Warning Letter involving BRAVO PIPELINE COMPANY. PHMSA's enforcement data identifies the cited regulation as 195.61(b). The case was opened on 2021-03-09 and is reported as closed as of 2021-03-09. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

42021031WL_Warning Letter_03092021_(21-203102).pdf: https://primis.phmsa.dot.gov/enforcement-documents/42021031WL/42021031WL_Warning%20Letter_03092021_(21-203102).pdf

42021031WL_Warning Letter_03092021_(21-203102)_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/42021031WL/42021031WL_Warning%20Letter_03092021_(21-203102)_text.pdf

42021031WL_Warning Letter_03092021_(21-203102)_text.pdf

WARNING LETTER
ELECTRONIC MAIL - RETURN RECEIPT REQUESTED
March 9, 2021
Vishal Gupta
President & General Manager
Bravo Pipeline Company
5 Greenway Plaza, Suite 110
Houston, Texas 77046
CPF 4-2021-031-WL
Dear Mr. Gupta:
On December 10, 2020, a representative of the Pipeline and Hazardous Materials Safety
Administration (PHMSA) pursuant to Chapter 601 of 49 United States Code (U.S.C.) inspected
Bravo Pipeline Company compliance with the National Pipeline Mapping System (NPMS)
submittal requirement for calendar year 2019.
As a result of the inspection, it is alleged that Bravo Pipeline Company has committed a probable
violation of the Pipeline Safety Regulations, Title 49, Code of Federal Regulations (CFR). The
item inspected and the probable violation is:
1. § 195.61 - National Pipeline Mapping System.
(a) …
(b) This information must be submitted each year, on or before June 15, representing
assets as of December 31 of the previous year. If no changes have occurred since the
previous year’s submission, the operator must refer to the information provided in
the NPMS Operator Standards manual available at www.npms.phmsa.dot.gov or
contact the PHMSA Geographic Information Systems Manager at (202) 366-4595.
Bravo Pipeline Company failed to submit the information required in paragraph (a) of § 195.61,
on or before June 15, representing its assets as of December 31 of the previous year. Specifically,
Bravo Pipeline Company failed to submit 1) Geospatial data, attributes, metadata, and transmittal
letter appropriate for use in the National Pipeline Mapping System; 2) the name of and address for
the operator; and 3) the name and contact information of a pipeline company employee, to be
displayed on a public Web site, who will serve as a contact for questions from the general public
about the operator's NPMS data for its assets as of December 31, 2019, by the due date of June 15,
2020.



2
Under 49 U.S.C. § 60122 and 49 CFR § 190.223, you are subject to a civil penalty not to exceed
$222,504 per violation per day the violation persists, up to a maximum of $2,225,034 for a related
series of violations. For violation occurring on or after July 31, 2019 and before January 11, 2021,
the maximum penalty may not exceed $218,647 per violation per day the violation persists, up to
a maximum of $2,186,465 for a related series of violations. For violation occurring on or after
November 27, 2018 and before July 31, 2019, the maximum penalty may not exceed $213,268 per
violation per day, with a maximum penalty not to exceed $2,132,679. For violation occurring on
or after November 2, 2015 and before November 27, 2018, the maximum penalty may not exceed
$209,002 per violation per day, with a maximum penalty not to exceed $2,090,022.
We have reviewed the circumstances and supporting documents involved in this case, and have
decided not to conduct additional enforcement action or penalty assessment proceedings at this
time. We advise you to complete an accurate and acceptable calendar year 2020 NPMS submittal
for all of the hazardous liquid pipelines in your calendar year 2020 Annual Report on or before
June 15, 2021. Failure to do so may result in Bravo Pipeline Company being subject to additional
enforcement action.
No reply to this letter is required. If you choose to reply, in your correspondence please refer to
CPF 4-2021-031-WL. Be advised that all material you submit in response to this enforcement
action is subject to being made publicly available. If you believe that any portion of your
responsive material qualifies for confidential treatment under 5 U.S.C. 552(b), along with the
complete original document you must provide a second copy of the document with the portions
you believe qualify for confidential treatment redacted and an explanation of why you believe the
redacted information qualifies for confidential treatment under 5 U.S.C. 552(b).
Sincerely,
Mary L. McDaniel, P.E.
Director, Southwest Region
Pipeline and Hazardous Materials Safety Administration
cc: Bradey Holland, Lead Plant Operations, Bravo Pipeline Company, bradey_holland@oxy.com

## Provenance

- Official: Yes
- Source: <https://primis.phmsa.dot.gov/enforcement-data/case/42021031WL>
- Source ID: `phmsa-enforcement`
- SHA-256: `e94aa38227505a09d7223527967b1c77d95c2dc524fbde513543796c3d20e56c`
- Retrieved: 2026-08-20T04:44:44.458Z
- Exported: 2026-08-22T22:23:59.837Z
- Document slug: `phmsa-enforcement-42021031wl`

### Source metadata

```json
{
  "cpf": "42021031WL",
  "operator": "BRAVO PIPELINE COMPANY",
  "region": "Southwest",
  "pipelineType": "INTERSTATE LIQUID",
  "caseStatus": "CLOSED",
  "citedSections": [
    "195.61(b)"
  ],
  "dataAsOf": "08/04/2026 12PM",
  "caseDataAsOf": "2026-08-04",
  "attachmentCount": 2,
  "attachments": [
    {
      "name": "42021031WL_Warning Letter_03092021_(21-203102).pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/42021031WL/42021031WL_Warning%20Letter_03092021_(21-203102).pdf",
      "bytes": 267526,
      "category": "agency_document"
    },
    {
      "name": "42021031WL_Warning Letter_03092021_(21-203102)_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/42021031WL/42021031WL_Warning%20Letter_03092021_(21-203102)_text.pdf",
      "bytes": 107743,
      "category": "agency_document"
    }
  ],
  "extractedAgencyDocumentCount": 1,
  "attachmentPolicy": "Official attachment links are retained. Agency-issued documents may also include a verified local PDF and page-level text representation.",
  "jurisdiction": "US",
  "operatorName": "BRAVO PIPELINE COMPANY"
}
```