# FLORIDA GAS TRANSMISSION CO — Corrective Action Order

**Citation:** CPF 42020008CAO  
**Type / status:** enforcement / historical  
**Agency:** Pipeline and Hazardous Materials Safety Administration  
**Effective:** Not stated  
**Published:** 2020-09-18

CLOSED corrective action order.

## Document text

Corrective Action Order involving FLORIDA GAS TRANSMISSION CO. The dataset does not identify a cited regulation for this case. The case was opened on 2020-09-18 and is reported as closed as of 2026-01-20. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

42020008CAO_Amended Corrective Action Order_10012020_(20-190995).pdf: https://primis.phmsa.dot.gov/enforcement-documents/42020008CAO/42020008CAO_Amended%20Corrective%20Action%20Order_10012020_(20-190995).pdf

42020008CAO_Amended Corrective Action Order_10012020_(20-190995)_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/42020008CAO/42020008CAO_Amended%20Corrective%20Action%20Order_10012020_(20-190995)_text.pdf

42020008CAO_Closure Letter_01202026_(20-190995).pdf: https://primis.phmsa.dot.gov/enforcement-documents/42020008CAO/42020008CAO_Closure%20Letter_01202026_(20-190995).pdf

42020008CAO_Closure Letter_01202026_(20-190995)_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/42020008CAO/42020008CAO_Closure%20Letter_01202026_(20-190995)_text.pdf

42020008CAO_Corrective Action Order_09182020_(20-190995).pdf: https://primis.phmsa.dot.gov/enforcement-documents/42020008CAO/42020008CAO_Corrective%20Action%20Order_09182020_(20-190995).pdf

42020008CAO_Corrective Action Order_09182020_(20-190995)_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/42020008CAO/42020008CAO_Corrective%20Action%20Order_09182020_(20-190995)_text.pdf

42020008CAO_Operator Hearing Request Withdrawn_10302020_(20-190995).pdf: https://primis.phmsa.dot.gov/enforcement-documents/42020008CAO/42020008CAO_Operator%20Hearing%20Request%20Withdrawn_10302020_(20-190995).pdf

42020008CAO_Operator Request for Hearing and Request Statement of Issues_10132020_(20-190995).pdf: https://primis.phmsa.dot.gov/enforcement-documents/42020008CAO/42020008CAO_Operator%20Request%20for%20Hearing%20and%20Request%20Statement%20of%20Issues_10132020_(20-190995).pdf

42020008CAO_PHC Hearing Scheduled_10232020_(20-190995).pdf: https://primis.phmsa.dot.gov/enforcement-documents/42020008CAO/42020008CAO_PHC%20Hearing%20Scheduled_10232020_(20-190995).pdf

42020008CAO_PHC Hearing Scheduled_10232020_(20-190995)_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/42020008CAO/42020008CAO_PHC%20Hearing%20Scheduled_10232020_(20-190995)_text.pdf

42020008CAO_Second Amended Corrective Action Order_10222020_(20-190995).pdf: https://primis.phmsa.dot.gov/enforcement-documents/42020008CAO/42020008CAO_Second%20Amended%20Corrective%20Action%20Order_10222020_(20-190995).pdf

42020008CAO_Second Amended Corrective Action Order_10222020_(20-190995)_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/42020008CAO/42020008CAO_Second%20Amended%20Corrective%20Action%20Order_10222020_(20-190995)_text.pdf

42020008CAO_Second Amended Corrective Action Order_10222020_(20-190995)_text.pdf

October 22, 2020
VIA ELECTRONIC MAIL TO: matthew.ramsey@energytransfer.com
Matthew Ramsey
Chief Operating Officer
Energy Transfer Partners, LP
8111 Westchester Drive
Dallas, Texas 75225
CPF No. 4-2020-008-CAO
Dear Mr. Ramsey:
Enclosed please find a Second Amended Corrective Action Order (Second ACAO) issued by the
Pipeline and Hazardous Materials Safety Administration, Office of Pipeline Safety, in the above-
referenced case to Florida Gas Transmission Company (FGT), which is operated by Energy
Transfer Partners, LP. The Second ACAO continues to require that FGT take corrective actions
previously ordered on September 18, 2020, and October 1, 2020, with respect to an incident that
occurred on the 12-inch Sanford Lateral on September 10, 2020, located in Sandford, Florida, and
a rupture that occurred on September 24, 2020, on FGT’s 18-inch FLMEA-21 pipeline located in
Lake Worth, Florida.
The Second ACAO modifies a few of the preliminary findings, including clarifying the location
of the September 24, 2020 incident and the prior Corrective Action Orders PHMSA issued for
FGT’s pre-1970 low-frequency electric resistance welded pipe. The Second ACAO also amends
the definition of the Affected Pipeline for the September 24, 2020 incident, and corrects
inconsistencies for two of the corrective actions regarding operating pressure restrictions of the
affected pipeline for the September 24, 2020 incident and documentation of costs. Finally, the
Second ACAO does not amend any of the deadlines in the Amended Corrective Action Order
issued on October 1, 2020.
Service of the Second ACAO by electronic transmission is deemed complete upon transmission
and acknowledgement of receipt, or as otherwise provided under 49 C.F.R. § 190.5. The terms
and conditions of this Order are effective upon completion of service.



Sincerely,
Alan K. Mayberry
Associate Administrator
for Pipeline Safety
Enclosure: Second ACAO
cc: Ms. Linda Daugherty, Deputy Associate Administrator for Field Operations, OPS
Ms. Mary L. McDaniel, P.E., Director, Southwestern Region, OPS
Mr. Eric Amundsen, Senior Vice President, Energy Transfer Partners, LP,
eric.amundsen@energytransfer.com



U.S. DEPARTMENT OF TRANSPORTATION
PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION
OFFICE OF PIPELINE SAFETY
WASHINGTON, D.C. 20590
____________________________________
In the Matter of )
Florida Gas Transmission Company, )
)
)
)
Respondent. )
____________________________________)
CPF No. 4-2020-008-CAO
SECOND AMENDED CORRECTIVE ACTION ORDER
Purpose and Background:
On September 18, 2020, the Pipeline and Hazardous Materials Safety Administration (PHMSA)
issued a Corrective Action Order under the authority of 49 U.S.C. § 60112 to require Florida Gas
Transmission Company (FGT or Respondent), which is operated by Energy Transfer Partners,
LP,1 to take necessary corrective actions to protect the public, property, and the environment from
potential hazards associated with a rupture that occurred on September 10, 2020, on FGT’s 12-
inch Sanford Lateral natural gas pipeline in Sanford, Florida (Incident 1). On October 1, 2020,
PHMSA issued an Amended Corrective Action Order to require Respondent take corrective
actions due to Incident 1 and a second rupture that occurred on September 24, 2020, on its 18-inch
FLMEA-21 line located in Lake Worth, Florida (Incident 2). FGT responded to the Amended
Corrective Action Order on October 13, 2020, to request a hearing.
PHMSA now issues this Second Amended Corrective Order (Second ACAO or Order), which
makes certain amendments to the Amended Corrective Action Order issued on October 1, 2020.
This Second ACAO supersedes both the September 18, 2020 Corrective Action Order and the
October 1, 2020 Amended Corrective Action Order.
Incident 1: In the early morning of September 10, 2020, FGT’s 12-inch Sanford Lateral ruptured
and subsequently ignited. Prior to the rupture, at 12:47am EDT, the line was operating at 695
pounds per square inch (psig) between the Sanford station and the DeBary station. At 12:52 am
EDT, the pressure reading at Sanford dropped to 409 psig and steadily decreased from that point.
FGT’s Control Room detected the drop in pressure and had the valves upstream and downstream
(upstream Valve 17-22U and downstream Valve 17-22ERB) of the failure site manually closed.
1 FGT is an approximately 5,300-mile system that transports natural gas from South Texas to South Florida. FGT is
owned by Florida Gas Transmission Company, LLC, a 100 percent owned subsidiary of Citrus Corp. Citrus Corp is
a 50/50 joint venture between Kinder Morgan, Inc. and Energy Transfer Partners, LP. FGT is operated by Energy
Transfer. See https://www.kindermorgan.com/Operations/Natural-Gas/Index (last accessed September 14, 2020).



CPF No. 4-2020-008-CAO
Page 2
At 2:08 am EDT the line was shut in. The size of the burn area around the rupture site was
determined to be 515 feet by 100 feet.
Reverse 911 notified 800 area homes and the local sheriff reported 20 homes were evacuated. The
fire was extinguished, and evacuated residents were allowed to return home within hours of
Incident 1. There were no reports of injuries or fatalities.
Incident 2: At approximately 9:50 am EDT on September 24, 2020, FGT’s FLMEA-21 18-inch
pipeline ruptured and ejected multiple pieces of pipeline into the air. FGT’s gas control was
notified by a representative of the Lake Worth Drainage District that their pipeline was blowing
natural gas. FGT’s representative confirmed the leak on the 18-inch pipeline and the line was
isolated between FGT’s two compressor stations (FGT CS 21 and CS 21.5). At the incident site,
FGT found a 13-foot portion of ejected pipeline that landed approximately 400 feet downstream
from the rupture site on the median of Lake Worth Road, and an additional 8.3-foot piece of ejected
pipeline was located approximately 200 feet east of the rupture site in a retaining pond behind a
Florida Turnpike toll booth. The outside lane of northbound traffic on the Florida Turnpike was
closed while FGT assessed the damage and initiated repairs. A mobile phone emergency alert was
sent to those within a half-mile of the gas rupture notifying those persons to shelter-in-place or
evacuate. An unknown number of people were evacuated from commercial businesses and a
nearby elementary school. Evacuees were allowed to return to the area once the gas flow at the
rupture site was secured.
Pursuant to 49 U.S.C. § 60117, PHMSA, Office of Pipeline Safety (OPS), initiated investigations
of both Incident 1 and Incident 2. The preliminary findings of the agency’s ongoing investigations
are as follows:
Preliminary Findings for Incident 1:
 FGT initially reported Incident 1 to the National Response Center (NRC) at 2:24 am
EDT on September 10, 2020 (NRC Report No. 1286952), indicating that Reverse 911
notified 800 area homes and that the local sheriff reported the evacuation of 20 homes
when the 12-inch Sanford Lateral ruptured and ignited a fire. FGT provided an update
to NRC after 48 hours that indicated an estimated release of 22 million cubic feet
(MMCF) of natural gas and caused the evacuation of 20 homes. FGT also reported that
all evacuees had returned to their homes.
 There were no injuries or fatalities associated with Incident 1; however, there is burn
damage to the surrounding vegetation measuring 515 feet by 100 feet. Additionally,
three overhead powerlines owned by Duke Energy, that shared the right-of-way
(ROW), were damaged and knocked down.
 The rupture occurred near Mile Post 15 on the 12-inch Sanford Lateral (12-inch line or
Sanford Lateral) that feeds a Duke Energy Power Plant and several local distribution
company (LDC) meter stations.



CPF No. 4-2020-008-CAO
Page 3
 The Sanford Lateral was constructed in 1959 with a 12-inch nominal diameter, 0.219-
inch wall thickness, X-42 grade pipe that was manufactured by Youngstown Sheet and
Tube. The pipe has a low-frequency electric resistance welded (LF ERW) seam and
is coated with a tape coating. The length of the 12-inch Sanford Lateral was measured
at 15.9 miles by a 2019 in-line inspection (ILI) run. The Sanford Lateral is part of a
larger FGT unit with a total of 654 miles.
 The Sanford Lateral was manually shut in between upstream Valve 17-22U and
downstream Valve 17-22ERB. On the evening of September 10, 2020, FGT cut the
failed 12-inch pipeline and installed a pre-tested weld cap downstream from the lateral
to Sanford FPU meter station. The weld cap location is approximately 0.5 miles
upstream of rupture location and downstream of an FPU lateral to two customers
(Sanford West and Sanford FPU) line, allowing a return to service of the remainder of
the line.
 Service has been restored to all 125 customers that initially lost service. The isolated
segment of pipeline, including the site of the rupture, is approximately 1.4 miles in
length and remains out of service.
 The Maximum Operating Pressure of the 12-inch Sanford Lateral is 713 psig. The
operating pressure at the time of the rupture was 695 psig. The portion of the Sanford
Lateral that resumed operations is currently operating at 344 psig, which is fifty percent
(50%) of operating pressure at the time of rupture. This pressure restriction was put
into place by FGT.
 The operator reported that it performed ILI runs of the Sanford Lateral in 2014 and
2019. ILI correlation data from these runs show corrosion growth rates as high as 17
thousandths of an inch per year. The 2019 ILI run had a large amount of corrosion
indications in the vicinity of rupture, many over forty percent (40%).
 Most of the pipeline ROW appears to be located in swamp areas with heavy vegetation
along its borders, making the 12-inch line more susceptible to active external corrosion
than other locations. The line also reportedly has river weights in the vicinity of the
rupture, and throughout the entire area where high corrosion rates are present.
 Aerial mapping and alignment sheets show a mix of sparsely populated swamp and
residential and commercial properties in close proximity to ROW.
 There have been no previous reportable incidents on the Sanford Lateral. FGT reports
that a 2012 rupture occurred in Melbourne, Florida and a 2014 rupture occurred in Port
St. John, Florida. Both were on different pipelines in the unit that includes the Sanford
Lateral. The 2012 rupture involved 20-inch 1959 vintage Youngstown Sheet and Tube
LF ERW pipe and was classified as original manufacturing related (not weld). The
2014 rupture involved an 8-inch 1962 vintage LF ERW pipe manufactured by Lonestar,
and was also classified original manufacturing related (not weld).



CPF No. 4-2020-008-CAO
Page 4
 Pre-1970 LF ERW pipe has been the focus of many studies and reviews. A final report
TTO Number 5, Integrity Management Program Delivery Order DTRS56-02-D-70036,
Integrity Management Program regarding Low Frequency ERW and Lap Welded
Longitudinal Seam Evaluation (Revision 3) was prepared by Michael Baker in
association with Kiefner and Associates, Inc., CorrMet Engineering Services, PC in
April 2004.2 The report was written to support the importance of operators correctly
selecting integrity assessment methods capable of assessing seam integrity and of
detecting corrosion and deformation anomalies.
 PHMSA has issued Advisory Bulletins on the safety risks of Low-Frequency Welded
ERW and Flash-welded Pipe manufactured prior to 1970. It also issued Alert Notice,
ALN-88-01, in January 1988, advising owners and operators of natural gas and
hazardous liquids pipelines to consider the threat from ERW pipe manufactured prior
to 1970. The operators were advised to determine whether their pipelines were
susceptible to ERW seam failures and address the potential impact on pipeline
integrity.
Preliminary Findings for Incident 2:
 FGT initially reported Incident 2 to the NRC at 10:53 am EDT on September 24, 2020
(NRC Report No. 1288141), indicating that a rupture, with no fire, occurred on FGT’s
18-inch FLMEA-21 pipeline. FGT provided an update to NRC (NRC Report No.
1288281) after 48 hours that indicated an estimated release of 12 MMCF of natural gas.
There were no injuries or fatalities associated with Incident 2.
 The rupture occurred approximately 350 feet north of the intersection of the Florida
Turnpike exit ramp and Lake Worth Road in Lake Worth, Florida. The rupture location
is about six miles south of FGT’s upstream compressor station, and 24 miles north of
FGT’s downstream compressor station.
 The FLMEA-21 pipeline was constructed in 1959 with an 18-inch nominal diameter,
0.25-inch wall thickness, X-52 grade pipe that was manufactured by Youngstown Sheet
and Tube. The pipe has an LF ERW seam and is coated with cold applied tape. The
length of the FLMEA-21 pipeline is 67.04 miles.
 The FLMEA-21 pipeline supplies gas to power plants, industrial facilities, and LDCs
in South Florida. The 18-inch FLMEA-21 pipeline shares the ROW with FGT’s 24-
inch, FLMEB-21 pipeline, which runs parallel to the FLMEA-21 pipeline and is located
approximately 20 feet away. The FLMEB-21 pipeline experienced no apparent
collateral damage due to Incident 2.
 The FLMEA-21 pipeline is currently shut in between FGT’s Main Line Valve (MLV)
20-3 and MLV 20-4, approximately 15 miles. The segment is shut in and isolated from
2 See https://www.phmsa.dot.gov/sites/phmsa.dot.gov/files/docs/technical-resources/pipeline/hazardous-liquid-
integrity-management/64376/tto5lowfrequencyerwfinalreportrev3april2004.pdf (last accessed September 14, 2020).



CPF No. 4-2020-008-CAO
Page 5
the FLMEB-21 mainline from CS 21 (MP 838.5) to MLV 20-5R (MP 871.8). The
segment continues to remain out of service.
 The Maximum Operating Pressure of the FLMEA-21 is 866 psig. The operating
pressure at the time of the rupture was 846 psig.
 In 2017, FGT performed an ILI of the FLMEA-21 pipeline with no actionable
indications of anomalies reported within the area near the Florida Turnpike exit ramp
and Lake Worth Blvd.
 Much of FGT’s FLMEA-21 pipeline shares the ROW with FGT’s FLMEB-21 pipeline
and the Florida Turnpike.
 Aerial mapping shows heavily populated and travelled area in the vicinity of the
pipeline. The pipeline is parallel and in close proximity (4 to 5 feet) from a retaining
wall for the Florida Turnpike. The retaining wall was severely damaged as a result of
this incident.
 There has been one reportable incident on the FLMEA-21 pipeline since 2012 that was
attributed to Stress Corrosion Cracking (SCC). The reportable incident was a leak on
the pipeline that occurred in December 2012 in Lake Worth, Florida approximately
400-feet north of the rupture site for Incident 2. In addition, FGT experienced two in-
service incidents on pre-1970 LF-ERW pipe manufactured by Youngstown Sheet and
Tube. One involving SCC occurred in 2009 on the FLMEA-20 18-inch mainline and
resulted in Corrective Action Order CPF No. 2-2009-1002H. The second involved a
hook crack and hard spot (not SCC) and occurred in 2012 on the FLMEA-18 20-inch
mainline and resulted in Corrective Action Order CPF No. 2-2012-1005H.
 As discussed in the Preliminary Findings for Incident 1, pre-1970 LF ERW pipe has
been the focus of many studies and reviews, including those reports cited above.
PHMSA has also issued notices, including Advisory Bulletins and Alert Notices, on
the safety risks of LF ERW and Flash-welded Pipe manufactured prior to 1970, as well
as advising operators to determine whether their pipelines were susceptible to ERW
seam failures and address the potential impact on pipeline integrity.
Determination of Necessity for Corrective Action Order and Right to Hearing:
Section 60112 of title 49, United States Code, authorizes PHMSA to determine that a pipeline
facility is or would be hazardous to life, property, or the environment and, if there is a likelihood
of serious harm, to expeditiously order the operator of the facility to take necessary corrective
action, including suspended or restricted use of the facility, physical inspection, testing, repair,
replacement, or other appropriate action. An order issued expeditiously must provide an
opportunity for a hearing as soon as practicable after the order is issued.
In deciding whether to issue an order, PHMSA must consider the following, if relevant: (1) the



CPF No. 4-2020-008-CAO
Page 6
characteristics of the pipe and other equipment used in the pipeline facility, including the age,
manufacture, physical properties, and method of manufacturing, constructing, or assembling
the equipment; (2) the nature of the material the pipeline facility transports, the corrosive and
deteriorative qualities of the material, the sequence in which the material are transported, and
the pressure required for transporting the material; (3) the aspects of the area in which the
pipeline facility is located, including climatic and geologic conditions and soil characteristics;
(4) the proximity of the area in which the pipeline facility is located to environmentally
sensitive areas; (5) the population density and population and growth patterns of the area in
which the pipeline facility is located; (6) any recommendation of the National Transportation
Safety Board made under another law; and (7) other factors PHMSA may consider appropriate.
After evaluating the foregoing preliminary findings of fact, I find that the continued operation of
the Affected Pipelines, as defined below, without corrective measures is or would be hazardous to
life, property and the environment. Given that both Incident 1 and Incident 2 involved pre-1970
LF ERW pipe, and that there is an increased likelihood that there are other locations along the
pipelines subject to the same operational cycles and fatigue, there is a heightened risk for imminent
failures along the pipe. Furthermore, given that the area of the rupture for Incident 1 appears to
be at a low point in the line which is located in a swamp, there is an increased possibility of the
presence of moisture that may increase the likelihood of increased external corrosion. In fact,
recent ILI data of the Sanford Lateral showed indications of increased corrosion in the vicinity of
the rupture. As for Incident 2, the location of the pipeline and the rupture site is in close proximity
to populated areas, including the Florida Turnpike. Therefore, after considering the age of the
pipelines, the manufacturing methods, the hazardous nature of the products being transported, the
pressure required for transporting the materials, and the attributes of the ROWs for each pipeline,
as well as the uncertainties as to the causes of the incidents and the ongoing investigation, I find
that a failure to issue this Order expeditiously to require immediate corrective action would result
in likely serious harm to life, property, and the environment.
Accordingly, this Second ACAO mandating immediate corrective action is issued without prior
notice and opportunity for a hearing. The terms and conditions of this Order are effective upon
receipt.
Within 10 days of receipt of this Order, Respondent may request a hearing, to be held as soon as
practicable, by notifying the Associate Administrator for Pipeline Safety in writing, with a copy
to the Director, Southwest Region, PHMSA (Director). If a hearing is requested, it will be held in
accordance with 49 C.F.R. § 190.211.
After receiving and analyzing additional data in the course of this investigation, PHMSA may
identify other corrective measures that need to be taken. Respondent will be notified of any
additional measures required and, if appropriate, PHMSA will consider amending this Order. To
the extent consistent with safety, Respondent will be afforded notice and an opportunity for a
hearing prior to the imposition of any additional corrective measures.
Required Corrective Actions:
Definitions for Incident 1:



CPF No. 4-2020-008-CAO
Page 7
Incident 1 Affected Pipeline3 – Means the entire 15.9 miles of the 12-inch Sanford Lateral
operated by Florida Gas Transmission that transports natural gas from FGT’s 26-inch
mainline to the Sanford West and Sanford FPU meter station.
Incident 1 Isolated Segment – Means the portion of the Incident 1 Affected Pipeline
between the weld cap location (approximately MP 14.8) and Valve 17-22ERB that remains
out of service.
Definitions for Incident 2:
Incident 2 Affected Pipeline – Means approximately 124.6 miles of pre-1970 LF ERW
pipe contained in the 18-inch FLMEA pipeline system.
Incident 2 Isolated Segment– Means the approximate 15 miles of the 18-inch FLMEA-21
pipeline (i.e. Incident 2 Affected Pipeline) between FGT’s MLV 20-3 and FGT’s MLV 20-
4.
Pursuant to 49 U.S.C. 60112, I hereby order FGT to immediately take the following corrective
actions:
1. Shutdown of the Isolated Segments. The Incident 1 Isolated Segment and Incident 2
Isolated Segment (collectively Isolated Segments) are currently out of service and must
remain shut down until their restart in accordance with this Order.
2. Operating Pressure Restriction of the Affected Pipelines. FGT must maintain a fifty
percent (50%) pressure reduction in the actual operating pressure along the entire length of
the Incident 1 Affected Pipeline such that the operating pressure along the pipeline will not
exceed fifty percent (50%) of the actual operating pressure in effect immediately prior to
the failure on September 10, 2020. FGT must initiate and maintain a twenty percent (20%)
pressure reduction in the actual operating pressure along the entire length of the Incident 2
Affected Pipeline such that the operating pressure along the pipeline will not exceed eighty
percent (80%) of the actual operating pressure in effect immediately prior to the failure on
September 24, 2020.
a. This pressure restriction is to remain in effect until written approval to increase the
pressure or return the pipelines to their pre-failure operating pressure is obtained
from the Director.
b. FGT must provide the Director by October 2, 2020 for Incident 1 and October 15,
2020 for Incident 2, the actual operating pressures of each compressor station and
each main line pressure regulating station on the Incident 1 Affected Pipeline and
Incident 2 Affected Pipeline (collectively Affected Pipelines) at the time of failure
and the reduced pressure restriction set-points at these same locations.
3 The Corrective Action Order issued on September 18, 2020, referred to this pipeline as the “Affected Segment.”
To avoid confusion with the “Isolated Segment,” the pipeline is hereafter referred to as the “Incident 1 Affected
Pipeline.”



CPF No. 4-2020-008-CAO
Page 8
c. This pressure restriction requires any relevant remote or local alarm limits, software
programming set-points or control points, and mechanical over-pressure devices to
be adjusted accordingly.
d. When determining the pressure restriction set-points, FGT must take into account
any ILI features or anomalies present in the Affected Pipelines to provide for
continued safe operation while further corrective actions are completed.
e. FGT must review the pressure restriction monthly by analyzing the operating
pressure data. FGT must take into account any ILI features or anomalies present in
the Affected Pipelines and immediately reduce the operating pressure to maintain
the safe operations of the Affected Pipelines, if warranted by the monthly review.
3. Repair/Restart Plan. Prior to resuming operation of the Isolated Segments, FGT must
develop and submit a written Repair/Restart Plan for each of the Isolated Segments to the
Director for approval.
a. The Director may approve the Repair/Restart Plan incrementally without approving
the entire plan, but the Isolated Segments cannot resume operation until the
Repair/Restart Plan is approved in its entirety.
b. Once approved by the Director, the Repair/Restart Plan will be incorporated by
reference into this Order.
c. The Repair/Restart Plan must provide plans and procedures for the repair of the
isolated segment of the pipelines.
d. The Repair/Restart Plan must provide for adequate patrolling of the Isolated
Segment during the restart process and must include incremental pressure increases
during start up, with each increment to be held for at least two hours.
e. The Repair/Restart Plan must include sufficient surveillance of the pipeline during
each pressure increment to ensure that no leaks are present when operation of the
line resumes.
f. The Repair/Restart Plan must specify a day-light restart and include advance
communications with local emergency response officials.
g. The Repair/Restart Plan must provide for a review of the Isolated Segments for
conditions similar to those of the failure, including a review of construction,
operating and maintenance and integrity management records such as ILI results,
hydrostatic pressure tests, root cause failure analysis of prior failures, aerial and
ground patrols, corrosion, cathodic protection, excavations and pipe
replacements. FGT must address any findings that require remedial measures to be
implemented prior to restart.
h. The Repair/Restart Plan must also include documentation of the completion of all
mandated actions, and a management of change plan to ensure that all procedural



CPF No. 4-2020-008-CAO
Page 9
modifications are incorporated into FGT’s operations and maintenance procedures
4. 5. 6. 7. manual.
i. The Repair/Restart Plan must provide for hydrostatic pressure testing of the Isolated
Segments.
Return to Service. After the Director approves the Repair/Restart Plan, FGT may return
the Isolated Segments to service, but the operating pressures must not exceed the pressure
restriction in accordance with Item 2 above.
Removal of Pressure Restriction. The Director may allow the removal or modification of
the pressure restriction in Item 2 above upon a written request from FGT demonstrating
that restoring the pipeline to its pre-failure operating pressure is justified based on a reliable
engineering analysis showing that the pressure increase is safe considering all known
defects, anomalies, and operating parameters of the pipeline.
a. The Director may allow the temporary removal or modification of the pressure
restrictions upon a written request from FGT demonstrating that temporary
mitigative and preventive measures are implemented prior to and during the
temporary removal or modification of the pressure restriction. The Director's
determination will be based on the known or suspected failure cause and provision
of evidence that preventative and mitigative actions taken by the operator provide
for the safe operation of the Affected Pipelines during the temporary removal or
modification of the pressure restriction. Appeals to determinations of the Director
in this regard will be decided by the Associate Administrator for Pipeline Safety.
Instrumented Leakage Survey. By October 18, 2020 for Incident 1, and October 31, 2020
for Incident 2, FGT must perform an aerial or ground instrumented leakage survey of the
Affected Pipelines. FGT must investigate all leak indications and remedy all leaks
discovered. FGT must submit documentation of this survey to the Director by November
2, 2020 for Incident 1, and within 45 calendar days of receipt of this Order for Incident 2.
Records Verification. As recommended in PHMSA Advisory Bulletin 2012-06, FGT must
verify the records for the Affected Pipelines to confirm the maximum allowable operating
pressure. FGT must submit documentation of this record verification to the Director by
November 2, 2020 for Incident 1, and within 45 calendar days of receipt of this Order for
Incident 2.
8. Review of Prior Inline Inspection Results. By October 18, 2020 for Incident 1, and
October 31, 2020 for Incident 2, FGT with the assistance of an outside third party, approved
by PHMSA, must conduct a review of any previous ILI results of the Affected Pipelines to
re-evaluate all ILI results from the past five calendar years, include a review of the ILI
vendors' raw data and analysis, and determine whether any features were present in the
failed pipe joint and any other pipe removed. Also, determine if any features with similar
characteristics are present elsewhere on the Affected Pipelines. FGT must submit
documentation of this ILI review to the Director by November 2, 2020 for Incident 1, and
November 15, 2020 for Incident 2.



CPF No. 4-2020-008-CAO
Page 10
a. List all ILI tool runs, tool types, and the calendar years of the tool runs. Provide ILI
results data, as requested, to PHMSA.
b. List, describe (type, size, wall loss, etc.), and identify the specific location of all ILI
features present in the failed joint and/or other pipe removed.
c. List, describe (type, size, wall loss, etc.), and identify the specific location of all ILI
features with similar characteristics present elsewhere on the Affected Pipelines.
d. Explain the process used to review the ILI results and the results of the reevaluation.
9. Mechanical and Metallurgical Testing. By November 2, 2020 for Incident 1, and
November 15, 2020 for Incident 2, FGT must submit for approval a plan for mechanical
and metallurgical testing and failure analysis of the failed pipe, including an analysis of
soil samples and any foreign materials, by an approved independent third-party laboratory.
Complete the testing and analysis as follows:
a. Document the chain-of-custody when handling and transporting the failed pipe
sections and other evidence from the failure sites.
b. Within 10 calendar days of receipt of this Order for Incident 2, FGT must develop
and submit the testing protocol and the proposed testing laboratory to the Director
for prior approval.
c. Prior to beginning the mechanical and metallurgical testing, provide the Director
with the scheduled date, time, and location of the testing to allow for an OPS
representative to witness the testing.
d. Ensure the testing laboratory distributes all reports whether draft or final in their
entirety to the Director at the same time they are made available to FGT.
10. Root Cause Failure Analysis. By December 17, 2020 for Incident 1, and December 30,
2020 for Incident 2, FGT must complete a root cause failure analysis (RCFA) and submit
a final report of this RCFA to the Director. The RCFAs must be supplemented or
facilitated by an independent third-party acceptable to the Director and must document the
decision-making process and all factors contributing to the failure. The final reports must
include findings and any lessons learned and whether the findings and any lessons learned
are applicable to other locations within FGT’s pipeline system.
11. Remedial Work Plan.
a. By December 17, 2020 for Incident 1, and December 30, 2020 for Incident 2, FGT
must submit Remedial Work Plan(s) (RWP) to the Director for approval. The
Director may approve the RWPs incrementally without approving the entire RWP.
FGT may also submit one RWP for both Incidents by December 17, 2020.
b. Once approved by the Director, the RWP(s) will be incorporated by reference into
this Order, and FGT must implement the RWP(s) as it is approved by the Director,
including any revisions to the plan.



CPF No. 4-2020-008-CAO
Page 11
c. The RWP(s) must specify the tests, inspections, assessments, evaluations, and
remedial measures FGT will use to verify the integrity of the Affected Pipelines. It
must address all known or suspected factors and causes of the September 10, 2020
and September 24, 2020 failures. FGT should consider both the risk of another
failure and the consequence of another failure to develop a prioritized schedule for
RWP related work along the Affected Pipelines.
d. The RWP must include a procedure or process to:
i. Identify pipe in the Affected Pipelines and other pipelines in the FGT
operating areas with characteristics similar to the contributing factors
identified for the September 10, 2020 and September 24, 2020 failures.
ii. Gather all data necessary to review the failure history (in service and
pressure test failures) of the Affected Pipelines and to prepare a written
report containing all the available information such as the locations, dates,
and causes of leaks and failures.
iii. Integrate the results of the metallurgical testing, root cause failure analysis,
and other corrective actions required by this Order with all relevant pre-
existing operational and assessment data for the Affected Pipelines. Pre-
existing operational data includes, but is not limited to, manufacturing and
construction, operations, maintenance, testing, repairs, prior metallurgical
analyses, and any third-party consultation information. Pre-existing
assessment data includes, but is not limited to, ILI tool runs, hydrostatic
pressure testing, direct assessments, close interval surveys, and direct or
alternating current voltage gradient surveys.
iv. Determine if conditions similar to those contributing to the failures on
September 10, 2020 and September 24, 2020 are likely to exist elsewhere
on FGT’s operational pipelines.
v. Conduct additional field tests, inspections, assessments, and/or evaluations
necessary to determine whether, and to what extent, the conditions
associated with the failures on September 10, 2020 and September 24, 2020,
and other failures from the failure history in Item 11(d)(ii) above or any
other integrity threats are present elsewhere on the Affected Pipelines or
other systems operated by FGT. At a minimum, this process must consider
all failure causes and specify the use of one or more of the following:
1. ILI tools that are technically appropriate for assessing the pipeline
system based on the cause of failures on September 10, 2020 and
September 24, 2020, and that can reliably detect and identify
anomalies;
2. Hydrostatic pressure testing;
3. Close-interval surveys;



e. f. CPF No. 4-2020-008-CAO
Page 12
4. Cathodic protection surveys, to include interference surveys in
coordination with other utilities (e.g. underground utilities,
overhead power lines, etc.) in the area;
5. Coating surveys;
6. Stress corrosion cracking surveys;
7. Selective seam corrosion surveys; and
8. Other tests, inspections, assessments, and evaluations appropriate
for the failure causes.
FGT may use the results of previous tests, inspections, assessments, and
evaluations if approved by the Director, provided the results of the tests,
inspections, assessments, and evaluations are analyzed with regard to the
factors known or suspected to have caused the September 10, 2020 and
September 24, 2020 failures.
vi. Describe the inspection and repair criteria FGT will use to prioritize,
excavate, evaluate, and repair anomalies, imperfections, and other identified
integrity threats. Include a description of how any defects will be graded
and a schedule for repairs or replacement.
vii. Based on the known history and condition of the Affected Pipelines,
describe the methods FGT will use to repair, replace, or take other
corrective measures to remediate the conditions associated with the pipeline
failures on September 10, 2020 and September 24, 2020, and to address
other known integrity threats along the Affected Pipelines. The repair,
replacement, or other corrective measures must meet the criteria specified
in Item 11(d)(vi) above.
viii. Implement continuing long-term periodic testing and integrity verification
measures to ensure the ongoing safe operation of the Affected Pipelines
considering the results of the analyses, inspections, evaluations, and
corrective measures undertaken pursuant to the Order.
The RWP must include a schedule for completion.
FGT must revise the RWP(s) as necessary to incorporate new information obtained
during the failure investigation and remedial activities, to incorporate the results of
actions undertaken pursuant to this Order, and to incorporate any modifications
required by the Director.
i. Submit any plan revisions to the Director for prior approval.
ii. The Director may approve plan revisions incrementally.



CPF No. 4-2020-008-CAO
Page 13
iii. Any and all revisions to the RWP(s) after it has been approved and
incorporated by reference into this Order will be fully described and
documented in the CAO Documentation Report (CDR).
12. CAO Documentation Report. When FGT has concluded all the items in this Order, it will
submit the final CDR in its entirety to the Director. This will allow the Director to complete
a thorough review of all actions taken by FGT with regards to this Order prior to approving
the closure of this Order. The intent is for the CDR to summarize all activities and
documentation associated with this Order in one document.
a. The Director may approve the CDR incrementally without approving the entire
CDR.
b. Once approved by the Director, the CDR will be incorporated by reference into this
Order.
c. The CDR must include, but is not necessarily limited to, the following elements:
i. Table of Contents;
ii. Summary of the pipeline failures of September 10, 2020 and September 24,
2020, and the response activities;
iii. Summary of pipe data/properties and all prior assessments of the Affected
Pipelines;
iv. Summary of all tests, inspections, assessments, evaluations, and analysis
required by the Order;
v. Summary of the Mechanical and Metallurgical Testing as required by the
Order;
vi. Summary of the RCFA with all root causes as required by the Order;
vii. Documentation of all actions taken by FGT to implement the RWP(s), the
results of those actions, and the inspection and repair criteria used;
viii. Documentation of any revisions to the RWP(s) including those necessary to
incorporate the results of actions undertaken pursuant to this Order and
whenever necessary to incorporate new information obtained during the
failure investigation and remedial activities;
ix. Lessons learned while completing this Order;
x. A path forward describing specific actions FGT will take on its entire
pipeline system as a result of the lessons learned from work on this Order;
and
xi. Other Appendices as required.
Other Requirements:



CPF No. 4-2020-008-CAO
Page 14
13. Approvals. With respect to each submission that under this Order requires the approval of
the Director, the Director may: (a) approve, in whole or part, the submission; (b) approve
the submission on specified conditions; (c) modify the submission to cure any deficiencies;
(d) disapprove in whole or in part, the submission, directing that Respondent modify the
submission, or (e) any combination of the above. In the event of approval, approval upon
conditions, or modification by the Director, Respondent shall proceed to take all action
required by the submission as approved or modified by the Director. If the Director
disapproves all or any portion of the submission, Respondent must correct all deficiencies
within the time specified by the Director, and resubmit it for approval.
14. Extensions of Time. The Director may grant an extension of time for compliance with any
of the terms of this Order upon a written request timely submitted demonstrating good
cause for an extension.
15. Reporting. Submit quarterly reports to the Director that: (1) include all available data and
results of the testing and evaluations required by this Order; and (2) describe the progress
of the repairs or other remedial actions being undertaken. The first quarterly report is due
on December 31, 2020. The Director may change the interval for the submission of these
reports.
16. Documentation of the Costs. It is requested but not required that Respondent maintain
documentation of the costs associated with implementation of this Order. Include in each
quarterly report submitted, the to-date total costs associated with: (1) preparation and
revision of procedures, studies and analyses; (2) physical changes to pipeline infrastructure,
including repairs, replacements and other modifications; and (3) environmental
remediation, if applicable.
Be advised that all material you submit in response to this enforcement action is subject to being
made publicly available. If you believe that any portion of your responsive material qualifies for
confidential treatment under 5 U.S.C. § 552(b), along with the complete original document you
must provide a second copy of the document with the portions you believe qualify for confidential
treatment redacted and an explanation of why you believe the redacted information qualifies for
confidential treatment under 5 U.S.C. § 552(b).
In your correspondence on this matter, please refer to “CPF No. 4-2020-008-CAO” and for each
document you submit, please provide a copy in electronic format whenever possible. The actions
required by this Order are in addition to and do not waive any requirements that apply to
Respondent’s pipeline system under 49 C.F.R. Parts 190 through 199, under any other order issued
to Respondent under authority of 49 U.S.C. Chapter 601, or under any other provision of Federal
or State law.
Respondent may appeal any decision of the Director to the Associate Administrator for Pipeline
Safety. Decisions of the Associate Administrator shall be final.
Failure to comply with this Order may result in the assessment of civil penalties and in referral to



CPF No. 4-2020-008-CAO
Page 15
the Attorney General for appropriate relief in United States District Court pursuant to
49 U.S.C. § 60120.
The terms and conditions of this Order are effective upon service in accordance with 49 C.F.R.
§ 190.5.
October 22, 2020
_________________________________ ________________________
Alan K. Mayberry Date Issued
Associate Administrator
for Pipeline Safety

42020008CAO_Corrective Action Order_09182020_(20-190995)_text.pdf

September 18, 2020
VIA ELECTRONIC MAIL TO: matthew.ramsey@energytransfer.com
Matthew Ramsey
Chief Operating Officer
Energy Transfer Partners, LP
8111 Westchester Drive
Dallas, Texas 75225
CPF No. 4-2020-008-CAO
Dear Mr. Ramsey:
Enclosed please find a Corrective Action Order (CAO) issued by the Pipeline and Hazardous
Materials Safety Administration (PHMSA), Office of Pipeline Safety (OPS), in the above-
referenced case. It requires Florida Gas Transmission Company, which is operated by Energy
Transfer Partners, LP, to take certain corrective actions with respect to a rupture that occurred on
the 12-inch Sanford Lateral located in Sanford, Florida.
Service of the CAO by electronic transmission is deemed complete upon transmission and
acknowledgement of receipt, or as otherwise provided under 49 C.F.R. § 190.5. The terms and
conditions of this Order are effective upon completion of service.
Sincerely,
Alan K. Mayberry
Associate Administrator
for Pipeline Safety
Enclosure: CAO
cc: Ms. Linda Daugherty, Deputy Associate Administrator for Field Operations, OPS
Ms. Mary McDaniel, Director, Southwestern Region, OPS
Mr. Eric Amundson, Senior Vice President, Energy Transfer Partners, LP,
eric.amundson@energytransfer.com
Ms. Kathryn Harryman, DOT Compliance, Florida Gas Transmission Company,
kathryn.harryman@energytransfer.com



U.S. DEPARTMENT OF TRANSPORTATION
PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION
OFFICE OF PIPELINE SAFETY
WASHINGTON, D.C. 20590
____________________________________
In the Matter of )
Florida Gas Transmission Company, )
)
)
)
Respondent. )
____________________________________)
CPF No. 4-2020-008-CAO
CORRECTIVE ACTION ORDER
Purpose and Background:
This Corrective Action Order (CAO or Order) is being issued under the authority of 49 U.S.C.
§ 60112 to require Florida Gas Transmission Company (FGT or Respondent), which is operated
by Energy Transfer Partners, LP,1 to take the necessary corrective actions to protect the public,
property, and the environment from potential hazards associated with the September 10, 2020
rupture and ignition from its 12-inch Sanford Lateral natural gas pipeline in Sanford, Florida
located in Seminole County (Incident).
In the early morning of September 10, 2020, FGT’s 12-inch Sanford Lateral ruptured and
subsequently ignited. Prior to the rupture, at 12:47am EDT, the line was operating at 688 pounds
per square inch (psig) between the Sanford station and the DeBary station. At 12:52 am EDT, the
pressure reading at Sanford dropped to 409 psig and steadily decreased from that point. FGT’s
Control Room detected the drop in pressure and had the valves upstream and downstream
(upstream Valve 17-22U and downstream Valve 17-216B) of the failure site manually closed. At
2:08 am EDT the line was shut in. The size of the burn area around the rupture site was determined
to be 515 feet by 100 feet.
Reverse 911 notified 800 area homes and the local sheriff reported 20 homes were evacuated. The
fire was extinguished, and evacuated residents were allowed to return home within hours of the
Incident. There were no reports of injuries or fatalities.
Pursuant to 49 U.S.C. § 60117, PHMSA, Office of Pipeline Safety (OPS), initiated an investigation
of the Incident. The preliminary findings of the agency’s ongoing investigation are as follows:
1 FGT is an approximately 5,300-mile system that transports natural gas from South Texas to South Florida. FGT is
owned by Florida Gas Transmission Company, LLC, a 100 percent owned subsidiary of Citrus Corp. Citrus Corp is
a 50/50 joint venture between Kinder Morgan, Inc. and Energy Transfer Partners, LP. FGT is operated by Energy
Transfer. See https://www kindermorgan.com/Operations/Natural-Gas/Index (last accessed September 14, 2020).



CPF No. 4-2020-008-CAO
Page 2
Preliminary Findings:
 FGT initially reported the Incident to the National Response Center (NRC) at 2:24 am
EDT on September 10, 2020 (NRC Report No. 1286952), indicating that Reverse 911
notified 800 area homes and that the local sheriff reported the evacuation of 20 homes
when the 12-inch Sanford Lateral ruptured and ignited a fire. FGT provided an update
to NRC after 48 hours that indicated an estimated release of 22 million cubic feet of
natural gas and caused the evacuation of 20 homes. FGT also reported that all evacuees
had returned to their homes.
 There were no injuries or fatalities associated with this Incident; however, there is burn
damage to the surrounding vegetation measuring 515 feet by 100 feet. Additionally,
three overhead powerlines owned by Duke Energy, that shared the right-of-way
(ROW), were damaged and knocked down.
 The rupture occurred near Mile Post 15 on the 12-inch Sanford Lateral (12-inch line or
Sanford Lateral) that feeds a Duke Energy Power Plant and a Sanford Florida Public
Utilities (FPU) meter station.
 The Sanford Lateral was constructed in 1959 with a 12-inch nominal diameter, 0.219-
inch wall thickness, X-42 grade pipe that was manufactured by Youngstown Sheet and
Tube. The pipe has a low-frequency electric resistance welded (LF ERW) seam and
is coated with a tape coating. The length of the 12-inch Sanford Lateral was measured
at 15.9 miles by a 2019 in-line inspection (ILI) run. The Sandford Lateral is part of a
larger FGT unit with a total of 654 miles.
 The Sanford Lateral was manually shut in between upstream Valve 17-22U and
downstream Valve 17-216B. On the evening of September 10, 2020, FGT cut the failed
12-inch pipeline and installed a pre-tested weld cap downstream from the lateral to
Sanford FPU meter station. The weld cap location is approximately 0.5 miles upstream
of rupture location and downstream of a FPU lateral to two customers (Sanford West
and Sanford FPU) line, allowing a return to service of the remainder of the line.
 Service has been restored to all 125 customers that initially lost service. The isolated
segment of pipeline, including the site of the rupture, is approximately 1.4 miles in
length and remains out of service.
 The Maximum Operating Pressure of the 12-inch Sanford Lateral is 713 psig. The
operating pressure at the time of the rupture was 688 psig. The portion of the Sanford
Lateral that resumed operations is currently operating at 344 psig, which is fifty percent
(50%) of operating pressure at the time of rupture. This pressure restriction was put
into place by FGT.
 The operator reported that it performed ILI runs of the Sanford Lateral in 2014 and
2019. ILI correlation data from these runs show corrosion growth rates as high as 17



CPF No. 4-2020-008-CAO
Page 3
millimeters per year. The 2019 ILI run had a large amount of corrosion indications in
the vicinity of rupture, many over forty percent (40%).
 Most of the pipeline ROW appears to be located in swamp areas with heavy vegetation
along its borders, making the 12-inch line more susceptible to active external corrosion
than other locations. The line also reportedly has river weights in the vicinity of the
rupture, and throughout the entire area where high corrosion rates are present.
 Aerial mapping and alignment sheets show a mix of sparsely populated swamp and
residential and commercial properties in close proximity to ROW.
 There have been no previous reportable incidents on the Sanford Lateral. FGT reports
that a 2012 rupture occurred in Melbourne, Florida and a 2014 rupture occurred in Port
St. John, Florida. Both were on different pipelines in the unit that includes the Sanford
Lateral. The 2012 rupture involved 1959 vintage Youngstown Tube and Steel LF ERW
pipe and was classified as original manufacturing related (not weld). The 2014 rupture
involved 1962 vintage LF ERW pipe manufactured by Lonestar, and was also classified
original manufacturing related (not weld).
 Pre-1970 LF ERW pipe has been the focus of many studies and reviews. A final report
TTO Number 5, Integrity Management Program Delivery Order DTRS56-02-D-70036,
Integrity Management Program regarding Low Frequency ERW and Lap Welded
Longitudinal Seam Evaluation (Revision 3) was prepared by Michael Baker in
association with Kiefner and Associates, Inc., CorrMet Engineering Services, PC in
April 2004.2 The report was written to support the importance of operators correctly
selecting integrity assessment methods capable of assessing seam integrity and of
detecting corrosion and deformation anomalies.
 PHMSA has issued Advisory Bulletins on the safety risks of Low-Frequency Welded
ERW and Flash-welded Pipe manufactured prior to 1970. It also issued Alert Notice,
ALN-88-01, in January 1988, advising owners and operators of natural gas and
hazardous liquids pipelines to consider the threat from ERW pipe manufactured prior
to 1970. The operators were advised to determine whether their pipelines were
susceptible to ERW seam failures and address the potential impact on pipeline
integrity.
Determination of Necessity for Corrective Action Order and Right to Hearing:
Section 60112 of Title 49, United States Code, provides for the issuance of a CAO, after reasonable
notice and the opportunity for a hearing, requiring corrective action, which may include the
suspended or restricted use of a pipeline facility, physical inspection, testing, repair, replacement,
or other action, as appropriate. The basis for making the determination that a pipeline facility is
2 See https://www.phmsa.dot.gov/sites/phmsa.dot.gov/files/docs/technical-resources/pipeline/hazardous-liquid-
integrity-management/64376/tto5lowfrequencyerwfinalreportrev3april2004.pdf (last accessed September 14, 2020).



CPF No. 4-2020-008-CAO
Page 4
hazardous and requiring corrective action is set forth both in the above-referenced statute and
49 C.F.R.§ 190.233.
Section 60112, and the regulations promulgated thereunder, provide for the issuance of a CAO
without prior opportunity for notice and hearing upon a finding that failure to issue the Order
expeditiously will likely result in serious harm to life, property or the environment. In such cases,
an opportunity for a hearing will be provided as soon as practicable after the issuance of the Order.
After evaluating the foregoing preliminary findings of fact, I find that the continued operation of
the Affected Segment, as defined below, without corrective measures is or would be hazardous to
life, property and the environment. Given that this is a pre-1970 LF ERW pipe, there is an
increased likelihood that there are other locations along the pipe that are subject to the same
operational cycles and fatigue, heightening the risk of imminent failures along the pipe.
Furthermore, given that the area of the rupture appears to be at a low point in the line which is
located in a swamp, there is an increased possibility of the presence of moisture that may increase
the likelihood of increased external corrosion. In fact, recent ILI data showed indications of
increased corrosion in the vicinity of the rupture. Therefore, after considering the age of the pipe,
the manufacturing method, the hazardous nature of the product being transported, the pressure
required for transporting the material, the attributes of the ROW, the uncertainties as to the cause
of the Incident, and the ongoing investigation of the Incident, I find that a failure to issue this Order
expeditiously to require immediate corrective action would result in likely serious harm to life,
property, and the environment.
Accordingly, this CAO mandating immediate corrective action is issued without prior notice and
opportunity for a hearing. The terms and conditions of this Order are effective upon receipt.
Within 10 days of receipt of this Order, Respondent may request a hearing, to be held as soon as
practicable, by notifying the Associate Administrator for Pipeline Safety in writing, with a copy
to the Director, Southwest Region, PHMSA (Director). If a hearing is requested, it will be held in
accordance with 49 C.F.R. § 190.211.
After receiving and analyzing additional data in the course of this investigation, PHMSA may
identify other corrective measures that need to be taken. Respondent will be notified of any
additional measures required and, if appropriate, PHMSA will consider amending this Order. To
the extent consistent with safety, Respondent will be afforded notice and an opportunity for a
hearing prior to the imposition of any additional corrective measures.
Required Corrective Actions:
Definitions:
Affected Segment – Means the entire 15.9 miles of the 12-inch Sanford Lateral operated
by Florida Gas Transmission that transports natural gas from FGT’s 26-inch mainline to
the serve the Duke Power Plant and Sanford FPU meter station.
Isolated Segment – Means the portion of the Affected Segment between the weld cap
location (approximately MP 14.5) and Valve 17-216B that remains out of service.



CPF No. 4-2020-008-CAO
Page 5
Pursuant to 49 U.S.C. 60112, I hereby order FGT to immediately take the following corrective
actions for the Isolated and Affected Segments:
1. Shutdown of the Isolated Segment. The Isolated Segment is currently out of service and
must remain shut down until its restart in accordance with this Order.
2. Operating Pressure Restriction of the Affected Segment. FGT must maintain a fifty
percent (50%) pressure reduction in the actual operating pressure along the entire length of
the Affected Segment such that the operating pressure along the Affected Segment will not
exceed fifty percent (50%) of the actual operating pressure in effect immediately prior to
the failure on September 10, 2020.
3. a. This pressure restriction is to remain in effect until written approval to increase the
pressure or return the pipeline to its pre-failure operating pressure is obtained from
the Director.
b. Within 14 calendar days of receipt of the Order, FGT must provide the Director the
actual operating pressures of each compressor station and each main line pressure
regulating station on the Affected Segment at the time of failure and the reduced
pressure restriction set-points at these same locations.
c. This pressure restriction requires any relevant remote or local alarm limits, software
programming set-points or control points, and mechanical over-pressure devices to
be adjusted accordingly.
d. When determining the pressure restriction set-points, FGT must take into account
any ILI features or anomalies present in the Affected Segment to provide for
continued safe operation while further corrective actions are completed.
e. FGT must review the pressure restriction monthly by analyzing the operating
pressure data. Take into account any ILI features or anomalies present in the
Affected Segment and immediately reduce the operating pressure to maintain the
safe operations of the Affected Segment, if warranted by the monthly review.
Restart Plan. Prior to resuming operation of the Isolated Segment, FGT must develop and
submit a written Restart Plan to the Director for approval.
a. The Director may approve the Restart Plan incrementally without approving the
entire plan but the Isolated Segment cannot resume operation until the Restart Plan
is approved in its entirety.
b. Once approved by the Director, the Restart Plan will be incorporated by reference
into this Order.
c. The Restart Plan must provide for adequate patrolling of the Isolated Segment
during the restart process and must include incremental pressure increases during
start up, with each increment to be held for at least two hours.



CPF No. 4-2020-008-CAO
Page 6
d. The Restart Plan must include sufficient surveillance of the pipeline during each
pressure increment to ensure that no leaks are present when operation of the line
resumes.
e. The Restart Plan must specify a day-light restart and include advance
communications with local emergency response officials.
f. The Restart Plan must provide for a review of the Isolated Segment for conditions
similar to those of the failure including a review of construction, operating and
maintenance and integrity management records such as ILI results, hydrostatic
pressure tests, root cause failure analysis of prior failures, aerial and ground patrols,
corrosion, cathodic protection, excavations and pipe replacements. FGT must
address any findings that require remedial measures to be implemented prior to
restart.
g. The Restart Plan must also include documentation of the completion of all
mandated actions, and a management of change plan to ensure that all procedural
modifications are incorporated into FGT’s operations and maintenance procedures
manual.
h. The Restart Plan must provide for hydrostatic pressure testing of the Isolated
Segment.
i. Prior to restart, submit to the Director a contingency plan to operate and monitor
the Isolated Segment during flooding conditions, including enhanced patrolling and
surveillance.
4. Return to Service. After the Director approves the Restart Plan, FGT may return the
Isolated Segment to service but the operating pressure must not exceed fifty percent (50%)
of the actual operating pressure in effect immediately prior to the failure on September 10,
2020, in accordance with Item 2 above.
5. Removal of Pressure Restriction. The Director may allow the removal or modification of
the pressure restriction upon a written request from FGT demonstrating that restoring the
pipeline to its pre-failure operating pressure is justified based on a reliable engineering
analysis showing that the pressure increase is safe considering all known defects,
anomalies, and operating parameters of the pipeline.
a. The Director may allow the temporary removal or modification of the pressure
restrictions upon a written request from FGT demonstrating that temporary
mitigative and preventive measures are implemented prior to and during the
temporary removal or modification of the pressure restriction. The Director's
determination will be based on the known or suspected failure cause and provision
of evidence that preventative and mitigative actions taken by the operator provide
for the safe operation of the Affected Segment during the temporary removal or
modification of the pressure restriction. Appeals to determinations of the Director
in this regard will be decided by the Associate Administrator for Pipeline Safety.



6. 7. 8. 9. CPF No. 4-2020-008-CAO
Page 7
Instrumented Leakage Survey. Within 30 calendar days of receipt of this Order, FGT must
perform an aerial or ground instrumented leakage survey of the Affected Segment. FGT
must investigate all leak indications and remedy all leaks discovered. FGT must submit
documentation of this survey to the Director within 45 days of receipt of this Order.
Records Verification. As recommended in PHMSA Advisory Bulletin 2012-06, verify the
records for the Affected Segment to confirm the maximum allowable operating
pressure. FGT must submit documentation of this this record verification to the Director
within 45 days of receipt of this Order.
Review of Prior Inline Inspection Results. Within 30 days of receipt of this Order, FGT
must conduct a review of any previous ILI results of the Affected Segment to re-evaluate
all ILI results from the past five calendar years, include a review of the ILI vendors' raw
data and analysis, and determine whether any features were present in the failed pipe joint
and any other pipe removed. Also, determine if any features with similar characteristics
are present elsewhere on the Affected Segment. FGT must submit documentation of this
ILI review to the Director within 45 days of receipt of this Order as follows:
a. List all ILI tool runs, tool types, and the calendar years of the tool runs.
b. List, describe (type, size, wall loss, etc.), and identify the specific location of all ILI
features present in the failed joint and/or other pipe removed.
c. List, describe (type, size, wall loss, etc.), and identify the specific location of all ILI
features with similar characteristics present elsewhere on the Affected Segment.
d. Explain the process used to review the ILI results and the results of the reevaluation.
Mechanical and Metallurgical Testing. Within 45 days of receipt of this Order, submit
for approval a plan for mechanical and metallurgical testing and failure analysis of the
failed pipe, including an analysis of soil samples and any foreign materials, by an approved
independent third-party laboratory. Complete the testing and analysis as follows:
a. Document the chain-of-custody when handling and transporting the failed pipe
section and other evidence from the failure site.
b. Within 10 days of receipt of this Order, develop and submit the testing protocol and
the proposed testing laboratory to the Director for prior approval.
c. Prior to beginning the mechanical and metallurgical testing, provide the Director
with the scheduled date, time, and location of the testing to allow for an OPS
representative to witness the testing.
d. Ensure the testing laboratory distributes all reports whether draft or final in their
entirety to the Director at the same time they are made available to FGT.
10. Root Cause Failure Analysis. Within 90 days following receipt of this Order, complete a
root cause failure analysis (RCFA) and submit a final report of this RCFA to the
Director. The RCFA must be supplemented or facilitated by an independent third-party
acceptable to the Director and must document the decision-making process and all factors



CPF No. 4-2020-008-CAO
Page 8
contributing to the failure. The final report must include findings and any lessons learned
and whether the findings and any lessons learned are applicable to other locations within
FGT’s pipeline system.
11. Remedial Work Plan.
a. Within 90 days following receipt of this Order, FGT must submit a Remedial Work
Plan (RWP) to the Director for approval. The Director may approve the RWP
incrementally without approving the entire RWP.
b. Once approved by the Director, the RWP will be incorporated by reference into this
Order, and FGT must implement the RWP as it is approved by the Director,
including any revisions to the plan.
c. The RWP must specify the tests, inspections, assessments, evaluations, and
remedial measures FGT will use to verify the integrity of the Affected Segment. It
must address all known or suspected factors and causes of the September 10, 2020
failure. FGT should consider both the risk of another failure and the consequence
of another failure to develop a prioritized schedule for RWP related work along the
Affected Segment.
d. The RWP must include a procedure or process to:
i. Identify pipe in the Affected Segment and other pipelines in the FGT
operating areas with characteristics similar to the contributing factors
identified for the September 10, 2020 failure.
ii. Gather all data necessary to review the failure history (in service and
pressure test failures) of the Affected Segment and to prepare a written
report containing all the available information such as the locations, dates,
and causes of leaks and failures.
iii. Integrate the results of the metallurgical testing, root cause failure analysis,
and other corrective actions required by this Order with all relevant pre-
existing operational and assessment data for the Affected Segment. Pre-
existing operational data includes, but is not limited to, manufacturing and
construction, operations, maintenance, testing, repairs, prior metallurgical
analyses, and any third-party consultation information. Pre-existing
assessment data includes, but is not limited to, ILI tool runs, hydrostatic
pressure testing, direct assessments, close interval surveys, and
DCVG/ACVG surveys.
iv. Determine if conditions similar to those contributing to the failure on
September 10, 2020 are likely to exist elsewhere on FGT’s operational
pipelines.
v. Conduct additional field tests, inspections, assessments, and/or evaluations
necessary to determine whether, and to what extent, the conditions
associated with the failure on September 10, 2020, and other failures from



CPF No. 4-2020-008-CAO
Page 9
the failure history in Item 11(d)(ii) above or any other integrity threats are
present elsewhere on the Affected Segment or other systems operated by
FGT. At a minimum, this process must consider all failure causes and
specify the use of one or more of the following:
1. ILI tools that are technically appropriate for assessing the pipeline
system based on the cause of failure on September 10, 2020, and
that can reliably detect and identify anomalies;
2. Hydrostatic pressure testing;
3. Close-interval surveys;
4. Cathodic protection surveys, to include interference surveys in
coordination with other utilities (e.g. underground utilities,
overhead power lines, etc.) in the area;
5. Coating surveys;
6. Stress corrosion cracking surveys;
7. Selective seam corrosion surveys; and
8. Other tests, inspections, assessments, and evaluations appropriate
for the failure causes.
FGT may use the results of previous tests, inspections, assessments, and
evaluations if approved by the Director, provided the results of the tests,
inspections, assessments, and evaluations are analyzed with regard to the
factors known or suspected to have caused the September 10, 2020 failure.
vi. Describe the inspection and repair criteria FGT will use to prioritize,
excavate, evaluate, and repair anomalies, imperfections, and other identified
integrity threats. Include a description of how any defects will be graded
and a schedule for repairs or replacement.
vii. Based on the known history and condition of the Affected Segment,
describe the methods FGT will use to repair, replace, or take other
corrective measures to remediate the conditions associated with the pipeline
failure on September 10, 2020, and to address other known integrity threats
along the Affected Segment. The repair, replacement, or other corrective
measures must meet the criteria specified in Item 11(d)(vi) above.
viii. Implement continuing long-term periodic testing and integrity verification
measures to ensure the ongoing safe operation of the Affected Segment
considering the results of the analyses, inspections, evaluations, and
corrective measures undertaken pursuant to the Order.
e. The RWP must include a schedule for completion.



CPF No. 4-2020-008-CAO
Page 10
f. FGT must revise the RWP as necessary to incorporate new information obtained
during the failure investigation and remedial activities, to incorporate the results of
actions undertaken pursuant to this Order, and to incorporate any modifications
required by the Director.
i. Submit any plan revisions to the Director for prior approval.
ii. The Director may approve plan revisions incrementally.
iii. Any and all revisions to the RWP after it has been approved and
incorporated by reference into this Order will be fully described and
documented in the CAO Documentation Report (CDR).
12. CAO Documentation Report. When FGT has concluded all the items in this Order it will
submit the final CDR in its entirety to the Director. This will allow the Director to complete
a thorough review of all actions taken by FGT with regards to this Order prior to approving
the closure of this Order. The intent is for the CDR to summarize all activities and
documentation associated with this Order in one document.
a. The Director may approve the CDR incrementally without approving the entire
CDR.
b. Once approved by the Director, the CDR will be incorporated by reference into this
Order.
c. The CDR must include, but is not necessarily limited to, the following elements:
i. Table of Contents;
ii. Summary of the pipeline failure of September 10, 2020, and the response
activities;
iii. Summary of pipe data/properties and all prior assessments of the Affected
Segment;
iv. Summary of all tests, inspections, assessments, evaluations, and analysis
required by the Order;
v. Summary of the Mechanical and Metallurgical Testing as required by the
Order;
vi. Summary of the RCFA with all root causes as required by the Order;
vii. Documentation of all actions taken by FGT to implement the RWP, the
results of those actions, and the inspection and repair criteria used;
viii. Documentation of any revisions to the RWP including those necessary to
incorporate the results of actions undertaken pursuant to this Order and
whenever necessary to incorporate new information obtained during the
failure investigation and remedial activities;



CPF No. 4-2020-008-CAO
Page 11
ix. Lessons learned while completing this Order;
x. A path forward describing specific actions FGT will take on its entire
pipeline system as a result of the lessons learned from work on this Order;
and
xi. Other Appendices as required.
Other Requirements:
13. Approvals. With respect to each submission that under this Order requires the approval of
the Director, the Director may: (a) approve, in whole or part, the submission; (b) approve
the submission on specified conditions; (c) modify the submission to cure any deficiencies;
(d) disapprove in whole or in part, the submission, directing that Respondent modify the
submission, or (e) any combination of the above. In the event of approval, approval upon
conditions, or modification by the Director, Respondent shall proceed to take all action
required by the submission as approved or modified by the Director. If the Director
disapproves all or any portion of the submission, Respondent must correct all deficiencies
within the time specified by the Director, and resubmit it for approval.
14. Extensions of Time. The Director may grant an extension of time for compliance with any
of the terms of this Order upon a written request timely submitted demonstrating good
cause for an extension.
15. Reporting. Submit quarterly reports to the Director that: (1) include all available data and
results of the testing and evaluations required by this Order; and (2) describe the progress
of the repairs or other remedial actions being undertaken. The first quarterly report is due
on December 31, 2020. The Director may change the interval for the submission of these
reports.
16. Documentation of the Costs. It is requested but not required that Respondent maintain
documentation of the costs associated with implementation of this Corrective Action
Order. Include in each monthly report submitted, the to-date total costs associated with:
(1) preparation and revision of procedures, studies and analyses; (2) physical changes to
pipeline infrastructure, including repairs, replacements and other modifications; and (3)
environmental remediation, if applicable.
Be advised that all material you submit in response to this enforcement action is subject to being
made publicly available. If you believe that any portion of your responsive material qualifies for
confidential treatment under 5 U.S.C. § 552(b), along with the complete original document you
must provide a second copy of the document with the portions you believe qualify for confidential
treatment redacted and an explanation of why you believe the redacted information qualifies for
confidential treatment under 5 U.S.C. § 552(b).
In your correspondence on this matter, please refer to “CPF No. 4-2020-008-CAO” and for each
document you submit, please provide a copy in electronic format whenever possible. The actions
required by this Order are in addition to and do not waive any requirements that apply to



CPF No. 4-2020-008-CAO
Page 12
Respondent’s pipeline system under 49 C.F.R. Parts 190 through 199, under any other order issued
to Respondent under authority of 49 U.S.C. Chapter 601, or under any other provision of Federal
or State law.
Respondent may appeal any decision of the Director to the Associate Administrator for Pipeline
Safety. Decisions of the Associate Administrator shall be final.
Failure to comply with this Order may result in the assessment of civil penalties and in referral to
the Attorney General for appropriate relief in United States District Court pursuant to
49 U.S.C. § 60120.
The terms and conditions of this Order are effective upon service in accordance with 49 C.F.R.
§ 190.5.
September 18, 2020
_________________________________ ________________________
Alan K. Mayberry Date Issued
Associate Administrator
for Pipeline Safety

42020008CAO_Amended Corrective Action Order_10012020_(20-190995)_text.pdf

October 1, 2020
VIA ELECTRONIC MAIL TO: matthew.ramsey@energytransfer.com
Mr. Matthew Ramsey
Chief Operating Officer
Energy Transfer Partners, LP
8111 Westchester Drive
Dallas, Texas 75225
CPF No. 4-2020-008-CAO
Dear Mr. Ramsey:
Enclosed please find an Amended Corrective Action Order (ACAO) issued by the Pipeline and
Hazardous Materials Safety Administration, Office of Pipeline Safety, in the above-referenced
case to Florida Gas Transmission Company (FGT), which is operated by Energy Transfer Partners,
LP. The ACAO requires FGT to take corrective actions with respect to a rupture that occurred on
September 24, 2020 on FGT’s 18-inch FLMEA-21 pipeline located in Lake Worth, Florida, in
addition to those actions previously ordered on September 18, 2020, with respect to an incident
that occurred on the 12-inch Sanford Lateral on September 10, 2020.
Service of the ACAO by electronic transmission is deemed complete upon transmission and
acknowledgement of receipt, or as otherwise provided under 49 C.F.R. § 190.5. The terms and
conditions of this Order are effective upon completion of service.
Sincerely,
Alan K. Mayberry
Associate Administrator
for Pipeline Safety
Enclosure: ACAO
cc: Ms. Linda Daugherty, Deputy Associate Administrator for Field Operations, OPS
Ms. Mary L. McDaniel, P.E., Director, Southwestern Region, OPS
Mr. Eric Amundsen, Senior Vice President, Energy Transfer Partners, LP,
eric.amundsen@energytransfer.com
CONFIRMATION OF RECEIPT REQUESTED



U.S. DEPARTMENT OF TRANSPORTATION
PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION
OFFICE OF PIPELINE SAFETY
WASHINGTON, D.C. 20590
____________________________________
In the Matter of )
Florida Gas Transmission Company, )
)
)
)
Respondent. )
____________________________________)
CPF No. 4-2020-008-CAO
AMENDED CORRECTIVE ACTION ORDER
Purpose and Background:
The Pipeline and Hazardous Materials Safety Administration (PHMSA) issues this Amended
Corrective Action Order (ACAO or Order) under the authority of 49 U.S.C. § 60112 to require
Florida Gas Transmission Company (FGT or Respondent), which is operated by Energy Transfer
Partners, LP,1 to take the necessary corrective actions to protect the public, property, and the
environment from potential hazards associated with a rupture that occurred on September 10, 2020,
on its 12-inch Sanford Lateral natural gas pipeline in Sanford, Florida (Incident 1) and a second
rupture that occurred on September 24, 2020, on its 18-inch FLMEA-21 line located in Lake
Worth, Florida (Incident 2). This ACAO amends the Corrective Action Order that was issued on
September 18, 2020.
Incident 1: In the early morning of September 10, 2020, FGT’s 12-inch Sanford Lateral ruptured
and subsequently ignited. Prior to the rupture, at 12:47am EDT, the line was operating at 695
pounds per square inch (psig) between the Sanford station and the DeBary station. At 12:52 am
EDT, the pressure reading at Sanford dropped to 409 psig and steadily decreased from that point.
FGT’s Control Room detected the drop in pressure and had the valves upstream and downstream
(upstream Valve 17-22U and downstream Valve 17-22ERB) of the failure site manually closed.
At 2:08 am EDT the line was shut in. The size of the burn area around the rupture site was
determined to be 515 feet by 100 feet.
Reverse 911 notified 800 area homes and the local sheriff reported 20 homes were evacuated. The
fire was extinguished, and evacuated residents were allowed to return home within hours of
Incident 1. There were no reports of injuries or fatalities.
1 FGT is an approximately 5,300-mile system that transports natural gas from South Texas to South Florida. FGT is
owned by Florida Gas Transmission Company, LLC, a 100 percent owned subsidiary of Citrus Corp. Citrus Corp is
a 50/50 joint venture between Kinder Morgan, Inc. and Energy Transfer Partners, LP. FGT is operated by Energy
Transfer. See https://www kindermorgan.com/Operations/Natural-Gas/Index (last accessed September 14, 2020).



CPF No. 4-2020-008-CAO
Page 2
Incident 2: At approximately 9:50 am EDT on September 24, 2020, FGT’s FLMEA-21 18-inch
pipeline ruptured and ejected multiple pieces of pipeline into the air. FGT’s gas control was
notified by a representative of the Lake Worth Drainage District that their pipeline was blowing
natural gas. FGT’s representative confirmed the leak on the 18-inch pipeline and the line was
isolated between FGT’s two compressor stations (FGT CS 21 and CS 21.5). At the incident site,
FGT found a 13-foot portion of ejected pipeline that landed approximately 400 feet downstream
from the rupture site on the median of Lake Worth Road, and an additional 8.3-foot piece of ejected
pipeline was located approximately 200 feet east of the rupture site in a retaining pond behind a
Florida Turnpike toll booth. The outside lane of northbound traffic on the Florida Turnpike was
closed while FGT assessed the damage and initiated repairs. A mobile phone emergency alert was
sent to those within a half-mile of the gas rupture notifying those persons to shelter-in-place or
evacuate. An unknown number of people were evacuated from commercial businesses and a
nearby elementary school. Evacuees were allowed to return to the area once the gas flow at the
rupture site was secured.
Pursuant to 49 U.S.C. § 60117, PHMSA, Office of Pipeline Safety (OPS), initiated investigations
of both Incident 1 and Incident 2. The preliminary findings of the agency’s ongoing investigations
are as follows:
Preliminary Findings for Incident 1:
 FGT initially reported Incident 1 to the National Response Center (NRC) at 2:24 am
EDT on September 10, 2020 (NRC Report No. 1286952), indicating that Reverse 911
notified 800 area homes and that the local sheriff reported the evacuation of 20 homes
when the 12-inch Sanford Lateral ruptured and ignited a fire. FGT provided an update
to NRC after 48 hours that indicated an estimated release of 22 million cubic feet
(MMCF) of natural gas and caused the evacuation of 20 homes. FGT also reported that
all evacuees had returned to their homes.
 There were no injuries or fatalities associated with Incident 1; however, there is burn
damage to the surrounding vegetation measuring 515 feet by 100 feet. Additionally,
three overhead powerlines owned by Duke Energy, that shared the right-of-way
(ROW), were damaged and knocked down.
 The rupture occurred near Mile Post 15 on the 12-inch Sanford Lateral (12-inch line or
Sanford Lateral) that feeds a Duke Energy Power Plant and a Sanford Florida Public
Utilities (FPU) meter station.
 The Sanford Lateral was constructed in 1959 with a 12-inch nominal diameter, 0.219-
inch wall thickness, X-42 grade pipe that was manufactured by Youngstown Sheet and
Tube. The pipe has a low-frequency electric resistance welded (LF ERW) seam and
is coated with a tape coating. The length of the 12-inch Sanford Lateral was measured
at 15.9 miles by a 2019 in-line inspection (ILI) run. The Sanford Lateral is part of a
larger FGT unit with a total of 654 miles.



CPF No. 4-2020-008-CAO
Page 3
 The Sanford Lateral was manually shut in between upstream Valve 17-22U and
downstream Valve 17-22ERB. On the evening of September 10, 2020, FGT cut the
failed 12-inch pipeline and installed a pre-tested weld cap downstream from the lateral
to Sanford FPU meter station. The weld cap location is approximately 0.5 miles
upstream of rupture location and downstream of an FPU lateral to two customers
(Sanford West and Sanford FPU) line, allowing a return to service of the remainder of
the line.
 Service has been restored to all 125 customers that initially lost service. The isolated
segment of pipeline, including the site of the rupture, is approximately 1.4 miles in
length and remains out of service.
 The Maximum Operating Pressure of the 12-inch Sanford Lateral is 713 psig. The
operating pressure at the time of the rupture was 695 psig. The portion of the Sanford
Lateral that resumed operations is currently operating at 344 psig, which is fifty percent
(50%) of operating pressure at the time of rupture. This pressure restriction was put
into place by FGT.
 The operator reported that it performed ILI runs of the Sanford Lateral in 2014 and
2019. ILI correlation data from these runs show corrosion growth rates as high as 17
thousandths of an inch per year. The 2019 ILI run had a large amount of corrosion
indications in the vicinity of rupture, many over forty percent (40%).
 Most of the pipeline ROW appears to be located in swamp areas with heavy vegetation
along its borders, making the 12-inch line more susceptible to active external corrosion
than other locations. The line also reportedly has river weights in the vicinity of the
rupture, and throughout the entire area where high corrosion rates are present.
 Aerial mapping and alignment sheets show a mix of sparsely populated swamp and
residential and commercial properties in close proximity to ROW.
 There have been no previous reportable incidents on the Sanford Lateral. FGT reports
that a 2012 rupture occurred in Melbourne, Florida and a 2014 rupture occurred in Port
St. John, Florida. Both were on different pipelines in the unit that includes the Sanford
Lateral. The 2012 rupture involved 20-inch 1959 vintage Youngstown Tube and Steel
LF ERW pipe and was classified as original manufacturing related (not weld). The
2014 rupture involved an 8-inch 1962 vintage LF ERW pipe manufactured by Lonestar,
and was also classified original manufacturing related (not weld).
 Pre-1970 LF ERW pipe has been the focus of many studies and reviews. A final report
TTO Number 5, Integrity Management Program Delivery Order DTRS56-02-D-70036,
Integrity Management Program regarding Low Frequency ERW and Lap Welded
Longitudinal Seam Evaluation (Revision 3) was prepared by Michael Baker in
association with Kiefner and Associates, Inc., CorrMet Engineering Services, PC in



CPF No. 4-2020-008-CAO
Page 4
April 2004.2 The report was written to support the importance of operators correctly
selecting integrity assessment methods capable of assessing seam integrity and of
detecting corrosion and deformation anomalies.
 PHMSA has issued Advisory Bulletins on the safety risks of Low-Frequency Welded
ERW and Flash-welded Pipe manufactured prior to 1970. It also issued Alert Notice,
ALN-88-01, in January 1988, advising owners and operators of natural gas and
hazardous liquids pipelines to consider the threat from ERW pipe manufactured prior
to 1970. The operators were advised to determine whether their pipelines were
susceptible to ERW seam failures and address the potential impact on pipeline
integrity.
Preliminary Findings for Incident 2:
 FGT initially reported Incident 2 to the NRC at 10:53 am EDT on September 24, 2020
(NRC Report No. 1288141), indicating that a rupture, with no fire, occurred on FGT’s
18-inch FLMEA-21 pipeline. FGT provided an update to NRC (NRC Report No.
1288281) after 48 hours that indicated an estimated release of 12 MMCF of natural gas.
There were no injuries or fatalities associated with Incident 2.
 The rupture occurred approximately 350 feet north of the intersection of the Florida
Turnpike and Lake Worth Road in Lake Worth, Florida. The rupture location is about
six miles south of FGT’s upstream compressor station, and 24 miles north of FGT’s
downstream compressor station.
 The FLMEA-21 pipeline was constructed in 1959 with an 18-inch nominal diameter,
0.25-inch wall thickness, X-52 grade pipe that was manufactured by Youngstown Sheet
and Tube. The pipe has an LF ERW seam and is coated with cold applied tape. The
length of the FLMEA-21 pipeline is 67.04 miles.
 The FLMEA-21 pipeline supplies gas to three power plants and four regulator stations
that supply natural gas to local distribution systems. The 18-inch FLMEA-21 pipeline
shares the ROW with FGT’s 24-inch, FLMEB-21 pipeline, which runs parallel to the
FLMEA-21 pipeline and is located approximately 20 feet away. The FLMEB-21
pipeline experienced no apparent collateral damage due to Incident 2.
 The FLMEA-21 pipeline is currently shut in between FGT’s Main Line Valve (MLV)
20-3 and MLV 20-4, approximately 15 miles. At MLV 20-3 there is a crossover to the
FLMEB-21 24-inch and another crossover at MLV 20-4 to revert back to the FLMEA-
21 18-inch. The segment continues to remain out of service.
 The Maximum Operating Pressure of the FLMEA-21 is 866 psig. The operating
pressure at the time of the rupture was 846 psig.
2 See https://www.phmsa.dot.gov/sites/phmsa.dot.gov/files/docs/technical-resources/pipeline/hazardous-liquid-
integrity-management/64376/tto5lowfrequencyerwfinalreportrev3april2004.pdf (last accessed September 14, 2020).



CPF No. 4-2020-008-CAO
Page 5
 In 2018, FGT performed an ILI of the FLMEA-21 pipeline with no actionable
indications of anomalies reported within the area near the Florida Turnpike exit ramp
and Lake Worth Blvd.
 Much of FGT’s FLMEA-21 pipeline shares the ROW with FGT’s FLMEB-21 pipeline
and the Florida Turnpike.
 Aerial mapping shows heavily populated and travelled area in the vicinity of the
pipeline. The pipeline is parallel and in close proximity (4 to 5 feet) from a retaining
wall for the Florida Turnpike. The retaining wall was severely damaged as a result of
this incident.
 There have been two reportable incidents on the FLMEA-21 pipeline since 2009 that
were attributed to Stress Corrosion Cracking (SCC). The first was in May 2009 in Palm
City, Florida, which resulted in a rupture of the pipeline. The second was a leak on the
pipeline that occurred in December 2012 in Lake Worth, Florida. The 2012 leak was
approximately 400-feet south of the rupture site for Incident 2.
 PHMSA issued Corrective Action Orders (CPF Nos. 2-2009-1002H and 2-2012-
1005H) for each of the previous two failures on the FLMEA-21 pipeline.
 As discussed in the Preliminary Findings for Incident 1, pre-1970 LF ERW pipe has
been the focus of many studies and reviews, including those reports cited above.
PHMSA has also issued noticed, including Advisory Bulletins and Alert Notices, on
the safety risks of LF ERW and Flash-welded Pipe manufactured prior to 1970, as well
as advising operators to determine whether their pipelines were susceptible to ERW
seam failures and address the potential impact on pipeline integrity.
Determination of Necessity for Corrective Action Order and Right to Hearing:
Section 60112 of title 49, United States Code, authorizes PHMSA to determine that a pipeline
facility is or would be hazardous to life, property, or the environment and, if there is a likelihood
of serious harm, to expeditiously order the operator of the facility to take necessary corrective
action, including suspended or restricted use of the facility, physical inspection, testing, repair,
replacement, or other appropriate action. An order issued expeditiously must provide an
opportunity for a hearing as soon as practicable after the order is issued.
In deciding whether to issue an order, PHMSA must consider the following, if relevant: (1) the
characteristics of the pipe and other equipment used in the pipeline facility, including the age,
manufacture, physical properties, and method of manufacturing, constructing, or assembling
the equipment; (2) the nature of the material the pipeline facility transports, the corrosive and
deteriorative qualities of the material, the sequence in which the material are transported, and
the pressure required for transporting the material; (3) the aspects of the area in which the
pipeline facility is located, including climatic and geologic conditions and soil characteristics;



CPF No. 4-2020-008-CAO
Page 6
(4) the proximity of the area in which the hazardous liquid pipeline facility is located to
environmentally sensitive areas; (5) the population density and population and growth patterns
of the area in which the pipeline facility is located; (6) any recommendation of the National
Transportation Safety Board made under another law; and (7) other factors PHMSA may
considers appropriate.
After evaluating the foregoing preliminary findings of fact, I find that the continued operation of
the Affected Pipelines, as defined below, without corrective measures is or would be hazardous to
life, property and the environment. Given that both Incident 1 and Incident 2 involved pre-1970
LF ERW pipe, and that there is an increased likelihood that there are other locations along the
pipelines subject to the same operational cycles and fatigue, there is a heightened risk for imminent
failures along the pipe. Furthermore, given that the area of the rupture for Incident 1 appears to
be at a low point in the line which is located in a swamp, there is an increased possibility of the
presence of moisture that may increase the likelihood of increased external corrosion. In fact,
recent ILI data of the Sanford Lateral showed indications of increased corrosion in the vicinity of
the rupture. As for Incident 2, the location of the pipeline and the rupture site is in close proximity
to populated areas, including the Florida Turnpike. Therefore, after considering the age of the
pipelines, the manufacturing methods, the hazardous nature of the products being transported, the
pressure required for transporting the materials, and the attributes of the ROWs for each pipeline,
as well as the uncertainties as to the causes of the incidents and the ongoing investigation, I find
that a failure to issue this Order expeditiously to require immediate corrective action would result
in likely serious harm to life, property, and the environment.
Accordingly, this ACAO mandating immediate corrective action is issued without prior notice and
opportunity for a hearing. The terms and conditions of this Order are effective upon receipt.
Within 10 days of receipt of this Order, Respondent may request a hearing, to be held as soon as
practicable, by notifying the Associate Administrator for Pipeline Safety in writing, with a copy
to the Director, Southwest Region, PHMSA (Director). If a hearing is requested, it will be held in
accordance with 49 C.F.R. § 190.211.
After receiving and analyzing additional data in the course of this investigation, PHMSA may
identify other corrective measures that need to be taken. Respondent will be notified of any
additional measures required and, if appropriate, PHMSA will consider amending this Order. To
the extent consistent with safety, Respondent will be afforded notice and an opportunity for a
hearing prior to the imposition of any additional corrective measures.
Required Corrective Actions:
Definitions for Incident 1:



CPF No. 4-2020-008-CAO
Page 7
Incident 1 Affected Pipeline3 – Means the entire 15.9 miles of the 12-inch Sanford Lateral
operated by Florida Gas Transmission that transports natural gas from FGT’s 26-inch
mainline to the Sanford West and Sanford FPU meter station.
Incident 1 Isolated Segment – Means the portion of the Incident 1 Affected Pipeline
between the weld cap location (approximately MP 14.8) and Valve 17-22ERB that remains
out of service.
Definitions for Incident 2:
Incident 2 Affected Pipeline – Means the entire 67.04 miles of the 18-inch FLMEA-21
pipeline and the 60.2 miles of the 24-inch FLMEB-21 pipeline.
Incident 2 Isolated Segment– Means the approximate 15 miles of the 18-inch FLMEA-21
pipeline (i.e. Incident 2 Affected Pipeline) between FGT’s MLV 20-3 and FGT’s MLV 20-
4.
Pursuant to 49 U.S.C. 60112, I hereby order FGT to immediately take the following corrective
actions:
1. Shutdown of the Isolated Segments. The Incident 1 Isolated Segment and Incident 2
Isolated Segment (collectively Isolated Segments) are currently out of service and must
remain shut down until its restart in accordance with this Order.
2. Operating Pressure Restriction of the Affected Pipelines. FGT must maintain a fifty
percent (50%) pressure reduction in the actual operating pressure along the entire length of
the Incident 1 Affected Pipeline such that the operating pressure along the pipeline will not
exceed fifty percent (50%) of the actual operating pressure in effect immediately prior to
the failure on September 10, 2020. FGT must initiate and maintain a twenty percent (20%)
pressure reduction in the actual operating pressure along the entire length of the Incident 2
Affected Pipeline such that the operating pressure along the pipeline will not exceed twenty
percent (20%) of the actual operating pressure in effect immediately prior to the failure on
September 24, 2020.
a. This pressure restriction is to remain in effect until written approval to increase the
pressure or return the pipelines to their pre-failure operating pressure is obtained
from the Director.
b. FGT must provide the Director by October 2, 2020 for Incident 1 and 14 calendar
days of receipt of this ACAO for Incident 2, the actual operating pressures of each
compressor station and each main line pressure regulating station on the Incident 1
Affected Pipeline and Incident 2 Affected Pipeline (collectively Affected Pipelines)
3 The Corrective Action Order issued on September 18, 2020, referred to this pipeline as the “Affected Segment.”
To avoid confusion with the “Isolated Segment,” the pipeline is hereafter referred to as the “Incident 1 Affected
Pipeline.”



CPF No. 4-2020-008-CAO
Page 8
at the time of failure and the reduced pressure restriction set-points at these same
locations.
c. This pressure restriction requires any relevant remote or local alarm limits, software
programming set-points or control points, and mechanical over-pressure devices to
be adjusted accordingly.
d. When determining the pressure restriction set-points, FGT must take into account
any ILI features or anomalies present in the Affected Pipelines to provide for
continued safe operation while further corrective actions are completed.
e. FGT must review the pressure restriction monthly by analyzing the operating
pressure data. FGT must take into account any ILI features or anomalies present in
the Affected Pipelines and immediately reduce the operating pressure to maintain
the safe operations of the Affected Pipelines, if warranted by the monthly review.
3. Repair/Restart Plan. Prior to resuming operation of the Isolated Segments, FGT must
develop and submit a written Repair/Restart Plan for each of the Isolated Segments to the
Director for approval.
a. The Director may approve the Repair/Restart Plan incrementally without approving
the entire plan, but the Isolated Segments cannot resume operation until the
Repair/Restart Plan is approved in its entirety.
b. Once approved by the Director, the Repair/Restart Plan will be incorporated by
reference into this Order.
c. The Repair/Restart Plan must provide plans and procedures for the repair of the
isolated segment of the pipelines.
d. The Repair/Restart Plan must provide for adequate patrolling of the Isolated
Segment during the restart process and must include incremental pressure increases
during start up, with each increment to be held for at least two hours.
e. The Repair/Restart Plan must include sufficient surveillance of the pipeline during
each pressure increment to ensure that no leaks are present when operation of the
line resumes.
f. The Repair/Restart Plan must specify a day-light restart and include advance
communications with local emergency response officials.
g. The Repair/Restart Plan must provide for a review of the Isolated Segments for
conditions similar to those of the failure, including a review of construction,
operating and maintenance and integrity management records such as ILI results,
hydrostatic pressure tests, root cause failure analysis of prior failures, aerial and
ground patrols, corrosion, cathodic protection, excavations and pipe
replacements. FGT must address any findings that require remedial measures to be
implemented prior to restart.



4. 5. 6. 7. 8. CPF No. 4-2020-008-CAO
Page 9
h. The Repair/Restart Plan must also include documentation of the completion of all
mandated actions, and a management of change plan to ensure that all procedural
modifications are incorporated into FGT’s operations and maintenance procedures
manual.
i. The Repair/Restart Plan must provide for hydrostatic pressure testing of the Isolated
Segments.
Return to Service. After the Director approves the Repair/Restart Plan, FGT may return
the Isolated Segments to service, but the operating pressures must not exceed the pressure
restriction in accordance with Item 2 above.
Removal of Pressure Restriction. The Director may allow the removal or modification of
the pressure restriction in Item 2 above upon a written request from FGT demonstrating
that restoring the pipeline to its pre-failure operating pressure is justified based on a reliable
engineering analysis showing that the pressure increase is safe considering all known
defects, anomalies, and operating parameters of the pipeline.
a. The Director may allow the temporary removal or modification of the pressure
restrictions upon a written request from FGT demonstrating that temporary
mitigative and preventive measures are implemented prior to and during the
temporary removal or modification of the pressure restriction. The Director's
determination will be based on the known or suspected failure cause and provision
of evidence that preventative and mitigative actions taken by the operator provide
for the safe operation of the Affected Pipelines during the temporary removal or
modification of the pressure restriction. Appeals to determinations of the Director
in this regard will be decided by the Associate Administrator for Pipeline Safety.
Instrumented Leakage Survey. By October 18, 2020 for Incident 1, and within 30 calendar
days of receipt of this Order for Incident 2, FGT must perform an aerial or ground
instrumented leakage survey of the Affected Pipelines. FGT must investigate all leak
indications and remedy all leaks discovered. FGT must submit documentation of this
survey to the Director by November 2, 2020 for Incident 1, and within 45 calendar days of
receipt of this Order for Incident 2.
Records Verification. As recommended in PHMSA Advisory Bulletin 2012-06, FGT must
verify the records for the Affected Pipelines to confirm the maximum allowable operating
pressure. FGT must submit documentation of this record verification to the Director by
November 2, 2020 for Incident 1, and within 45 calendar days of receipt of this Order for
Incident 2.
Review of Prior Inline Inspection Results. By October 18, 2020 for Incident 1, and within
30 calendar days of receipt of this Order for Incident 2, FGT with the assistance of an
outside third party, approved by PHMSA, conduct a review of any previous ILI results of
the Affected Pipelines to re-evaluate all ILI results from the past five calendar years,
include a review of the ILI vendors' raw data and analysis, and determine whether any
features were present in the failed pipe joint and any other pipe removed. Also, determine
if any features with similar characteristics are present elsewhere on the Affected



CPF No. 4-2020-008-CAO
Page 10
Pipelines. FGT must submit documentation of this ILI review to the Director by November
2, 2020 for Incident 1, and within 45 calendar days of receipt of this Order for Incident 2.
a. List all ILI tool runs, tool types, and the calendar years of the tool runs. Provide ILI
results data, as requested, to PHMSA.
b. List, describe (type, size, wall loss, etc.), and identify the specific location of all ILI
features present in the failed joint and/or other pipe removed.
c. List, describe (type, size, wall loss, etc.), and identify the specific location of all ILI
features with similar characteristics present elsewhere on the Affected Pipelines.
d. Explain the process used to review the ILI results and the results of the reevaluation.
9. Mechanical and Metallurgical Testing. By November 2, 2020 for Incident 1, and within
45 calendar days of receipt of this Order for Incident 2, FGT must submit for approval a
plan for mechanical and metallurgical testing and failure analysis of the failed pipe,
including an analysis of soil samples and any foreign materials, by an approved
independent third-party laboratory. Complete the testing and analysis as follows:
a. Document the chain-of-custody when handling and transporting the failed pipe
sections and other evidence from the failure sites.
b. Within 10 calendar days of receipt of this Order for Incident 2, FGT must develop
and submit the testing protocol and the proposed testing laboratory to the Director
for prior approval.
c. Prior to beginning the mechanical and metallurgical testing, provide the Director
with the scheduled date, time, and location of the testing to allow for an OPS
representative to witness the testing.
d. Ensure the testing laboratory distributes all reports whether draft or final in their
entirety to the Director at the same time they are made available to FGT.
10. Root Cause Failure Analysis. By December 17, 2020 for Incident 1, and within 90
calendar days of receipt of this Order for Incident 2, FGT must complete a root cause failure
analysis (RCFA) and submit a final report of this RCFA to the Director. The RCFAs must
be supplemented or facilitated by an independent third-party acceptable to the Director and
must document the decision-making process and all factors contributing to the failure. The
final reports must include findings and any lessons learned and whether the findings and
any lessons learned are applicable to other locations within FGT’s pipeline system.
11. Remedial Work Plan.
a. By December 17, 2020 for Incident 1, and within 90 calendar days of receipt of this
Order for Incident 2, FGT must submit Remedial Work Plan(s) (RWP) to the
Director for approval. The Director may approve the RWPs incrementally without
approving the entire RWP. FGT may also submit one RWP for both Incidents by
December 17, 2020.



CPF No. 4-2020-008-CAO
Page 11
b. Once approved by the Director, the RWP(s) will be incorporated by reference into
this Order, and FGT must implement the RWP(s) as it is approved by the Director,
including any revisions to the plan.
c. The RWP(s) must specify the tests, inspections, assessments, evaluations, and
remedial measures FGT will use to verify the integrity of the Affected Pipelines. It
must address all known or suspected factors and causes of the September 10, 2020
and September 24, 2020 failures. FGT should consider both the risk of another
failure and the consequence of another failure to develop a prioritized schedule for
RWP related work along the Affected Pipelines.
d. The RWP must include a procedure or process to:
i. Identify pipe in the Affected Pipelines and other pipelines in the FGT
operating areas with characteristics similar to the contributing factors
identified for the September 10, 2020 and September 24, 2020 failures.
ii. Gather all data necessary to review the failure history (in service and
pressure test failures) of the Affected Pipelines and to prepare a written
report containing all the available information such as the locations, dates,
and causes of leaks and failures.
iii. Integrate the results of the metallurgical testing, root cause failure analysis,
and other corrective actions required by this Order with all relevant pre-
existing operational and assessment data for the Affected Pipelines. Pre-
existing operational data includes, but is not limited to, manufacturing and
construction, operations, maintenance, testing, repairs, prior metallurgical
analyses, and any third-party consultation information. Pre-existing
assessment data includes, but is not limited to, ILI tool runs, hydrostatic
pressure testing, direct assessments, close interval surveys, and direct or
alternating current voltage gradient surveys.
iv. Determine if conditions similar to those contributing to the failures on
September 10, 2020 and September 24, 2020 are likely to exist elsewhere
on FGT’s operational pipelines.
v. Conduct additional field tests, inspections, assessments, and/or evaluations
necessary to determine whether, and to what extent, the conditions
associated with the failures on September 10, 2020 and September 24, 2020,
and other failures from the failure history in Item 11(d)(ii) above or any
other integrity threats are present elsewhere on the Affected Pipelines or
other systems operated by FGT. At a minimum, this process must consider
all failure causes and specify the use of one or more of the following:
1. ILI tools that are technically appropriate for assessing the pipeline
system based on the cause of failures on September 10, 2020 and
September 24, 2020, and that can reliably detect and identify
anomalies;



e. f. CPF No. 4-2020-008-CAO
Page 12
2. Hydrostatic pressure testing;
3. Close-interval surveys;
4. Cathodic protection surveys, to include interference surveys in
coordination with other utilities (e.g. underground utilities,
overhead power lines, etc.) in the area;
5. Coating surveys;
6. Stress corrosion cracking surveys;
7. Selective seam corrosion surveys; and
8. Other tests, inspections, assessments, and evaluations appropriate
for the failure causes.
FGT may use the results of previous tests, inspections, assessments, and
evaluations if approved by the Director, provided the results of the tests,
inspections, assessments, and evaluations are analyzed with regard to the
factors known or suspected to have caused the September 10, 2020 and
September 24, 2020 failures.
vi. Describe the inspection and repair criteria FGT will use to prioritize,
excavate, evaluate, and repair anomalies, imperfections, and other identified
integrity threats. Include a description of how any defects will be graded
and a schedule for repairs or replacement.
vii. Based on the known history and condition of the Affected Pipelines,
describe the methods FGT will use to repair, replace, or take other
corrective measures to remediate the conditions associated with the pipeline
failures on September 10, 2020 and September 24, 2020, and to address
other known integrity threats along the Affected Pipelines. The repair,
replacement, or other corrective measures must meet the criteria specified
in Item 11(d)(vi) above.
viii. Implement continuing long-term periodic testing and integrity verification
measures to ensure the ongoing safe operation of the Affected Pipelines
considering the results of the analyses, inspections, evaluations, and
corrective measures undertaken pursuant to the Order.
The RWP must include a schedule for completion.
FGT must revise the RWP(s) as necessary to incorporate new information obtained
during the failure investigation and remedial activities, to incorporate the results of
actions undertaken pursuant to this Order, and to incorporate any modifications
required by the Director.
i. Submit any plan revisions to the Director for prior approval.



CPF No. 4-2020-008-CAO
Page 13
ii. The Director may approve plan revisions incrementally.
iii. Any and all revisions to the RWP(s) after it has been approved and
incorporated by reference into this Order will be fully described and
documented in the CAO Documentation Report (CDR).
12. CAO Documentation Report. When FGT has concluded all the items in this Order, it will
submit the final CDR in its entirety to the Director. This will allow the Director to complete
a thorough review of all actions taken by FGT with regards to this Order prior to approving
the closure of this Order. The intent is for the CDR to summarize all activities and
documentation associated with this Order in one document.
a. The Director may approve the CDR incrementally without approving the entire
CDR.
b. Once approved by the Director, the CDR will be incorporated by reference into this
Order.
c. The CDR must include, but is not necessarily limited to, the following elements:
i. Table of Contents;
ii. Summary of the pipeline failures of September 10, 2020 and September 24,
2020, and the response activities;
iii. Summary of pipe data/properties and all prior assessments of the Affected
Pipelines;
iv. Summary of all tests, inspections, assessments, evaluations, and analysis
required by the Order;
v. Summary of the Mechanical and Metallurgical Testing as required by the
Order;
vi. Summary of the RCFA with all root causes as required by the Order;
vii. Documentation of all actions taken by FGT to implement the RWP(s), the
results of those actions, and the inspection and repair criteria used;
viii. Documentation of any revisions to the RWP(s) including those necessary to
incorporate the results of actions undertaken pursuant to this Order and
whenever necessary to incorporate new information obtained during the
failure investigation and remedial activities;
ix. Lessons learned while completing this Order;
x. A path forward describing specific actions FGT will take on its entire
pipeline system as a result of the lessons learned from work on this Order;
and
xi. Other Appendices as required.



CPF No. 4-2020-008-CAO
Page 14
Other Requirements:
13. Approvals. With respect to each submission that under this Order requires the approval of
the Director, the Director may: (a) approve, in whole or part, the submission; (b) approve
the submission on specified conditions; (c) modify the submission to cure any deficiencies;
(d) disapprove in whole or in part, the submission, directing that Respondent modify the
submission, or (e) any combination of the above. In the event of approval, approval upon
conditions, or modification by the Director, Respondent shall proceed to take all action
required by the submission as approved or modified by the Director. If the Director
disapproves all or any portion of the submission, Respondent must correct all deficiencies
within the time specified by the Director, and resubmit it for approval.
14. Extensions of Time. The Director may grant an extension of time for compliance with any
of the terms of this Order upon a written request timely submitted demonstrating good
cause for an extension.
15. Reporting. Submit quarterly reports to the Director that: (1) include all available data and
results of the testing and evaluations required by this Order; and (2) describe the progress
of the repairs or other remedial actions being undertaken. The first quarterly report is due
on December 31, 2020. The Director may change the interval for the submission of these
reports.
16. Documentation of the Costs. It is requested but not required that Respondent maintain
documentation of the costs associated with implementation of this ACAO. Include in each
monthly report submitted, the to-date total costs associated with: (1) preparation and
revision of procedures, studies and analyses; (2) physical changes to pipeline infrastructure,
including repairs, replacements and other modifications; and (3) environmental
remediation, if applicable.
Be advised that all material you submit in response to this enforcement action is subject to being
made publicly available. If you believe that any portion of your responsive material qualifies for
confidential treatment under 5 U.S.C. § 552(b), along with the complete original document you
must provide a second copy of the document with the portions you believe qualify for confidential
treatment redacted and an explanation of why you believe the redacted information qualifies for
confidential treatment under 5 U.S.C. § 552(b).
In your correspondence on this matter, please refer to “CPF No. 4-2020-008-CAO” and for each
document you submit, please provide a copy in electronic format whenever possible. The actions
required by this Order are in addition to and do not waive any requirements that apply to
Respondent’s pipeline system under 49 C.F.R. Parts 190 through 199, under any other order issued
to Respondent under authority of 49 U.S.C. Chapter 601, or under any other provision of Federal
or State law.
Respondent may appeal any decision of the Director to the Associate Administrator for Pipeline
Safety. Decisions of the Associate Administrator shall be final.



CPF No. 4-2020-008-CAO
Page 15
Failure to comply with this Order may result in the assessment of civil penalties and in referral to
the Attorney General for appropriate relief in United States District Court pursuant to
49 U.S.C. § 60120.
The terms and conditions of this Order are effective upon service in accordance with 49 C.F.R.
§ 190.5.
October 1, 2020
________________________________ ________________________
Alan K. Mayberry Date Issued
Associate Administrator
for Pipeline Safety

42020008CAO_PHC Hearing Scheduled_10232020_(20-190995)_text.pdf

October 23, 2020
VIA ELECTRONIC MAIL TO: catherine.little@troutman.com and mary.mcdaniel@dot.gov
Ms. Catherine D. Little, Esq.
Counsel for Florida Gas Transmission Company
Troutman Pepper Hamilton Sanders, LLP
600 Peachtree Street, NE, Suite 3000
Atlanta, Georgia 30308
Ms. Mary McDaniel
Director, Southwest Region
Pipeline and Hazardous Materials Safety Administration
8701 South Gessner, Suite 630
Houston, Texas 77074
Re: Notice of Hearing, Florida Gas Transmission Company
CPF No. 4-2020-008-CAO
Dear Ms. Little and Ms. McDaniel:
In accordance with 49 C.F.R. § 190.233, an informal hearing will be held regarding the Second
Amended Corrective Action Order issued by the Pipeline and Hazardous Materials Safety
Administration in the above-referenced case. The hearing will take place on November 4, 2020,
beginning at 8:30 a.m. Central Time.
The hearing will be held via videoconference. I will provide the videoconference information prior
to the hearing. At least 2 calendar days prior to the hearing (or by November 2, 2019), both parties
must submit and exchange any additional written materials they intend to present at the hearing and
the name and email address of each attendee. This information should be provided electronically.
Materials not submitted by this date may be excluded.
If you have any questions, please do not hesitate to contact me.
Sincerely,
Larry White
Presiding Official
cc: Mr. Matthew Ramsey, Chief Operating Officer, Energy Transfer, LP,
matthew.ramsey@energytransfer.com
Mr. Todd Nardozzi, Director – Regulatory Compliance, Energy Transfer, LP,
todd.nardozzi@energytransfer.com
Ms. Melanie Lampton, Counsel, Southwest Region, Office of Pipeline Safety,
melanie.lampton@dot.gov

42020008CAO_Closure Letter_01202026_(20-190995)_text.pdf

U.S. Department of Transportation
Pipeline and Hazardous Materials
Safety Administration 8701 S. Gessner, Suite 630
Houston TX 77074
VIA ELECTRONIC MAIL TO: tom.long@energytransfer.com
January 20, 2026
Thomas Long
Chief Operating Officer
Energy Transfer Partners, LP
8111 Westchester Drive
Dallas, Texas 75225
RE: CPF 4-2020-008-CAO
Dear Mr. Long:
On October 1, 2020, the Pipeline and Hazardous Materials Safety Administration (PHMSA) issued
an Amended Corrective Action Order (ACAO) to Florida Gas Transmission Company (FGT) in
the above-referenced case. This Order required FGT to take corrective actions related to a rupture
that occurred on September 24, 2020 on FGT’s 18-inch FLME-21 pipeline located in Lake Worth,
Florida, in addition to the actions previously ordered on September 18, 2020, pertaining to an
incident on the 12-inch Sanford Lateral on September 10, 2020.
Based on PHMSA’s review of the documentation submitted by FGT, it has been determined that
you have complied with the terms of the ACAO.
Accordingly, this case is now closed, and no further action is contemplated with respect to the
matters involved in this case. Thank you for your cooperation in this matter.
Sincerely,
Bryan Lethcoe
Director, Southwest Region, Office of Pipeline Safety
Pipeline and Hazardous Materials Safety Administration
cc: Greg McIlwain, Executive Vice President of Operations, Energy Transfer, LP,
gregory.mcilwain@energytransfer.com
Eric Amundsen, Senior Vice President of Operations, Energy Transfer, LP,
eric.amundsen@energytransfer.com
Todd Stamm, Senior Vice President of Operations, Energy Transfer, LP,
todd.stamm@energytransfer.com



Daniel Wentworth, Senior Vice President Operations, Energy Transfer, LP,
daniel.wentworth@energytransfer.com
Dave Shellhouse, Vice President, Operations, Energy Transfer, LP,
dave.shellhouse@energytransfer.com
Jennifer Street, Senior Vice President of Operations Services, Energy Transfer, LP,
jennifer.street@energytransfer.com
Keegan Pieper, Assistant General Counsel, Energy Transfer, LP,
keegan.pieper@energytransfer.com
Matthew Stork, Vice President of Tech Services, Energy Transfer, LP,
matthew.stork@energytransfer.com
Todd Nardozzi, Director, DOT Compliance, Energy Transfer, LP,
todd.nardozzi@energytransfer.com
Susie Sjulin, Director, DOT Compliance, Energy Transfer, LP,
susie.sjulin@energytransfer.com
2

## Provenance

- Official: Yes
- Source: <https://primis.phmsa.dot.gov/enforcement-data/case/42020008CAO>
- Source ID: `phmsa-enforcement`
- SHA-256: `f316470a102f3faf20dd1a048d5290ca3df8f8a22dbe48d778ad28025dedee62`
- Retrieved: 2026-08-20T04:44:44.458Z
- Exported: 2026-08-24T06:33:08.886Z
- Document slug: `phmsa-enforcement-42020008cao`

### Source metadata

```json
{
  "cpf": "42020008CAO",
  "operator": "FLORIDA GAS TRANSMISSION CO",
  "region": "Southwest",
  "pipelineType": "INTERSTATE GAS TRANSMISSION",
  "caseStatus": "CLOSED",
  "citedSections": [],
  "dataAsOf": "08/04/2026 12PM",
  "caseDataAsOf": "2026-08-04",
  "attachmentCount": 12,
  "attachments": [
    {
      "name": "42020008CAO_Amended Corrective Action Order_10012020_(20-190995).pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/42020008CAO/42020008CAO_Amended%20Corrective%20Action%20Order_10012020_(20-190995).pdf",
      "bytes": 314271,
      "category": "agency_document"
    },
    {
      "name": "42020008CAO_Amended Corrective Action Order_10012020_(20-190995)_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/42020008CAO/42020008CAO_Amended%20Corrective%20Action%20Order_10012020_(20-190995)_text.pdf",
      "bytes": 278174,
      "category": "agency_document"
    },
    {
      "name": "42020008CAO_Closure Letter_01202026_(20-190995).pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/42020008CAO/42020008CAO_Closure%20Letter_01202026_(20-190995).pdf",
      "bytes": 141978,
      "category": "agency_document"
    },
    {
      "name": "42020008CAO_Closure Letter_01202026_(20-190995)_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/42020008CAO/42020008CAO_Closure%20Letter_01202026_(20-190995)_text.pdf",
      "bytes": 154140,
      "category": "agency_document"
    },
    {
      "name": "42020008CAO_Corrective Action Order_09182020_(20-190995).pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/42020008CAO/42020008CAO_Corrective%20Action%20Order_09182020_(20-190995).pdf",
      "bytes": 455295,
      "category": "agency_document"
    },
    {
      "name": "42020008CAO_Corrective Action Order_09182020_(20-190995)_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/42020008CAO/42020008CAO_Corrective%20Action%20Order_09182020_(20-190995)_text.pdf",
      "bytes": 260903,
      "category": "agency_document"
    },
    {
      "name": "42020008CAO_Operator Hearing Request Withdrawn_10302020_(20-190995).pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/42020008CAO/42020008CAO_Operator%20Hearing%20Request%20Withdrawn_10302020_(20-190995).pdf",
      "bytes": 264868,
      "category": "party_submission"
    },
    {
      "name": "42020008CAO_Operator Request for Hearing and Request Statement of Issues_10132020_(20-190995).pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/42020008CAO/42020008CAO_Operator%20Request%20for%20Hearing%20and%20Request%20Statement%20of%20Issues_10132020_(20-190995).pdf",
      "bytes": 298446,
      "category": "party_submission"
    },
    {
      "name": "42020008CAO_PHC Hearing Scheduled_10232020_(20-190995).pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/42020008CAO/42020008CAO_PHC%20Hearing%20Scheduled_10232020_(20-190995).pdf",
      "bytes": 157618,
      "category": "agency_document"
    },
    {
      "name": "42020008CAO_PHC Hearing Scheduled_10232020_(20-190995)_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/42020008CAO/42020008CAO_PHC%20Hearing%20Scheduled_10232020_(20-190995)_text.pdf",
      "bytes": 79438,
      "category": "agency_document"
    },
    {
      "name": "42020008CAO_Second Amended Corrective Action Order_10222020_(20-190995).pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/42020008CAO/42020008CAO_Second%20Amended%20Corrective%20Action%20Order_10222020_(20-190995).pdf",
      "bytes": 303885,
      "category": "agency_document"
    },
    {
      "name": "42020008CAO_Second Amended Corrective Action Order_10222020_(20-190995)_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/42020008CAO/42020008CAO_Second%20Amended%20Corrective%20Action%20Order_10222020_(20-190995)_text.pdf",
      "bytes": 277001,
      "category": "agency_document"
    }
  ],
  "extractedAgencyDocumentCount": 5,
  "attachmentPolicy": "Official attachment links are retained. Agency-issued documents may also include a verified local PDF and page-level text representation.",
  "jurisdiction": "US",
  "operatorName": "FLORIDA GAS TRANSMISSION CO"
}
```
