# ENTERPRISE CRUDE PIPELINE LLC — Notice of Amendment

**Citation:** CPF 42022002NOA  
**Type / status:** enforcement / historical  
**Agency:** Pipeline and Hazardous Materials Safety Administration  
**Effective:** Not stated  
**Published:** 2022-08-31

CLOSED notice of amendment citing 195.402(c)(3), 195.414(a), 195.414(b), 195.414(c), 195.414(d), 195.452(f)(6).

## Document text

Notice of Amendment involving ENTERPRISE CRUDE PIPELINE LLC. PHMSA's enforcement data identifies the cited regulations as 195.402(c)(3),  195.414(a),  195.414(b),  195.414(c),  195.414(d),  195.452(f)(6). The case was opened on 2022-08-31 and is reported as closed as of 2022-11-18. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

42022002NOA_Closure Letter_11182022_(21-209759).pdf: https://primis.phmsa.dot.gov/enforcement-documents/42022002NOA/42022002NOA_Closure%20Letter_11182022_(21-209759).pdf

42022002NOA_Closure Letter_11182022_(21-209759)_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/42022002NOA/42022002NOA_Closure%20Letter_11182022_(21-209759)_text.pdf

42022002NOA_Notice of Amendment_08312022_(21-209759).pdf: https://primis.phmsa.dot.gov/enforcement-documents/42022002NOA/42022002NOA_Notice%20of%20Amendment_08312022_(21-209759).pdf

42022002NOA_Notice of Amendment_08312022_(21-209759)_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/42022002NOA/42022002NOA_Notice%20of%20Amendment_08312022_(21-209759)_text.pdf

42022002NOA_Operator Response to Notice_09232022_(21-209759).pdf: https://primis.phmsa.dot.gov/enforcement-documents/42022002NOA/42022002NOA_Operator%20Response%20to%20Notice_09232022_(21-209759).pdf

42022002NOA_Closure Letter_11182022_(21-209759)_text.pdf

VIA ELECTRONIC MAIL
November 18, 2022
Jeff Morton
Director, Transportation Compliance
Enterprise Crude Pipeline LLC
1100 Louisiana Street
Houston, Texas 77002
CPF 4-2022-002-NOA
Dear Mr. Morton:
From May 3, 2021, through September 30, 2021, a representative of the Pipeline and Hazardous
Materials Safety Administration (PHMSA) pursuant to Chapter 601 of 49 United States Code
(U.S.C.), inspected Enterprise Crude Pipeline LLC’s (Enterprise) Seaway 30-inch Crude System,
Houston Crude System, and Midland Crude System in Oklahoma and Texas. As a result of the
inspection, PHMSA issued a Notice of Amendment to Enterprise Crude Pipeline LLC on August
31, 2022, which proposed amendments to its procedures.
Enterprise Crude Pipeline LLC submitted its final amended procedures on September 23, 2022.
PHMSA staff reviewed the amended procedures, and it appears the inadequacies identified in this
Notice of Amendment have been corrected.
This letter is to inform you no further action is necessary and this case is now closed. Thank you
for your cooperation.
Sincerely,
Bryan Lethcoe
Director, Southwest Region, Office of Pipeline Safety
Pipeline and Hazardous Materials Safety Administration

42022002NOA_Notice of Amendment_08312022_(21-209759)_text.pdf

NOTICE OF AMENDMENT
CERTIFIED MAIL - RETURN RECEIPT REQUESTED
August 31, 2022
Jeff Morton
Director, Transportation Compliance
Enterprise Crude Pipeline LLC
1100 Louisiana Street
Houston, Texas 77002
CPF 4-2022-002-NOA
Dear Mr. Morton:
From May 3, 2021 through September 30, 2021, a representative of the Pipeline and Hazardous
Materials Safety Administration (PHMSA) pursuant to Chapter 601 of 49 United States Code
(U.S.C.), inspected Enterprise Crude Pipeline LLC’s (Enterprise) Seaway 30-inch Crude System,
Houston Crude System, and Midland Crude System in Oklahoma and Texas.
On the basis of the inspection, PHMSA has identified inadequacies found within Enterprise’s plans
or procedures, as described below:
1. § 195.402 Procedural manual for operations, maintenance, and emergencies.
(a) . . . .
(c) Maintenance and normal operations. The manual required by
paragraph (a) of this section must include procedures for the following
to provide safety during maintenance and normal operations:
(1) . . . .
(3) Operating, maintaining, and repairing the pipeline system in
accordance with each of the requirements of this subpart and subpart
H of this part.
§ 195.414 Inspections of pipelines in areas affected by extreme weather and natural
disasters.
(a) General. Following an extreme weather event or natural disaster
that has the likelihood of damage to infrastructure by the scouring or
movement of the soil surrounding the pipeline, such as a named
tropical storm or hurricane; a flood that exceeds the river, shoreline,
or creek high-water banks in the area of the pipeline; a landslide in the
area of the pipeline; or an earthquake in the area of the pipeline,
an operator must inspect all potentially affected pipeline facilities to
detect conditions that could adversely affect the safe operation of that



pipeline.
(b) Inspection method. An operator must consider the nature of the
event and the physical characteristics, operating conditions, location,
and prior history of the affected pipeline in determining the
appropriate method for performing the initial inspection to determine
the extent of any damage and the need for the additional assessments
required under paragraph (a) of this section.
(c) Time period. The inspection required under paragraph (a) of
this section must commence within 72 hours after the cessation of the
event, defined as the point in time when the affected area can be safely
accessed by the personnel and equipment required to perform the
inspection as determined under paragraph (b) of this section. In the
event that the operator is unable to commence the inspection due to the
unavailability of personnel or equipment, the operator must notify the
appropriate PHMSA Region Director as soon as practicable.
(d) Remedial action. An operator must take prompt and
appropriate remedial action to ensure the safe operation of a pipeline
based on the information obtained as a result of performing the
inspection required under paragraph (a) of this section. Such actions
might include, but are not limited to:
(1) Reducing the operating pressure or shutting down the pipeline;
(2) Modifying, repairing, or replacing any damaged pipeline
facilities;
(3) Preventing, mitigating, or eliminating any unsafe conditions in
the pipeline right-of-way;
(4) Performing additional patrols, surveys, tests, or inspections;
(5) Implementing emergency response activities with Federal, State,
or local personnel; and
(6) Notifying affected communities of the steps that can be taken to
ensure public safety
Enterprise’s written procedures for conducting operations, maintenance, and emergency
preparedness and response activities were inadequate to ensure safe operation of a pipeline facility
in accordance with § 195.402(c)(3). Specifically, Enterprise failed to include procedures for
inspection of its pipelines in areas affected by extreme weather and natural disasters in accordance
with § 195.414.
At the time of the inspection, Enterprise provided a draft copy of procedures to address § 195.414;
however, these procedures had not been implemented into any program or manual. Following the
inspection, on November 23, 2021, Enterprise provided the Table of Contents of Enterprise
Products’ Hurricane Plan 2021 (effective Date 6/1/2021, Rev. 12) for its South Texas Terminals,
and Section 5.7 Natural Disasters of its 2021 Emergency Response Plan in response to PHMSA’s
Post Inspection Findings. The records provided do not include the required provisions of §
195.414.



Therefore, Enterprise’s written procedures for conducting operations, maintenance, and
emergency preparedness and response activities were inadequate to ensure safe operation of a
pipeline facility in accordance with § 195.402(c)(3). Enterprise must revise its procedures to
address this requirement.
2. § 195.452 Pipeline integrity management in high consequence areas.
(a) . . . .
(f) What are the elements of an integrity management program? An
integrity management program begins with the initial framework. An
operator must continually change the program to reflect operating
experience, conclusions drawn from results of the integrity
assessments, and other maintenance and surveillance data, and
evaluation of consequences of a failure on the high consequence area.
An operator must include, at minimum, each of the following elements
in its written integrity management program:
(1) . . . .
(6) Identification of preventive and mitigative measures to protect
the high consequence area (see paragraph (i) of this section);
Enterprise’s written procedures for integrity management were inadequate to ensure safe operation
of a pipeline facility in accordance with § 195.452(f)(6). Specifically, Enterprise’s written
integrity management procedures failed to include a timeframe for implementation of preventive
and mitigative (P&M) measures to protect high consequence areas. Due to the inadequate
procedures, Enterprise failed to implement several identified P&M measures. In two instances,
five or more years passed before Enterprise approved the plan to address identified P&M
measures.1 Those P&M measures, identified in 2014 and 2015, have not been implemented.
Section 6-01.2.2.7.4 of the Information Analysis Facilities Procedure (IM Procedure 6-01F, Rev.
Date 5/14/20214, Rev. 09) states that “all preventive and mitigative recommendations requiring
action shall be prioritized, addressed, and administered under the Company capital project or
expense project process.” However, this procedure failed to include a timeframe for
implementation of identified P&M measures. Enterprise must amend its procedures to address
this deficiency to ensure identified P&M measures are timely implemented.
Therefore, Enterprise’s written procedures for integrity management were inadequate to ensure
safe operation of a pipeline facility in accordance with § 195.452(f)(6). Enterprise must revise its
procedures to address this requirement.
Response to this Notice
This Notice is provided pursuant to 49 U.S.C. § 60108(a) and 49 C.F.R. § 190.206. Enclosed as
part of this Notice is a document entitled Response Options for Pipeline Operators in Compliance
1 See Exh. A-5, Post Inspection Written Preliminary Findings, at 3-5 (Nov. 10, 2021); Exh. B-1, Midland Tank Farm
IMP Record, at 2.1.8 & 2.2.3 (Aug. 18, 2021); Exh. B-3, Cushing West Tank Farm IMP Records, at 2.1.4, 2.1.8,
2.2.3 (Aug. 18, 2021).



Proceedings. Please refer to this document and note the response options. Be advised that all
material you submit in response to this enforcement action is subject to being made publicly
available. If you believe that any portion of your responsive material qualifies for confidential
treatment under 5 U.S.C. § 552(b), along with the complete original document you must provide
a second copy of the document with the portions you believe qualify for confidential treatment
redacted and an explanation of why you believe the redacted information qualifies for confidential
treatment under 5 U.S.C. § 552(b).
Following the receipt of this Notice, you have 30 days to submit written comments, revised
procedures, or a request for a hearing under § 190.211. If you do not respond within 30 days of
receipt of this Notice, this constitutes a waiver of your right to contest the allegations in this Notice
and authorizes the Associate Administrator for Pipeline Safety to find facts as alleged in this Notice
without further notice to you and to issue an Order Directing Amendment. If your plans or
procedures are found inadequate as alleged in this Notice, you may be ordered to amend your plans
or procedures to correct the inadequacies (49 C.F.R. § 190.206). If you are not contesting this
Notice, we propose that you submit your amended procedures to my office within 30 days of
receipt of this Notice. This period may be extended by written request for good cause. Once the
inadequacies identified herein have been addressed in your amended procedures, this enforcement
action will be closed.
It is requested (not mandated) that Enterprise Crude Pipeline LLC maintain documentation of the
safety improvement costs associated with fulfilling this Notice of Amendment
(preparation/revision of plans, procedures) and submit the total to the Director, Southwest Region,
Pipeline and Hazardous Materials Safety Administration. In correspondence concerning this
matter, please refer to CPF 4-2022-002-NOA and, for each document you submit, please provide
a copy in electronic format whenever possible.
Sincerely,
Bryan Lethcoe
Director, Southwest Region
Pipeline and Hazardous Materials Safety Administration
Enclosure: Response Options for Pipeline Operators in Enforcement Proceedings

## Provenance

- Official: Yes
- Source: <https://primis.phmsa.dot.gov/enforcement-data/case/42022002NOA>
- Source ID: `phmsa-enforcement`
- SHA-256: `35fd3dc46a011d25d57e848a4a70d584e9857c401d31564c9a221a53add104a6`
- Retrieved: 2026-08-20T04:44:44.458Z
- Exported: 2026-08-22T18:59:56.799Z
- Document slug: `phmsa-enforcement-42022002noa`

### Source metadata

```json
{
  "cpf": "42022002NOA",
  "operator": "ENTERPRISE CRUDE PIPELINE LLC",
  "region": "Southwest",
  "pipelineType": "INTERSTATE LIQUID",
  "caseStatus": "CLOSED",
  "citedSections": [
    "195.402(c)(3)",
    "195.414(a)",
    "195.414(b)",
    "195.414(c)",
    "195.414(d)",
    "195.452(f)(6)"
  ],
  "dataAsOf": "08/04/2026 12PM",
  "caseDataAsOf": "2026-08-04",
  "attachmentCount": 5,
  "attachments": [
    {
      "name": "42022002NOA_Closure Letter_11182022_(21-209759).pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/42022002NOA/42022002NOA_Closure%20Letter_11182022_(21-209759).pdf",
      "bytes": 224716,
      "category": "agency_document"
    },
    {
      "name": "42022002NOA_Closure Letter_11182022_(21-209759)_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/42022002NOA/42022002NOA_Closure%20Letter_11182022_(21-209759)_text.pdf",
      "bytes": 60178,
      "category": "agency_document"
    },
    {
      "name": "42022002NOA_Notice of Amendment_08312022_(21-209759).pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/42022002NOA/42022002NOA_Notice%20of%20Amendment_08312022_(21-209759).pdf",
      "bytes": 311904,
      "category": "agency_document"
    },
    {
      "name": "42022002NOA_Notice of Amendment_08312022_(21-209759)_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/42022002NOA/42022002NOA_Notice%20of%20Amendment_08312022_(21-209759)_text.pdf",
      "bytes": 80359,
      "category": "agency_document"
    },
    {
      "name": "42022002NOA_Operator Response to Notice_09232022_(21-209759).pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/42022002NOA/42022002NOA_Operator%20Response%20to%20Notice_09232022_(21-209759).pdf",
      "bytes": 577960,
      "category": "party_submission"
    }
  ],
  "extractedAgencyDocumentCount": 2,
  "attachmentPolicy": "Official attachment links are retained. Agency-issued documents may also include a verified local PDF and page-level text representation.",
  "jurisdiction": "US",
  "operatorName": "ENTERPRISE CRUDE PIPELINE LLC"
}
```