# CHEYENNE RAIL HUB — Notice of Amendment

**Citation:** CPF 520166002M  
**Type / status:** enforcement / historical  
**Agency:** Pipeline and Hazardous Materials Safety Administration  
**Effective:** Not stated  
**Published:** 2016-03-17

CLOSED notice of amendment citing 195.110(a), 195.446(h).

## Document text

Notice of Amendment involving CHEYENNE RAIL HUB. PHMSA's enforcement data identifies the cited regulations as 195.110(a),  195.446(h). The case was opened on 2016-03-17 and is reported as closed as of 2016-05-05. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

520166002M_Closure Letter_05052016.pdf: https://primis.phmsa.dot.gov/enforcement-documents/520166002M/520166002M_Closure%20Letter_05052016.pdf

520166002M_Closure Letter_05052016_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/520166002M/520166002M_Closure%20Letter_05052016_text.pdf

520166002M_Notice of Amendment_03172016.pdf: https://primis.phmsa.dot.gov/enforcement-documents/520166002M/520166002M_Notice%20of%20Amendment_03172016.pdf

520166002M_Notice of Amendment_03172016_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/520166002M/520166002M_Notice%20of%20Amendment_03172016_text.pdf

520166002M_Operator Response to Notice_04012016.pdf: https://primis.phmsa.dot.gov/enforcement-documents/520166002M/520166002M_Operator%20Response%20to%20Notice_04012016.pdf

520166002M_Notice of Amendment_03172016_text.pdf

NOTICE OF AMENDMENT
CERTIFIED MAIL - RETURN RECEIPT REQUESTED
March 17, 2016
Mr. Daniel Withers
President
Cogent Energy Solutions LLC
3100 Timmons Lane, Suite 210
Houston, TX 77027
CPF 5-2016-6002M
Dear Mr. Withers:
On February 9-11, 2016, representatives of the Pipeline and Hazardous Materials Safety
Administration (PHMSA), pursuant to Chapter 601 of 49 United States Code, inspected
Cogent Energy Solutions LLC’s Cheyenne Rail Hub operation and maintenance procedures
and implementing records at your facilities in Cheyenne, WY.
On the basis of the inspection, PHMSA has identified the apparent inadequacies found within
Cheyenne Rail Hub’s plans or procedures, as described below:
1. §195.446 Control Room Management
(h) Training. Each operator must establish a controller training program and
review the training program content to identify potential improvements at least
once each calendar year, but at intervals not to exceed 15 months. An operator's
program must provide for training each controller to carry out the roles and
responsibilities defined by the operator. In addition, the training program must
include the following elements:
(1) Responding to abnormal operating conditions likely to occur simultaneously
or in sequence;



(2) Use of a computerized simulator or non-computerized (tabletop) method for
training controllers to recognize abnormal operating conditions;
(3) Training controllers on their responsibilities for communication under the
operator's emergency response procedures;
(4) Training that will provide a controller a working knowledge of the pipeline
system, especially during the development of abnormal operating conditions; and
(5) For pipeline operating setups that are periodically, but infrequently used,
providing an opportunity for controllers to review relevant procedures in
advance of their application.
Cheyenne Rail Hub’s Control Room Management program did not address the requirement of
195.446(h) to review the training program content to identify potential improvements at least
once each calendar year, but at intervals not to exceed 15 months. Cheyenne Rail Hub needs
to add the requirement to “identify potential improvements at least once each calendar year,
but at intervals not to exceed 15 months” to their control room management program. The
required review must at minimum address items 195.446(h)(1) through (5).
2. §195.110 External loads
(a) Anticipated external loads (e.g.), earthquakes, vibration, thermal expansion,
and contraction must be provided for in designing a pipeline system. In
providing for expansion and flexibility, §419 of ASME/ANSI B31.4 must be
followed.
Cheyenne Rail Hub’s operation and maintenance manual (O&M) does not reference
ASME/ANSI B31.4 with respect to §195.110. Cheyenne Rail Hub’s O&M manual needs to
reference AMSE/ANSI B31.4 with respect to anticipated external loads. The anticipated
loads that are expected for your Cogent facility should be identified.
Response to this Notice
This Notice is provided pursuant to 49 U.S.C. § 60108(a) and 49 C.F.R. § 190.237. Enclosed
as part of this Notice is a document entitled Response Options for Pipeline Operators in
Compliance Proceedings. Please refer to this document and note the response options. Be
advised that all material you submit in response to this enforcement action is subject to being
made publicly available. If you believe that any portion of your responsive material qualifies
for confidential treatment under 5 U.S.C. 552(b), along with the complete original document
you must provide a second copy of the document with the portions you believe qualify for
confidential treatment redacted and an explanation of why you believe the redacted
information qualifies for confidential treatment under 5 U.S.C. 552(b). If you do not respond
within 30 days of receipt of this Notice, this constitutes a waiver of your right to contest the
allegations in this Notice and authorizes the Associate Administrator for Pipeline Safety to
find facts as alleged in this Notice without further notice to you and to issue a Final Order.
2



If, after opportunity for a hearing, your plans or procedures are found inadequate as alleged in
this Notice, you may be ordered to amend your plans or procedures to correct the
inadequacies (49 C.F.R. § 190.237). If you are not contesting this Notice, we propose that
you submit your amended procedures to my office within [number of days] days of receipt of
this Notice. This period may be extended by written request for good cause. Once the
inadequacies identified herein have been addressed in your amended procedures, this
enforcement action will be closed.
It is requested (not mandated) that Cheyenne Rail Hub maintain documentation of the safety
improvement costs associated with fulfilling this Notice of Amendment (preparation/revision
of plans, procedures) and submit the total to Chris Hoidal, Director, Western Region, Pipeline
and Hazardous Materials Safety Administration. In correspondence concerning this matter,
please refer to CPF 5-2016-6002M and, for each document you submit, please provide a copy
in electronic format whenever possible.
Sincerely,
Chris Hoidal
Director, Western Region
Pipeline and Hazardous Materials Safety Administration
Enclosure: Response Options for Pipeline Operators in Compliance Proceedings
cc: PHP-60 Compliance Registry
PHP-500 Ogirima (#152004)
3

520166002M_Closure Letter_05052016_text.pdf

CERTIFIED MAIL - RETURN RECEIPT REQUESTED
May 5, 2016
Mr. Daniel Withers
President
Cogent Energy Solutions LLC
3100 Timmons Lane, Suite 210
Houston, TX 77027
CPF 5-2016-6002M
Closure of Case
Dear Mr. Withers:
On February 9-11, 2016, a representative from the Pipeline and Hazardous Materials Safety
Administration (PHMSA), pursuant to chapter 601 of 49 United States Code, conducted an on-site
pipeline safety inspection of Cogent Energy Solution LLC’s Cheyenne Rail Hub procedures and
records at your facilities in Cheyenne, Wyoming. As a result of the inspection, Cogent Energy
Solutions LLC was issued a Notice of Amendment on March 17, 2016 which proposed amendment of
your procedures.
Cogent Energy Solutions LLC submitted its amended procedures on April 1, 2016. My staff reviewed
the amended procedures, and it appears that the inadequacies outlined in this Notice of Amendment
have been corrected.
This letter is to inform you no further action is necessary and this case is now closed. Thank you for
your cooperation.
Sincerely,
Chris Hoidal
Director, Western Region
Pipeline and Hazardous Materials Safety Administration
cc: PHP-60 Compliance Registry
PHP-500 Ogirima (#152004)

## Provenance

- Official: Yes
- Source: <https://primis.phmsa.dot.gov/enforcement-data/case/520166002M>
- Source ID: `phmsa-enforcement`
- SHA-256: `9cf66b76b3cc4a67ceb7aea85a7e89fdfe846a9af5581f383cb9682145a78c61`
- Retrieved: 2026-08-20T04:44:44.458Z
- Exported: 2026-08-24T16:00:10.944Z
- Document slug: `phmsa-enforcement-520166002m`

### Source metadata

```json
{
  "cpf": "520166002M",
  "operator": "CHEYENNE RAIL HUB",
  "region": "Western",
  "pipelineType": "INTRASTATE LIQUID ONSHORE",
  "caseStatus": "CLOSED",
  "citedSections": [
    "195.110(a)",
    "195.446(h)"
  ],
  "dataAsOf": "08/04/2026 12PM",
  "caseDataAsOf": "2026-08-04",
  "attachmentCount": 5,
  "attachments": [
    {
      "name": "520166002M_Closure Letter_05052016.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/520166002M/520166002M_Closure%20Letter_05052016.pdf",
      "bytes": 27599,
      "category": "agency_document"
    },
    {
      "name": "520166002M_Closure Letter_05052016_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/520166002M/520166002M_Closure%20Letter_05052016_text.pdf",
      "bytes": 7630,
      "category": "agency_document"
    },
    {
      "name": "520166002M_Notice of Amendment_03172016.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/520166002M/520166002M_Notice%20of%20Amendment_03172016.pdf",
      "bytes": 279110,
      "category": "agency_document"
    },
    {
      "name": "520166002M_Notice of Amendment_03172016_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/520166002M/520166002M_Notice%20of%20Amendment_03172016_text.pdf",
      "bytes": 12124,
      "category": "agency_document"
    },
    {
      "name": "520166002M_Operator Response to Notice_04012016.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/520166002M/520166002M_Operator%20Response%20to%20Notice_04012016.pdf",
      "bytes": 1121956,
      "category": "party_submission"
    }
  ],
  "extractedAgencyDocumentCount": 2,
  "attachmentPolicy": "Official attachment links are retained. Agency-issued documents may also include a verified local PDF and page-level text representation.",
  "jurisdiction": "US",
  "operatorName": "CHEYENNE RAIL HUB"
}
```