# COLORADO INTERSTATE GAS CO — Notice of Probable Violation

**Citation:** CPF 520166005  
**Type / status:** enforcement / historical  
**Agency:** Pipeline and Hazardous Materials Safety Administration  
**Effective:** Not stated  
**Published:** 2016-08-26

CLOSED notice of probable violation citing 195.420(b), 195.428(a), 195.452(h)(1), 195.452(h)(3), 195.452(h)(4)(ii)(a).

## Document text

Notice of Probable Violation involving COLORADO INTERSTATE GAS CO. PHMSA's enforcement data identifies the cited regulations as 195.420(b),  195.428(a),  195.452(h)(1),  195.452(h)(3),  195.452(h)(4)(ii)(a). The case was opened on 2016-08-26 and is reported as closed as of 2018-06-20. Proposed civil penalty: $198,000. Assessed civil penalty: $154,800. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

520166005_Final Order_06012018.pdf: https://primis.phmsa.dot.gov/enforcement-documents/520166005/520166005_Final%20Order_06012018.pdf

520166005_Final Order_06012018_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/520166005/520166005_Final%20Order_06012018_text.pdf

520166005_NOPV PCP_08262016.pdf: https://primis.phmsa.dot.gov/enforcement-documents/520166005/520166005_NOPV%20PCP_08262016.pdf

520166005_NOPV PCP_08262016_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/520166005/520166005_NOPV%20PCP_08262016_text.pdf

520166005_Operator Response to Notice and Request for Hearing_10052016.pdf: https://primis.phmsa.dot.gov/enforcement-documents/520166005/520166005_Operator%20Response%20to%20Notice%20and%20Request%20for%20Hearing_10052016.pdf

520166005_Final Order_06012018_text.pdf

June 1, 2018
Mr. Thomas A. Martin
President, Natural Gas Pipelines Group
Kinder Morgan, Inc.
1001 Louisiana Street, Suite 1000
Houston, TX 77002
Re: CPF No. 5-2016-6005
Dear Mr. Martin:
Enclosed please find the Final Order issued in the above-referenced case. It makes findings of
violation and assesses a reduced civil penalty of $154,800 against Colorado Interstate Gas
Company, LLC, a subsidiary of Kinder Morgan, Inc. The penalty payment terms are set forth in
the Final Order. This enforcement action closes automatically upon receipt of payment. Service
of the Final Order by certified mail is effective upon the date of mailing as provided under
49 C.F.R. § 190.5.
Thank you for your cooperation in this matter.
Sincerely,
Alan K. Mayberry
Associate Administrator
for Pipeline Safety
Enclosure
cc: Director, Western Region, Office of Pipeline Safety, PHMSA
Mr. Mark A. Kissel, Principal Executive Officer and President, Colorado Interstate
Gas Company, LLC
Ms. Jessica Toll, Esq., Assistant General Counsel, Kinder Morgan, 370 Van Gordon
Street, Lakewood, CO 80228
Ms. Catherine D. Little, Esq., Hunton & Williams, Bank of America Plaza, Suite 5200,
600 Peachtree Street, N.E., Atlanta, GA 30308
CERTIFIED MAIL - RETURN RECEIPT REQUESTED



U.S. DEPARTMENT OF TRANSPORTATION
PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION
OFFICE OF PIPELINE SAFETY
WASHINGTON, D.C. 20590
_________________________________________
In the Matter of )
Colorado Interstate Gas Company, LLC, ) CPF No. 5-2016-6005
a subsidiary of Kinder Morgan, Inc., )
)
)
)
Respondent. )
_________________________________________ )
FINAL ORDER
From August 10 through August 14, 2015, pursuant to 49 U.S.C. § 60117, a representative of the
Pipeline and Hazardous Materials Safety Administration (PHMSA), Office of Pipeline Safety
(OPS), conducted an on-site pipeline safety inspection of the facilities and records of Colorado
Interstate Gas Company, LLC (CIG or Respondent), in Sinclair, Wyoming. CIG is a system of
approximately 6,185 miles of natural gas pipelines and 10 miles of hazardous liquid pipelines.1
It transports products from production areas in the U.S. Rocky Mountains and the Anadarko
Basin to Colorado and Wyoming and indirectly to the Midwest, Southwest, California, and
Pacific Northwest and is owned and operated by Kinder Morgan, Inc.2
As a result of the inspection, the Director, Western Region, OPS (Director), issued to
Respondent, by letter dated August 26, 2016, a Notice of Probable Violation and Proposed Civil
Penalty (Notice). In accordance with 49 C.F.R. § 190.207, the Notice proposed finding that CIG
committed five violations of 49 C.F.R. Part 195 and proposed assessing a civil penalty of
$198,000 for the alleged violations.
CIG responded to the Notice by letter dated October 5, 2016 (Response), as supplemented by a
submission dated March 13, 2017. CIG did not contest the alleged violations, but disagreed with
the amount of the proposed civil penalty in the Notice and requested a hearing. A hearing was
subsequently held on March 22, 2017 in Lakewood, Colorado, with an attorney from the Office
of Chief Counsel, PHMSA, presiding. At the hearing, Respondent was represented by counsel.
After the hearing, Respondent provided a post-hearing submission by letter dated April 21, 2017
(Closing).
1 Pipeline Safety Violation Report (Violation Report), (Aug. 25, 2016) (on file with PHMSA), at 1.
2 https://www.kindermorgan.com/pages/business/gas_pipelines/west/CIG/default.aspx (last accessed Jan. 11, 2018).



CPF No. 5-2016-6005
Page 2
FINDINGS OF VIOLATION
Item 1: The Notice alleged that Respondent violated 49 C.F.R. § 195.452(h)(4), which states, in
relevant part:
§ 195.452 Pipeline integrity management in high consequence areas.
(a) …
(h) What actions must an operator take to address integrity issues?
(1) …
(4) Special requirements for scheduling remediation
(i) …
(ii) 60-day conditions. Except for conditions listed in paragraph (h)(4)(i)
of this section, an operator must schedule evaluation and remediation of the
following conditions within 60 days of discovery of condition.
(A) A dent located on the top of the pipeline (above the 4 and 8 o'clock
positions) with a depth greater than 3% of the pipeline diameter (greater
than 0.250 inches in depth for a pipeline diameter less than Nominal Pipe
Size (NPS) 12).
The Notice alleged that Respondent violated 49 C.F.R. § 195.452(h)(4) by failing to schedule
evaluation and remediation of an anomalous condition within 60 days of its discovery following
an integrity assessment. Specifically, the Notice alleged that CIG failed to classify a dent
discovered on January 16, 2013, on the top of Line 188-A located above the 4 and 8 o’clock
positions with a depth greater than three percent of the pipeline diameter (Line 188-A dent) as
mandating the 60-day requirement for scheduling remediation. In its Response and at the
hearing, CIG did not contest the allegation. Accordingly, after considering all of the evidence, I
find that Respondent violated 49 C.F.R. § 195.452(h)(4) by failing to classify a dent on the top of
the pipeline located above the 4 and 8 o’clock positions with a depth greater than three percent of
the pipeline diameter as mandating the 60-day requirement for scheduling remediation.
Item 2: The Notice alleged that Respondent violated 49 C.F.R. § 195.452(h)(3), which states:
§ 195.452 Pipeline integrity management in high consequence areas.
(a)…
(h) What actions must an operator take to address integrity issues?
(1)…
(3) Schedule for evaluation and remediation. An operator must complete
remediation of a condition according to a schedule prioritizing the
conditions for evaluation and remediation. If an operator cannot meet the
schedule for any condition, the operator must explain the reasons why it
cannot meet the schedule and how the changed schedule will not jeopardize
public safety or environmental protection.
The Notice alleged that Respondent violated 49 C.F.R. § 195.452(h)(3) by failing to complete
remediation of an anomalous condition according to a schedule prioritizing the conditions for
evaluation and remediation or alternatively explaining the reasons why it could not meet the



CPF No. 5-2016-6005
Page 3
schedule and how a changed schedule would not jeopardize public safety or environmental
protection. Specifically, the Notice alleged that CIG did not complete the remediation of the
Line 188-A dent until May 1, 2014, which was over 60 days following discovery, nor did it
explain the reasons why it could not meet the schedule and how the changed schedule would not
jeopardize public safety or environmental protection. In its Response and at the hearing, CIG did
not contest the allegation. Accordingly, after considering all of the evidence, I find that
Respondent violated 49 C.F.R. § 195.452(h)(3) by failing to complete remediation of a condition
according to a schedule prioritizing the conditions for evaluation and remediation or alternatively
explaining the reasons why it could not meet the schedule and how a changed schedule would
not jeopardize public safety or environmental protection.
Item 3: The Notice alleged that Respondent violated 49 C.F.R. § 195.452(h)(1), which states, in
relevant part:
§ 195.452 Pipeline integrity management in high consequence areas.
(a)…
(h) What actions must an operator take to address integrity issues?
(1) General requirements. An operator must take prompt action to
address all anomalous conditions the operator discovers through the
integrity assessment or information analysis. In addressing all conditions,
an operator must evaluate all anomalous conditions and remediate those that
could reduce a pipeline's integrity. An operator must be able to demonstrate
that the remediation of the condition will ensure the condition is unlikely to
pose a threat to the long-term integrity of the pipeline. An operator must
comply with §195.422 when making a repair.
(i) Temporary pressure reduction. An operator must notify PHMSA, in
accordance with paragraph (m) of this section, if the operator cannot meet
the schedule for evaluation and remediation required under paragraph (h)(3)
of this section and cannot provide safety through a temporary reduction in
operating pressure.
The Notice alleged that Respondent violated 49 C.F.R. § 195.452(h)(1) by failing to notify
PHMSA about the lack of prompt action when the scheduled period for evaluation and
remediation of an anomalous condition that could reduce a pipeline's integrity was not met.
Specifically, the Notice alleged that CIG did not notify PHMSA when the scheduled period for
evaluation and remediation of the Line 188-A dent was not met and safety was not provided
through a temporary reduction in operating pressure. In its Response and at the hearing, CIG did
not contest the allegation. Accordingly, after considering all of the evidence, I find that
Respondent violated 49 C.F.R. § 195.452(h)(1) by failing to notify PHMSA about the lack of
prompt action when the scheduled period for evaluation and remediation of an anomalous
condition that could reduce a pipeline's integrity was not met.
Item 4: The Notice alleged that Respondent violated 49 C.F.R. § 195.420(b), which states:
§ 195.420 Valve maintenance.
(a)…



CPF No. 5-2016-6005
Page 4
(b) Each operator shall, at intervals not exceeding 71∕2 months, but at
least twice each calendar year, inspect each mainline valve to determine that
it is functioning properly.
The Notice alleged that Respondent violated 49 C.F.R. § 195.420(b) by failing to inspect each
mainline valve at intervals not exceeding 7 ½ months, but at least twice each calendar year.
Specifically, the Notice alleged that the valve inspections for three CIG pipelines having two
mainline valves each were conducted annually rather than twice each year between 2012 and
2014. In its Response and at the hearing, CIG did not contest the allegation.
Accordingly, after considering all of the evidence, I find that Respondent violated 49 C.F.R.
§ 195.420(b) by failing to inspect each mainline valve at intervals not exceeding 7½ months, but
at least twice each calendar year.
Item 5: The Notice alleged that Respondent violated 49 C.F.R. § 195.428(a), which states:
§ 195.428 Overpressure safety devices and overfill protection systems.
(a) Except as provided in paragraph (b) of this section, each operator
shall, at intervals not exceeding 15 months, but at least once each calendar
year, or in the case of pipelines used to carry highly volatile liquids, at
intervals not to exceed 7½ months, but at least twice each calendar year,
inspect and test each pressure limiting device, relief valve, pressure
regulator, or other item of pressure control equipment to determine that it is
functioning properly, is in good mechanical condition, and is adequate from
the standpoint of capacity and reliability of operation for the service in
which it is used.
The Notice alleged that Respondent violated 49 C.F.R. § 195.428(a) by failing to inspect and test
each pressure relief valve to ensure adequate capacity, reliability, good condition, and proper
functioning at intervals not exceeding 15 months, but at least once each calendar year.
Specifically, the Notice alleged that pressure relief valve PCV-93 was not inspected in 2013 and
2014 and that pressure relief valves PSV-114 and 115 were not inspected in 2013. In its
Response and at the hearing, CIG did not contest the allegation.
Accordingly, after considering all of the evidence, I find that Respondent violated 49 C.F.R.
§ 195.428(a) by failing to inspect and test each pressure relief valve to ensure adequate capacity,
reliability, good condition, and proper functioning at intervals not exceeding 15 months, but at
least once each calendar year.
These findings of violation will be considered prior offenses in any subsequent enforcement
action taken against Respondent.
ASSESSMENT OF PENALTY
Under 49 U.S.C. § 60122, Respondent is subject to an administrative civil penalty not to exceed



CPF No. 5-2016-6005
Page 5
$200,000 per violation for each day of the violation, up to a maximum of $2,000,000 for any
related series of violations.3 In determining the amount of a civil penalty under 49 U.S.C.
§ 60122 and 49 C.F.R. § 190.225, I must consider the following criteria: the nature,
circumstances, and gravity of the violation, including adverse impact on the environment; the
degree of Respondent’s culpability; the history of Respondent’s prior offenses; and any effect
that the penalty may have on its ability to continue doing business; and the good faith of
Respondent in attempting to comply with the pipeline safety regulations. In addition, I may
consider the economic benefit gained from the violation without any reduction because of
subsequent damages, and such other matters as justice may require. The Notice proposed a total
civil penalty of $198,000 for the five violations cited above.
Item 1: The Notice proposed a civil penalty of $43,200 for Respondent’s violation of 49 C.F.R.
§ 195.452(h)(4), for failing to classify a dent on the top of the pipeline located above the 4 and 8
o’clock positions with a depth greater than three percent of the pipeline diameter as mandating
special requirements for scheduling remediation.
In its Response and at the hearing, CIG contended that the proposed penalties in the Notice were
duplicative, excessive, and failed to account for and appropriately apply the penalty
consideration factors.4 Respondent pointed to the fact that Items 1, 2, and 3 involved the same
failure to address the dent anomaly identified on Line 188-A on November 13, 2002, and argued
that the Notice effectively alleged the same violation three separate times.5 CIG submits that the
proposed penalties for Items 2 and 3 should be withdrawn because they are duplicative of Item
1.6 Respondent also argued for a reduction in the Item 1 penalty amount.
For its part, OPS disagreed that Items 1, 2, and 3 were duplicative and argued that they relied on
different evidence. Specifically, OPS argued that the regulation cited in Item 1 was intended to
ensure repairs would be properly prioritized in developing the schedule and cited the absence of
the schedule. OPS argued that the regulation cited in Item 2 focused on performing the repair
and noted that it was possible to schedule repairs but not complete them and vice versa. OPS
also explained that Item 3 focused on the reporting requirement which involved yet a different
act or omission.
Having considered the arguments of both parties, I find that OPS was able to establish that Items
1, 2, and 3 are separate violations because the evidence for each does not entirely overlap with
any other. I also find, however, that Respondent raised a compelling fairness concern in arguing
that the proposed civil penalties for these items overlapped insofar as Items 1 and 2 are
concerned. The particular regulatory language cited in the Item 2 violation involving failure to
complete remediation “according to a schedule…” in effect re-codified the matter of scheduling
3 These amounts are adjusted annually for inflation. See, e.g., Pipeline Safety: Inflation Adjustment of Maximum
Civil Penalties, 82 Fed. Reg. 19325 (April 27, 2017).
4 Pre-Hearing Submittal at 4.
5 Id. at 5.
6 Post-Hearing Submittal at 3.



CPF No. 5-2016-6005
Page 6
into the repair requirement making an additional citation to the scheduling regulation in Item 1
generally unnecessary in cases where an operator failed to schedule and repair. The manner in
which these particular regulations were drafted, whether inadvertently or not, included both
scheduling and repair in the regulation cited in Item 2, making it partially overlap with the
requirement for a schedule in the regulation cited in Item 1.
Two Notice items can be upheld as separate violations because they do not overlap entirely in
terms of evidence. With respect to imposing penalties, however, to the extent that at least some
of the conduct required (or prohibited) by two given regulations overlaps, fairness can compel
the merging of the proposed penalty for the narrower violation with that of the broader violation
under the “other matters as justice may require” factor. In this instance, CIG had no way of
knowing which fraction of the proposed penalty for the broader Item 2 violation (i.e., schedule
and complete a repair) was for the conduct that went beyond the conduct prohibited by the
narrower Item 1 violation (i.e., a schedule only). The agency’s enforcement goals are not
furthered by the aggregation of penalties under the code sections cited in the Notice in this
particular case. Based upon the foregoing, I withdraw the proposed penalty amount for violation
of 49 C.F.R. § 195.452(h)(4). The penalty for failing to schedule and complete the repair will be
assessed below in Item 2.
Item 2: The Notice proposed a civil penalty of $43,200 for Respondent’s violation of 49 C.F.R.
§ 195.452(h)(3), for failing to complete remediation of a condition according to a schedule
prioritizing the conditions for evaluation and remediation or alternatively explaining the reasons
why it could not meet the schedule and how a changed schedule would not jeopardize public
safety or environmental protection. In its Response and at the hearing, Respondent argued that
the proposed penalties for Items 1, 2, and 3 were duplicative and involved the same failure to
address the dent anomaly identified on Line 188-A. As discussed above, the penalty proposed
for Item 1 has been withdrawn based on the “other matters as justice may require” factor and I
will now apply the penalty factors to this item.
With respect to the nature and circumstances of CIG’s violation of § 195.452(h)(3), an effective
integrity management program is a key part of sound pipeline operations. With respect to the
gravity of the offense, the failure to take prompt remedial action following the discovery of a
dent with metal loss continued for over one year, well beyond the 60-day regulatory deadline and
represents a significant compromise to the safe operation of the pipeline. Although the length of
pipe affected was not extensive when compared with the overall size of the system, it transported
highly volatile liquids which are among the highest risk products transported by pipeline if an
accidental release should occur. With respect to culpability, CIG explained that the violation
was the result of maintenance intervals for gas pipelines under Part 192 inadvertently being used
for this hazardous liquid system.7 OPS countered that even if CIG believed it was operating
under Part 192, the discovery of the dent with metal loss should have triggered prompt remedial
action such as a reduction in operating pressure which did not occur. CIG also noted that the
non-compliance was corrected by the operator prior to the OPS inspection, however a credit for
this was already reflected in the proposed civil penalty amount. In addition, the record supports
the proposed treatment of the factors for prior offenses and good faith. Respondent has
7 Id. at 2.



CPF No. 5-2016-6005
Page 7
presented no information or arguments that would warrant a reduction in the amount of the civil
penalty proposed in the Notice for this violation. Accordingly, having reviewed the record and
considered the assessment criteria, I assess Respondent a civil penalty of $43,200 for violation of
49 C.F.R. § 195.452(h)(3).
Item 3: The Notice proposed a civil penalty of $43,200 for Respondent’s violation of 49 C.F.R.
§ 195.452(h)(1), for failing to notify PHMSA about the lack of prompt action when the
scheduled period for evaluation and remediation of an anomalous condition that could reduce a
pipeline's integrity was not met. In its Response and at the hearing, Respondent argued that the
proposed penalties for Items 1, 2, and 3 were duplicative and involved the same failure to
address the dent anomaly identified on Line 188-A. As discussed above, the penalty proposed
for Item 1 has been withdrawn based on the “other matters as justice may require” factor.
Respondent’s argument that Item 3 was duplicative with another penalized item was
unpersuasive. Respondent’s obligation to notify PHMSA concerning the lack of prompt action
did not arise until after the 60-day period following discovery of the condition and therefore
constituted a distinct act or omission that did not involve any overlapping conduct with Item 2.
With respect to the nature and circumstances of CIG’s violation of § 195.452(h)(1), an effective
integrity management program is a key part of sound pipeline operations. With respect to the
gravity of the offense, failure to comply with the notification requirement in the absence of
prompt remedial action following the discovery of a dent with metal loss impedes other steps
from being taken to protect the public where necessary which represents a significant
compromise to safe operation of the pipeline. With respect to culpability, CIG explained that the
violation was the result of maintenance intervals for gas pipelines under Part 192 inadvertently
being used for this hazardous liquid system. OPS countered that even if CIG believed it was
operating under Part 192, the discovery of the dent with metal loss should have triggered prompt
remedial action such as a reduction in operating pressure which did not occur. CIG also noted
that the non-compliance was corrected by the operator prior to the OPS inspection, however a
credit for this was already reflected in the proposed civil penalty amount. In addition, the record
supports the proposed treatment of the factors for prior offenses and good faith. Respondent has
presented no information or arguments that would warrant a reduction in the amount of the civil
penalty proposed in the Notice for this violation. Accordingly, having reviewed the record and
considered the assessment criteria, I assess Respondent a civil penalty of $43,200 for violation of
49 C.F.R. § 195.452(h)(1).
Item 4: The Notice proposed a civil penalty of $34,200 for Respondent’s violation of 49 C.F.R.
§ 195.420(b), for failing to inspect each mainline valve at intervals not exceeding 7 ½ months,
but at least twice each calendar year. With respect to the nature and circumstances of CIG’s
violation of § 195.420(b), the timely inspection of mainline valves is a basic code requirement.
With respect to the gravity of the offense, ensuring the proper functioning of mainline valves is a
key part of safety because the failure of such a valve to fully close when needed could
compromise safety. With respect to culpability, CIG explained that the violation was the result
of maintenance intervals for gas pipelines under Part 192 inadvertently being used for this
hazardous liquid system. OPS countered that even if CIG believed it was operating under Part
192, the discovery of the dent with metal loss should have triggered prompt remedial action such
as a reduction in operating pressure which did not occur. CIG also noted that the non-



CPF No. 5-2016-6005
Page 8
compliance was corrected by the operator prior to the OPS inspection, however a credit for this
was already reflected in the proposed civil penalty amount. In addition, the record supports the
proposed treatment of the factors for prior offenses and good faith. Respondent has presented no
information or arguments that would warrant a reduction in the amount of the civil penalty
proposed in the Notice for this violation. Accordingly, having reviewed the record and
considered the assessment criteria, I assess Respondent a civil penalty of $34,200 for violation of
49 C.F.R. § 195.420(b).
Item 5: The Notice proposed a civil penalty of $34,200 for Respondent’s violation of 49 C.F.R.
§ 195.428(a), for failing to inspect and test each pressure relief valve to ensure adequate
capacity, reliability, good condition, and proper functioning at intervals not exceeding 15
months, but at least once each calendar year. With respect to the nature and circumstances of
CIG’s violation of § 195.428(a), inspecting pressure relief devices is a basic code requirement.
With respect to the gravity of the offense, ensuring the proper functioning of these devices is a
key part of safety because the failure of a pressure relief valve can compromise safety in the
event of a pressure surge or other abnormal event. With respect to culpability, CIG explained
that the violation was the result of maintenance intervals for gas pipelines under Part 192
inadvertently being used for this hazardous liquid system. OPS countered that even if CIG
believed it was operating under Part 192, the discovery of the dent with metal loss should have
triggered prompt remedial action such as a reduction in operating pressure which did not occur.
CIG also noted that the non-compliance was corrected by the operator prior to the OPS
inspection, however a credit for this was already reflected in the proposed civil penalty amount.
In addition, the record supports the proposed treatment of the factors for prior offenses and good
faith. Respondent has presented no information or arguments that would warrant a reduction in
the amount of the civil penalty proposed in the Notice for this violation. Accordingly, having
reviewed the record and considered the assessment criteria, I assess Respondent a civil penalty of
$34,200 for violation of 49 C.F.R. § 195.428(a).
In summary, having reviewed the record and considered the assessment criteria for each of the
Items cited above, I assess Respondent a total civil penalty of $154,800.
Payment of the civil penalty must be made within 20 days of service. Federal regulations
(49 C.F.R. § 89.21(b)(3)) require such payment to be made by wire transfer through the Federal
Reserve Communications System (Fedwire), to the account of the U.S. Treasury. Detailed
instructions are contained in the enclosure. Questions concerning wire transfers should be
directed to: Financial Operations Division (AMK-325), Federal Aviation Administration, Mike
Monroney Aeronautical Center, 6500 S MacArthur Blvd, Oklahoma City, Oklahoma 79169.
The Financial Operations Division telephone number is (405) 954-8845.
Failure to pay the $154,800 civil penalty will result in accrual of interest at the current annual
rate in accordance with 31 U.S.C. § 3717, 31 C.F.R. § 901.9 and 49 C.F.R. § 89.23. Pursuant to
those same authorities, a late penalty charge of six percent (6%) per annum will be charged if
payment is not made within 110 days of service. Furthermore, failure to pay the civil penalty
may result in referral of the matter to the Attorney General for appropriate action in a district
court of the United States.



CPF No. 5-2016-6005
Page 9
Under 49 C.F.R. § 190.243, Respondent may submit a Petition for Reconsideration of this Final
Order to the Associate Administrator, Office of Pipeline Safety, PHMSA, 1200 New Jersey
Avenue, SE, East Building, 2nd Floor, Washington, DC 20590, with a copy sent to the Office of
Chief Counsel, PHMSA, at the same address, no later than 20 days after receipt of service of the
Final Order by Respondent. Any petition submitted must contain a brief statement of the issue(s)
and meet all other requirements of 49 C.F.R. § 190.243. The filing of a petition automatically
stays the payment of any civil penalty assessed. The other terms of the order, including any
corrective action, remain in effect unless the Associate Administrator, upon request, grants a
stay. If Respondent submits payment of the civil penalty, the Final Order becomes the final
administrative decision and the right to petition for reconsideration is waived.
The terms and conditions of this Final Order are effective upon service in accordance with
49 C.F.R. § 190.5.
June 1, 2018
___________________________________ __________________________
Alan K. Mayberry Date Issued
Associate Administrator
for Pipeline Safety

## Provenance

- Official: Yes
- Source: <https://primis.phmsa.dot.gov/enforcement-data/case/520166005>
- Source ID: `phmsa-enforcement`
- SHA-256: `d52fb47238ebce9e1aaaff1aaefa6aef1e73831adf10e27fad359aa17360ff03`
- Retrieved: 2026-08-20T04:44:44.458Z
- Exported: 2026-08-22T04:03:50.947Z
- Document slug: `phmsa-enforcement-520166005`

### Source metadata

```json
{
  "cpf": "520166005",
  "operator": "COLORADO INTERSTATE GAS CO",
  "region": "Western",
  "pipelineType": "INTRASTATE LIQUID ONSHORE",
  "caseStatus": "CLOSED",
  "citedSections": [
    "195.420(b)",
    "195.428(a)",
    "195.452(h)(1)",
    "195.452(h)(3)",
    "195.452(h)(4)(ii)(a)"
  ],
  "dataAsOf": "08/04/2026 12PM",
  "caseDataAsOf": "2026-08-04",
  "attachmentCount": 5,
  "attachments": [
    {
      "name": "520166005_Final Order_06012018.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/520166005/520166005_Final%20Order_06012018.pdf",
      "bytes": 2838948,
      "category": "agency_document"
    },
    {
      "name": "520166005_Final Order_06012018_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/520166005/520166005_Final%20Order_06012018_text.pdf",
      "bytes": 136311,
      "category": "agency_document"
    },
    {
      "name": "520166005_NOPV PCP_08262016.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/520166005/520166005_NOPV%20PCP_08262016.pdf",
      "bytes": 250820,
      "category": "case_document"
    },
    {
      "name": "520166005_NOPV PCP_08262016_text.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/520166005/520166005_NOPV%20PCP_08262016_text.pdf",
      "bytes": 102378,
      "category": "case_document"
    },
    {
      "name": "520166005_Operator Response to Notice and Request for Hearing_10052016.pdf",
      "url": "https://primis.phmsa.dot.gov/enforcement-documents/520166005/520166005_Operator%20Response%20to%20Notice%20and%20Request%20for%20Hearing_10052016.pdf",
      "bytes": 111284,
      "category": "party_submission"
    }
  ],