# State of Colorado Public Utilities Commission — Pipeline Safety Interpretation

**Citation:** PI-09-0006  
**Type / status:** guidance / guidance  
**Agency:** Pipeline and Hazardous Materials Safety Administration  
**Effective:** Not stated  
**Published:** 2009-02-20

PI-09-0006 response to State of Colorado Public Utilities Commission concerning 192.8.

## Document text

<<<PAGE 1>>>

U.S. Department
of Transportation
Pipeline and Hazardous
Materials Safety
Administration
1200 New Jersey Ave. S E
Washington. DC 20590
FEB 2 0 2009
Mr. Stephan Pott, PE
Chief, Gas Pipeline Safety
State of Colorado Public Utilities Commission
1560 Broadway, Suite 250
Denver, CO 80202
Ref. No.: PI-08-0010
Dear Mr. Pott:
The Pipeline and Hazardous Materials Safety Administration (PHMSA) reviewed your
December 11, 2008, letter transmitting an October 22, 2008, petition received by the Colorado
Public Utilities Commission (CO-PUC) from DCP Midstream for a finding that the endpoint of
the gathering designation for an intrastate gas pipeline should be extended beyond a gas
processing plant. Specifically, DCP Midstream requested a finding that the gathering
designation for a rural section of the ANGI intrastate pipeline be extended an additional 7.8
miles from the DCP Midstream Greeley Plant to the DCP Midstream Mewboum Gas Plant, both
of which are located in Weld County, Colorado.
Per 49 CFR § 192.8 (a)(2) and Section 2.2 (a)(I)(A) of API RP 80, DCP Midstream included
documentation they feel demonstrates that extending the gathering designation an additional 7.8
miles from the Greely Plant to the Mewboum Plant was justified based on sound engineering
principles.
Additional correspondence with DCP Midstream determined the following:
• The Greeley Plant separates the methane out and sells it there; the liquids are placed in
tanks at the facility and eventually transported to the intended destination via truck.
• The remainder of the gas, including 90% ethane, 5% methane, and 2% C02 is then
transported to the Mewboum Plant for additional processing.
• The normal operating pressure ofthe line is apPJ:oximately 300 psig, down to
approximately 150 psig when delivered to the downstream plant
Based on the information provided in DCP Midstream's petition, the additional correspondence,
and your recommendation, PHMSA finds that extending the endpoint of the gathering
designation for the ANGI gas pipeline an additional 7.8 miles to the Mewbome Plant is
warranted as long as the current operating parameters and operating pressures remain the same.
Accordingly, to the extent this condition is met, PHMSA grants the petition. IfDCP Midstream

<<<PAGE 2>>>

Page 2
Mr. Stephan Pott, PE
State of Colorado Public Utilities Commission -- ANGI Intrastate Pipeline
Ref. No.: PI-08-0010
makes any significant changes to the operation of this line, such as increasing the pressure to
where the ethane might be in a liquid super critical phase, DCP Midstream will be required to
contact the CO-PUC and/or PHMSA's Western Region to make a new detennination.
Sincerely,
"--I Director, Office of Regulations

<<<PAGE 3>>>

PUBLIC UTiUTIES COMMISSION Department of Regulatory Agencies . -=
D. Rico Munn • . . ,
Ron Binz, Chairman Executive Director i ~~ .,.
James K. Tarpey, Commissioner • , •
Matt Baker, Commissioner
Doug Dean, Director
Bill Ritter, Jr.
Govemor
December 9,2008
Mr. Jeffrey D. Wiese
Associate Administrator for Pipeline Safety
U.S. Department of Transportation
Pipeline and Hazardous Materials Safety Administration, PHP-l
East Building, 2nd Floor
1200 New Jersey Ave., SE
Washington, DC 20590
DEC 1 12008
RE: Petition for Review-DCP Midstream
ANGI Pipeline
On October 22, 2008 DCP Midstream, a gathering and processing company operating in several
producing gas field in Colorado has, under § 190.9, petitioned the Public Utilities Commission
(PUC), for a review of extending the endpoint of gathering beyond a processing plant. This
request for review involves a rural 7.8 mile long pipeline system between the DCP Midstream
Greeley and the Mewbourn Gas Plants located in Weld County, Colorado.
Although § 190.9 was not adopted by the Public Utilities Commission, Pipeline Safety staff has
reviewed the petition from DCP Midstream (attached) under the alternative PUC rule 4904,4
Code of Colorado Regulations (CCR) 723-4 Rules Regulating Gas Utilities and Pipeline
Operators.
This review does not address applicability of §40-1-1 03, C.R.S. or whether it is a Henshaw
pipeline, and pertains only to pipeline safety regulations found under 4 Code of Colorado
Regulations (CCR) 723-4 Rules Regulating Gas Utilities and Pipeline Operators.
The endpoint of gathering, under § 192.8(a)(2) and API Recommended Practice (RP) 80, may
not extend beyond the first downstream natural gas processing plant, unless the operator can
demonstrate, using sound engineering principles, that gathering extends to a further downstream
plant.
This system was reviewed using guidelines found in API RP 80, a field review, and as required
under § 192.8(a)(2) an analysis by the DCP Midstream engineering Department.
1560 Broadway, Suite 250, Denver, Colorado 80202, 303-894-2000
www.dora.state.co.uslpuc Fax 303-894-2065
TTY Users 711 (Relay Colorado) Transportation Fax 303-894-2071
Permit and Insurance (Outside Denver) 1-800-888-0170 Consumer Affairs (Outside Denver) 1-800-456-0858
Consumer Affairs 303-894-2070

<<<PAGE 4>>>

Mr. Jeffrey D. Wiese
Page 2
December 9,2009
Under Rule 4904 the Chief of the PUC Gas Pipeline Safety section, has reviewed and agrees
with the following facts:
• DCP Midstream is aware of PUC rule 4952(c) as it applies to the ANGI pipeline.
• The ANGI pipeline is a 7.8 mile long rural (Class 1 as defined under § 192.5) gathering
line connecting the Greeley and Mcwbourn Gas Plants.
• The ANGI system's method of construction and materials used has been reviewed by the
DCP Midstream Director of Asset Integrity and maximum allowable operating pressure
determined in compliance with § 192.619.
• The request is consistent with the "gathering function" as described in RP-80 2.4.2.
• The dethanizer residue gas stream components from the Greeley Gas Plant to the
Mewboum Gas Plant is 98.68% ethane, propane, and carbon dioxide.
• The gross dry heating value of the dethanizer residue gas stream from the Greeley Gas
Plant at 14.65 psi a is 1764.3 BTU.
• The Mewbourn Gas Plant is not a production treatment facility but is designed to treat,
dehydrate, and process gas.
• The Mewbourn Gas Plant is a defined and recognized gathering endpoint.
• Raw, untreated gas from local producing natural gas wells flows directly into the ANGI
pipeline, commingled, and final treatment, dehydration, and processing take place at the
Mewbourn Plant. Final treated residue gas is sold to an intrastate and interstate pipeline.
• Pipeline markers are located and maintained at each public road and railroad crossing in
compliance with § 192.707(d) and PUC Rule 4952(c).
Based on these factors I recommend that the request to designate the 7.8 mile ANGI pipeline
system as a gathering pipeline as it applies to § 192.8(a)(2) be approved.
:Si;4Wtr
Stephan Port, PE
Chief, Gas Pipeline Safety
Cc: Mr. Chris Hoidal, Regional Director
PHMSA Western Region

<<<PAGE 5>>>

dc::p
Midstream",
October 22, 2008
VIA CERTIFIED MAIL
RETURN RECEIPT REQUESTED
Tracking Number 91 71082133393290942642
Steve Pott, Chief
Colorado Public Utilities Commission
1560 Broadway, Suite 250
Denver, CO 80202
ZDLt) CC1 23 Hi 3: 21
Re: Classifying Gathering Line under 192.8(a)(2)
DCP Midstream
Weld County Gathering System
Weld County, Colorado
Dear Mr. Pott:
DCP Midstream (DCP) is petitioning the Colorado Public Utilities Commission (PUC) for
a review for approval under § 190.9 for extending the endpoint of gathering beyond the
first processing plant as defined under § 192.8(a)(2).
The following information has been attached to this letter in order to support this petition:
1) Schematic illustrating 6" line between Greeley Plant and Mewbourn Plant
(Figure 1)
2) Gas Analysis of the ethane stream (showing CO2)
3) Analysis to identify regulated onshore gathering lines §192.8(b)(1) (DCP
Form 45)
DCP has evaluated this onshore gathering line using 49 CFR Part 192 and API RP 80 to
determine if the specified line would qualify as an onshore gathering line in accordance
with 49 CFR 192.8(a)(2). The enclosed information supports DCP's request to classify
the 6-inch pipeline between the Greeley and Mewbourn plants as gathering.
Figure 1 schematic describes the justification for two plants to complete the processing.
DCP plans to take the ethane stream off of the Greeley plant process and transport the
gas stream via the 6-inch pipeline to the inlet of the Mewbourn plant. This ethane
stream will be commingled with the other gas gathered from the area and treated,
dehydrated, and processed at the Mewbourn Plant as a combined stream. It is
necessary to recombine the ethane stream with the other unprocessed gas because the
stream contains approximately 2.5 mole percent CO2. DCP believes this is adequate
engineering justification to classify the 6-inch pipeline as gathering and move the
endpoint of gathering to the Mewbourn Plant.

<<<PAGE 6>>>

OCP is documenting the line and its current regulatory status as follows and on the
attached documentation (Form 45).
The usage of the line meets the criteria as defined in ~OT § 192.8 (a)(2):
The endpoint of gathering, under section 2.2(a)(1)(A) of API RP 80, may not extend
beyond the first downstream natural gas processing plant, unless the operator can
demonstrate, using sound engineering principles, that gathering extends to a further
downstream plant.
The line is a 6" diameter steel pipeline, 0.188 w.t., grade X42 with a MAOP of 1,440 psi.
The pipeline operates between 60% SMYS and is Class 1.
OCP respectfully requests that the PUC review this packet as cited in DOT §190.9(a) to
determine if this meets "sound engineering principles" to justify the further downstream
plant as the endpoint of gathering:
In circumstances where a rule contained in parts 192, 193 and 195 of this chapter
authorizes the Administrator to make a finding or approval, an operator may petition the
Administrator for such a finding or approval
In addition, the PUC rule §4904 provides for this same interpretation process under the
state rule.
(a) An operator may request a regulatory interpretation of any of these rules by
submitting a written request to the Chief The requestor shall include his or her return
address and the specific application and rule reference with the request.
If you have any questions regarding the regulatory justification for line, please do not
hesitate to contact me at (303) 605-1979. Please direct your written response to
OCP Midstream
Jeannette Jones
370 1 ih Street, Suite 2500
Denver, CO 80202
Sincerely,
~~
Director - Asset Integrity
OCP Midstream
Attachments:
OCP Midstream Onshore Gas Gathering Line Evaluation Forms
Schematic of line (Figure 1)
Gas Analysis of Ethane Stream (Greeley Plant)
Cc: J. Kuchinski (OCP), T. Olin (OCP), C. Smith (DCP)
Page 2of2

<<<PAGE 7>>>

DCP Form 45 c:lc::p Midstream.
Gas Pipeline Maximum Allowable Operating Pressure and % of SMYS Calculations
Record Retention: Completed MAOP Calculation Forms are kept all file with the asset/or the lif e of the pipelille and made available.
upon request. for impecfiofl.
Cells requiring user entry; Used to automatically calculate MAOP - Blue
Cells with automatic calculations based on info provided - Yellow
~~~----~~~~--~~~~--~~~----------------------------~-------------------.------,
PODS Pipeline Segment Name ..;;;B;.;;I ______________________________ _
Pipeline System ANGI Weld County
()perating Asset
PODS Station Begin: ~~~~~~~~~~~~~
40° 21' 49.10" N
End: 104°44'8.03"W 40° 16'3.21"N
Date Constructed (nunldd/yyyy)
o
r Gas Transmission Line (Complete Sections 3 and 5)
r All transmission lines are regulated by DOT regardless of class location
Designated Start and End Points for regulated segments must be either latitude/longitude coordinates, or stationing addresses.
Regulated Start Point: __ __ Regulated End Point:
P' Onshore Gas Gathering (Complete Sections 3, 4, and 5)
r Offshore Gas Gathering (Complete Sections 3 and 5)
r Tl - M
D = 61-6 (in.)
t = 0.1 (in.)
S = 42 000 (psi)
P'Steel (Complete Section 3A)
r Plastic (Complete Sections 3B)
Section 3A: Calculations for Steel Pipelines:
Outside Diameter of Pipe:
Nominal Wall Thickness of Pipe:
Specified Minimum Yield Strength (SMYS) for Steel:
S = 24,000 Grade Unknown
S = 30,000 Grade A
S = 35,000 Grade B
S = 42,000 Grade X42
S = 46,000 Grade X46
S = 52,000 Grade X52
r Design Factor Override - check to override current class location and default to class 3 design factor
Design Factor Used for Steel based on Class Location: F = 0.72 I
F = 0.72 for Class 1 Locations F '" 0.50 for Class 3 Locations
F '" 0.60 for Class 2 Locations F '" 0.40 for Class 4 Locations
Longitudinal Joint Factor (Using § 192.113): E=
E '" 1.0 for Seamless, ERW, or DSA W
E = 0.8 for other pipe manufactwing specification and pipe>4 inches
E = 0.6 for furnace butt-weld
E = 0.6 for other pipe manufactwing process and pipe 4 inches or less
to I
Temperature Derating Factor (Using § 192.115):
T = 1.000 for 250 OF or less
T = 0.967 for 300 OF
T '" 0.933 for 350 O F
T =
T = 0.900 for 400 O F
T = 0.867 for 450 OF
DCP Form 45 §192.603(b)
Page 1 of 3
Rev 3 June 2007

<<<PAGE 8>>>

1,716.3 I(psig)
2,018.181(psig)
[ 2.22o.o l(psig)
HTFIL--_I_ .lo--,I
DCP Form 45 c:Jcp
Gas Pipeline Maximum Allowable Operating Pressure and % of SMYS Calculations
Midstream_
Compare 1 - 5 to define lowest MAOP:
2 SI
I.
Design MAOP =
x F x E x T
D
2.
TestMAOP =
Hydrates, prf}!!ure
HTF
Hydrotest Pressure*
.. Corrected test pressure at maximum elevation (lowest pressure) in test section.
Where HTF= hydrotest factor detcnnincd under § 192.619(a)(2)
(Use §192.619(a)(2» summarized below for HTF:
Segment Segment
Class Installed before Installed after Converted under
Location (Nov 12, 1970) (Nov 12, 1970) §192.15
1 1.10 1.10 1.25
2 1.25 1.25 1.25
3 1.40 1.50 1.50
4 1.40 1.50 1.50
3. Operating Limited MAOP = MAOP limited by pipeline / system, fitting, or equipment.
Itcm Flange Rating Pressure Rating I, .0 I (psig)
4. MAOP of Pipeline = Lowest of 1,2, and 3: MAOP = 1,440.00 I (psig)
5. lfno test records exist, use grandfathered MAOP (§ 192.619(a)(3» based on 5 year previous operating pressure:
MonthlDayfYear: ________ Highest Operating Pressure: MAOP for Steel Pipeline based on lowest of 1 to 5:
6. Pressure at 100% Hoop Stress:
2 Sf
P 1OO ". '" -0 I (psig)
:==1 , = 44=0=.0~1 (psig)
2,383.7 I (psig)
Where: P J()()"1n = Pressure that creates 1 00% hoop stress
S = Tensile strength ofthe pipe
D = Outside Diameter
t = wall thickness
MAOP x 100
7. Hoop Stress as a Percentage of SMYS =
~OO%
Based on #7: P' MAOP produces a hoop stress >= 20% ofSMYS
r MAOP produces a hoop stress <20%
60.41 1% SMYS
D =~ (in.)
t = (in.)
T = Degrees Fahrenheit
SDR=
S = (psi)
r F = 0.25 for Wet Gas Service
I I (psig)
Section 38: Calculations for Plastic Pipelines:
Outside Diameter of Pipe:
Nominal Wall Thickness of Pipe:
Soil Temperature (for PE3408 pipe only, for all other pipe, eoter 100)
Standard Dimension Ratio:
Long Term Hydrostatic Strength:
Design Service Factor: 1. Design MAOP ""
P' F = 0.32 for DIy Gas Service
2 SI
-----x F
(D - t)
2. Alternate method for determining design pressure using SDR of plastic pipe.
'--
__ .....,1 (psig)
Design MAOP = 2 S x F
(SDR - 1)
DCP Form 45 §192.603(b) Page 20f3 Rev 3 June 2007

<<<PAGE 9>>>

c:Jcp Midstream_
'--
__ -JI(psig)
'--_-.;...-\!(psig)
I (psig)
:======~I (psig)
DCP Form 45
Gas Pipeline Maximum Allowable Operating Pressure and % of SMYS Calculations
3. Hydra test pressure
TestMAOP =
HTF
Hydrotest Pressure'"
'" Corrected test pressure at maximum elevation (lowest pressure) in test section.
Where HTF~ Hydrotest factor determined under §192.619(a)(2)(i)
(Use § 192.619(a)(2)(i» HTF = 1.5 for all plastic pipelines regardless of class location.
4. Operating Limited MAOP = MAOP limited by pipeline / system, fitting, or equipment.
Item
Pressure Rating
5. MAOP of Pipeline = Lowest of 1,2,3, and 4:
MAOP ""
6. lfno test records exist, use grandfathercd MAOP (§ 192.619(a)(3» based on highest operating pressure the 5 years
prior to July, I 1970 for transmission pipelines or the 5 years prior March 15, 2006 for gathering pipelines.
MonthlDaylY ear: Highest Operating Pressure: I (psig)
MAOP for Plastic Pipeline based on lowest of I to 6: I (psig)
r MAOP is >= 125 psig
r MAOP is <125 psig
[Sf. · 0 HR ·
Determine if Pipeline is Regulated Type A or Type B based on MAOP or Percent SMYS and class location
Designated Start and End Points for regulated segments must be either latitude/longitude coordinates, or stationing addresses.
r N/A; Onshore vacuum line operating <0 psig; Exempt from DOT Part 192
P" N/A; Onshore gathering line in Class I location; not regulated
r Regulated Type A steel & produces hoop stress >= 20% SMYS or Plastic & MAOP>'" I 25 psig; Class 2,3, or 4
Regulated Start Point: Regulated End Point:
r Regulated Type B steel & produces hoop stress < 2oolo SMYS or Plastic & MAOP<125 psig; Area I (Class 3 or 4)
Regulated Start Point: Regulated End Point:
r Regulated Class 2 Type B steel & produces hoop stress < 2oolo SMYS or Plastic & MAOP<125 psig; Area 2
r Area 2 (a) Method = 220 yd by I mile; II to 45 houses (Traditional Class 2 Calculation)
r Area 2 (b) Method = ISO ft by I mile; II to 45 r Area 2 (c) Method = ISO ft by 1000 feet 5+ houses
Regulated Start Point: Regulated End Point:
r Not Regulated Class 2 Type B; Area 2 Method used; Insufficient house count
r Area 2 Method = 150 ft by I mile; 10 or fewer houses r Area 2 Method 0: ISO ft by 1000 feet; <5 houses
~~.'" An
Dale:
ate.
DCP Form 45 §192.603(b) Page 3 of 3 Rev 3 June 2007

<<<PAGE 10>>>

.-: "
~~: (: c ~ ;
I' '-lLl'l ii "
FIGURE 1
EXTEND GATHERING TO
MEWBOURN GAS PLANT
UNDER DOT 192.8 (a)(2)
~
I (GA THERING SYSTEM)
1---
DC? MIDSTREAM
GREELEY GAS PLANT
PROCESSING AND
FRACTIONA TION
N w.'
s
-
I
I
\ ~I--__ (_GA_T_H_ER_ING SYSTEM)
-
(GATHERING SYSTEM) / !
_ I ''-----I..-t
~I--L.....,.
1
DC? MIDSTREAM
MEWBOURN GAS PLANT
TREA TlNG D£HYDRA nON
RESIDUE GAS .... .= ___ --f AND PROCESSING I---Ip~ NGL
SCHEMATIC
MEWBOURN GAS PLANT ADDITON
WELD GATHERING SYSTEM
di:;p Midstream.
Weld County
COLORADO
DWG NO. \data\Drawlngs\Standords\J_Jones\MewbournSchematic

<<<PAGE 11>>>

,
NATURAL GAS ANALYSIS
PROJECT NO. 200810091
COMPANY NA MF. : Dcr MIOSTREAM - LP
ACCOUNT NO.
PRODUCER
GREELEY PLANT
LEASE NO.
NAMEIl>ESCKIP : DETHANIZER OVERIIEAD
'"PlELDDATA'''
SAMPl.ED BY
D.S.
SAM PLE PR ES
278
SAMPLE TEMP
67
COMMENTS
S POt'
ANALYS IS NO.: 01
ANALYSIS DATE; OCTonER IG. 20 0~
SAMPLF DATE : OCTOBER 15.2008
TO:
CYLI NDER NO. 0 ·8
COMPONENTS
AMfl lENT TEMP.:
GRAVITY
VAPOR PRES.
GPM @
14.65
HELIUM
HYDROGEN
OXYGEN/ARGON
NITROGEN
CO2
METHANE
ETHANE
PROPANE
ISOBUTANE
N-BUTANE
ISOPF.NTANE
N·PENTANE
HeXANES+
NORM
MOLE%
0.00
0.00
0.00
0.01
2.50
1.31
90.90
5 28
0.00
0.00
0.00
0.00
0.00
100.00
(;PM (a!
14.13
24. IKO
1.4·17
0.000
0.000
0.000
0.000
0.000
24 .312
1.455
0.000
0.000
0.000
0.000
0000
TOTAL
I3TU@60DWF
GROSS DRY REAL =
GROSS WET REA L =
25.627
14.65
25 .767
14.73
RELATIVE DENSITY (AIR- I @14('96PSIA60F) :
1764.3
17JJ.5
I 'c)78 3
1774.0
1741. 1
COM PRESSIBILITY FACTOR
0.991 4 5
NOtE.- R/;.'FERENCE CPA 1161(ASTM DI 9<15). ]U5, a 117] CURRENr PUBLICi nONS

<<<PAGE 12>>>

## Provenance

- Official: Yes
- Source: <https://www.phmsa.dot.gov/sites/phmsa.dot.gov/files/legacy/interpretations/Interpretation%20Files/Pipeline/2009/PI-09-0006.pdf>
- Source ID: `phmsa`
- SHA-256: `1487a8343b24407bcba1a04ab0f2598f5eb8f2777cc9f759b43dafa5456a00cf`
- Retrieved: 2026-08-20T00:59:31.977Z
- Exported: 2026-08-22T05:30:54.918Z
- Document slug: `phmsa-interpretation-pi-09-0006`

### Source metadata

```json
{
  "materialSubtype": "interpretation",
  "interpretationArea": "pipeline_safety",
  "representation": "full_text_from_official_pdf",
  "companies": [
    "State of Colorado Public Utilities Commission"
  ],
  "individuals": [
    "Mr. Stephan Pott, PE"
  ],
  "refIds": [
    "PI-09-0006"
  ],
  "catalogDates": [
    "2009-02-20"
  ],
  "catalogParts": [
    192
  ],
  "catalogRowCount": 1,
  "sourceRecordUrls": [
    "https://www.phmsa.dot.gov/node/63286"
  ],
  "linkedAttachmentUrls": [],
  "unavailableResponseUrls": [],
  "duplicateRepresentationUrls": [],
  "citedSections": [
    "192.8",
    "190.9",
    "192.5",
    "192.619",
    "192.707(d)",
    "192.113",
    "192.115",
    "192.603(b)",
    "192.15"
  ],
  "catalogPageUrls": [
    "https://www.phmsa.dot.gov/regulations/title49/section/1928"
  ],
  "pdfUrls": [
    "https://www.phmsa.dot.gov/sites/phmsa.dot.gov/files/legacy/interpretations/Interpretation%20Files/Pipeline/2009/PI-09-0006.pdf"
  ],
  "representations": [
    {
      "viewUrl": "https://www.phmsa.dot.gov/sites/phmsa.dot.gov/files/legacy/interpretations/Interpretation%20Files/Pipeline/2009/PI-09-0006.pdf",
      "detailUrl": null,
      "detailHtmlPath": null,
      "pdfUrl": "https://www.phmsa.dot.gov/sites/phmsa.dot.gov/files/legacy/interpretations/Interpretation%20Files/Pipeline/2009/PI-09-0006.pdf",
      "pdfArtifactPath": "data/sources/phmsa-interpretations/pi-09-0006.pdf",
      "pdfArtifactSha256": "def74bb4ef88276176a5da2aa21cef10f6943a6590add3ef9e90f75f7dbc658e",
      "extractedTextPath": "data/sources/phmsa-interpretations/pi-09-0006.v2.txt",
      "extractedTextSha256": "40204edf04ca857420e2c655db3ef6854ace2836c891ea982fec3f507b241fe9",
      "pageCount": 12,
      "extractionVersion": 2
    }
  ],
  "caveat": "Interpretations apply regulations to the facts presented and do not create independently enforceable requirements.",
  "jurisdiction": "US"
}
```
