# ONEOK NGL PIPELINE, LLC — Notice of Probable Violation

**Citation:** CPF 420195017  
**Type / status:** enforcement / historical  
**Agency:** Pipeline and Hazardous Materials Safety Administration  
**Effective:** Not stated  
**Published:** 2019-09-16

CLOSED notice of probable violation citing 195.452(a), 195.452(h)(4)(ii)(b).

## Document text

Notice of Probable Violation involving ONEOK NGL PIPELINE, LLC. PHMSA's enforcement data identifies the cited regulations as 195.452(a),  195.452(h)(4)(ii)(b). The case was opened on 2019-09-16 and is reported as closed as of 2020-01-14. Proposed civil penalty: $63,900. Assessed civil penalty: $63,900. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

420195017_Final Order_01142019.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420195017/420195017_Final%20Order_01142019.pdf

420195017_Final Order_01142019_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420195017/420195017_Final%20Order_01142019_text.pdf

420195017_Final Order_01142020.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420195017/420195017_Final%20Order_01142020.pdf

420195017_NOPV PCP_09162019.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420195017/420195017_NOPV%20PCP_09162019.pdf

420195017_NOPV PCP_09162019_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420195017/420195017_NOPV%20PCP_09162019_text.pdf

420195017_Operator Response to Notice_10182019.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420195017/420195017_Operator%20Response%20to%20Notice_10182019.pdf

420195017_Final Order_01142019_text.pdf

January 14, 2020
Mr. Terry K. Spencer
President and Chief Executive Officer
ONEOK, Inc.
100 West Fifth Street
Tulsa, Oklahoma 74103
Re: CPF No. 4-2019-5017
Dear Mr. Spencer:
Enclosed please find the Final Order issued in the above-referenced case. It makes a finding of
violation against your subsidiary, ONEOK NGL Pipeline, LLC, and finds that the civil penalty
amount of $63,900 has been paid in full. This case is now closed. Service of the Final Order by
certified mail is effective upon the date of mailing as provided under 49 C.F.R. § 190.5.
Thank you for your cooperation in this matter.
Sincerely,
Alan K. Mayberry
Associate Administrator
for Pipeline Safety
Enclosures (Final Order and NOPV)
cc: Ms. Mary McDaniel, Director, Southwest Region, Office of Pipeline Safety, PHMSA
Mr. Scott Schingen, Vice President - NGL Operations, ONEOK, Inc.
CERTIFIED MAIL - RETURN RECEIPT REQUESTED



U.S. DEPARTMENT OF TRANSPORTATION
PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION
OFFICE OF PIPELINE SAFETY
WASHINGTON, D.C. 20590
____________________________________
In the Matter of )
ONEOK NGL Pipeline, LLC, ) CPF No. 4-2019-5017
a subsidiary of ONEOK, Inc., )
)
)
)
Respondent. )
____________________________________)
FINAL ORDER
On September 16, 2019, pursuant to 49 C.F.R. § 190.207, the Director, Southwest Region,
Office of Pipeline Safety (OPS), issued a Notice of Probable Violation (Notice) to ONEOK NGL
Pipeline, LLC (Respondent), a subsidiary of ONEOK, Inc.1 The Notice proposed finding that
Respondent had violated the pipeline safety regulations in 49 C.F.R. Part 195 and proposed a
civil penalty of $63,900. Respondent did not contest the allegation of violation and paid the
proposed civil penalty by wire transfer on October 15, 2019. In accordance with
§ 190.208(a)(1), such payment authorizes the entry of this final order.
Based upon a review of all of the evidence, pursuant to § 190.213, I find Respondent violated the
pipeline safety regulations listed below, as more fully described in the enclosed Notice:
49 C.F.R. § 195.452(h)(4)(ii)(B) (Item 1) ─ Respondent failed to remediate a
dent with metal loss on the bottom of the Lufkin to Mont Belvieu Loop Index
21084 10-inch pipeline segment within 60 days of discovery.
This finding of violation will be considered a prior offense in any subsequent enforcement action
taken against Respondent. In accordance with 49 C.F.R. § 190.223, Respondent is assessed the
proposed civil penalty amount of $63,900, which Respondent has already paid in full.
The terms and conditions of this order are effective upon service in accordance with 49 C.F.R.
§ 190.5.
January 14, 2020
___________________________________ _________________________
Alan K. Mayberry Date Issued
Associate Administrator
for Pipeline Safety
1 ONEOK, Inc.’s website, available at https://www.oneok.com/customers/ngl (last accessed on December 23, 2019).

420195017_Final Order_01142020.pdf

U.S. Department
JAN 1 4 2020
1200 New Jersey Ave., SE
of Transportation
Washington, DC 20590
Pipeline and Hazardous Materials
Safety Administratior
Mr. Terry K. Spencer
President and Chief Executive Officer
ONEOK, Inc.
100 West Fifth Street
Tulsa, Oklahoma 74103
Re: CPF No. 4-2019-5017
Dear Mr. Spencer:
Enclosed please find the Final Order issued in the above-referenced case. It makes a finding of
violation against your subsidiary, ONEOK NGL Pipeline, LLC, and finds that the civil penalty
amount of $63,900 has been paid in full. This case is now closed. Service of the Final Order by
certified mail is effective upon the date of mailing as provided under 49 C.F.R. § 190.5.
Thank you for your cooperation in this matter.
Sincerely,
Associate Administrator
for Pipeline Safety
Enclosures (Final Order and NOPV)
CC:
Ms. Mary McDaniel, Director, Southwest Region, Office of Pipeline Safety, PHMSA
Mr. Scott Schingen, Vice President - NGL Operations, ONEOK, Inc.
CERTIFIED MAIL - RETURN RECEIPT REQUESTED



U.S. DEPARTMENT OF TRANSPORTATION
PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION
OFFICE OF PIPELINE SAFETY
WASHINGTON, D.C. 20590
In the Matter of
ONEOK NGL Pipeline, LLC,
CPF No. 4-2019-5017
a subsidiary of ONEOK, Inc.,
Respondent.
FINAL ORDER
On September 16, 2019, pursuant to 49 C.F.R. § 190.207, the Director, Southwest Region,
Uttice ot Pipeline Satety (OPS), issued a Notice of Probable Violation (Notice) to ONEOK NGL
Pipeline, LLC (Respondent), a subsidiary of ONEOK, Inc.' The Notice proposed finding that
ivil penalty of $63,900. Respondent did not contest the allegation of violation and paid th
espondent had violated the pipeline safety regulations in 49 C.F.R. Part 195 and proposed
proposed civil penalty by wire transfer on October 15, 2019. In accordance with
§ 190.208(a)(1), such payment authorizes the entry of this final order.
Based upon a review of all of the evidence, pursuant to § 190.213, I find Respondent violated the
pipeline safety regulations listed below, as more fully described in the enclosed Notice:
49 C.F.R. § 195.452(h)(4)(ii)(B) (Item 1) - Respondent failed to remediate a
dent with metal loss on the bottom of the Lufkin to Mont Belvieu Loop Index
21084 10-inch pipeline segment within 60 days of discovery.
This finding of violation will be considered a prior offense in any subsequent enforcement action
taken against Respondent. In accordance with 49 C.F.R. § 190.223, Respondent is assessed the
proposed civil penalty amount of $63,900, which Respondent has already paid in full.
The terms and conditions of this order are effective upon service in accordance with 49 C.F.R.
§ 190.5.
Plant Wan
JAN 1 4 2020
Alan K. Mayberry
Date Issued
Associate Administrator
for Pipeline Safety
'ONEOK, Inc.'s website, available at https://www.oneok.com/customers/ngl (last accessed on December 23, 2019).



U.S. Department
8701 S. Gessner, Suite 630
of Transportation
Houston, TX 77074
Pipeline and
Administration
Hazardous Materials Safety
NOTICE OF PROBABLE VIOLATION
and
PROPOSED CIVIL PENALTY
CERTIFIED MAIL - RETURN RECEIPT REQUESTED
September 16, 2019
Scott Schingen
Vice President NGL Operations
Oneok NGL Pipeline, LLC
100 West Fifth Street
Tulsa, Oklahoma 74103
CPF 4-2019-5017
Dear Mr. Schingen:
From October 15, 2018 to March 20, 2019, a representative of the Pipeline and Hazardous
Materials Safety Administration (PHMSA), Office of Pipeline Safety (OPS), pursuant to Chapter
601 of 49 United States Code (U.S.C.) inspected Oneok NGL Pipeline, LLC's (Oneok) West Texas
LPG System Pipelines in New Mexico and Texas.
As a result of the inspection, it is alleged that you have committed a probable violation of the
Pipeline Safety Regulations, Title 49, Code of Federal Regulations (CFR). The item inspected
and the probable violation is:



1.
$195.452 Pipeline integrity management in high consequence areas.
(a) Which pipelines are covered by this section? This section applies to each hazardous
liquid pipeline and carbon dioxide pipeline that could affect a high consequence area,
including any pipeline located in a high consequence area unless the operator
effectively demonstrates by risk assessment that the pipeline could not affect the area.
(b) What actions must an operator take to address integrity issues?
(4) Special requirements for scheduling remediation
(ii) 60-day conditions. Except for conditions listed in paragraph (h)(4)(i) of this
section, an operator must schedule evaluation and remediation of the following
conditions within 60 days of discovery of condition.
(B) A dent located on the bottom of the pipeline that has any indication of metal loss,
cracking or a stress riser.
Oneok failed to remediate a dent with metal loss on the bottom of the Lufkin to Mont Belvieu
Loop Index 21084 10-inch pipeline segment within 60 days of discovery on the as required by §
195.452(h) (4)(ii)(B).
Oneok performed an in-line inspection of the Lufkin to Mont Belvieu Loop Index 21084 10-inch
pipeline segment on January 24, 2017, using a T.D. Williamson (TDW) combination Magnetic.
Flux Leakage and Deformation inspection tool. TDW issued to Oneok a Final Pipeline Inspection
Report on June 27, 2017. The Final Report indicated a 1 percent dent with 10 percent external
metal loss at the same orientation on the bottom of the pipe. The bottom side dent with indication
of metal loss was located in a High Consequence Area; therefore, Oneok was required to remediate
the dent with metal loss within 60 days of discovery in accordance with § 195.452(h) (4)(ii)(B).
On November 15, 2017, Oneok remediated the dent with metal loss by welding a Type-B sleeve
over the anomaly. With the discovery date for the conditions being June 27, 2017, Oneok exceeded
the 60-day remediation schedule by 81 days.
Proposed Civil Penalty
Under 49 U.S.C. § 60122 and 49 CFR § 190.223, you are subject to a civil penalty not to exceed
$218,647 per violation per day the violation persists, up to a maximum of $2,186,465 for a related
series of violations. For violation occurring on or after November 27, 2018 and before July 31,
2019, the maximum penalty may not exceed $213,268 per violation per day, with a maximum
penalty not to exceed $2,132,679. For violation occurring on or after November 2, 2015 and
before November 27, 2018, the maximum penalty may not exceed $209,002 per violation per day,
with a maximum penalty not to exceed $2,090,022. For violations occurring prior to November
2, 2015, the maximum penalty may not exceed $200,000 per violation per day, with a maximum
penalty not to exceed $2,000,000 for a related series of violations. The Compliance Officer has
reviewed the circumstances and supporting documentation involved for the above probable
violation and has recommended that you be preliminarily assessed a civil penalty of $63,900.
2



Response to this Notice
Enclosed as part of this Notice is a document entitled Response Options for Pipeline Operators in
Compliance Proceedings. Please refer to this document and note the response options. All
material submit in response to this enforcement action may be made publicly available. If you
believe that any portion of your responsive material qualifies for confidential treatment under 5
U.S.C. 552(b), along with the complete original document you must provide a second copy of the
document with the portions you believe qualify for confidential treatment redacted and an
explanation of why you believe the redacted information qualifies for confidential treatment under
5 U.S.C. 552(b).
Following the receipt of this Notice, you have 30 days to submit written comments, or request a
hearing under 49 CFR § 190.211. If you do not respond within 30 days of receipt of this Notice,
this constitutes a waiver of your right to contest the allegations in this Notice and authorizes the
Associate Administrator for Pipeline Safety to find facts as alleged in this Notice without further
notice to you and to issue a Final Order. If you are responding to this Notice, we propose that you
submit your correspondence to my office within 30 days from the receipt of this Notice. This
period may be extended by written request for good cause.
In your correspondence on this matter, please refer to CPF 4-2019-5017 and, for each document
you submit, please provide a copy in electronic format whenever possible.
Sincerely,
Mary L. McDaniel, P.E.
Director, Southwest Region
Pipeline and Hazardous Materials Safety Administration
Enclosure: Response Options for Pipeline Operators in Compliance Proceedings

## Provenance

- Official: Yes
- Source: <https://primis.phmsa.dot.gov/enforcement-data/case/420195017>
- Source ID: `phmsa-enforcement`
- SHA-256: `398aaf13ab9eb5fbf9596bb7362814cb63d8bd83a87da52b947db1c26ef99f53`
- Retrieved: 2026-08-20T04:44:44.458Z
- Exported: 2026-08-22T18:26:04.694Z
- Document slug: `phmsa-enforcement-420195017`

### Source metadata

```json
{
  "cpf": "420195017",
  "operator": "ONEOK NGL PIPELINE, LLC",
  "region": "Southwest",
  "pipelineType": "INTERSTATE LIQUID ONSHORE",
  "caseStatus": "CLOSED",
  "citedSections": [
    "195.452(a)",
    "195.452(h)(4)(ii)(b)"
  ],
  "dataAsOf": "08/04/2026 12PM",
  "caseDataAsOf": "2026-08-04",
  "attachmentCount": 6,
  "attachments": [
    {
      "name": "420195017_Final Order_01142019.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420195017/420195017_Final%20Order_01142019.pdf",
      "bytes": 481550,
      "category": "agency_document"
    },
    {
      "name": "420195017_Final Order_01142019_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420195017/420195017_Final%20Order_01142019_text.pdf",
      "bytes": 121022,
      "category": "agency_document"
    },
    {
      "name": "420195017_Final Order_01142020.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420195017/420195017_Final%20Order_01142020.pdf",
      "bytes": 760121,
      "category": "agency_document"
    },
    {
      "name": "420195017_NOPV PCP_09162019.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420195017/420195017_NOPV%20PCP_09162019.pdf",
      "bytes": 62347,
      "category": "case_document"
    },
    {
      "name": "420195017_NOPV PCP_09162019_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420195017/420195017_NOPV%20PCP_09162019_text.pdf",
      "bytes": 140954,
      "category": "case_document"
    },
    {
      "name": "420195017_Operator Response to Notice_10182019.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/420195017/420195017_Operator%20Response%20to%20Notice_10182019.pdf",
      "bytes": 25415,
      "category": "party_submission"
    }
  ],
  "extractedAgencyDocumentCount": 2,
  "attachmentPolicy": "Official attachment links are retained. Agency-issued documents may also include a verified local PDF and page-level text representation.",
  "jurisdiction": "US",
  "operatorName": "ONEOK NGL PIPELINE, LLC"
}
```