# Pipeline Safety Interpretation PI-09-0016

**Citation:** PI-09-0016  
**Type / status:** guidance / guidance  
**Agency:** Pipeline and Hazardous Materials Safety Administration  
**Effective:** Not stated  
**Published:** 2009-09-10

PI-09-0016 concerning 192.620.

## Document text

<<<PAGE 1>>>

U.S. Department
of Transportation
Pipeline and Hazardous
Materials Safety
Administration
1200 New Jersey Avenue, SE
Washington, 0 C 20590
SEP 1 0 2009
Mr. Gregory P. Bilinski
Vice President
Spectra Energy
P.O. Box 1642
Houston, TX 7725 I -1642
Dear Mr. Bilinski:
On December 22, 2008, you wrote to the Pipeline and Hazardous Materials Safety
Administration (PHMSA) to request an interpretation of §§ 192.620(c)(6), (d)(5)(ii), (d)(lO)(iii)
and (d)( 11 )(ii)(A).
Pursuant to Chapter 601, Title 49, United States Code. PHMSA has responsibility for protecting
against risks to life, property, and the environment posed by pipelines. In carrying out its
responsibilities, PHMSA has established design, construction, operation, and maintenance
standards and regulations for gas pipelines and has responsibility for enforcing these
requirements.
Our interpretations to your requests are as follows:
Question: Texas Eastern Transmission, LP (TETLP) reads the § 192.620(c)(6) language as
applying to construction commencing after the effective date of the [maximum allowable
operating pressure (MAOP)] Final Rule and not to construction prior to the effective date on
existing pipelines. TETLP requests an interpretation clarifying that § 192 .620( c)( 6) does not
apply retroactively to the existing segments ofTETLP's Lines 1 and 2 covered by the proposed
special permit.
Response: All construction tasks associated with implementing alternative MAOP must comply
with § 192.620( c )(6), regardless of when the task was performed. In cases where previously
completed construction tasks do not fully comply with § J92.620(c)(6), such as pipelines
constructed prior to the effective date of the rule. operators may apply for a special permit in
order to get relief from this requirement.
Question: On § 192.620(d)(5)(ii» - TETLP is reviewing customer separation equipment for
receipt points on the pipelines covered by the proposed special permit. TETLP requests an
interpretation from PHMSA clarifying that properly designed separation equipment operated by
TETLP's customers will satisfy this requirement.
The Pipeline and Hazardous Materials Safety Administration, Office of Pipeline Safety, provides written clarification of the Regulations (49 eFR
Parts 190-199) in the fonn of interpretation letters, These letters reflect the agency's curren! application of the regulations to the specific facts
presented by the person requesting the clarification. Interpretations do not create legally-enforceable rights or obligations and are provided to
help the public understand how to comply with the regulations.

<<<PAGE 2>>>

2
Response: Part 192 applies to operators of pipelines. This includes design, construction,
operational, maintenance, integrity management, operator qualification, and all other
requirements. All requirements must be implemented by pipeline operators. Customers of the
operator who are not themselves pipeline operators are not obligated to comply with Part 192
and PHMSA has no enforcement authority over them. TETLP is directly responsible for
compliance with 192.620( d)(5)(ii) as it applies to its pipelines and must document the monitoring
it conducts to ensure that contaminants that could contribute to corrosion are not present in its
pipeline. If separation equipment owned and operated by one of TETLP's customers was
operated improperly or otherwise failed to perform adequately resulting in contaminants entering
the pipeline, TETLP would be obligated to correct the problem by addressing the situation with
the customer, but PHMSA would hold TETLP responsible for the circumstances leading to and
resulting from the failure to protect against any corrosion occurring in its pipeline.
Question: On § 192.620e d)(l O)(iii» - TETLP requests an interpretation from PHMSA to clarify
that direct examination techniques are acceptable alternatives to external corrosion direct
assessment ("ECDA") or internal corrosion direct assessment ("ICDA") for non-piggable
segments operating at the alternate design factors. TETLP believes that direct examination
techniques can be more effective and provide a better assessment than ECDA and ICDA for
short segments of non-piggable lines.
Response: In accordance with National Association of Corrosion Engineers (NACE) 0502-2002,
Section 3.4.1.3, 100 percent direct examination is an acceptable method and complies with
§ 192.925. American Society for Testing and Materials (ASME) B3 I .8S, Section 6.1 also
indicates that operators may choose to conduct direct examination of the entire length of the
segment being assessed. To address external corrosion and dents, operators must make detailed
measurements and/or maps of the metal loss and/or indentation. To address internal corrosion,
operators must examine the pipe for internal metal loss by Non-Destructive Evaluation (NDE)
methods such as ultrasonic testing. To address stress corrosion cracking (SCC), operators must
examine the pipe for SCC by NDE methods such as magnetic particle inspection. (See also
§ 192.939 as it relates to the maximum intervals for each of the different reassessment methods.)
Question: In the rule, § 192.620(d)(lJ)(ii)(A) requires that a dent discovered during the baseline
assessment for integrity under paragraph (d)(9) that meets the criteria in § 192.309(b) be
repaired. In the preamble of the Final Rule, PHMSA states,
"With respect to dents, the repair criteria of§J92.309(b) apply only for dents found
during construction baseline assessments (i.e., for new pipelines). PHMSA notes that this
section already requires repair of two percent dents for pipelines over J 2-314 inches in
diameter. The criteria for repairing dents on existing pipelines and subsequent
assessments on new pipelines and existing pipelines are in § J92.933(d)." (73 FR 62165)
TETLP agrees with PHMSA's stated intent, however, points out that the language in the Final
Rule does not reflect this intent. The Final Rule language could be interpreted to require dents in
existing lines to be remedied in accordance with § I 92.309(b) and § 192.933(d). TETLP
requests an interpretation from PHMSA to clarify that § 192.309(b) is applicable only to new
The Pipeline and Hazardous Materials Safety Administration, Office of Pipeline Safety, provides written clarification of the Regulations (49 CFR
Parts 190-199) in the form of interpretation letters. These letters reflect the agency's current application of the regulations to the specific facts
presented by the person requesting the clarification. Interpretations do not create legally-enforceable rights or obligations and are provided to
help the public understand how to comply with the regulations.

<<<PAGE 3>>>

3
pipelines, and that dents identified by baseline assessments for existing pipelines are to be
remedied in accordance with § 192.933(d).
Response: The excerpt of the preamble of the final rule cited in the question merely
acknowledges that the pre-existing § 192.309(b) applied to new pipelines under construction and
that the pre-existing § 192.933(d) applied to existing operational pipelines. As stated in the
initial paragraph of the response ....
"PHMSA recognizes that the repair criteria in this rule are more stringent than those in
subpart 0. PHMSA considers this appropriate. A pipeline that will operate under
alternative MA OP is subject to more stress and has less wall thickness margin to failure
than most pipelines operating under subpart 0 (with the exception of some grandfathered
lines). "
The repair criteria in § 192.620( d)(ll )(ii) are intended to require that dents in existing lines
implementing alternative MAOP must be repaired if they meet criteria in either § 192 J09(b)
[per § 192.620(d)(lI)(ii)(A)] or § 192.933(d) [per § 192.620(d)(lI)(ii)(B)]. This is intended to
assure that existing pipelines that will be operated at stress levels allowed by the alternative
MAOP rule are in "like new" condition with respect to dent defects.
I hope that this infonnation is helpful to you. If I can further assist you with this or any other
pipeline safety regulatory matter, please contact me at (202) 366-4046.
Sincerely,
Director, Office of Regulations
The Pipeline and Hazardous Materials Safety Administration. Office of Pipeline Safety. provides written clarification of the Regulations (49 CFR
Parts 190-199) in the fonn of interpretation letters. These letters reflect the agency's current application of the regulations to the specific facts
presented by the person requesting the clarification. Interpretations do not create legally-enforceable rights or obligations and are provided to
help the public understand how to comply with the regulations.

<<<PAGE 4>>>

Texas Eastern Transmission, LP
5400 Westheimer Court
Houston, TX 77056-5310
713.627.5400 main
Mailing Address;
P.O. Box 1642
Houston, TX 77251-1642
Spectii'J)
Energ~
JAN 0 '1 20tJ9
December 22, 2008
Mr. Jeff Wiese
Associate Administrator for Pipeline Safety
Pipeline and Hazardous Materials Safety Administration
1200 New Jersey Ave., S.E., East Building
Washington, D.C. 20590
RE: Docket No. PHMSA-2008-0257
Petition for Special Permit
Texas Eastern Transmission, L.P.
Dear Mr. Wiese,
On September 11, 2008, Texas Eastern Transmission, L.P. ("TETLP") petitioned the
Pipeline and Hazardous Materials Safety Administration ("PHMSA") for a special permit
to increase the maximum allowable operating pressure ("MAOP") of a portion of its
pipeline system in Pennsylvania from 1,000 psig to 1,112 psig. The special permit
petition requested a waiver under Section 60118(c) of the United States Federal Code
from the requirements of Sections 192.111, 192.201, 192.611, and 192.619 of Title 49 of
the Code of Federal Regulations to allow this MAOP increase.
Since the petition was filed, PHMSA has issued a final rule, "Pipeline Safety: Standards
for Increasing the Maximum Allowable Operating Pressure for Gas Transmission
Pipelines" ("Final Rule"), that provides regulations for operation of new and existing
pipelines using higher design factors. In the preamble of the final rule, PHMSA indicated
they would no longer process special permit requests as operators would be expected to
comply with the Final Rule to increase their MAOP. TETLP has reviewed the Final
Rule, and has determined that segments of TETLP's Lines 1 and 2 substantially meet
most of the requirements of the Final Rule. TETLP Lines 1 and 2 do not retroactively
meet a limited number of the specified requirements in the Final Rule, such as the those
requirements regarding pipe and coating manufacturing testing and inspection,
construction inspection, and operator qualification requirements for previous
construction. In some cases, the specified requirements were not yet recognized as "best
practice", in other cases, the specified requirements were substantially met but supporting
documentation does not exist.
Through the course of several discussions, PHMSA has indicated to TETLP that PHMSA
would consider a special permit to waive specific requirements of the Final Rule, and
www.spectraenergy.com

<<<PAGE 5>>>

Docket No. PHMSA-2008-0257
TETLP Request for Special Pennit
December 22, 2008
Page 2 of II
recommended that TETLP to submit a letter requesting a modification to TETLP's
September 11, 2008 special permit petition. TETLP hereby requests its special permit
petition for segments of TETLP Lines 1 and 2 be amended as detailed in this letter to
request a limited number of specific requirements of the Final Rule be waived to allow
the proposed MAOP uprate.
Specifically, TETLP requests a limited Special Permit that waives the requirements of the
following sections:
• 49 CFR 192.l12( a) (1 )
• 49 CFR 192.1 12(c)(l)
• 49 CFR 192.l12(c)(2)(i)
• 49 CFR 192.1 12(c)(2)(ii)
• 49 CFR 192.112( c )(2)(iii)
• 49 CFR 192.l12(d)(2)(i)
• 49 CFR 192.112(f)(1)
• 49 CFR 192.620(d)(5)(iii)
In addition, TETLP requests an interpretation of the requirements of the following
sections of the rule as they pertain to existing pipelines:
• 49 CFR 192.l12( d)(l)
• 49 CFR 192.112(d)(2)
• 49 CFR 192.620(c)(6)
• 49 CFR 192.620(d)(5)(ii)
• 49 CFR 192.620( d)(7)(i)
• 49 CFR 192.620( d)(7)(ii)
• 49 CFR 192.620( d)(l O)(iii)
• 49 CFR 192.620(d)(ll)(ii)(A)
BACKGROUND
The proposed special permit would apply to TETLP's 36-inch Lines 1 and 2 from its
Uniontown, P A compressor station to a mainline regulating station approximately 7 miles
west of its Lambertville, NJ compressor station (See Appendix A for a map of the TETLP
pipeline system and Appendix B for a schematic showing the scope of the proposed
uprate). The MAOP uprate is part of two proposed pipeline capacity expansion projects,
called the TEMAX and TIME III Projects (See Appendix C for a TEMAX and Time III
facilities map). These proposed projects will increase U.S. natural gas transportation and
supply reliability by connecting natural gas from the Rocky Mountains to growing
markets throughout Pennsylvania and the Northeast region. TETLP has commenced with
the FERC pre-filing process for the TEMAX and TIME III Project FERC under Docket
#PF08-27.

<<<PAGE 6>>>

Docket No. PHMSA-2008-0257
TETLP Request for Special Permit
December 22, 2008
Page 3 of 11
Under the increased pressure of 1,112 psig, these pipeline segments would operate as
high as 80% of specified minimum yield strength ("SMYS") in Class 1, 67% of SMYS in
Class 2 and 56% of SMYS in Class 3 areas. There are currently no Class 4 areas on the
system, and TETLP does not propose to include any future Class 4 areas under this
special penn it. Additionally, TETLP does not propose to operate the compressor stations
or meter stations under the alternate design factors specified in the Final Rule.
TETLP has perfonned a thorough evaluation of the pipeline segments covered by the
proposed special pennit and has concluded that these segments can safely and reliably
operate at the higher MAOP. This evaluation included reviews of the pipeline design,
fracture control, materials and construction, as well as their operating and maintenance
history. This evaluation also included recommendations for any additional integrity
management activities needed to ensure improved pipeline safety at the higher operating
pressures. The original special pennit petition includes details of this evaluation. As a
result of TETLP's review of the Final Rule, TETLP is proposing additional integrity
management activities beyond those proposed in the September 11, 2008 petition to
address specific issues in the Final Rule. The proposed integrity management activities
are summarized later in this letter.
MODIFIED SPECIAL PERMIT REQUEST
TETLP has reviewed the Final Rule, and has detennined the pipelines covered by the
proposed MAOP increase do not retroactively meet a limited number of the specified
requirements of the Final Rule. TETLP largely agrees with the technical conditions
specified for construction of new pipelines to operate at 80% SMYS, however these same
conditions applied to existing pipelines are not realistically achievable in every case.
Specifically, some of the detailed requirements regarding pipe fabrication, inspection and
testing have been applied only very recently as "best practices" and are not typical for
pipelines constructed at the time of TETLP Lines 1 and 2. In other case, documentation
is difficult to produce to demonstrate full compliance that all specified conditions are
met. However, in many cases, documentation exists to demonstrate that requirements are
substantially met.
TETLP hereby modifies its original special pennit petition filed on September 11, 2008
to request PHMSA to waive the requirements of the sections of the Final Rule specified
below. Each section of the Final Rule to be included in the modified special pennit
request is shown in italics, followed by a description of the specific requirement for
which TETLP requests a special pennit. In some cases, TETLP is requesting an
interpretation of the Final Rule language rather than a special pennit.

<<<PAGE 7>>>

Docket No. PHMSA-2008-0257
TETLP Request for Special Penn it
December 22, 2008
Page 4 of II
49 CFR J92.112(a)(l)
The plate. skelp. or coil used for the pipe must be micro-alloyed. fine grain, fully killed.
continuously cast steel with calcium treatment.
The plate used for the pipe is continuous cast, micro-alloyed, fine grain, and fully killed.
The micro-alloy content is demonstrated by the presence of titanium, vanadium and
niobium in the mill test report documentation. The silicon composition of 0.2%
(nominal) demonstrates that the material was fully killed. Calcium treatment was applied
for a large majority of the pipe, but documentation is not available for each individual
pipe supplier.
The original purpose of calcium addition as a sulfide shape control element became
obsolete by the time TETLP Lines 1 and 2 were constructed due to the already low levels
of sulfur in the steel composition. Calcium treatment is now primarily used to increase
pipe toughness. Since each pipe supplier achieved adequate toughness to meet the ductile
fracture arrest conditions specified by PHMSA in the Final Rule, TETLP believes it has
met the intent of this provision and requests the proposed special permit include a waiver
from the requirement for calcium treatment for existing segments of its Lines 1 and 2
covered by the proposed MAOP increase. Appendix L of the special permit petition
dated September 11,2008, "Design Basis for the CRP Fracture Control Plan" documents
compliance with the requirements of a fracture control plan.
49 CFR 192.1 12(c)(l)
There must be an internal quality management program at all mills involved in
producing steel, plate, coil, skelp, and/or rolling pipe to be operated at alternative
MAOP. These programs must be structured to eliminate or detect defects and inclusions
affecting pipe quality.
The requirement for a quality management program at the steel, plate, coil, skelp and/or
roIling mills was not a standard industry practice at the time the pipe was manufactured,
nor was it a requirement or recommended practice of any applicable consensus standard.
Each pipe supplier had a longstanding relationship with the individual plate
manufacturer. TETLP implemented a quality assurance program at the pipe mills.
TETLP believes the integrity of the pipeline is validated by the pipe mill inspections and
hydrostatic testing, the weld seam and girth weld non-destructive examination ("NDE"),
the post construction hydrostatic testing and the safe operating history of these pipelines.
TETLP requests a special permit waiving the requirements of the internal quality
management program for the mills producing steel, plate, coil, skelp, and/or rolling pipe
for existing segments of Lines 1 and 2 covered by the proposed special permit.
49 CFR 192.l12(c)(2)
A mill inspection program or internal quality management program must include (i) and
either (ii) or (iii): '

<<<PAGE 8>>>

Docket No. PHMSA-2008-0257
TETLP Request for Special Permit
December 22, 2008
Page 5 of 11
See comments to each individual subsection below.
49 CFR 192.112(c)(2)(i)
An ultrasonic test of the ends and at least 35 percent of the surface of the platelcoil or
pipe to identify imperfections that impair serviceability such as laminations, cracks, and
inclusions. At least 95 percent of the lengths of pipe manufactured must be tested For all
pipelines designed after [the effective date of the final rule j, the test must be done in
accordance with ASTM A5781A578M Level B, or AP15L Paragraph 7.8.10 (incorporated
by reference, see §I92. 7) or equivalent method, and either
For the pipe covered by this proposed special pennit, ultrasonic testing was required at
each end of each pipe to inspect for mid-wall laminations. Pipe seam weld inspections
were also performed for all of the pipe covered by the proposed special permit. Pipe
body UT inspection was specified in the purchase orders for a majority of the pipe
produced, but not 100%. In some cases, the pipe body UT inspection may not have
achieved 35% coverage of the pipe body. TETLP requests a special permit waiving the
requirement for pipe or plate surface UT inspection.
TETLP believes the primary benefit of pipe body UT inspection is to check for
laminations that could cause welding problems in longitudinal seam or girth weld. Once
the pipeline has been installed with 100% NDE of seam and girth welds, laminations are
of minimal concern to pipeline integrity.
49 CFR 192.112(c)(2)(ii)
A macro etch test or other equivalent method to identify inclusions that may form
centerline segregation during the continuous casting process. Use of sulfur prints is not
an equivalent method The test must be carried out on the first or second slab of each
sequence graded with an acceptance criteria of one or two on the Mannesmann scale or
equivalent; or
Macro etch testing of the continuous cast slabs was not conducted during steelmaking for
TETLP Lines 1 and 2 This process was established as an industry practice much later,
and applied to continuous cast slabs used for gas transmission pipes only very recently.
Macro etch testing is primarily performed to prevent laminations in the finished pipe. As
noted above, TETLP believes the primary benefit of pipe body UT inspection is to check
for laminations that could cause seam or girth weld defects. Once the pipeline has been
installed with 100% NDE of seam and girth welds, laminations are of minimal concern to
pipeline integrity. TETLP requests a special permit waiving the requirement for macro
etch testing.
49 CPR 192.1 12(c)(2)(iii)
A quality assurance monitoring program implemented by the operator that includes
audits of (a) all steelmaking and casting facilities, (b) quality control plans and
manufacturing procedure specifications, (c) equipment maintenance and records of

<<<PAGE 9>>>

Docket No. PHMSA-2008-0257
TETLP Request for Special Permit
December 22, 2008
Page 6 of II
conformance, (d) applicable casting superheat and speeds, and (e) centerline segregation
monitoring records to ensure mitigation of centerline segregation during the continuous
casting process.
The requirement for a Company quality assurance monitoring program as specified was
not a standard industry practice at the time the pipe was manufactured, nor was it a
requirement or recommended practice of any applicable consensus standard. TETLP did
not perform this type of quality assurance monitoring program for the pipe covered by the
proposed special permit. Each pipe supplier had a longstanding relationship with the
individual plate manufacturer. TETLP implemented a quality assurance program at the
pipe mills. TETLP believes the integrity of the pipeline is validated by the pipe mill
inspections and hydrostatic testing, the weld seam and girth weld non-destructive
examination ("NDE"), the post construction hydrostatic testing and the safe operating
history of these pipelines, and requests a special permit waiving the requirements for a
quality management program as specified in this section.
49 CFR 192.1 12(d)(l)
There must be a quality assurance program for pipe seam welds to assure tensile strength
provided in API Specification 5L (incorporated by rejerence, see §i92. 7) for appropriate
grades.
The line pipe for Lines 1 and 2 was manufactured in conformance with the edition of API
5L in effect at the time of the pipe orders. TETLP requests an interpretation clarifying
seam tensile strength testing for existing pipelines must have been performed in
accordance with the DOT referenced version of API 5L in effect at the time of the pipe
order.
49 CFR 192.1 12(d)(2)
There must be a hardness test, using Vickers (Hv i 0) hardness test method or equivalent
test method, to assure a maximum hardness of280 Vickers of the following:
For original CRP pipe, Rockwell seam hardness testing was applied with a specification
limit equivalent to HRC equal to 22 max. An HRC value of 22 is approximately
equivalent to a value of 245 on the Vickers scale; substantially below the PHMSA
requirement of 280. Any Rockwell hardness results above HRC = 22 or equivalent were
evaluated using the Vickers test method. Subsequent loops included seam weld Vickers
testing compliant with the PHMSA requirements. TETLP requests an interpretation from
PHMSA clarifying TETLP's Rockwell hardness testing is adequate to meet the
requirements of § 192.112( d)(2).
49 CFR 192.l12(d)(2)(i)
A cross section of the weld seam of one pipe from each heat plus one pipe from each
welding line per day,' and

<<<PAGE 10>>>

Docket No. PHMSA-2008-0257
TETLP Request for Special Permit
December 22,2008
Page 7 of 11
The requirement for weld seam inspection testing at the stated frequency was not an
industry standard practice, nor was this a recommended practice or requirement of any
applicable consensus standard at the time the pipe was manufactured. TETLP typically
specified a testing frequency of once per welding machine per day. TETLP believes the
integrity of the pipeline is validated by the post construction hydrostatic test and the safe
operating history of the lines covered by the special permit. TETLP requests a special
permit waiving the frequency requirements stated in §I92.112(d)(2)(i).
49 CFR 192.1 12(f)(l)
The pipe must be protected against external corrosion by a non-shielding coating.
The pipe covered by the proposed special permit is coated with FBE. Girth welds are
coated primarily with field applied FBE or 2-part epoxy coatings. Records indicate the
use of shrink sleeves at tie-in and repair welds for some of the construction from 1992
through 1995. Approximately 56 miles of pipeline was installed in this period of time.
TETLP has identified a number of locations where shrink sleeves were installed. TETLP
proposes to evaluate MFL data to identify any detectable indications of external corrosion
near girth welds. Locations with detectable indications of external corrosion at girth
welds will be identified, excavated and examined. Shrink sleeves in these locations will
be removed. TETLP also proposes to excavate a limited number of locations where
shrink sleeves are known to be present and ILl logs do not indicate metal loss. TETLP
personnel will remove the coating and evaluate the condition of the pipe. The absence of
detectable metal loss on the ILl log indicates that the girth weld coating system is intact
and SCC would be highly unlikely.
Given the presence of the shrink sleeves, TETLP requests that this section be included in
a special pennit with a conditions that require excavation and examination of a limited
number of known locations with shrink sleeves and the evaluation of high-resolution
MFL data at girth welds to identify measureable indications of metal loss as a possible
indicator of the presence of a failed shrink sleeve.
49 CFR 192.620(c)(6)
If the performance of a construction task associated with implementing alternative
MAOP can affoct the integrity of the pipeline segment, treat that task as a "covered
task", notwithstanding the definition in §J92.80J(b) and implement the requirements of
subpart N as appropriate.
TETLP reads this language as applying to construction commencing after the effective
date of the Final Rule and not to construction prior to the effective date on existing
pipelines. TETLP requests an interpretation clarifying that §192.620(c)(6) does not apply
retroactively to the existing segments ofTETLP's Lines 1 and 2 covered by the proposed
special permit.

<<<PAGE 11>>>

Docket No. PHMSA-200S-0257
TETLP Request for Special Permit
December 22, 200S
Page S of 11
49 CFR 192.620(d)(5)(ii)
At points where gas with potentially deleterious contaminants enters the pipeline, use
filter separators or separators and gas quality monitoring equipment.
TETLP is reviewing customer separation equipment for receipt points on the pipelines
covered by the proposed special permit. TETLP requests an interpretation from PHMSA
clarifying that properly designed separation equipment operated by TETLP's customers
will satisfy this requirement.
49 CFR 192.620(d)(5)(iii)
Use gas quality monitoring equipment that includes a moisture analyzer, chromatograph,
and periodic hydrogen sulfide sampling.
TETLP is reviewing currently installed gas quality monitoring equipment. TETLP has
several small volume receipt points (Jess than 15 mmcfd) delivering gas into the
segments of pipeline covered by the proposed special permit. TETLP's policy is to take
spot gas samples for small volume receipt points up to 5 mmcfd and utilize continuous
gas samplers for receipt points between 5 mmcfd and 15 mmcfd. TETLP typically
installs gas chromatographs only for those points with a volume greater than 15 mmcfd.
TETLP proposes to continue spot sampling for receipt points up to 5 mmcfd and
continuous gas samplers for receipt points between 5 mmcfd and 15 mmcfd, and requests
the special permit allow this philosophy. TETLP believes that small volume receipts,
even if the gas does not meet tariff gas quality specifications, will adequately blend to
eliminate the risk of internal corrosion from this gas.
TETLP requests that this section be addressed in the proposed special permit. TETLP
will document the effect of blending based on proposed flows and compositions prior to
operation at the increased pressure and then reevaluate the effect of blending on an
annual basis.
49 CFR 192.620(d)(7)(i)
Within six months after placing the cathodic protection of a new pipeline segment in
operation, or within six months after certifying a segment under § J92.620(c)(J) of an
existing pipeline segment under this section. assess the adequacy of the cathodic
protection through an indirect method such as close-interval survey, and the integrity of
the coating using direct current voltage gradient (DCVG) or alternating current voltage
gradient (ACVG).
During the construction of most of the pipelines covered by the proposed special permit,
TETLP performed post backfill coating integrity testing, and remediated coating holidays
that didn't meet TETLP's requirements. Since the coating integrity assessments to
identify and remediate coating damage caused during construction have already been
performed, TETLP requests an interpretation from PHMSA that clarifies the coating
integrity surveys do not need to be duplicated for TETLP Lines 1 and 2.

<<<PAGE 12>>>

Docket No. PHMSA-2008-02S7
TETLP Request for Special Permit
December 22, 2008
Page 9 of II
49 CFR 192.620(d)(7)(ii)
Remediate any construction damaged coating with a voltage drop classified as moderate
or severe (IR drop greater than 35%for DCVG or 50 dBuv for ACVG) under section 4 of
NACE RP-0502-2002 (incorporated by reference, see §192. 7).
Given that this provision states "construction damaged coating", TETLP presumes that
this applies to new pipelines and construction on existing pipelines after the effective date
of the rule, and not existing pipelines constructed prior to the effective date. TETLP
performed post backfill coating integrity testing for most of the pipelines covered by the
special permit, and remediated coating holidays that didn't meet TETLP's requirements.
Additionally, TETLP will be performing a close interval survey on these pipelines to
assure adequate cathodic protection. TETLP has also performed approximately 218
miles of in-line inspections with MFL tools, with very few indications of corrosion. This
validates that the coating and cathodic protection systems are performing adequately to
protect the pipeline. TETLP requests an interpretation from PHMSA clarifying that the
requirement for remediation of construction damaged coating is applicable only to
pipelines installed after the effective date of the Final Rule.
49 CFR 192.620(d)(10)(iii)
Use direct assessment (per §192.925, §192.927 and/or §192.929) or pressure testing (per
subpart J of this part) for periodic assessment of a portion of a segment to the extent
permittedfor a baseline assessment under paragraph (d)(8)(iii) of this section.
TETLP requests an interpretation from PHMSA to clarify that direct examination
techniques are acceptable alternatives to external corrosion direct assessment ("ECDA")
or internal corrosion direct assessment ("ICDA") for non-piggable segments operating at
the alternate design factors. TETLP believes that direct examination techniques can be
more effective and provide a better assessment than ECDA and ICDA for short segments
of non-piggable lines.
49 CFR 192.620(d)(11)(ii)(A)
The defect is a dent discovered during the baseline assessment for integrity under
paragraph (d)(9)' of this section and the defect meets the criteriafor immediate repair in
§192.309(b).
In the preamble of the Final Rule, PHMSA states "With respect to dents, the repair
criteria of §192.309(b) apply only for dents found during construction baseline
assessments (i.e., for new pipelines). PHMSA notes that this section already requires
repair of two percent dents for pipelines over 12Y4 inches in diameter. The criteria for
repairing dents on existing pipelines and subsequent assessments on new pipelines and
existing pipelines are in §192.933(d)." (73 FR 62165) TETLP agrees with PHMSA's
I The fmal rule language references section (d)(8), however TETLP believes this is a typographical error.
TETLP believes (d)(9) is the correct section reference for the baseline assessment.

<<<PAGE 13>>>

Docket No. PHMSA-2008-0257
TETLP Request for Special Pennit
December 22, 2008
Page 10 ofll
stated intent, however points out that the language in the Final Rule does not reflect this
intent. TETLP interprets the Final Rule language to require dents in existing lines to be
remediated in accordance with § I 92.309(b) and § I 92.933( d). TETLP requests an
interpretation from PHMSA to clarify that § 192 .309(b) is applicable only to new
pipelines, and that dents identified by baseline assessments for existing pipelines are to be
remediated in accordance with §192.933(d).
PROPOSED INTEGRITY MANAGEMENT ACTIVITIES TO SUPPORT THE
PROPOSED SPECIAL PERMIT
To ensure that this proposed special permit will achieve an increase in pipeline safety and
integrity, TETLP will apply its Pipeline Integrity Management Plan (IMP) to all
segments of Lines 1 & 2 covered under this proposed special permit. If the special
pennit request is granted and TETLP obtains approval from the Federal Energy
Regulatory Commission (FERC) to reflect this uprated MAOP in its FERC-certificated
design, TETLP's IMP will be applied to all segments of Lines 1 & 2 that have been
uprated, not just those in HCAs. Specifically, TETLP proposes to perform the following
integrity activities:
• Perform in-line inspection on the special permit segments with high resolution
magnetic flux leakage (MFL) and multi-channel geometry tools within 2 years prior
to the MAOP uprate.
• Perform a close-interval survey (CIS), or similar performance assessment, of the
cathodic protection (CP) system on the special pennit segments within 2 years prior
to the MAOP uprate.
• Remediate all actionable anomalies based on an operating pressure of 1,112 psig and
using the criteria in the TETLP IMP and the Final Rule prior to increasing the
pressure.
• Integrate CIS data with the in-line inspection results to address any cathodic
protection enhancements needed to improve long-term integrity of the pipeline.
These documented enhancements will be implemented within one-year of the
pressure increase.
• Replace pressure rated components as needed to meet a minimum of 1,112 psig prior
to increasing pressure.
• Perform a leak survey in accordance with TETLP's Standard Operating Procedures
after the pressure increase.
• Perform inspections and preventive and mitigative measures in accordance with the
TETLP IMP on the segments of Line 1 & 2 pipeline system that are operating at the
alternate design factors.
• Perform reassessment using in-line inspection in accordance with Part 192 Subpart 0
requirements or more frequently based on a technical review of reassessment
intervals for these pipelines operating at a MAOP of 1,112 psig.

<<<PAGE 14>>>

Docket No. PHMSA-2008-0257
TETLP Request for Special Permit
December 22, 2008
Page II of II
• Hydrostatic retesting of several segments of Line 1 that were not tested to 125% of
MAOP during original construction.
• Evaluate ILl logs to identify indications of external corrosion in close proximity to
girth welds and excavate those locations that are likely to have failed shrink sleeves.
• Develop a plan for excavation of a limited number of known shrink sleeve locations,
removal of the shrink sleeve at these locations and evaluation of the pipe for see and
external corrosion.
• Perform long term coating integrity surveys for pipelines operating over 1200 F.
SUMMARY
TETLP has reviewed the Final Rule, and has determined that segments ofTETLP's Lines
1 and 2 substantially meet most of the requirements of the Final Rule. However, TETLP
Lines 1 and 2 do not retroactively meet a limited number of the specified requirements in
the Final Rule, such as the those requirements regarding pipe and coating manufacturing
testing and inspection, construction inspection, and operator qualification requirements
for previous construction. In some cases, the specified requirements were not yet
recognized as "best practice", in other cases, the specified requirements were
substantially met but supporting documentation does not exist. As a result, TETLP is
requesting its special permit petition dated September 11, 2008 be modified as detailed in
this letter. Additionally, TETLP requests interpretations regarding certain sections of the
Final Rule as to how these sections apply to existing pipelines.
TETLP's believes the pipelines covered by the proposed special permit are well suited to
operation at the higher design factors specified by the Final Rule. Through the proposed
special permit, TETLP commits to apply rigorous integrity management activities to the
entire pipeline covered by the special permit.
We look forward to continued discussions and progress on this special permit petition.
Please contact Rick Kivela at 713-627-6388 if you have any questions or request any
additional information.
L-
Attachments

<<<PAGE 15>>>

cc w/Attachments:
William Gute - PHMSA
Alan Mayberry - PHMSA
Byron Coy - PHMSA
Clyde Myers - PHMSA

<<<PAGE 16>>>

TETLP LINES 1 & 2
PROPOSED MAOP UPRATE
YURK
NEW
SYL.VANIA
VIRGINIA
NOKTH CARCINA
..t-
CARININA
Appendix
AICHICN
.LNOS
_Pogend
6 ats knos
VINADIRI
Station Site (No Horsepower)
Spectra)
Energy-
Texas Eastern Tranamission Corporation
3400 farbeimur Ca. Housem. TX T7056-9310 7131827-9490
Compressor Station
Noturai Ges Storage Flaid
Texas Eastern Transmisaion, LP
dinahinpi-l (PISIST:- wits.en./cc0.sg
OKLUIOMA
KANSAS
TrX ^9

<<<PAGE 17>>>

APPENDIX B
TETLP LINES 1 & 2
SCOPE OF MAOP UPRATE
Mainline regulator al
MP 1428.88
36-inch Line 2
20-inch Line 2
36·inch Line 1
Uniontown) Bedford
....
Chambersburg Heidlersburg Marietta
36·inch Line 1
20-inch Line 2 -)
Lambertville (26)
MP 1435.90
I 20·inch Line 1
Uprate Phase 1 (2010) J 1 Uprate Phase 2 (Date T8D) ,-1
Philadelphia system Skippack system
J
NOTES :
Red denotes the pipeline segments under consideration for a MAOP uprate (from 1000 psig to 1112 psig).
TETLP is proposing a phased implementation of the uprate, with Phase 1 being uprated in Nov. 2010 and Phase 2
being uprated for a future undefined expansion project.
The uprate will also include compressor station yard and unit piping at Uniontown, Bedford. Chambersburg and
Heidlersburg in Phase 1 and Marietta in Phase 2. The compressor stations will be designed for a 1200 psig MAOP.
and thus will not be included in the special permit.
Eagle Compressor Station does not compress on the mainline. It compresses gas from the mainline into the Philadelphia
lateral (20" Line 1-H). Therefore this unit piping is not subject to the proposed uprate.

<<<PAGE 18>>>

APPENDIX C
TEMAX and TIME III Facilities MaD
•
Existing Compressor Station
I .. MAOP Uprate
o Replace & Add Compressor Units
o ExIsting Pipeline Loop or Replacement
• III New Pipeline extension
Leidy Storage PA
exas taste
Holbrook
fTEM ~
Accident
Storage
§pectt;)
~nergy
~
.1

## Provenance

- Official: Yes
- Source: <https://www.phmsa.dot.gov/sites/phmsa.dot.gov/files/legacy/interpretations/Interpretation%20Files/Pipeline/2009/PI-09-0016.pdf>
- Source ID: `phmsa`
- SHA-256: `a1f9679e98ef84fa1665e8055b0030b9c7c5b26f5bf1cb4c6e63e1c56f3f8763`
- Retrieved: 2026-08-20T00:59:31.977Z
- Exported: 2026-08-22T05:26:04.387Z
- Document slug: `phmsa-interpretation-pi-09-0016`

### Source metadata

```json
{
  "materialSubtype": "interpretation",
  "interpretationArea": "pipeline_safety",
  "representation": "full_text_from_official_pdf",
  "companies": [],
  "individuals": [],
  "refIds": [
    "PI-09-0016"
  ],
  "catalogDates": [
    "2009-09-10"
  ],
  "catalogParts": [
    192
  ],
  "catalogRowCount": 1,
  "sourceRecordUrls": [
    "https://www.phmsa.dot.gov/node/66171"
  ],
  "linkedAttachmentUrls": [],
  "unavailableResponseUrls": [],
  "duplicateRepresentationUrls": [],
  "citedSections": [
    "192.620",
    "192.620(c)(6)",
    "192.620e",
    "192.925",
    "192.939",
    "192.309(b)",
    "192.933(d)",
    "192.111",
    "192.201",
    "192.611",
    "192.619",
    "192.1",
    "192.112",
    "192.927",
    "192.929"
  ],
  "catalogPageUrls": [
    "https://www.phmsa.dot.gov/regulations/title49/section/192620"
  ],
  "pdfUrls": [
    "https://www.phmsa.dot.gov/sites/phmsa.dot.gov/files/legacy/interpretations/Interpretation%20Files/Pipeline/2009/PI-09-0016.pdf"
  ],
  "representations": [
    {
      "viewUrl": "https://www.phmsa.dot.gov/sites/phmsa.dot.gov/files/legacy/interpretations/Interpretation%20Files/Pipeline/2009/PI-09-0016.pdf",
      "detailUrl": null,
      "detailHtmlPath": null,
      "pdfUrl": "https://www.phmsa.dot.gov/sites/phmsa.dot.gov/files/legacy/interpretations/Interpretation%20Files/Pipeline/2009/PI-09-0016.pdf",
      "pdfArtifactPath": "data/sources/phmsa-interpretations/pi-09-0016.pdf",
      "pdfArtifactSha256": "6d73c938fe00a88c9bb840e0512b9c1d411dc70a8b5bd8174e9e3969827d2b6e",
      "extractedTextPath": "data/sources/phmsa-interpretations/pi-09-0016.v2.txt",
      "extractedTextSha256": "e044c6e66b3d73be027118ff5f227189325851882bb5976d731b50029263db13",
      "pageCount": 18,
      "extractionVersion": 2
    }
  ],
  "caveat": "Interpretations apply regulations to the facts presented and do not create independently enforceable requirements.",
  "jurisdiction": "US"
}
```
