aviation Administration, Mike
Monroney Aeronautical Center, 6500 S MacArthur Blvd, Oklahoma City, Oklahoma 79169.
The Financial Operations Division telephone number is (405) 954-8845.
Failure to pay the $88,300 civil penalty will result in accrual of interest at the current annual rate
in accordance with 31 U.S.C. § 3717, 31 C.F.R. § 901.9 and 49 C.F.R. § 89.23. Pursuant to
those same authorities, a late penalty charge of six percent (6%) per annum will be charged if
payment is not made within 110 days of service. Furthermore, failure to pay the civil penalty
may result in referral of the matter to the Attorney General for appropriate action in a district
court of the United States.
COMPLIANCE ORDER
The Notice proposed a compliance order with respect to Items 1, 3, 4, 5, and 6 in the Notice for
violations of 49 C.F.R. §§ 194.107(c)(1)(ix), 195.402(c)(5), 195.402(c)(13), 195.402(d)(5) and
195.403(b), respectively. Under 49 U.S.C. § 60118(a), each person who engages in the
transportation of hazardous liquids or who owns or operates a pipeline facility is required to
comply with the applicable safety standards established under chapter 601. Pursuant to the
authority of 49 U.S.C. § 60118(b) and 49 C.F.R. § 190.217, Respondent is ordered to take the
following actions to ensure compliance with the pipeline safety regulations applicable to its
operations:



CPF No. 4-2018-5016
Page 8
1. With respect to the violation of § 194.107(c)(1)(ix) (Item 1), Respondent must,
upon completion of their emergency response drills, perform an objective evaluation
of personnel, procedures, drill scenarios, and other factors, where lessons learned are
used in response plan revisions in accordance with Harvest’s Facility Response Plan
Guidelines – Section 7.3.2 Certification, to include a signature of an authorized
representative. This must be completed within 30 days of any drills that are
scheduled, in the normal course, on or after the receipt of the Final Order.
2. With respect to the violation of § 195.402(c)(5) (Item 3), Respondent must amend
the procedures contained in its Liquid O&M Manual, Section B: Conduct the
Investigation to identify analyses, techniques, or methods to analyze pipeline
accidents to determine their causes. These procedures should also include detailed
information on how to conduct an accident investigation with updated diagrams. This
must be completed within 30 days of receipt of the Final Order.
3. With respect to the violation of § 195.402(c)(13) (Item 4), Respondent must
conduct reviews of operations personnel and document those reviews on form F-
195.402(c)(13),3 entitled Review of Work Done by Operator in accordance with
Harvest’s Liquid O&M Manual P-195.402c13: Review of Work Done by Operator.
This must be completed within 30 days of receipt of the Final Order.
4. With respect to the violation of § 195.402(d)(5) (Item 5), Respondent must begin
documenting its reviews of responses of control center personnel to abnormal
operating conditions in accordance with Harvest’s Liquid O&M Manual P-
195.402d5: Abnormal Operations.4 This must be completed within 30 days of receipt
of the Final Order.
5. With respect to the violation of § 195.403(b) (Item 6), Respondent must conduct
reviews of emergency personnel performance and document these reviews at the
required interval, in accordance with Harvest’s Liquid O&M Manual P-195.403:
Training. This must be completed within 30 days of any drills that are scheduled, in
the normal course, on or after the receipt of the Final Order.
The Director may grant an extension of time to comply with any of the required items upon a
written request timely submitted by the Respondent and demonstrating good cause for an
extension.
It is requested (not mandated) that Respondent maintain documentation of the safety
3 Harvest may continue to use form F195.402(c)(13), but is encouraged to analyze the form to ensure that it sufficiently
captures all necessary information.
4 Harvest may continue to use its current procedures, but is encouraged to analyze those procedures to ensure that
they provide sufficient information on how to periodically review the response of operator personnel to determine the
effectiveness of the procedures controlling abnormal operation and how to take corrective action where deficiencies
are found.



CPF No. 4-2018-5016
Page 9
improvement costs associated with fulfilling this Compliance Order and submit the total to the
Director. It is requested that these costs be reported in two categories: (1) total cost associated
with preparation/revision of plans, procedures, studies and analyses; and (2) total cost associated
with replacements, additions and other changes to pipeline infrastructure.
Failure to comply with this Order may result in the administrative assessment of civil penalties
not to exceed $200,000, as adjusted for inflation (49 C.F.R. § 190.223), for each violation for
each day the violation continues or in referral to the Attorney General for appropriate relief in a
district court of the United States.
WARNING ITEM
With respect to Item 2, the Notice alleged a probable violation of Part 194 but did not propose a
civil penalty or compliance order for this item. Therefore, this is considered to be a warning
item. The warning was for:
49 C.F.R. § 194.121(a) (Item 2) ─ Respondent’s alleged failure to timely
resubmit its response plan to OPS.
If OPS finds a violation of this provision in a subsequent inspection, Respondent may be subject
to future enforcement action.
Under 49 C.F.R. § 190.243, Respondent may submit a Petition for Reconsideration of this Final
Order to the Associate Administrator, Office of Pipeline Safety, PHMSA, 1200 New Jersey
Avenue, SE, East Building, 2nd Floor, Washington, DC 20590, with a copy sent to the Office of
Chief Counsel, PHMSA, at the same address, no later than 20 days after receipt of service of this
Final Order by Respondent. Any petition submitted must contain a statement of the issue(s) and
meet all other requirements of 49 C.F.R. § 190.243. The filing of a petition automatically stays
the payment of any civil penalty assessed. The other terms of the order, including corrective
action, remain in effect unless the Associate Administrator, upon request, grants a stay.
The terms and conditions of this Final Order are effective upon service in accordance with 49
C.F.R. § 190.5.
September 12, 2019
___________________________________ __________________________
Alan K. Mayberry Date Issued
Associate Administrator
for Pipeline Safety

## Provenance

- Official: Yes
- Source: <https://primis.phmsa.dot.gov/enforcement-data/case/420185016>
- Source ID: `phmsa-enforcement`
- SHA-256: `bb27059a494c9195f54ad4f0970ad5e6a816c60e5f87df4215649a88a702118d`
- Retrieved: 2026-08-20T04:44:44.458Z
- Exported: 2026-08-22T22:28:58.350Z
- Document slug: `phmsa-enforcement-420185016`

### Source metadata

```json
{
  "cpf": "420185016",
  "operator": "HARVEST MIDSTREAM COMPANY",
  "region": "Southwest",
  "pipelineType": "INTERSTATE LIQUID ONSHORE",
  "caseStatus": "CLOSED",
  "citedSections": [
    "194.107(c)(1)(ix)",
    "194.121(a)",
    "195.402(c)(13)",
    "195.402(c)(5)",
    "195.402(d)(5)",
    "195.403(b)",
    "195.403(c)"
  ],
  "dataAsOf": "08/04/2026 12PM",
  "caseDataAsOf": "2026-08-04",
  "attachmentCount": 7,
  "attachments": [
    {
      "name": "420185016_Closure Letter_02042020.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420185016/420185016_Closure%20Letter_02042020.pdf",
      "bytes": 19218,
      "category": "agency_document"
    },
    {
      "name": "420185016_Closure Letter_02042020_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420185016/420185016_Closure%20Letter_02042020_text.pdf",
      "bytes": 75931,
      "category": "agency_document"
    },
    {
      "name": "420185016_Final Order_09122019.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420185016/420185016_Final%20Order_09122019.pdf",
      "bytes": 1198895,
      "category": "agency_document"
    },
    {
      "name": "420185016_Final Order_09122019_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420185016/420185016_Final%20Order_09122019_text.pdf",
      "bytes": 170135,
      "category": "agency_document"
    },
    {
      "name": "420185016_NOPV PCP PCO_08312018.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420185016/420185016_NOPV%20PCP%20PCO_08312018.pdf",
      "bytes": 136044,
      "category": "agency_document"
    },
    {
      "name": "420185016_NOPV PCP PCO_08312018_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420185016/420185016_NOPV%20PCP%20PCO_08312018_text.pdf",
      "bytes": 515495,
      "category": "agency_document"
    },
    {
      "name": "420185016_Operator Response to Notice_12182018.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420185016/420185016_Operator%20Response%20to%20Notice_12182018.pdf",
      "bytes": 585504,
      "category": "party_submission"
    }
  ],
  "extractedAgencyDocumentCount": 3,
  "attachmentPolicy": "Official attachment links are retained. Agency-issued documents may also include a verified local PDF and page-level text representation.",
  "jurisdiction": "US",
  "operatorName": "HARVEST MIDSTREAM COMPANY"
}
```