# FAIRBANKS NATURAL GAS — Notice of Probable Violation

**Citation:** CPF 520163005  
**Type / status:** enforcement / historical  
**Agency:** Pipeline and Hazardous Materials Safety Administration  
**Effective:** Not stated  
**Published:** 2016-09-16

CLOSED notice of probable violation citing 193.2607(b).

## Document text

Notice of Probable Violation involving FAIRBANKS NATURAL GAS. PHMSA's enforcement data identifies the cited regulation as 193.2607(b). The case was opened on 2016-09-16 and is reported as closed as of 2020-12-03. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

520163005_Closure Letter_12032020.pdf: https://primis.phmsa.dot.gov/enforcement-documents/520163005/520163005_Closure%20Letter_12032020.pdf

520163005_Closure Letter_12032020_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/520163005/520163005_Closure%20Letter_12032020_text.pdf

520163005_Final Order_01142020.pdf: https://primis.phmsa.dot.gov/enforcement-documents/520163005/520163005_Final%20Order_01142020.pdf

520163005_Final Order_01142020_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/520163005/520163005_Final%20Order_01142020_text.pdf

520163005_NOPV PCO_09162016.pdf: https://primis.phmsa.dot.gov/enforcement-documents/520163005/520163005_NOPV%20PCO_09162016.pdf

520163005_NOPV PCO_09162016_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/520163005/520163005_NOPV%20PCO_09162016_text.pdf

520163005_Operator Response to Notice_10142016.pdf: https://primis.phmsa.dot.gov/enforcement-documents/520163005/520163005_Operator%20Response%20to%20Notice_10142016.pdf

520163005_Final Order_01142020_text.pdf

January 14, 2020
Mr. Daniel W. Britton
President and Chief Executive Officer
Fairbanks Natural Gas, LLC
3408 International Way
Fairbanks, Alaska 99701
Re: CPF No. 5-2016-3005
Dear Mr. Britton:
Enclosed please find the Final Order issued in the above-referenced case. It makes a finding of
violation and specifies actions that need to be taken to comply with the pipeline safety
regulations. When the terms of the compliance order are completed, as determined by the
Director, Western Region, this enforcement action will be closed. Service of the Final Order by
certified mail is effective upon the date of mailing as provided under 49 C.F.R. § 190.5.
Thank you for your cooperation in this matter.
Sincerely,
Alan K. Mayberry
Administrator
for Pipeline Safety
Enclosure (Final Order and NOPV)
cc: Mr. Dustin Hubbard, Director, Western Region, Office of Pipeline Safety, PHMSA
Mr. Chris Gillespie, Operations Engineer, Fairbanks Natural Gas, LLC
CERTIFIED MAIL - RETURN RECEIPT REQUESTED



U.S. DEPARTMENT OF TRANSPORTATION
PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION
OFFICE OF PIPELINE SAFETY
WASHINGTON, D.C. 20590
____________________________________
In the Matter of )
Fairbanks Natural Gas, LLC, ) CPF No. 5-2016-3005
)
)
)
Respondent. )
____________________________________)
FINAL ORDER
On September 16, 2016, pursuant to 49 C.F.R. § 190.207, the Director, Western Region, Office
of Pipeline Safety (OPS), issued a Notice of Probable Violation and Proposed Compliance Order
(Notice) to Fairbanks Natural Gas, LLC (Respondent). The Notice proposed finding that
Respondent had violated the pipeline safety regulations in 49 C.F.R. Part 193 and proposed
certain measures to correct the alleged violation. Respondent did not contest the allegation of
violation or corrective measures.
Based upon a review of all the evidence, pursuant to § 190.213, I find Respondent violated the
pipeline safety regulation listed below, as more fully described in the Notice, which is
incorporated by reference:
49 C.F.R. § 193.2607(b) (Item 1) – Respondent failed to keep its LNG plant
grounds free from rubbish, debris and other material which present a fire hazard.
This finding of violation will be considered a prior offense in any subsequent enforcement action
taken against Respondent.
The Notice proposed a compliance order with respect to Item 1 in the Notice for violation of 49
C.F.R. § 193.2607(b). Under 49 U.S.C. § 60118(a), each person who engages in the
transportation of gas or who owns or operates a pipeline facility is required to comply with the
applicable safety standards established under chapter 601. Pursuant to the authority of 49 U.S.C.
§ 60118(b) and 49 C.F.R. § 190.217, Respondent is ordered to take the following actions to
ensure compliance with the pipeline safety regulations applicable to its operations:1
COMPLIANCE ORDER
1 Note: On August 14, 2019, pursuant to 49 C.F.R. § 190.9, FNG filed a Petition for finding or approval (Petition)
requesting permission to deviate from the requirements of § 193.2173. The approval of the Petition may supersede
the requirements of this Order.



CPF No. 5-2016-3005
Page 2
1. With respect to the violation of § 193.2607(b) (Item 1), Respondent must develop
and implement a means to keep all LNG vaults and impoundments free of water,
snow, and ice. FNG must document all details of any facility changes made because
of this Order. FNG must revise its operations and maintenance procedures to record
and document ice, snow, and water removal maintenance activities.
The Director may grant an extension of time to comply with any of the required items upon a
written request timely submitted by the Respondent and demonstrating good cause for an
extension.
It is requested (not mandated) that Respondent maintain documentation of the safety
improvement costs associated with fulfilling this Compliance Order and submit the total to the
Director. It is requested that these costs be reported in two categories: (1) total cost associated
with preparation/revision of plans, procedures, studies and analyses; and (2) total cost associated
with replacements, additions and other changes to pipeline infrastructure.
Failure to comply with this Order may result in the administrative assessment of civil penalties
not to exceed $200,000, as adjusted for inflation (49 C.F.R. § 190.223), for each violation for
each day the violation continues or in referral to the Attorney General for appropriate relief in a
district court of the United States.
Under 49 C.F.R. § 190.243, Respondent may submit a Petition for Reconsideration of this Final
Order to the Associate Administrator, Office of Pipeline Safety, PHMSA, 1200 New Jersey
Avenue, SE, East Building, 2nd Floor, Washington, DC 20590, with a copy sent to the Office of
Chief Counsel, PHMSA, at the same address, no later than 20 days after receipt of service of this
Final Order by Respondent. Any petition submitted must contain a statement of the issue(s) and
meet all other requirements of 49 C.F.R. § 190.243. The terms of the order, including corrective
action, remain in effect unless the Associate Administrator, upon request, grants a stay.
The terms and conditions of this Final Order are effective upon service in accordance with 49
C.F.R. § 190.5.
January 14, 2020
___________________________________ __________________________
Alan K. Mayberry Date Issued
Associate Administrator
for Pipeline Safety

520163005_Closure Letter_12032020_text.pdf

VIA E-MAIL TO MR. DANIEL W. BRITTON
December 3, 2020
Mr. Daniel W. Britton
President and Chief Executive Officer
Fairbanks Natural Gas, LLC
3408 International Way
Fairbanks, Alaska 99701
CPF 5-2016-3005
Closure Letter
Dear Mr. Britton:
On January 14, 2020, the Pipeline and Hazardous Materials Safety Administration (PHMSA)
issued to Fairbanks Natural Gas, LLC a Final Order in the above-referenced case. This Order
required you to amend your procedures and take corrective actions on your facilities. Based on
our review of the documentation provided, the terms of this Order have been met.
Accordingly, this case is now closed and no further action is required. Thank you for your
cooperation in this matter.
Sincerely,
Dustin Hubbard
Director, Western Region
Pipeline and Hazardous Materials Safety Administration
cc: PHP-60 Compliance Registry
PHP-500 J. Owens

## Provenance

- Official: Yes
- Source: <https://primis.phmsa.dot.gov/enforcement-data/case/520163005>
- Source ID: `phmsa-enforcement`
- SHA-256: `b808b7b3ec5450bba2740c86d0d160211b726704870f900a52e021d11b5f1f6e`
- Retrieved: 2026-08-20T04:44:44.458Z
- Exported: 2026-08-22T13:56:43.721Z
- Document slug: `phmsa-enforcement-520163005`

### Source metadata

```json
{
  "cpf": "520163005",
  "operator": "FAIRBANKS NATURAL GAS",
  "region": "Western",
  "pipelineType": "INTERSTATE LNG ONSHORE",
  "caseStatus": "CLOSED",
  "citedSections": [
    "193.2607(b)"
  ],
  "dataAsOf": "08/04/2026 12PM",
  "caseDataAsOf": "2026-08-04",
  "attachmentCount": 7,
  "attachments": [
    {
      "name": "520163005_Closure Letter_12032020.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/520163005/520163005_Closure%20Letter_12032020.pdf",
      "bytes": 235922,
      "category": "agency_document"
    },
    {
      "name": "520163005_Closure Letter_12032020_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/520163005/520163005_Closure%20Letter_12032020_text.pdf",
      "bytes": 72703,
      "category": "agency_document"
    },
    {
      "name": "520163005_Final Order_01142020.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/520163005/520163005_Final%20Order_01142020.pdf",
      "bytes": 881614,
      "category": "agency_document"
    },
    {
      "name": "520163005_Final Order_01142020_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/520163005/520163005_Final%20Order_01142020_text.pdf",
      "bytes": 91027,
      "category": "agency_document"
    },
    {
      "name": "520163005_NOPV PCO_09162016.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/520163005/520163005_NOPV%20PCO_09162016.pdf",
      "bytes": 142930,
      "category": "case_document"
    },
    {
      "name": "520163005_NOPV PCO_09162016_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/520163005/520163005_NOPV%20PCO_09162016_text.pdf",
      "bytes": 87038,
      "category": "case_document"
    },
    {
      "name": "520163005_Operator Response to Notice_10142016.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/520163005/520163005_Operator%20Response%20to%20Notice_10142016.pdf",
      "bytes": 187122,
      "category": "party_submission"
    }
  ],
  "extractedAgencyDocumentCount": 2,
  "attachmentPolicy": "Official attachment links are retained. Agency-issued documents may also include a verified local PDF and page-level text representation.",
  "jurisdiction": "US",
  "operatorName": "FAIRBANKS NATURAL GAS"
}
```