# PHILLIPS 66 PIPELINE LLC — Notice of Probable Violation

**Citation:** CPF 520085038  
**Type / status:** enforcement / historical  
**Agency:** Pipeline and Hazardous Materials Safety Administration  
**Effective:** Not stated  
**Published:** 2008-10-15

CLOSED notice of probable violation citing 195.452(f)(4).

## Document text

Notice of Probable Violation involving PHILLIPS 66 PIPELINE LLC. PHMSA's enforcement data identifies the cited regulation as 195.452(f)(4). The case was opened on 2008-10-15 and is reported as closed as of 2011-02-28. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

520085038_closure letter_02282011.pdf: https://primis.phmsa.dot.gov/enforcement-documents/520085038/520085038_closure%20letter_02282011.pdf

520085038_closure letter_02282011_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/520085038/520085038_closure%20letter_02282011_text.pdf

520085038_Final Order_05052009.pdf: https://primis.phmsa.dot.gov/enforcement-documents/520085038/520085038_Final%20Order_05052009.pdf

520085038_Final Order_05052009_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/520085038/520085038_Final%20Order_05052009_text.pdf

520085038_nopv pco_10152008_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/520085038/520085038_nopv%20pco_10152008_text.pdf

520085038_closure letter_02282011_text.pdf

CERTIFIED MAIL - RETURN RECEIPT REQUESTED
February 28, 2011
Mr. Todd L. Tulio
Manager, Regulatory Compliance
ConocoPhillips Pipe Line Company
TN-5100
600 North Dairy Ashford
Houston, TX 77252-2197
CPF 5-2008-5038
Dear Mr. Tulio:
On May 5, 2009, the Pipeline and Hazardous Materials Safety Administration (PHMSA) issued
to ConocoPhillips Pipe Line Company a Final Order in the above-referenced case. This Order
included a Compliance Order. Based on our review of the documentation you provided, it has
been determined that you have complied with the terms of this Order. The detail records
pertaining to your evaluation and remediation will be reviewed on the next IMP inspection.
Accordingly, this case is now closed and no further action is contemplated with respect to the
matters involved in this case. Thank you for your cooperation in this matter.
Sincerely,
Chris Hoidal
Director, Western Region
Pipeline and Hazardous Materials Safety Administration
cc: PHP-60 Compliance Registry
PHP-500 H. Nguyen (#121862)

520085038_Final Order_05052009_text.pdf

May 5 2009
Ms. Margaret A. Yaege
President
ConocoPhillips Pipe Line Company
600 North Dairy Ashford
Houston, TX 77079
Re: CPF No. 5-2008-5038
Dear Ms. Yaege:
Enclosed is the Final Order issued in the above-referenced case. It makes a finding of violation
and specifies actions that ConocoPhillips needs to take to comply with the pipeline safety
regulations. When the terms of the compliance order have been completed, as determined by the
Director, Western Region, this enforcement action will be closed. Your receipt of this Final
Order constitutes service of that document under 49 C.F.R. § 190.5.
Thank you for your cooperation in this matter.
Sincerely,
Jeffrey D. Wiese
Associate Administrator
for Pipeline Safety
Enclosure
cc: Mr. Chris Hoidal, Director, Western Region, PHMSA
Mr. Todd Tullio, Director, Regulatory Compliance
ConocoPhillips Pipe Line Company
1000 South Pine
Ponca City, OK 76602
CERTIFIED MAIL – RETURN RECEIPT REQUESTED [7005 1160 0001 0046 9488]



U.S. DEPARTMENT OF TRANSPORTATION
PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION
OFFICE OF PIPELINE SAFETY
WASHINGTON, D.C. 20590
___________________________________
In the Matter of )
ConocoPhillips Pipe Line Company, ) CPF No.5-2008-5038
)
)
)
Respondent. )
___________________________________ )
FINAL ORDER
On May 19–23 and June 2–5, 2008, pursuant to 49 U.S.C. § 60117, representatives of the
Pipeline and Hazardous Materials Safety Administration (PHMSA), Office of Pipeline Safety
(OPS), conducted an inspection of the Integrity Management Program (IMP) of ConocoPhillips
Pipe Line Company (ConocoPhillips or Respondent) at its offices in Ponca City, Oklahoma.
ConocoPhillips operates approximately 10,556 miles of DOT-regulated hazardous liquid
pipelines that transport crude oil, refined products, and highly volatile liquids. As a result of the
inspection, the Director, Western Region, OPS (Director), issued to ConocoPhillips, by letter
dated October 15, 2008, a Notice of Probable Violation and Proposed Compliance Order
(Notice). In accordance with 49 C.F.R. § 190.207, the Notice proposed finding that
ConocoPhillips had violated 49 C.F.R. § 195.452 and proposed ordering ConocoPhillips to take
certain measures to correct the alleged violation.
ConocoPhillips responded to the Notice by letter dated November 18, 2008 (Response). The
company did not contest the allegation of violation but requested a modification of the proposed
Compliance Order. Respondent did not request a hearing and therefore has waived its right to
one.
FINDING OF VIOLATION
In its Response, ConocoPhillips did not contest the allegation in the Notice that it violated 49
C.F.R. Part 195, as follows:
Item 1: The Notice alleged that Respondent violated 49 C.F.R. § 195.452, which states in
relevant part:
§ 195.452 Pipeline integrity management in high consequence areas.
(a) . . . .
(f) What are the elements of an integrity management program? An integrity
management program begins with the initial framework. An operator must
continually change the program to reflect operating experience, conclusions
drawn from results of the integrity assessments, and other maintenance and



2
surveillance data, and evaluation of consequences of a failure on the high
consequence area. An operator must include, at minimum, each of the following
elements in its written integrity management program:
(1) . . .
(4) Criteria for remedial actions to address integrity issues raised by the
assessment methods and information analysis (see paragraph (h) of this section) .
. . .
(h) What actions must an operator take to address integrity issues?
(1) General requirements. An operator must take prompt action to address all
anomalous conditions the operator discovers through the integrity assessment or
information analysis. In addressing all conditions, an operator must evaluate all
anomalous conditions and remediate those that could reduce a pipeline’s integrity.
An operator must be able to demonstrate that the remediation of the condition will
ensure the condition is unlikely to pose a threat to the long-term integrity of the
pipeline. . . . .
(2) . . .
(4) Special requirements for scheduling remediation—
(i) Immediate repair conditions . . .
(iii) 180-day conditions. Except for conditions listed in paragraph (h)(4)(i) or
(ii) of this section, an operator must schedule evaluation and remediation of the
following within 180 days of discovery of the condition:
(A) A dent with a depth greater than 2% of the pipeline’s diameter (0.250
inches in depth for a pipeline diameter less than NPS 12) that affects pipe
curvature at a girth weld or a longitudinal seam weld.
(B) A dent located on the top of the pipeline (above 4 and 8 o’clock position)
with a depth greater than 2% of the pipeline’s diameter (0.250 inches in depth for
a pipeline diameter less than NPS 12).
(C) A dent located on the bottom of the pipeline with a depth greater than 6%
of the pipeline’s diameter.
(D) A calculation of the remaining strength of the pipe shows an operating
pressure that is less than the current established maximum operating pressure at
the location of the anomaly. Suitable remaining strength calculation methods
include, but are not limited to, ASME/ANSI B31G (“Manual for Determining the
Remaining Strength of Corroded Pipelines” (1991)) or AGA Pipeline Research
Committee Project PR-3-805 (“A Modified Criterion for Evaluating the
Remaining Strength of Corroded Pipe” (December 1989)). These documents are
incorporated by reference and are available at the addresses listed in § 195.3.
(E) An area of general corrosion with a predicted metal loss greater than 50%
of nominal wall.
(F) Predicted metal loss greater than 50% of nominal wall that is located at a
crossing of another pipeline, or is in an area with widespread circumferential
corrosion, or is in an area that could affect a girth weld.
(G) A potential crack indication that when excavated is determined to be a crack.
(H) Corrosion of or along a longitudinal seam weld.
(I) A gouge or groove greater than 12.5% of nominal wall.



3
The Notice alleged that ConocoPhillips violated § 195.452(h)(4)(iii) by failing to properly
schedule the evaluation and remediation of certain anomalous conditions that must be remediated
within 180 days of their discovery. Specifically, the Notice alleged that ConocoPhillips did not
integrate data showing the known longitudinal seam orientation of its pipeline with results it had
obtained from in-line inspections (ILIs), a process that is necessary to identify potentially
corrosion might be serious enough to warrant remediation within 180 days, it is necessary to
integrate longitudinal seam orientation data with relevant ILI results. Respondent did not contest
this allegation and indicated that it would integrate its long seam orientation data with ILI results.
Accordingly, upon consideration of all of the evidence, I find that Respondent violated 49 C.F.R.
within 180 days of their discovery.
significant corrosion along longitudinal seam welds.1 To identify longitudinal seam welds where
§ 195.452(h)(4)(iii) by failing to properly identify anomalous conditions that must be remediated
This finding of violation will be considered a prior offense in any subsequent enforcement action
taken against Respondent.
COMPLIANCE ORDER
The Notice proposed a compliance order with respect to Item 1 in the Notice for a violation of 49
C.F.R. § 195.452. Under 49 U.S.C. § 60118(a), each person who engages in the transportation
of hazardous liquids or who owns or operates a pipeline facility is required to comply with the
applicable safety standards established under chapter 601.
In its Response, ConocoPhillips requested an adjustment of the 60-day deadline in the proposed
Compliance Order for integrating its longitudinal seam orientation data with the ILI results.
Respondent explained that it needed additional time to integrate and analyze all the information.
The Director has reviewed and agrees with Respondent’s alternative schedule, which is reflected
in the amended compliance terms below. This Compliance Order, however, does not constitute
acceptance or approval of the proposed corrective actions outlined in the company’s Response.
The Director will review and address the adequacy of ConocoPhillips’ plans and procedures in
the context of submittals provided to the Director in response to this Compliance Order.
Pursuant to the authority of 49 U.S.C. § 60118(b) and 49 C.F.R. § 190.217, Respondent is
ordered to take the following actions to ensure compliance with the pipeline safety regulations
applicable to its operations. Respondent must:
1. Review its in-line inspection data and/or records to verify that all of the defects
associated with long seam corrosion have been discovered, categorized, and repaired in
accordance with 49 C.F.R. § 195.452(h)(4)(iii).
2. In accordance with the schedule proposed in Respondent’s Response, and in no event
later than December 31, 2009, complete the above item and submit the required
documentation and procedures to the Director, Western Region, Pipeline and Hazardous
Materials Safety Administration, 12300 West Dakota Avenue, Suite 110, Lakewood,
Colorado 80228.
1 Subsection (H) of 49 C.F.R. § 195.452(h)(4)(iii), as quoted above.



4
3. Maintain documentation of the safety improvement costs associated with fulfilling this
Compliance Order and report the total costs to the Director as follows: (a) total cost
associated with preparation/revision of plans and procedures, and performance of studies
and analyses; and (b) total cost associated with physical changes, if any, to the pipeline
infrastructures, including replacements and additions.
The Director may grant an extension of time to comply with any of the required items upon a
written request timely submitted by the Respondent demonstrating good cause for an extension.
Failure to comply with this Order may result in administrative assessment of civil penalties not
to exceed $100,000 for each violation for each day the violation continues or in referral to the
Attorney General for appropriate relief in a district court of the United States.
Under 49 C.F.R. § 190.215, Respondent has a right to submit a Petition for Reconsideration of
this Final Order. The petition must be received within 20 days of Respondent’s receipt of this
Final Order and must contain a brief statement of the issue(s). The terms of the order, including
any required corrective action, shall remain in full force and effect unless the Associate
Administrator, upon request, grants a stay. The terms and conditions of this Final Order shall be
effective upon receipt.
___________________________________ __________________________
Jeffrey D. Wiese Date Issued
Associate Administrator
for Pipeline Safety

## Provenance

- Official: Yes
- Source: <https://primis.phmsa.dot.gov/enforcement-data/case/520085038>
- Source ID: `phmsa-enforcement`
- SHA-256: `71e76a5cd9fc899e537b226082bb6db8f7cfaea15d5416efeca275fda02339b0`
- Retrieved: 2026-08-20T04:44:44.458Z
- Exported: 2026-08-23T16:20:17.712Z
- Document slug: `phmsa-enforcement-520085038`

### Source metadata

```json
{
  "cpf": "520085038",
  "operator": "PHILLIPS 66 PIPELINE LLC",
  "region": "Western",
  "pipelineType": "INTERSTATE LIQUID ONSHORE",
  "caseStatus": "CLOSED",
  "citedSections": [
    "195.452(f)(4)"
  ],
  "dataAsOf": "08/04/2026 12PM",
  "caseDataAsOf": "2026-08-04",
  "attachmentCount": 5,
  "attachments": [
    {
      "name": "520085038_closure letter_02282011.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/520085038/520085038_closure%20letter_02282011.pdf",
      "bytes": 63901,
      "category": "agency_document"
    },
    {
      "name": "520085038_closure letter_02282011_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/520085038/520085038_closure%20letter_02282011_text.pdf",
      "bytes": 9505,
      "category": "agency_document"
    },
    {
      "name": "520085038_Final Order_05052009.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/520085038/520085038_Final%20Order_05052009.pdf",
      "bytes": 221086,
      "category": "agency_document"
    },
    {
      "name": "520085038_Final Order_05052009_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/520085038/520085038_Final%20Order_05052009_text.pdf",
      "bytes": 26939,
      "category": "agency_document"
    },
    {
      "name": "520085038_nopv pco_10152008_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/520085038/520085038_nopv%20pco_10152008_text.pdf",
      "bytes": 320668,
      "category": "case_document"
    }
  ],
  "extractedAgencyDocumentCount": 2,
  "attachmentPolicy": "Official attachment links are retained. Agency-issued documents may also include a verified local PDF and page-level text representation.",
  "jurisdiction": "US",
  "operatorName": "PHILLIPS 66 PIPELINE LLC"
}
```