# VALERO PARTNERS OPERATING CO. LLC — Notice of Probable Violation

**Citation:** CPF 42021039NOPV  
**Type / status:** enforcement / historical  
**Agency:** Pipeline and Hazardous Materials Safety Administration  
**Effective:** Not stated  
**Published:** 2021-11-23

CLOSED notice of probable violation citing 195.214(a), 195.402(a), 195.402(c)(10), 195.420(b), 195.583(b).

## Document text

Notice of Probable Violation involving VALERO PARTNERS OPERATING CO. LLC. PHMSA's enforcement data identifies the cited regulations as 195.214(a),  195.402(a),  195.402(c)(10),  195.420(b),  195.583(b). The case was opened on 2021-11-23 and is reported as closed as of 2023-01-30. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

42021039NOPV_Closure Letter_01302023_(20-178576).pdf: https://primis.phmsa.dot.gov/enforcement-documents/42021039NOPV/42021039NOPV_Closure%20Letter_01302023_(20-178576).pdf

42021039NOPV_Closure Letter_01302023_(20-178576)_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/42021039NOPV/42021039NOPV_Closure%20Letter_01302023_(20-178576)_text.pdf

42021039NOPV_Final Order_02282022_(20-178576).pdf: https://primis.phmsa.dot.gov/enforcement-documents/42021039NOPV/42021039NOPV_Final%20Order_02282022_(20-178576).pdf

42021039NOPV_Final Order_02282022_(20-178576)_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/42021039NOPV/42021039NOPV_Final%20Order_02282022_(20-178576)_text.pdf

42021039NOPV_PCO_11232021_(20-178576).pdf: https://primis.phmsa.dot.gov/enforcement-documents/42021039NOPV/42021039NOPV_PCO_11232021_(20-178576).pdf

42021039NOPV_PCO_11232021_(20-178576)_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/42021039NOPV/42021039NOPV_PCO_11232021_(20-178576)_text.pdf

42021039NOPV_Closure Letter_01302023_(20-178576)_text.pdf

VIA ELECTRONIC MAIL
January 30, 2023
Fred Hampton
Vice President
Valero Partners Operating Co. LLC
One Valero Way
San Antonio, Texas 78249
CPF 4-2021-039-NOPV
Dear Mr. Hampton:
From May 4, 2020 through May 8, 2020, representatives of the Pipeline and Hazardous Materials
Safety Administration (PHMSA) pursuant to Chapter 601 of 49 United States Code (U.S.C.)
inspected Valero Partners Operating Co. LLC’s (Valero) written Operations & Maintenance
(O&M) procedural manual and associated records. As a result of the inspection, PHMSA issued
a Notice of Probable Violation (Notice) and Proposed Compliance Order on November 23, 2021,
and Final Order on February 28, 2022.
Valero submitted its response to the Final Order on May 27, 2022. PHMSA reviewed the responses
provided to demonstrate compliance with the Compliance Order and determined that Valero has
complied with the terms of the Final Order.
This letter is to inform you no further response in this case is required, and this case is now closed.
Thank you for your cooperation in this matter.
Sincerely,
Bryan Lethcoe
Director, Southwest Region
Pipeline and Hazardous Materials Safety Administration
cc: Darin Banther, Manager Regulatory Compliance, Valero, Darin.Banther@valero.com

42021039NOPV_Final Order_02282022_(20-178576)_text.pdf

February 28, 2022
VIA ELECTRONIC MAIL TO: fred.hampton@valero.com
Mr. Fred Hampton
Vice President
Valero Partners Operating Co. LLC
One Valero Way
San Antonio, Texas 78249
Re: CPF No. 4-2021-039-NOPV
Dear Mr. Hampton:
Enclosed please find the Final Order issued in the above-referenced case. It makes findings of
violation and specifies actions that need to be taken to comply with the pipeline safety
regulations. When the terms of the compliance order are completed, as determined by the
Director, Southwest Region, this enforcement action will be closed. Service of the Final Order
by e-mail is effective upon the date of transmission and acknowledgement of receipt as provided
under 49 C.F.R. § 190.5.
Thank you for your cooperation in this matter.
Sincerely,
Alan K. Mayberry
Associate Administrator
for Pipeline Safety
Enclosures (Final Order and NOPV)
cc: Ms. Mary McDaniel, Director, Southwest Region, Office of Pipeline Safety, PHMSA
Mr. Darin Banther, Manager – Regulatory Compliance, Valero Partners Operating Co. LLC,
darin.banther@valero.com
CONFIRMATION OF RECEIPT REQUESTED



U.S. DEPARTMENT OF TRANSPORTATION
PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION
OFFICE OF PIPELINE SAFETY
WASHINGTON, D.C. 20590
____________________________________
In the Matter of )
Valero Partners Operating Co. LLC, ) CPF No. 4-2021-039-NOPV
)
)
)
Respondent. )
____________________________________)
FINAL ORDER
On November 23, 2021, pursuant to 49 C.F.R. § 190.207, the Director, Southwest Region, Office
of Pipeline Safety (OPS), issued a Notice of Probable Violation (Notice) to Valero Partners
Operating Co. LLC (Respondent). The Notice proposed finding that Respondent had violated
the pipeline safety regulations in 49 C.F.R. Part 195. The Notice also proposed certain measures
to correct the violations. Respondent did not contest the allegations of violation or corrective
measures.
Based upon a review of all of the evidence, pursuant to § 190.213, I find Respondent violated the
pipeline safety regulations listed below, as more fully described in the enclosed Notice, which is
incorporated by reference:
49 C.F.R. § 195.214(a) (Item 1) ─ Respondent failed to qualify its welding
procedures to ensure welding would be performed by a qualified welder or
welding operator in accordance with welding procedures qualified under Section
5, Section 12, Appendix A, or Appendix B of API Standard 1104, or Section IX
of the ASME Boiler and Pressure Vessel Code.
49 C.F.R. § 195.420(b) (Item 3) ─ Respondent failed to inspect each mainline
valve at intervals not exceeding 7 ½ months, but at least twice each calendar year,
to determine that it is functioning properly.
49 C.F.R. § 195.583(b) (Item 4) ─ Respondent failed to give particular attention
to pipe at soil-to-air interfaces, under thermal insulation, under disbonded
coatings, at pipe supports, in splash zones, at deck penetrations, and in spans over
water during atmospheric corrosion inspections.
These findings of violation will be considered prior offenses in any subsequent enforcement
action taken against Respondent.



CPF No. 4-2021-039-NOPV
Page 2
Compliance Actions
Pursuant to 49 U.S.C. § 60118(b) and 49 C.F.R. § 190.217, Respondent is ordered to take the
actions proposed in the enclosed Notice to correct the violations. The Director may grant an
extension of time to comply with any of the required items upon a written request timely
submitted by the Respondent and demonstrating good cause for an extension. Upon completion
of ordered actions, Respondent may request that the Director close the case. Failure to comply
with this Order may result in the assessment of civil penalties under 49 C.F.R. § 190.223 or in
referral to the Attorney General for appropriate relief in a district court of the United States.
Warning Item
With respect to Item 2, the Notice alleged a probable violation of 49 C.F.R. § 195.402, but did
not propose a civil penalty or compliance order for this item. Therefore, this is considered a
warning item. If OPS finds a violation of this provision in a subsequent inspection, Respondent
may be subject to future enforcement action.
The terms and conditions of this order are effective upon service in accordance with 49 C.F.R.
§ 190.5.
February 28, 2022
___________________________________ _________________________
Alan K. Mayberry Date Issued
Associate Administrator
for Pipeline Safety

## Provenance

- Official: Yes
- Source: <https://primis.phmsa.dot.gov/enforcement-data/case/42021039NOPV>
- Source ID: `phmsa-enforcement`
- SHA-256: `828872646b1d72579da3072dd8890abb6abbd3511f56ce4379b36c59d67a789d`
- Retrieved: 2026-08-20T04:44:44.458Z
- Exported: 2026-08-22T18:28:00.747Z
- Document slug: `phmsa-enforcement-42021039nopv`

### Source metadata

```json
{
  "cpf": "42021039NOPV",
  "operator": "VALERO PARTNERS OPERATING CO. LLC",
  "region": "Southwest",
  "pipelineType": "INTERSTATE LIQUID, INTRASTATE LIQUID",
  "caseStatus": "CLOSED",
  "citedSections": [
    "195.214(a)",
    "195.402(a)",
    "195.402(c)(10)",
    "195.420(b)",
    "195.583(b)"
  ],
  "dataAsOf": "08/04/2026 12PM",
  "caseDataAsOf": "2026-08-04",
  "attachmentCount": 6,
  "attachments": [
    {
      "name": "42021039NOPV_Closure Letter_01302023_(20-178576).pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/42021039NOPV/42021039NOPV_Closure%20Letter_01302023_(20-178576).pdf",
      "bytes": 227592,
      "category": "agency_document"
    },
    {
      "name": "42021039NOPV_Closure Letter_01302023_(20-178576)_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/42021039NOPV/42021039NOPV_Closure%20Letter_01302023_(20-178576)_text.pdf",
      "bytes": 62530,
      "category": "agency_document"
    },
    {
      "name": "42021039NOPV_Final Order_02282022_(20-178576).pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/42021039NOPV/42021039NOPV_Final%20Order_02282022_(20-178576).pdf",
      "bytes": 583741,
      "category": "agency_document"
    },
    {
      "name": "42021039NOPV_Final Order_02282022_(20-178576)_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/42021039NOPV/42021039NOPV_Final%20Order_02282022_(20-178576)_text.pdf",
      "bytes": 109358,
      "category": "agency_document"
    },
    {
      "name": "42021039NOPV_PCO_11232021_(20-178576).pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/42021039NOPV/42021039NOPV_PCO_11232021_(20-178576).pdf",
      "bytes": 373322,
      "category": "case_document"
    },
    {
      "name": "42021039NOPV_PCO_11232021_(20-178576)_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/42021039NOPV/42021039NOPV_PCO_11232021_(20-178576)_text.pdf",
      "bytes": 180075,
      "category": "case_document"
    }
  ],
  "extractedAgencyDocumentCount": 2,
  "attachmentPolicy": "Official attachment links are retained. Agency-issued documents may also include a verified local PDF and page-level text representation.",
  "jurisdiction": "US",
  "operatorName": "VALERO PARTNERS OPERATING CO. LLC"
}
```