# FREEPORT LNG DEVELOPMENT, L.P. — Notice of Amendment

**Citation:** CPF 42023059NOA  
**Type / status:** enforcement / historical  
**Agency:** Pipeline and Hazardous Materials Safety Administration  
**Effective:** Not stated  
**Published:** 2023-11-02

CLOSED notice of amendment citing 192.493, 192.605(b)(2), 192.615(a)(12).

## Document text

Notice of Amendment involving FREEPORT LNG DEVELOPMENT, L.P.. PHMSA's enforcement data identifies the cited regulations as 192.493,  192.605(b)(2),  192.615(a)(12). The case was opened on 2023-11-02 and is reported as closed as of 2024-03-20. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

42023059NOA_Closure Letter_03182024_(23-264730).pdf: https://primis.phmsa.dot.gov/enforcement-documents/42023059NOA/42023059NOA_Closure%20Letter_03182024_(23-264730).pdf

42023059NOA_Closure Letter_03182024_(23-264730)_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/42023059NOA/42023059NOA_Closure%20Letter_03182024_(23-264730)_text.pdf

42023059NOA_Notice of Amendment_11022023_(23-264730).pdf: https://primis.phmsa.dot.gov/enforcement-documents/42023059NOA/42023059NOA_Notice%20of%20Amendment_11022023_(23-264730).pdf

42023059NOA_Notice of Amendment_11022023_(23-264730)_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/42023059NOA/42023059NOA_Notice%20of%20Amendment_11022023_(23-264730)_text.pdf

42023059NOA_Operator Response to Notice_11302023_(23-264730).pdf: https://primis.phmsa.dot.gov/enforcement-documents/42023059NOA/42023059NOA_Operator%20Response%20to%20Notice_11302023_(23-264730).pdf

42023059NOA_Notice of Amendment_11022023_(23-264730)_text.pdf

NOTICE OF AMENDMENT
VIA ELECTRONIC MAIL TO: mmallet@freeportlng.com
November 2, 2023
Mark Mallett
Chief Operating Officer
Freeport LNG Development, LP
333 Clay Street
Houston, Texas 77002
CPF 4-2023-059-NOA
Dear Mr. Mallett:
From February 27 to April 4, 2023, representatives of the Pipeline and Hazardous Materials Safety
Administration (PHMSA) pursuant to Chapter 601 of 49 United States Code (U.S.C.) inspected
Freeport LNG Development, LP’s (FLNG) integrity management plan and maintenance and
operations procedures in Freeport, Texas.
On the basis of the inspection, PHMSA has identified the apparent inadequacies found within
FLNG’s plans and/or procedures as described below:
1. § 192.605 Procedural manual for operations, maintenance, and
emergencies.
(a) . . . .
(b) Maintenance and normal operations. The manual required by
paragraph (a) of this section must include procedures for the following,
if applicable, to provide safety during maintenance and operations.
(1) . . . .
(2) Controlling corrosion in accordance with the operations and
maintenance requirements of Subpart I of this part.



§ 192.493 In-line inspection of pipelines.
When conducting in-line inspections of pipelines required by this
part, an operator must comply with API STD 1163, ANSI/ASNT ILI -
PQ, and NACE SP0102, (incorporated by reference, see § 192.7).
Assessments may be conducted using tethered or remotely controlled
tools, not explicitly discussed in NACE SP0102, provided they comply
with those sections of NACE SP0102 that are applicable.
FLNG’s written procedures for controlling corrosion were inadequate to assure the safe operation
of a pipeline facility in accordance with § 192.605(b)(2). Specifically, FLNG’s procedure for
conducting in-line inspections (ILI), In-Line Inspection and Analysis, PPL-OPS-PRC-9001-
071.0001 (Revision: 0, dated April 28, 2021), failed to include ILI survey acceptance criteria
required by NACE SP0102, section 5.1.5 Survey-acceptance criteria in accordance with § 192.493.
Section 2.2.1.2 of FLNG’s In-Line Inspection and Analysis procedure stated that FLNG will rerun
the ILI tool if the results are not acceptable, as determined by the ILI Project Manager. However,
FLNG’s procedure does not include the requirement to develop and agree to a set of survey-
acceptance criteria that define when a rerun survey is required in accordance with section 5.1.5 of
NACE SP0102.
Therefore, FLNG’s written procedures for controlling corrosion were inadequate to assure the safe
operation of a pipeline facility in accordance with § 192.605(b)(2). FLNG must amend its ILI and
Analysis procedure to require development of ILI survey acceptance criteria as required by NACE
SP0102.
2. § 192.615 Emergency plans.
(a) Each operator shall establish written procedures to minimize
the hazard resulting from a gas pipeline emergency. At a minimum, the
procedures must provide for the following:
(1) . . . .
(12) Each operator must develop written rupture identification
procedures to evaluate and identify whether a notification of potential
rupture, as defined in § 192.3, is an actual rupture event or a non-
rupture event. These procedures must, at a minimum, specify the
sources of information, operational factors, and other criteria that
operator personnel use to evaluate a notification of potential rupture
and identify an actual rupture. For operators installing valves in
accordance with § 192.179(e), § 192.179(f), or that are subject to the
requirements in § 192.634, those procedures must provide for rupture
identification as soon as practicable.



FLNG’s written procedure to minimize the hazard resulting from a gas pipeline emergency was
inadequate to assure safe operation of a pipeline facility in accordance with § 192.615(a)(12).
Specifically, FLNG’s procedure Freeport LNG Facilities – Integrated Contingency Plan
(Revision: 0, dated August 2022) failed to include criteria to evaluate and identify whether a
notification of potential rupture, as defined in § 192.3, is an actual rupture event or a non-rupture
event in accordance with § 192.615(a)(12).
FLNG failed to include written rupture identification procedures in its Integrated Contingency
Plan. The procedure failed to specify the sources of information, operational factors, and other
criteria that operator personnel use to evaluate a notification of a potential rupture and identify an
actual rupture.
Therefore, FLNG’s written procedure to minimize the hazard resulting from a gas pipeline
emergency was inadequate to assure safe operation of a pipeline facility in accordance with §
192.615(a)(12). FLNG must revise its procedure as specified above.
Response to this Notice
This Notice is provided pursuant to 49 U.S.C. § 60108(a) and 49 C.F.R. § 190.206. Enclosed as
part of this Notice is a document entitled Response Options for Pipeline Operators in Enforcement
Proceedings.
Please refer to this document and note the response options. Be advised that all material you
submit in response to this enforcement action is subject to being made publicly available. If you
believe that any portion of your responsive material qualifies for confidential treatment under 5
U.S.C. § 552(b), along with the complete original document you must provide a second copy of
the document with the portions you believe qualify for confidential treatment redacted and an
explanation of why you believe the redacted information qualifies for confidential treatment under
5 U.S.C. § 552(b).
Following the receipt of this Notice, you have 30 days to submit written comments, revised
procedures, or a request for a hearing under § 190.211. If you do not respond within 30 days of
receipt of this Notice, this constitutes a waiver of your right to contest the allegations in this Notice
and authorizes the Associate Administrator for Pipeline Safety to find facts as alleged in this Notice
without further notice to you and to issue an Order Directing Amendment. If your plans or
procedures are found inadequate as alleged in this Notice, you may be ordered to amend your plans
or procedures to correct the inadequacies (49 C.F.R. § 190.206). If you are not contesting this
Notice, we propose that you submit your amended procedures to my office within 30 days of
receipt of this Notice. This period may be extended by written request for good cause. Once the
inadequacies identified herein have been addressed in your amended procedures, this enforcement
action will be closed.



It is requested (not mandated) that Freeport LNG Development, LP, maintain documentation of
the safety improvement costs associated with fulfilling this Notice of Amendment
(preparation/revision of plans, procedures) and submit the total to Bryan Lethcoe, Director,
Southwest, Pipeline and Hazardous Materials Safety Administration. In correspondence
concerning this matter, please refer to CPF 4-2023-059-NOA and, for each document you submit,
please provide a copy in electronic format whenever possible.
Sincerely,
Bryan Lethcoe
Director, Southwest Region, Office Pipeline Safety
Pipeline and Hazardous Materials Safety Administration
Enclosure: Response Options for Pipeline Operators in Enforcement Proceedings
cc: Michael Stephenson, Regulatory Compliance Manager, MStephenson@freeportlng.com
David Pesses, Sr. Compliance Specialist, DPesses@freeportlng.com

42023059NOA_Closure Letter_03182024_(23-264730)_text.pdf

VIA ELECTRONIC MAIL TO: mmoppert@freeportlng.com
March 18, 2024
Michael Moppert
Chief Operating Officer
Freeport LNG Development, L.P.
333 Clay Street
Houston, Texas 77002
CPF 4-2023-059-NOA
Dear Mr. Moppert:
On November 02, 2023, the Pipeline and Hazardous Materials Safety Administration (PHMSA)
issued the Notice of Ammendment (Notice) to Freeport LNG Development, L.P. (FLNG) requiring
amendments of its integrity management plan and maintenance and operations procedures. On
February 2, 2024 FLNG submitted its amended procedures, and it appears that the inadequacy
outlined in this Notice have been corrected.
Accordingly, this case is now closed, and no further action is contemplated with respect to the
matters involved in this case. Thank you for your cooperation.
Sincerely,
Bryan Lethcoe
Director, Southwest Region, Office of Pipeline Safety
Pipeline and Hazardous Materials Safety Administration
cc: Mr. Mike Stephenson, Director, Regulatory Affairs, MStephenson@freeportlng.com
Mr. David Pesses, Senior Regulatory Compliance Specialist, DPesses@freeportlng.com

## Provenance

- Official: Yes
- Source: <https://primis.phmsa.dot.gov/enforcement-data/case/42023059NOA>
- Source ID: `phmsa-enforcement`
- SHA-256: `487669bc12e801eb36601e0bedae858314ba6060042c9ea79f63071eaa8f2345`
- Retrieved: 2026-08-20T04:44:44.458Z
- Exported: 2026-08-22T13:29:58.640Z
- Document slug: `phmsa-enforcement-42023059noa`

### Source metadata

```json
{
  "cpf": "42023059NOA",
  "operator": "FREEPORT LNG DEVELOPMENT, L.P.",
  "region": "Southwest",
  "pipelineType": "INTERSTATE GAS TRANSMISSION",
  "caseStatus": "CLOSED",
  "citedSections": [
    "192.493",
    "192.605(b)(2)",
    "192.615(a)(12)"
  ],
  "dataAsOf": "08/04/2026 12PM",
  "caseDataAsOf": "2026-08-04",
  "attachmentCount": 5,
  "attachments": [
    {
      "name": "42023059NOA_Closure Letter_03182024_(23-264730).pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/42023059NOA/42023059NOA_Closure%20Letter_03182024_(23-264730).pdf",
      "bytes": 246810,
      "category": "agency_document"
    },
    {
      "name": "42023059NOA_Closure Letter_03182024_(23-264730)_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/42023059NOA/42023059NOA_Closure%20Letter_03182024_(23-264730)_text.pdf",
      "bytes": 98142,
      "category": "agency_document"
    },
    {
      "name": "42023059NOA_Notice of Amendment_11022023_(23-264730).pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/42023059NOA/42023059NOA_Notice%20of%20Amendment_11022023_(23-264730).pdf",
      "bytes": 346467,
      "category": "agency_document"
    },
    {
      "name": "42023059NOA_Notice of Amendment_11022023_(23-264730)_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/42023059NOA/42023059NOA_Notice%20of%20Amendment_11022023_(23-264730)_text.pdf",
      "bytes": 223183,
      "category": "agency_document"
    },
    {
      "name": "42023059NOA_Operator Response to Notice_11302023_(23-264730).pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/42023059NOA/42023059NOA_Operator%20Response%20to%20Notice_11302023_(23-264730).pdf",
      "bytes": 637458,
      "category": "party_submission"
    }
  ],
  "extractedAgencyDocumentCount": 2,
  "attachmentPolicy": "Official attachment links are retained. Agency-issued documents may also include a verified local PDF and page-level text representation.",
  "jurisdiction": "US",
  "operatorName": "FREEPORT LNG DEVELOPMENT, L.P."
}
```