# GULF SOUTH PIPELINE COMPANY, LP — Gas transmission and gathering — incident on 2015-03-15

**Citation:** PHMSA Report 20150045  
**Type / status:** incident / historical  
**Agency:** Pipeline and Hazardous Materials Safety Administration  
**Effective:** 2015-03-15  
**Published:** 2015-04-02

Gas transmission and gathering incident in DEQUINCY, CALCASIEU County, LA. Reported cause: CORROSION FAILURE. Reported consequences: 0 fatalities, 0 injuries, 10 NATURAL GAS released, $197,208 reported property damage. Operator-reported incident data submitted to PHMSA, generally within 30 days. Records may be supplemented or corrected and do not represent final agency causal findings. PHMSA trend classification: significant incident, not serious.

## Document text

Gas transmission and gathering incident in DEQUINCY, CALCASIEU County, LA. Reported cause: CORROSION FAILURE. Reported consequences: 0 fatalities, 0 injuries, 10 NATURAL GAS released, $197,208 reported property damage. Operator-reported incident data submitted to PHMSA, generally within 30 days. Records may be supplemented or corrected and do not represent final agency causal findings.

Report number: 20150045.

Operator ID: 31728.

Reported incident date: 3/15/2015 16:10.

Location detail: 40.3

Cause detail: EXTERNAL CORROSION

Cause detail: LEAK DISCOVERED ON PIPELINE THAT IS 7 FEET UNDER WATER IN A CREEK WITH A MUD LINE AT 11 FEET. PRESSURE WAS LOWERED FROM 375 PSIG TO 300 PSIG. INITIAL INDICATIONS ARE THAT THIS IS A FITTING LEAK. WHEN WATER RECEDES, REMEDIATION WILL OCCUR. UNTIL THAT TIME, THIS SECTION OF LINE REMAINS ISOLATED AND PRESSURE LOWERED. 2-12-16 LEAK IS LOCATED IN A DEEP CREEK IN A NARROW RIGHT OF WAY. FOR THIS REASON, REPAIR IS SCHEDULED FOR JULY/AUGUST 2016 TIME FRAME WHEN WATER LEVELS WILL BE LOWER AND PERMITTING CAN BE OBTAINED. 3-30-17 GULF SOUTH EXPECTS TO REPAIR IN LATE APRIL 2017. 5-18-17 GULF SOUTH CUT AND CAPPED THE LINE. THE FINAL REPORT IS BEING SUBMITTED NOW (9-26-17) BECAUSE OF THE AMOUNT OF TIME REQUIRED TO BE ABLE TO CORRECTLY DOCUMENT THE REPAIR COSTS. 10-16-17 REVISED APPARENT CAUSE TO EXTERNAL CORROSION BASED ON ADDITIONAL INFORMATION RECEIVED AND ANSWERED ADDITIONAL QUESTIONS THAT RESULTED FROM THAT CHANGE.

PHMSA trend classification: significant incident, not serious.

PHMSA standardized cause: CORROSION — EXTERNAL.

PHMSA indexed costs: $198,533 reported total cost, $99,991.066 in 1984 dollars, $245,188.111 in current-year dollars.

PHMSA trend flags, standardized causes, and indexed costs are analytical fields added to operator-reported incident data. They do not represent final agency causal findings.

## Provenance

- Official: Yes
- Source: <https://data.transportation.gov/api/views/27nc-rsge/files/2b05c2d8-d14a-4c56-ac1c-7d23a4bc31c8?download=true&filename=Gas%20Transmission%20%26%20Gathering%20Incident%20Data%20-%20January%202010%20to%20present.zip>
- Source ID: `phmsa-pipeline-incidents`
- SHA-256: `f8982679ecfa2f63c1a8fc50d54f503b5eef7342304cf090c877ab8e71319af2`
- Retrieved: 2026-08-20T03:30:32.010Z
- Exported: 2026-08-25T10:20:10.186Z
- Document slug: `phmsa-incident-5bd41aad19995a44b72a87f0`

### Source metadata

```json
{
  "recordKind": "pipeline_incident",
  "datasetType": "gas_transmission_gathering",
  "datasetLabel": "Gas transmission and gathering",
  "datasetPeriod": "January 2010 to present",
  "report": {
    "number": "20150045",
    "supplementalNumber": "17470",
    "type": "SUPPLEMENTAL FINAL",
    "receivedDate": "2015-04-02",
    "receivedDateRaw": "4/2/2015"
  },
  "operator": {
    "id": "31728",
    "name": "GULF SOUTH PIPELINE COMPANY, LP"
  },
  "incident": {
    "date": "2015-03-15",
    "dateRaw": "3/15/2015 16:10"
  },
  "location": {
    "city": "DEQUINCY",
    "county": "CALCASIEU",
    "state": "LA",
    "postalCode": "70633",
    "latitude": 30.3964,
    "longitude": -93.2926,
    "type": "PIPELINE RIGHT-OF-WAY",
    "details": {
      "DESIGNATED_NAME": "40.3"
    },
    "facilityName": "CALL JUNCTION TO IOWA COMPRESSOR STATION"
  },
  "cause": {
    "category": "CORROSION FAILURE",
    "details": {
      "CAUSE_DETAILS": "EXTERNAL CORROSION",
      "NARRATIVE": "LEAK DISCOVERED ON PIPELINE THAT IS 7 FEET UNDER WATER IN A CREEK WITH A MUD LINE AT 11 FEET. PRESSURE WAS LOWERED FROM 375 PSIG TO 300 PSIG. INITIAL INDICATIONS ARE THAT THIS IS A FITTING LEAK. WHEN WATER RECEDES, REMEDIATION WILL OCCUR. UNTIL THAT TIME, THIS SECTION OF LINE REMAINS ISOLATED AND PRESSURE LOWERED. 2-12-16 LEAK IS LOCATED IN A DEEP CREEK IN A NARROW RIGHT OF WAY. FOR THIS REASON, REPAIR IS SCHEDULED FOR JULY/AUGUST 2016 TIME FRAME WHEN WATER LEVELS WILL BE LOWER AND PERMITTING CAN BE OBTAINED. 3-30-17 GULF SOUTH EXPECTS TO REPAIR IN LATE APRIL 2017. 5-18-17 GULF SOUTH CUT AND CAPPED THE LINE. THE FINAL REPORT IS BEING SUBMITTED NOW (9-26-17) BECAUSE OF THE AMOUNT OF TIME REQUIRED TO BE ABLE TO CORRECTLY DOCUMENT THE REPAIR COSTS. 10-16-17 REVISED APPARENT CAUSE TO EXTERNAL CORROSION BASED ON ADDITIONAL INFORMATION RECEIVED AND ANSWERED ADDITIONAL QUESTIONS THAT RESULTED FROM THAT CHANGE."
    }
  },
  "consequences": {
    "fatalities": 0,
    "injuries": 0,
    "commodity": "NATURAL GAS",
    "release": "10",
    "propertyDamage": 197208,
    "estimatedOperatorCost": 0,
    "estimatedEmergencyCost": 400,
    "estimatedEnvironmentalCost": null,
    "ignition": "NO",
    "explosion": "NO",
    "evacuated": 0,
    "raw": {
      "FATAL": "0",
      "INJURE": "0",
      "UNINTENTIONAL_RELEASE": "10",
      "EST_COST_PROP_DAMAGE": "197208",
      "PRPTY": "198533"
    }
  },
  "provenance": {
    "viewId": "27nc-rsge",
    "viewUrl": "https://data.transportation.gov/api/views/27nc-rsge",
    "assetId": "2b05c2d8-d14a-4c56-ac1c-7d23a4bc31c8",
    "archiveFilename": "Gas Transmission & Gathering Incident Data - January 2010 to present.zip",
    "archiveSha256": "fe0b136ca4b00ac987a8bc2e195098accf910d97512c5fc3b59e62d9da5f674e",
    "memberPath": "incident_gas_transmission_gathering_jan2010_present.txt",
    "memberSha256": "b435f2a25718cf54c54e00294e6788c4f9c6860e02fb86355e75d294c243c4dd",
    "rowNumber": 1348,
    "rowSha256": "bda0fab34319bd7fcd32987f70db4173238b2fb21bbe7407a9c45dd740b60ee4"
  },
  "caveat": "Operator-reported incident data submitted to PHMSA, generally within 30 days. Records may be supplemented or corrected and do not represent final agency causal findings.",
  "operatorReported": true,
  "finalAgencyFinding": false,
  "flaggedAnalysis": {
    "dataAsOf": "2026-07-31",
    "flags": {
      "fireFirst": null,
      "significant": true,
      "serious": false
    },
    "standardizedCause": {
      "sevenCategory": "CORROSION",
      "sevenSubcategory": "EXTERNAL",
      "eightCategory": "CORROSION",
      "eightSubcategory": "EXTERNAL"
    },
    "costs": {
      "reported": 198533,
      "in1984Dollars": 99991.06582943066,
      "currentYearDollars": 245188.11061438
    },
    "caveat": "PHMSA trend flags, standardized causes, and indexed costs are analytical fields added to operator-reported incident data. They do not represent final agency causal findings.",
    "provenance": {
      "sourceUrl": "https://www.phmsa.dot.gov/sites/phmsa.dot.gov/files/data_statistics/pipeline/PHMSA_Pipeline_Safety_Flagged_Incidents.zip",
      "landingPageUrl": "https://www.phmsa.dot.gov/data-and-statistics/pipeline/pipeline-incident-flagged-files",
      "catalogUrl": "https://data.transportation.gov/Pipelines-and-Hazmat/Pipeline-Incident-Flagged-Files/qdme-9bbm",
      "retrievalMode": "official_live",
      "archivedAt": null,
      "archiveSha256": "317e6a3e16d60b9b677efe391dc40258b5dd7ead83fb8bea74cb553cedfbbdec",
      "workbook": "gtggungs2010toPresent.xlsx",
      "sheet": "gtggungs2010toPresent",
      "rowNumber": 644,
      "rowSha256": "3f703e57d60c3c9b73573b1823d9b07809d57d48dd7099437a14a50563b2ae91"
    }
  },
  "jurisdiction": "US",
  "operatorName": "GULF SOUTH PIPELINE COMPANY, LP"
}
```